From:Bailey, David E SAW <David.E.Bailey2@usace.army.mil>
Sent:Friday, July 01, 2016 9:30 AM
To:Elliott, Jason C; Wrenn, Brian L; Parker, Jerry A; Hayes, Meredith D
Subject:RE: U-3615B Skeet Club Road Stream
Thanks for the pictures and status update.
-Dave Bailey
---
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Phone: (919) 554-4884, Ext. 30.
Fax: (919) 562-0421
Email: David.E.Bailey2@usace.army.mil
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we
continue to do so, please complete the Customer Satisfaction Survey located at
http://corpsmapu.usace.army.mil/cm_apex/f?p=136:4:0.
-----Original Message-----
From: Elliott, Jason C \[mailto:jelliott@ncdot.gov\]
Sent: Friday, July 01, 2016 8:19 AM
To: Wrenn, Brian L <brian.wrenn@ncdenr.gov>; Parker, Jerry A <jparker@ncdot.gov>; Bailey, David E SAW
<David.E.Bailey2@usace.army.mil>; Hayes, Meredith D <mdhayes3@ncdot.gov>
Cc: Elliott, Jason C <jelliott@ncdot.gov>
Subject: \[EXTERNAL\] U-3615B Skeet Club Road Stream
Good morning all,
Per our discussion at the stream relocation for Skeet Club on Wednesday, I'm sending you all some brief minutes of
what we discussed. Brian/Jerry if there's anything I've missed let me know.
* We walked the entire stream relocation. As of Wednesday the contractor had completed all of the proposed
relocation with the exception of the tie-in's at each end of the project. The project was built entirely in the dry and the
purpose for our review was to ensure that the agencies were satisfied that DOT could turn water into the new stream
and begin back filling the old channel.
* Brian Wrenn with NCDWR agreed that DOT had constructed a stable channel (with seeding & mulching completed
and coir fiber matting installed on the banks throughout) and that water could be turned into the new channel. He
requested that DOT install silt fence around the pipe crossing (both up and downstream) and install silt fence as needed
along the upper reach to protect the new channel from the work zone. We also discussed installed SF as needed around
the waste pile. Seeding and mulching was completed along both the upper and lower reaches on the terrace as of
Wednesday afternoon.
1
* I revisited the site yesterday and the tie-in is complete and stable. I've included photos of water in the new
channel per Brian's request. I'm hoping we get rain this weekend which will increase the flow and assist with vegetation
establishment. The site will need to have live staking and reforestation scheduled to be completed this winter prior to
DOT beginning the monitoring requirements. Monitoring at this site consists of vegetation monitoring and photo
documentation of channel stability.
Please let me know if you have any additional info that I may have missed. Thanks and I hope you all have a good
holiday weekend.
Jason C. Elliott
PDEA - Natural Environment Section
Natural Environment Engineering Group
NC Department of Transportation
1598 Mail Service Center
Raleigh, NC 27699-1598
Phone: 919-707-6114
Fax: 919-212-5785
________________________________
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third
parties.
2