Loading...
HomeMy WebLinkAbout20160110 Ver 3_401 Application_20161017 Carpenter,Kristi From:Murray, Christopher A Sent:Monday, October 17, 2016 11:19 AM To:Alsmeyer, Eric C SAW; Ridings, Rob; Monte.K.Matthews@usace.army.mil Cc:Carpenter,Kristi; Hinnant, Chadwick D; Jordan, David A; Harper, Aaron A Subject:RE: NCDOT Division 5 permit application for widening of Rogers Road (SR 2052) and replacement of Bridge No. 910132 over Smith Creek in Wake Forest, Wake County; TIP/WBS: 17BP.5.R.47 Attachments:SF910132 REVISED FINAL #2 Permit Drawings BUFFER Oct 13 2016.pdf; SF910132 REVISED FINAL #2 Permit Drawings Oct 13 2016.pdf Follow Up Flag:Follow up Flag Status:Completed Reference: NCDENR-DWR Project Number: 20160110 (Issued on March 4, 2016; Version 2 issued on June 22, 2016) USACE Action ID: Not Known (Action ID: SAW-2016-00701 issued on June 23, 2016) Eric, Monte and Rob, The Department is applying for a permit modification for this project due to the following: A) Anticipated additional jurisdictional impacts that are necessary to properly stabilize and complete the project and B) To address additional recent unpermitted jurisdictional impacts recently conducted by the contractor for this project (note: these have all been reported to the USACE and NCDENR-DWR). These issues are addressed below: ISSUE # 1 -The contractor for the project conducted land disturbing activities in the riparian buffer at the Smith-Austin Mitigation Site near 21+00 Lt. This site is characterized as a former NCDEQ Division of Mitigation Services (DMS) compensatory mitigation site currently managed by the DEQ Land and Aquatic Resources Stewardship Program. This action resulted in an additional 508.4 square feet of BZ 1 impacts and an additional 276.4 square feet of BZ 2 impact. The Department has recently agreed to conduct a reforestation plan proposed by DEQ personnel. See below image: 1 ISSUE # 2 -Off-site stormwater runoff from adjacent properties near 15+00 to 20+00 Rt has resulted in destabilization of the bridge embankment along the west streambank. A review of the area indicates recent removal of a stormwater pond by others (that used to provide some storage of runoff) and installation of a greenway that is diverting and concentrating runoff to our project. The Design Build hydro engineers have evaluated the area and are proposing to collect stormwater runoff into a rip rap lined base ditch from near 19+07 to 20+97 Rt. Note that this ditch is in the same location of an old drainage swale that existed on-site recently until the above-mentioned removal of the stormwater pond by others. This proposed rip rap lined base ditch has a larger cross sectional footprint than the previously permitted rip rap lined ditch and will thus require a larger opening along the west streambank. The Department proposes to install additional Class II rip rap bank stabilization at this location. This action will result in an additional 666.3 square feet of BZ 1 impacts, an additional 803.2 square feet of BZ 2 impact and 22 linear feet of permanent streambank impact due to installation of Class II rip rap. Note that Class II rip rap bank stabilization on west bank is located within footprint of previously permitted Class II rip rap bank stabilization on east streambank. See below images: 2 ri 3 ISSUE # 3 -The contractor for the project installed Class II rip rap bank stabilization along the west streambank under the bridge deck. Note that this activity was not depicted on the plans or most recent permit drawing. This action will result in an additional 85 linear feet of permanent streambank impact due to installation of Class II rip rap. Note that Class II rip rap bank stabilization