Loading...
HomeMy WebLinkAbout20051881 Ver 3_More Info Received_20081030[Fwd: RE: Piedmont Crossing DWQ#05-1881 ver2] Subject: [Fwd: RE: Piedmont Crossing DWQ#05-188 1ver2] From: Sue Homewood <Sue.Homewood@ncmail.net> Date: Thu, 30 Oct 2008 08:45:32 -0400 To: Laurie J Dennison <Laurie.J.Dennison@ncmail.net> for file ------- Original Message -------- Subject:RE: Piedmont Crossing DWQ#05-188 1ver2 Date:Thu, 30 Oct 2008 08:24:50 -0400 From:Wendell Overby <woverby(&,,sandec.com> To:Sue Homewood <Sue.Homewood(a),ncmai].net> CC:Ian McMillan <Ian.McMiIIan(a)ncmail.net>, Bob Zarzecki <bzarzecki(a,sandec.com> References: <02FDOC8DB72E5C46AO39136BFE8B7BFE48D715(a)SEC3.sandec.local> <4908C80C.7080201 a,ncmail.net> Sue/Ian, Here is additional information I found in the file that we sent to Andy Williams. It may shed some light on what the applicant proposes to do (i.e. 36' structure over 4' stream). The Corps wanted information regarding the City of High Point's acceptance of the structure as well as their acknowledgement of maintenance. The City of High Point has approved the structure plans attached. I have approved hard copies in our files. Thank you, Wendell Overby Environmental West Manager Soil & Environmental Consultants, PA E-Mail: woverby(a,sandec.com www.SandEC.com Charlotte Office 248 LePhillip Court Concord, NC 28025 Phone: 704-720-9405 Fax: 704-720-9406 Greensboro Office 3817-E Lawndale Dr. Greensboro, NC 27455 Phone: 336-540-8234 Fax: 336-540-8235 This electronic communication, including all attachments, is intended only for the named addressee (s) and may contain confidential information. This electronic communication may not have passed through our standard review/quality control process. Design data and recommendations included herein are provided as a matter of convenience and should not be used for final design. Rely only on final, hardcopy materials bearing the consultant's original signature and seal. If you are not the named addressee (s), any use, dissemination, distribution or copying of this communication is prohibited. If you have received this electronic communication in error, please notify the sender by return e-mail and delete the original communication from your system. Thank you ............. From: Sue Homewood [mailto:Sue.Homewood@ncmail.net] Sent: Wednesday, October 29, 2008 4:31 PM To: Wendell Overby Cc: Ian McMillan Subject: Re: Piedmont Crossing DWQ#05-1881ver2 Hi Wendell, 1 of 3 10/30/2008 9:12 AM [Fwd: RE: Piedmont Crossing DWQ#05-188 1ver2] I've reviewed the current permit modification and documents you submitted today. I have two things: I would like to go out to site S-1 and confirm that the work has been done to reduce the impacts back to 81 feet. I can do that this Friday afternoon, late next Thurs. afternoon, or anytime next Friday. Shouldn't take long to look at that one site real quick. I know that you are proposing the same bottomless structure that was approved by DWQ in 2005; however new applications, including modifications, require our most current rules, policies and procedures to be met. So we're going to require that geotechnical investigations be done in accordance with our public notice dated August 27, 2007 (you can find it on this website: http://h2o.enr.state.nc.us/ncwetlands/rd pub not html) I'll draft a letter stating this, but I'd like to wait until after I've seen site S-1 in case anything comes up that I would want to add to the letter. I know Bob mentioned a meeting regarding the bottomless culvert, and we'd be happy to coordinate that, however I'd like for it to involve Ian McMillan since he worked on the development of our policy. I can come to Raleigh. Sue Sue Homewood NC DENR Winston-Salem Regional Office Division of Water Quality 585 Waughtown Street Winston-Salem, NC 27107 Voice: (336) 771-5000 FAX: (336) 771-4630 On 10/29/2008 10:21 AM, Wendell Overby wrote: Sue, Could you let me know the status of the 401 review for our most recent submittal for Piedmont Crossing? If I can answer any questions you may have about the submittal please let me know. Also let me know if you feel an office or site meeting is needed. The attached information will likely be helpful to your review of the PCN submittal. Hopefully it won't make things more confusing. I've sent the attached information to Andy Williams today for his approval/comments. In essence S&EC has prepared a stream repair/bank stabilization plan for