r
Michael F. Easley, Governor
William G. Ross Jr., Secretary
North Carolina Department of Environment and Natural Resources
Coleen H. Sullins, Director
Division of Water Quality
April 18, 2008
DWQ EXP No. 08-0187v2
Warren County
ITAC 242 LLC
Attn: Mr. Jeff Stallings
11417 West Finch Ave.
Middlesex, NC 27557
Subject Property: Lake Gaston Pit Stop
UT to Lake Gaston [030207, 23-(12) WS-V, 13]
Approval of 401 Water Quality Certification with Additional Conditions - Express Review Program
Dear Mr. Stallings:
You have our approval, in accordance with the attached conditions and those listed below, to place fill
within or otherwise impact 70 linear feet of perennial stream for the purpose of extending the culvert for
road widening on Highway 903 in order to access the proposed gas station at the subject property, as
described within your application dated April 8, 2008 and received by the N.C. Division of Water Quality
(DWQ) on April 15, 2008. After reviewing your application, we have decided that the impacts are
covered by General Water Quality Certification Number(s) 3704 (GC3704). The Certification(s) allows
you to use Nationwide Permit(s) 14 when issued by the US Army Corps of Engineers (USACE). In
addition, you should obtain or otherwise comply with any other required federal, state or local permits
before you go ahead with your project including (but not limited to) Erosion and Sediment Control, and
Non-discharge regulations. Also, this approval to proceed with your proposed impacts or to conduct
impacts to waters as depicted in your application shall expire upon expiration of the 404 or CAMA
Permit.
This approval is for the purpose and design that you described in your application. If you change your
project, you must notify us and you may be required to send us a new application. If the property is sold,
the new owner must be given a copy of this Certification and approval letter and is thereby responsible for
complying with all conditions. If total fills for this project (now or in the future) exceed one acre of
wetland or 150 linear feet of stream, compensatory mitigation may be required as described in 15A
NCAC 2H.0506 (h). This approval requires you to follow the conditions listed in the attached
certification and any additional conditions listed below.
401 Oversight/Express Review Permitting Unit
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
2321 Crabtree Boulevard, Suite 250, Raleigh, North Carolina 27604
Phone: 919-733-1786 / FAX 919-733-6893 / Internet: http://li2o.enr. state. nc. us/ncwetlands
One
N Carolina
Jl naturally
An Equal Opportunity/Affirmative Action Employer - 50% Recycled/ 10% Post Consumer Paper
Lake Gaston Pit Stop
EXP 08-0187v2
Page 2 of 4
April 18, 2008
The Additional Conditions of the Certification are:
Impacts Approved
The following impacts are hereby approved as long as all of the other specific and general
conditions of this Certification (and Isolated Wetland Permit) are met. No other impacts are
approved including incidental impacts:
Impact Type Amount Approved
nits Plan Location or Reference
Stream (perennial) 70 (linear feet) Aril 8, 2008 PCN page 8 of 12
2. Erosion & Sediment Control Practices
Erosion and sediment control practices must be in full compliance with all specifications
governing the proper design, installation and operation and maintenance of such Best
Management Practices in order to protect surface waters standards:
a. The erosion and sediment control measures for the project must be designed, installed,
operated, and maintained in accordance with the most recent version of the North Carolina
Sediment and Erosion Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion control
measures must be such that they equal, or exceed, the requirements specified in the most
recent version of the North Carolina Sediment and Erosion Control Manual. The devices
shall be maintained on all construction sites, borrow sites, and waste pile (spoil) projects,
including contractor-owned or leased borrow pits associated with the project.
c. For borrow pit sites, the erosion and sediment control measures must be designed, installed,
operated, and maintained in accordance with the most recent version of the North Carolina
Surface Mining Manual.
d. The reclamation measures and implementation must comply with the reclamation in
accordance with the requirements of the Sedimentation Pollution Control Act.
No Waste, Spoil, Solids, or Fill of Any Kind
No waste, spoil, solids, or fill of any kind shall occur in wetlands, waters, or riparian areas beyond
the footprint of the impacts depicted in the Pre-Construction Notification. All construction
activities, including the design, installation, operation, and maintenance of sediment and erosion
control Best Management Practices, shall be performed so that no violations of state water quality
standards, statutes, or rules occur.
4. No Sediment & Erosion Control Measures w/n Wetlands or Waters
Sediment and erosion control measures shall not be placed in wetlands or waters to the maximum
extent practicable. If placement of sediment and erosion control devices in wetlands and waters
is unavoidable, they shall be removed and the natural grade restored within six months of the date
that the Division of Land Resources has released the project.