on west bank is located within footprint of previously permitted Class II rip rap bank stabilization on east streambank. See below image: 4 ISSUE # 4 -Stormwater runoff from adjacent development has resulted in displacement of previously installed Class I rip rap outlet protection at the outlet of a 42 inch pipe structure at 27+80 Lt. The Design Build hydro engineers have evaluated the area and are proposing additional Class II rip rap at the tail end of this ditch and tie this rip rap on the streambanks of the directly adjacent jurisdictional stream. This action will result in an additional 18 linear feet of permanent streambank impact due to installation of Class II rip rap bank stabilization and a reduction of 7 linear feet of temporary stream impact (associated with culvert construction impact). See below image: 5 riorip ISSUE # 5 -Stormwater runoff from adjacent development has resulted in displacement of previously installed Class II rip rap installed on the streambank at the outlet of a 42 inch pipe structure at 28+21 Rt. The Design Build hydro engineers have evaluated the area and are proposing to install a rip rap dissipator basin (i.e. outlet channel improvements) within the streambed and banks of this jurisdictional stream. This action will result in an additional 4 linear feet of permanent stream impact and a reduction of 4 linear feet of temporary stream impact. See below image: 6 Additional riparian buffer impact calculation by Design Build hydro engineers: -The Design Build hydro engineers re-evaluated riparian buffer impacts at the project and had determined a reduction of 5.5 sq feet of BZ 2 impact at Permit Site 1 (bridge) and an increase of 276.8 sq ft of BZ 2 impact at Permit Site 2 (Aluminum Box Culvert). Note that these impacts are described as allowable road crossing impacts. Please advise if you need additional information. Thanks, Chris Murray From: Murray, Christopher A Sent: Tuesday, June 21, 2016 5:05 PM To: Alsmeyer, Eric C SAW <Eric.C.Alsmeyer@usace.army.mil>; Ridings, Rob <rob.ridings@ncdenr.gov> Cc: Carpenter,Kristi <kristilynn.carpenter@ncdenr.gov>; 'Jeff.Moore@kimley-horn.com' <Jeff.Moore@kimley- horn.com>; Watson, Malcolm C <mcwatson@ncdot.gov>; matt.adams@blytheconstruction.com; Hinnant, Chadwick D <cdhinnant@ncdot.gov>; Jernigan, Dennis W <dwjernigan@ncdot.gov> 7 Subject: RE: NCDOT Division 5 permit application for widening of Rogers Road (SR 2052) and replacement of Bridge No. 910132 over Smith Creek in Wake Forest, Wake County; TIP/WBS: 17BP.5.R.47 Reference: NCDENR-DWR Project Number: 20160110 (Issued on March 4, 2016) USACE Action ID: Not Known (Permit not issued) Eric and Rob, The Department has been coordinating with the NCDEQ Division of Mitigation Services to reduce impacts to the adjacent mitigation site at this project. Michael Ellison (Director of the DMS) has earlier today provided approval of the required revisions. These revisions have resulted in some significant changes to the hydraulic design at Bridge 910132 near Stations 20+00 to 24+00 Lt/Rt. The attached file: Bridge 910132 and Rogers Road (SR 2052) Drainage Revision Narrative provides a comprehensive review of these hydraulic design revisions. Note also attached REVISED FINAL stream and riparian buffer permit drawing package for the entire project. It appears that there is no increase to jurisdictional impacts previously noted for the project in the February 4, 2016 permit application. Please contact me if you need additional information. Thanks, Chris Murray From: Murray, Christopher A Sent: Monday, April 25, 2016 9:59 AM To: Alsmeyer, Eric C SAW <Eric.C.Alsmeyer@usace.army.mil>; Ridings, Rob <rob.ridings@ncdenr.gov> Cc: Carpenter,Kristi <kristilynn.carpenter@ncdenr.gov> Subject: RE: NCDOT Division 5 permit application for widening of Rogers Road (SR 2052) and replacement of Bridge No. 910132 over Smith Creek in Wake Forest, Wake County; TIP/WBS: 17BP.5.R.47 Reference: NCDENR-DWR Project Number: 20160110 (Issued on March 4, 2016) Eric and Rob, The Department applied for a permit for this project on February 4, 2016. The NCDENR-DWR issued certifications for the project on March 4, 2016. Two construction issues have come up at this time. Note the following: Issue at Site 1 (Bridge near 21+00 -L-) A portion of the project limits at the bridge is located within the Smith Austin Creek Mitigation Site and this use requires coordination with the North Carolina Interagency Review Team. An existing rock cross vane installed as part of the mitigation site is located directly at the outlet of proposed standard v ditches upstream of the bridge. The Department proposes “field-set and integrate” the ditches to the existing rock cross vane. Specifically, the ditches will be shifted as necessary to be slightly upstream of the top of the rock cross vane to provide at least 2 feet of separation between the low point of the proposed ditches and the top of the rock cross vane. This solution will integrate the proposed ditches and rock vane together, creating the most stable long-term solution. This information is depicted below: 8 l Issue at Site 2 (Single-barrel culvert near 27+25 -L-) The fill on the right shoulder of the road (downstream side of the culvert) exceeds the maximum allowable of 5.0 feet for the aluminum box culvert per AASHTO specifications. We were under the understanding this 5.0’ max cover applied under the roadway, but according to Pomona Pipes (delegate designer of the culvert) it also applies on the shoulder. As currently designed there is approximately 5.7’ of fill at the right shoulder point. To reduce the fill, we are proposing to raise the downstream invert 1 foot to the natural channel bed elevation. The invert at the outlet will be set to match the adjacent downstream elevation. A mix of Class B and Class I rip rap will be installed in the a slight blow hole (i.e. countersunk) in the streambed below the outlet. The upstream invert would remain buried 1 foot and a one foot sill would be placed at the upstream face (slightly inset inside the culvert). A mix of Class B and Class I rip rap will be installed in the streambed (i.e. countersunk) up to the top of sill. The countersunk rip rap in the streambed at the inlet and outlet of the culvert is fully within the previously permitted stream improvements. 9 This proposed revision is depicted on the Culvert Survey Report: 10 Revised stream and riparian buffer permit drawings that depict these changes are attached to this email. Please advise if you need additional information regarding this permit application. Thanks, Chris Murray 11 From: Murray, Christopher A Sent: Thursday, February 04, 2016 9:36 AM To: Alsmeyer, Eric C SAW; Ridings, Rob Cc: Carpenter,Kristi Subject: NCDOT Division 5 permit application for widening of Rogers Road (SR 2052) and replacement of Bridge No. 910132 over Smith Creek in Wake Forest, Wake County; TIP/WBS: 17BP.5.R.47 Eric and Rob, NCDOT Division 5 proposes to widen Rogers Road (SR 2052) and replace Bridge No. 910132 over Smith Creek in Wake Forest, Wake County . The following information is attached as part of this permit application: -Signed and scanned copy of PCN form -In-lieu fee mitigation acceptance letter -FINAL Stream Permit Drawing Package -FINAL Riparian Buffer Permit Drawing Package Please contact me if you need additional information. Thanks, Chris Murray Christopher A. Murray, PWS Division Environmental Supervisor Division 5 (919) 220-4633 office cmurray@ncdot.gov NCDOT-Division 5 2612 N. Duke Street Courier: 17-27-03 Durham, NC 27704 Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties. 12 ESi�]Opi�ONS.E�$1�10 SY�GF SEE p�EidiLN ], SxE(ETT i-Bn F PCiLAS5�Pi�PBAAcu[5i i0 T�N� 5SEE OEtn4iL B, SAEE1 1-8 1 SY5 1 SEE N�E ipOn 3.