Impact S-1. You may recall at our site meeting that the first road crossing we met on (S-1) resulted in 88 If of stream impact as opposed to the approved 74 If. Additionally, impact S-2 was redesigned prior to construction and resulted in 67 If of stream impact as compared to 75 If in the initial 401 approval. As such mitigable stream impacts for the project totaled 155 If. In an effort to avoid compensatory mitigation S&EC discussed repair/stabilization measures with Andy. He was agreeable to produce a modified NW permit without the stream mitigation condition provided the plan (primarily to remove the excess riprap from the streambed) was performed and pictures provided. The work has been done with the exception of live staking of banks (waiting for best planting time) which will be done within a month. If you require hardcopies of the information please let me know. I do apologize for the quality of the pics however, the file size of the digital copies are huge. Sincerely, 2 of 3 10/30/2008 9:12 AM [Fwd: RE: Piedmont Crossing DWQ#05-188 1ver2] Wendell Overby Environmental West Manager Soil & Environmental Consultants, PA E-Mail: woverbygsandec.com www.SandEC.com Charlotte Office 248 LePhillip Court Concord, NC 28025 Phone: 704-720-9405 Fax: 704-720-9406 Greensboro Office 3817-E Lawndale Dr. Greensboro, NC 27455 Phone: 336-540-8234 Fax: 336-540-8235 ...........This electronic communication, including all attachments, is intended onlyfor the named addressee (s) and may contain confidential information. This electronic communication may not have passed through our standard review/quality control process. Design data and recommendations included herein are provided as a matter of convenience and should not be used for final design. Rely only on final, hardcopy materials bearing the consultant's original signature and seal. if you are not the named addressee (s), any use, dissemination, distribution or copying of this communication is prohibited /f you have received this electronic communication in error, please notify the sender by return e-mail and delete the original communication from your system. Thank you ............. Sue Homewood NC DENR Winston-Salem Regional Office Division of Water Quality 585 Waughtown Street Winston-Salem, NC 27107 Voice: (336) 771-5000 FAX: (336) 771-4630 bridgetocorp.pdf Content-Type: application/octet-stream Content-Encoding: base64 span.pdf Content-Type: application/octet-stream Content-Encoding: base64 3 of 3 10/30/2008 9:12 AM JAMESTOWN ENGINEERING GROUP, INC. CIVIL ENGINEERS & SURVEYORS LAND PLANNING • MUNICIPAI, CONSULTING /4Er in C. 117 Fast Main Street • P.O. Box 365 • Jamestown, N.C. 27282 Telephone (336) 886.5523 Fax (336) 886.5478 www jainestownenginecring.com September 17, 2008 Re: Piedmont Crossing - Lilliefield Subdivision Phase 2 City of High Point JEG Job No. 2004-068 USACE Raleigh Regulatory Field Office Attention: Andrew Williams 3331 Heritage Trade Drive, Suite 105 Wake Forest, NC 27587 Dear Mr. Williams: This letter is in reference to the recent pre-construction notification submitted by S&EC for the Piedmont Crossing project in High Point, NC. As you are aware, the plans for proposed culvert impact (S-3) have been changed back to an arch span. The proposed span will be a 36' x 10' Con-Span Bridge System (see attached plans). Piles will be driven down to bedrock, and a pile cap will be installed on the piles for the bridge foundation. The City of High Point has approved the 36' x 10' Con-Span Bridge System. During construction/installation of the crossing, necessary inspections will be made such that an engineering certification can be provided indicating that the bridge was installed in conformance with the plans provided by Contech Bridge Solutions, Inc. The duration of construction for the bridge shall be approximately 3 to 4 weeks without consideration of unfavorable weather conditions. Once construction is complete and the bridge has been certified, the City of High Point understands that it will accept the Public Right-of-Way, which includes the bridge, for ownership and maintenance. If there are any questions or concerns, please feel free to contact Don Franklin (City of High Point - Engineering Services) or myself. Yours very truly, JAMESTOWN ENGINEERING GROUP, INC. Ravindra Bissram, PE Cc: Don Franklin, Engineering Services, City of High Point, P.O. Box 230, 211 South Hamilton Street, High Point, NC 27261