5. Stream Protection Conditions
If concrete is used during the construction, a dry work area should be maintained to prevent direct
contact between curing concrete and stream water. Water that inadvertently contacts uncured
concrete should not be discharged to surface waters due to the potential for elevated pH and
possible aquatic life and fish kills.
During the construction of the project, no staging of equipment of any kind is permitted in waters
of the U.S., or protected riparian buffers.
Lake Gaston Pit Stop
EXP 08-0187v2
Page 3 of 4
April 18, 2008
6. Protective Fencing
The outside buffer, wetland or water boundary and along the construction corridor within these
boundaries approved under this authorization shall be clearly marked with orange warning fencing
(or similar high visibility material) for the areas that have been approved to infringe within the
buffer, wetland or water prior to any land disturbing activities to ensure compliance with GC 3704.
7. Construction Conditions
A copy of this Water Quality Certification shall be posted on the construction site at all times. In
addition, the Water Quality Certification and all subsequent modifications, if any, shall be
maintained with the Division Engineer and the on-site project manager.
The outside buffer, wetland or water boundary located within the construction corridor approved
by this authorization shall be clearly marked by highly visible fencing prior to any land disturbing
activities. Impacts to areas within the fencing are prohibited unless otherwise authorized by this
certification.
Stormwater Management Plan
The final, written stormwater management plans submitted with your PCN form and received by
the NC Division of Water Quality on April 15, 2008 with revisions received on April 18, 2008,
must be implemented. All stormwater management facilities must be constructed and operational
before any permanent building is occupied at the Lake Gaston Pit Stop. The structural stormwater
practices as approved by this Office as well as the drainage patterns must be maintained in
perpetuity. No changes to the structural stormwater practices shall be made without written
authorization from the Division of Water Quality.
The Operation & Maintenance (O&M) agreement for the proposed bioretention basin signed by
the current landowner on April 8, 2008 must transfer with the sale of the land or transfer of
responsibility for the stormwater facilities. DWQ must be notified promptly of every transfer.
9. Certificate of Completion
Upon completion of all work approved within the 401 Water Quality Certification or applicable
Buffer Rules, and any subsequent modifications, the applicant is required to return the attached
certificate of completion to the 401 Oversight/Express Review Permitting Unit, North Carolina
Division of Water Quality, 1650 Mail Service Center, Raleigh, NC, 27699-1650.
10. Notification of Construction
The applicant and/or authorized agent shall contact the DWQ Express Review Program in writing
at the letterhead address within ten (10) days of the commencement of construction.
16. The applicant/permittee and their authorized agents shall conduct all activities in a manner consistent
with State water quality standards (including any requirements resulting from compliance with
§303(d) of the Clean Water Act), and any other appropriate requirements of State and Federal Law.
If the Division determines that such standards or laws are not being met,-including failure to sustain a
designated or achieved use, or that State or Federal law is being violated, or that further conditions are
necessary to assure compliance, then the Division may reevaluate and modify this General Water
Quality Certification.
Violations of any condition herein set forth may result in revocation of this Certification and may result in
criminal and/or civil penalties. The authorization to proceed with your proposed impacts or to conduct
impacts to waters as depicted in your application and as authorized by this Certification, shall expire upon
expiration of the 404 or CAMA Permit.
Lake Gaston Pit Stop
EXP 08-0187v2
Page 4 of 4
April 18, 2008
If you do not accept any of the conditions of this Certification (associated with the approved wetland or
stream impacts), you may ask for an adjudicatory hearing. You must act within 60 days of the date that
you receive this letter. To ask for a hearing, send a written petition, which conforms to Chapter 150B of
the North Carolina General Statutes to the Office of Administrative Hearings, 6714 Mail Service Center,
Raleigh, N.C. 27699-6714. This certification and its conditions are final and binding unless you ask for a
hearing.
Any disputes over determinations regarding this Authorization Certificate (associated with the approved
buffer impacts) shall be referred in writing to the Director for a decision. The Director's decision is
subject to review as provided in Articles 3 and 4 of G.S. 150B.
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water
Act. If you have any questions, please telephone Lia Myott or Joseph Gyamfi 919-733-1786.
CHSIcbkllem
7 Si el
Coleen H. Sullins
cc: USACE Raleigh Regulatory Field Office
DWQ Raleigh Regional Office
DLR Raleigh Regional Office
File copy
Central Files
Ray Watson Jr., 6235-9 Falls ofNeuse Rd., #123, Raleigh, NC 27615
File: 080187v2LakeGastonPitStop(W arren)EXP+401