�uEE i5 zSB LGFo ER<L 'V' OrtLH N/ LI.<55 'B' RiP 1 TONS, EST i5 Sv Gf� DECTL>iLSS4, qSUEEip2-6pu L ESiT]CS7a Cf0ip2 iOHSEI B' IP R<P � �� _ �,u-.. � ., �,. / ' .�i PE�aN EXl9 /�.tiR CROSS ✓bVf N iMEGRATE P/A.VOSEO 0/!Cn£5 .4N0 Si i Sr GF ' Eu&WR�ENT PFViECT/ON wi CRO55 vavE �d�� ,�+' W/ YIXIVRE OF CL0.55 B A40 CLASS lRR � pip qp EST 2 T0.45 CC B AN.EST 2 i0M5 CL l RR ExGIxEER i0 FiElD vEFffr iHSTaLL�IKN � p�����'�. \ � "'� ' /F' 1 \ / _ '- � uco�na �"5'i \� �-__ _ _ �— ; �F — � . � / 7.-�.: ..', "'C �/ �i ��.-. �F' '�.' -�\ . : . . �� i I �:Ir�� � � I j - � I tYiSIING �t � V. C.nsrnva zw9zw . �r� � � � � p.rr a�rm,n so ec ackweo i I ��uk ;r �i. _.. I . .�� �..i.. ,.um . - r 9 � - - � NOR AL W 5 EL 22] �—� � _���.��_:�1.� �, .I ::, . nDAunt i� �t I i I._T.(_�_ L—___�_—_ �. �.IOP OF B/Jlrc rPIG4ry- rOPIOF BM'K l(EFTI J- : vY� —I �.- — T 'I _ _ :�'I.`. i TOX �O! p{ {GYq��J 5 ��,•• � I � I MIY �F .L55 5 NiD CSq� $5� ! P i _ � ( f�-N SJ.F 1 6 IXhVN$T IN.iTqC I �ILL 42 n1� �lL >� -GAM � �. .. ' � f Y ✓E/ iT��d F1 ,� L ii - .m.e.�m i seo�n.�.�n�a�een,,,�ean�� -nn �� msmn �-�� + aun'e„aowo.��e.meie.�� n � m ��nsam�m.mn.�me �.L gpp¢mvlsa�lFe g A Ibtlelwalen Inslall � J� mk�pmpnllewf Ishmmup�eb � Icr1 �rymvertof 1 rt 1-1� � J�A F _ loalbelow t b G I .. I ��I � Y NY ! II '] .. . •..no�.�e � n r � ni . + . . emg�..ae ro i n � �ii +i � �j ti-•�,— � e+��_ ,_ - ..�k v s n.i�� � < m.a� eaamsn ll`� �� I� �l� i (�9. 15.' �'Ac„a/"�tP� �.. Ka .� � W mq n _ o1Rie�EEK . � � � � i �„ _ ��E�T� � ��sr . �, �1 i !I � I ' i u sa s ss � 9 r� �i � � i �►' I - n,; g+oo� �'�� i'�i 1 i,� ���i r` � f. � `�` �.�,�,�`a�'�:..�, z�.� � �,� ,��� a, , ,� i�e3"a � s _ ..,— � � `l� -�i r��.. '� i �� � a� � 7 � i � ,,.. �� r��� n �,_4F� e� ,, � ��' r��� ��. I4� �B bufferimpac5at SmitM1-Austin Mitigetion Site 111 �" __ � — — f ``o n C Adtli[ional Class 11 rip rap bank s[abihza[ion on wes[ bank associated with constmction of np rap ,. linetl base tlrtch Additional Class II rip rap bank stabilization on west bank associated with contractor mistake. � �� N �.� � ce i =��:..` � � _________. \ �.', � JMHW/ - � �T '� �� 9 >\ J� �-- �i5^; � � � _ gcP� � � ,� � 8 TB� �;; � ,"fr �,❑ wiM REMOVE/REPLACE CB �nE ro Exisrin�c ie• / Additional Class II rip rap bank stabilization at tail end of ditch. � % i . ........� � �� �— _ _"�`�`-_ — _ �,..�E�,.._c CB -�TO MH 36' 36' Sv5T5M H(['-I ���� � RETo� 3'n'�� � RCMOVC ANC R�=PL�CC �ETd� � 1 i J� u9/ T0�6 VU M�Ir� �w��Eli� /. � � \ � �, � � �� � � ��_ � � � �„ ✓„ ,C }� :l � �� n - - � � � �� � ,� � �' � • � I , -..... � � I /� ...� _-_ P-iv 2D+00 � \ \ �\ �1 � iii`R ` �� � O - � .� i � �� _- ,- � � �R ,'r � � 1 � ��� �� ❑O � I��db se�d[��M1 � �'3`"�"" ��� �� l� :��� � �� �v�l.r� �`,-�n . �'. ,..���� t. � �� � � - _ _ _ �l i , . n - - a . ` �'>c- � � 4�� � . :: � _ ' �� � � ��� � E /�/ � � �� / A Atldi[ional Qass II rip rap . u Mn bank stabilization on west � � � _ � bankassociatedwith �� � contrac[or mis[ake. _ �� �l' - — �I i � � � I CB N ��� ilk'�"�.\��// .._ .� W ., �.%d\ �?�VI.�C�`t'-�'- ,,_ _ _ ; `/��/ �,1 REMOVE BUNp JB, / / IO'FCP,dN� FES / Cl:u[ Ins[all rip rap tlissipator � e�*c 'u'n � baslrt 6's�sT[�n a[r<m � e[�aov[ nrvc a_r-_nu .��..n a� � i_.�o ni ia..o wi , i —� �I a ;� \ _ : ��.. �.c � �, � � �1 flAP V � / /� � � @ �-- ClIOrv ��� / I -. �� �\ � . , ,,i�, _ � �_ ���