I visited the Skeet Club Road project (U-3615B) yesterday. At the time of my visit the dual pipes permitted for
installation under Johnson St. had been installed and stream flow returned to the pipes. Sediment and erosion control
devices are to be installed today and the area temporarily seeded early next week. Rip rap stabilization of the upstream
and downstream banks, headwall construction, and channel relocation downstream of the pipes will be started in the
next few weeks. Completion of these items will require further dewatering of the work area with the stream being
pumped around to a point downstream of the work area.
I did a little digging regarding the power pole foundations recently installed on either side of Johnson St. DOT applied
for and received a buffer impact authorization in March 2016. The following links provide electronic copies of the
application and the approval letter for the utility impacts. If you have any further questions, please do not hesitate to
contact me. Thanks.