Wrenn, Brian L
From:Williams, Andrew E SAW <Andrew.E.Williams2@usace.army.mil>
Sent:Wednesday, October 12, 2016 2:31 PM
To:Wrenn, Brian L; Dilday, Jason L
Cc:Matthew Cook
Subject:RE: R2536_ENV_SEC01 - Channel Stabilization
Jason,
I concur with Brian. Our concern was with the vegetation being established on the banks, not in the channel. We don't
want the contractor to release water into a channel and then have erosive flows destabilize the banks, etc.
Andrew Williams
Regulatory Project Manager
US Army Corps of Engineers
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
919-554-4884 ex. 26
-----Original Message-----
From: Wrenn, Brian L \[mailto:brian.wrenn@ncdenr.gov\]
Sent: Wednesday, October 12, 2016 9:43 AM
To: Dilday, Jason L <jldilday@ncdot.gov>; Williams, Andrew E SAW <Andrew.E.Williams2@usace.army.mil>
Cc: Matthew Cook <mcook@rkk.com>
Subject: \[EXTERNAL\] RE: R2536_ENV_SEC01 - Channel Stabilization
Jason,
Andy and I were out on site 9/28 and the vegetation looked very similar to the photos Matt provided from 10/10.
During our site visit, Andy and I both indicated that we would prefer a little more vegetation established prior to turning
water into the channel. Frankly, I'm surprised that more vegetation has not been established since our site visit. It
clearly isn't a lack of water. We told Erin Hager and Ed Dunn that once vegetation started coming up along the lower
section of the channel, we would likely approve turning the stream into the channel. We also said we would accept
photos of the area rather than scheduling another site visit. I understand Matt's concerns, but I'd still prefer to see
vegetation at least beginning to peek through the matting consistently along that lower section.
On another topic at R-2536, we had requested some records and photos from Erin Hager based off of our 9/28 visit. We
still haven't received all of those. I know that they have probably been cleaning up from Matthew, but I would still like
to see the requested information.
Thanks,
Brian Wrenn
1
919-707-8792 (office)
919-710-6516 (mobile)
From: Dilday, Jason L
Sent: Wednesday, October 12, 2016 7:26 AM
To: Wrenn, Brian L <brian.wrenn@ncdenr.gov>; 'andrew.e.williams2@usace.army.mil'
<andrew.e.williams2@usace.army.mil>
Subject: FW: R2536_ENV_SEC01 - Channel Stabilization
Brian and Andy,
Below is an email I received from the design build team for the Asheboro Bypass concerning a stream relocation. They
are having some problem with establishing grass on a section of the relocation. Because of the stipulation in their
contract that the consultants cannot directly contact agency members, I had Matt Cook summarize below what the
problem was. Please let me know what you think.
Jason
From: Matthew Cook \[mailto:mcook@rkk.com\]
Sent: Tuesday, October 11, 2016 3:52 PM
To: Dilday, Jason L <jldilday@ncdot.gov <mailto:jldilday@ncdot.gov> >
Cc: Michael Prince <mprince@wbcci.com <mailto:mprince@wbcci.com> >; Tina Swiezy <tswiezy@rkk.com
<mailto:tswiezy@rkk.com> >; Mike Merritt <mmerritt@rkk.com <mailto:mmerritt@rkk.com> >; Jim Eisenhardt
<jeisenhardt@rkk.com <mailto:jeisenhardt@rkk.com> >; Jeff Meador <jmeador@rkk.com <mailto:jmeador@rkk.com>
>; Blakley, Reuben <rblakley@ncdot.gov <mailto:rblakley@ncdot.gov> >
Subject: R2536_ENV_SEC01 - Channel Stabilization
Jason
We have a location on the Asheboro Bypass where we are having issues establishing a grass lined channel. It is -L- 66+00
- 71+00 RT. This is the outlet of RCBC 100. It is a large channel relocation with overbanks. Currently no water has been
released in to it so that the liner can be established.
The contractor finished construction of this channel over a month ago. This is shown in the attached pdf 026-
R2536_EC_psh08A.pdf, the first phase of the RCBC construction sequence. Our plan was to sod the bottom and low
flow banks so that it would stabilize quickly. This would then allow us to release water through it. DWR advised against
this because fescue sod is not considered a native seed. So, the contractor seeded the area. Prior to Hurricane
2
Matthew, they had seeded it three times in the last five weeks. They also had their seeding contractor on site yesterday
to see what additionally they could do. From the attached pictures, you can see that the seed in some locations has
taken root and is becoming established, especially at the pic taken closest to the proposed RCBC outlet. IMG_3.pdf was
taken near the outlet of the proposed RCBC facing upstream, IMG_2.pdf was taken half way down the channel facing
upstream, and IMG_1.pdf was taken where the channel ties in to the existing stream facing upstream. In order to move
to phase 2 (attached 027-R2536_EC_psh08B.pdf), the channel needs to be stabilized. The contractor has even been
using the water truck to try to water the area when it hasn't rained. The pics attached were taken October 10 which is
about 24 hours after they had just received 4" of rain from Hurricane Matthew. The site is holding up well.
There is some grass established. The standing water near the stream tie in is due to the erosion control device there
keeping it from leaving the site. Also, this area is more shaded than the areas near the proposed RCBC outlet. If we are
allowed to release water through the channel, this would essentially remove almost 1200' of meandering jurisdictional
stream through the site and place it in a stable plastic lined channel. The RCBC construction could then begin.
My question is how much grass is needed to be considered stable? The bottom of the channel currently is not erodible
material since it has been lined with coir fiber matting. Also, jurisdictional streams do not generally exhibit grass in the
flow line. While we realize the necessity to not allow sediment to leave the site, once water is released through this
channel the grass will probably die off due to the constant presence of water. I am asking this because we want to do
what is right, but we don't want to wait another month to establish grass that is going to die when the water is released.
Are we primarily waiting for grass to become established on the overbanks?
Please feel free to forward this to Brian Wrenn and Andy Williams. We would like to have their input as well. We are
also having our monthly ride through next Tuesday, October 18 and would like them to come. Any guidance you can
provide would be welcomed. Thanks.
___________________________________
Matthew L. Cook, P.E.
Project Manager
RK&K
900 Ridgefield Dr., Suite 350
Raleigh, NC 27609
919.878.9560 P | 919.653.7350 D
Blockedwww.rkk.com <Blockedhttp://www.rkk.com>
3
<Blockedhttps://www.facebook.com/rkkengineers?ref=br_tf> <Blockedhttps://twitter.com/rkk_social>
<Blockedhttp://www.linkedin.com/company/rk&k-engineers-llp?trk=prof-following-company-logo>
<Blockedhttp://www.youtube.com/c/Rkksocial>
RESPONSIVE PEOPLE | CREATIVE SOLUTIONS
"RK&K" and "RK&K Engineers" are registered trade names of Rummel, Klepper & Kahl, LLP, a Maryland limited liability
partnership. This message contains confidential information intended only for the person or persons named above. If
you have received this message in error, please immediately notify the sender by return email and delete the message.
Thank you.
________________________________
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third
parties.
4