Wanucha, Dave
From:Alsmeyer, Eric C CIV USARMY CESAW (US) <Eric.C.Alsmeyer@usace.army.mil>
Sent:Tuesday, June 27, 2017 11:38 AM
To:Slaughter, Johnathan H
Cc:Chambers, Marla J; Wanucha, Dave
Subject:RE: NC 18 Shoulder Failure Application; Alleghany County; AID SAW-2017-01297.
Attachments:NCDOT_NC18_PermaShield Wall_Alleghany_13-F.pdf; 2017NWP13.pdf
Heath: Attached to this message is your requested Section 404 permit authorization for the following project:
AID SAW-2017-01297, NCDOT, Project Number: 11.100311; NC 18 Shoulder Failure Application; Alleghany County;
In the future, when you expect to start construction on a project before the maximum 45-day review period will be up for a PCN,
please contact me before you submit the PCN, so we can coordinate with the resource agencies, and ensure that you will get the
required approval before you start work.
Also attached are the corresponding regional and general conditions, and a copy of the permit compliance certification. The
Wilmington District is committed to providing the highest level of support to the public. To help us ensure we continue to do so,
please complete the Customer Satisfaction Survey located at http://corpsmapu.usace.army.mil/cm_apex/f?p=136:4:0.
Please note that the general and special conditions must be strictly adhered to in order for this permit authorization to remain
valid and that the compliance certification must be returned to this office when the work is completed.
This electronic copy is your official Department of the Army authorization; no paper copy will be mailed.
Please reply or call if you have any questions or if I may serve you in any other way.
Eric Alsmeyer
Project Manager
Regulatory Division Office
US Army Corps of Engineers, Wilmington District
3331 Heritage Trade Drive, Suite 105, Wake Forest, NC 27587
Tel: (919) 554-4884, x23
Fax: (919) 562-0421
Regulatory Homepage:
http://www.saw.usace.army.mil/Missions/RegulatoryPermitProgram.aspx (If you need information that is not yet available on
our new website, please let me
know)
-----Original Message-----
From: Slaughter, Johnathan H \[mailto:hslaughter@ncdot.gov\]
Sent: Thursday, June 15, 2017 3:12 PM
To: Alsmeyer, Eric C CIV USARMY CESAW (US) <Eric.C.Alsmeyer@usace.army.mil>; Carpenter,Kristi
<kristilynn.carpenter@ncdenr.gov>; Wanucha, Dave <dave.wanucha@ncdenr.gov>; Chambers, Marla J
<marla.chambers@ncwildlife.org>
Cc: Joyce, Jason F <jjoyce@ncdot.gov>; Church, James W <jwchurch1@ncdot.gov>; Souther, Zachary S <zssouther@ncdot.gov>
Subject: \[Non-DoD Source\] NC 18 Shoulder Failure Application
Eric/Dave,
1
Please see attached permit application. We have an out-of-state specialized contractor lined up for this work. He will be in our
area to start on 6/23/17 as I understand it. As a result, this may be an after-the-fact permit depending on when you issue it. No
tree cutting is expected. Call if you have questions.
________________________________
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
2