HomeMy WebLinkAbout20010550 Ver 7_Email_20081006Re Construction issue on R-2809A (Wake Forest Bypass) Subject Re Construction issue on R-2809A (Wake Forest Bypass) From Rob Ridings <rob ridings@ncmail net> Date Mon, 06 Oct 2008 10 40 57 -0400 To "Murray, Christopher A" <cmurray@ncdot gov> Chris, This sounds like a good solution to me I'll support it -Rob Murray, Christopher A wrote Eric and Rob, o/ O 5?d A) C The Department is currently planning construction work at Stream Permit Site No 1 near 9+10 Lt -L- Construction at the site involves extension of a corrugated metal pipe structure only at the downstream pipe section A construction issue has come up at this site which is addressed below Issue Construction involves extension of a metal pipe structure and installation of 26 linear feet of rip rap on the streambank below the pipe structure A site investigation earlier this week revealed a small mass of rock and tree root which is serving as an unstable grade control feature approximately 5 to 10 linear feet downstream of the lower part of the pipe extension There is approximately a 1 5 to 2 0 foot change in elevation of the stream bed at the grade control structure We are concerned about the stability of the grade control feature, it will likely fail during installation of the pipe structure or installation of the 26 linear feet of rip rap below the pipe structure If it falls, the stream will headcut (due to the streambed elevation change) up to the pipe outlet The pipe will then be perched We propose to install the invert of the pipe structure based on the streambed elevation below the grade control feature We are aware that this is not the typical construction scenario However, it appears appropriate based on the existing on-site features Permitting This proposed construction scenario will not result in additional impacts to streams, wetlands or riparian buffers The attached drawing roughly depicts the existing scenario assessment and plan at the site Thanks Chris Murray Please let me know if you agree with our 1 of 2 10/6/2008 10 41 AM Re Construction issue on R-2809A (Wake Forest Bypass) P? ?i?,e? down 5tre q.,, took 1t,-4 oar p;pe S+(VtArrr ktte n "N Sk{e.?... De.?` caul rOA k j Q\ E-? a? S c r r•4 &t ? ?? r?Qt'?' ?[af ox J? d. 9..w S'lYC q..,. OA ?firea.. bMk, Q IAU ? P i') e- It) CA J? V 4- 2 of 2 .,\ snt-ll eV,,. 4 A Si f e- G,., ? Ir tic, 4'( 0 "'t 6 Q ? 0 tral cvAkt 0 ? eo i vrc- 10/6/2008 10 41 AM