HomeMy WebLinkAbout20141169 All Versions_Email_20080522 Re: R-2514: Prep for 5/22/08 Mtgs
Subject: Re: R-2514: Prep for 5/22/08 Mtgs
From: Mark Pierce <mspierce@dot.state.nc.us>
Date: Wed, 23 Apr 2008 10:48:19 -0400
To: David Wainwright <David.Wainwright@ncmail.net>
David,
Would you be willing to summarize your management of this work and either you or Matt Smith
(Environmental Services, Inc.) describe the results during our CP2A Meeting on 5/22/08 ? I have
included copies of the 10/3/07 ESI Report including your 9/14/07 letter to ESI in the CP2A (northern
portion of project) Meeting Packet. Please let me know how you want this presented during our
meeting.
Thanks,
Mark
733-7844 x214
David Wainwright wrote:
Mark,
I don't object to putting something together. Do you have anything
specific in mind?
David Wainwright
NCDENR, Division of Water Quality
Transportation Permitting Unit
Raleigh, NC
David.wainwright@ncmail.net
919-715-3415
Mark Pierce wrote:
> *William and David,*
> I am writing to coordinate and prepare for our CP2 Revisited Meeting
> and our CP2A (Northern Portion) Meeting on 5/22/08 for R-2514 (US 17 -
> Belgrade to New Bern). USACE, DWQ, NCDOT, Wilbur Smith Associates,
> and Environmental Services, Inc. have addressed the action items from
> our previous concurrence meetings conducted in 2007. I would request
> that each of us present a summary and response to those action items
> to the Merger Process Team during our 5/22/08 concurrence meetings.
> Please review the following action items and let me know whether you
> would be willing to lead the discussion of these topics with the
> Merger Process Team. Also, please let me know if you have other
1 of 2 4/23/2008 10:47 AM
Re: R-2514: Prep for 5/22/08 Mtgs
> topics and suggestions for our meetings.
> -William Wescott (USACE):_
> * What is the current status of the Byrd Landfill Disposal Site
> Violation ? You mentioned that the Byrd Landfill Site could be
> evaluated in its pre-violation condition. Would you be willing to
> share these topics with the Merger Process Team during our 5/22/08
> concurrence meeting ?
> * You and ESI reverified the jurisdictional areas for the
> entire project. You mentioned that the bridge lengths were not
> changed due to the reverification of jurisdictional areas. Would you
> be willing to share these topics with the Merger Process Team during
> our 5/22/08 concurrence meeting ?
> -David Wainwright (DWQ):_
> * You and ESI prepared the Neuse River Basin Buffer Impacts
> assessment and documentation. Would you be willing to present a
> summary of the assessment to the Merger Process Team during our
> 5/22/08 concurrence meeting ?
> Thanks,
> Mark
> (919) 733-7844 x214
2 of 2 4/23/2008 10:47 AM