Herndon, Mason
Friday, February 12, 2016 4:52 PM
Carpenter,Kristi
Chapman, Amy
FW: B-4929 PCN
Follow up
Completed
Kristi Lynn,
FYI, I placed the application for B-4929 (DWR# 20150955) on hold in BIMS for an incomplete application based on a
conversation I had with the Corps today and the e-mail below. I have also scanned this e-mail into Lasefiche for
documentation as to why the application is on hold.
Have a Great Weekend!
MH
-----Original Message-----
From: Shaver, Brad E SAW [mailto:Brad.E.Shaver@usace.army.mil]
Sent: Friday, February 12, 2016 9:52 AM
To: Stanton, Tyler P<tstanton@ncdot.gov>; Rivenbark, Chris <crivenbark@ncdot.gov>
Cc: Herndon, Mason <mason.herndon@ncdenr.gov>; Lane, Stephen <stephen.lane@ncdenr.gov>; "Lucas, Ron"
<ron.lucas@fhwa.dot.gov>; Matthews, Monte K SAW <Monte.K.Matthews@usace.army.mil>
Subject: RE: B-4929 PCN
Tyler,
I appreciate you speaking with me yesterday about the GP 31 application for B 4929. The application is currently
considered incomplete and processing cannot begin based on the following deficiencies:
- Condition G of GP 31 states, "No work shall be authorized by this RGP within the twenty coastal counties, as defined
by the NCDCM, without prior consultation with NOAA Fisheries. For each activity reviewed by the Corps where it is
determined that the activity may affect Essential Fish Habitat (EFH) for federally managed species, an EFH Assessment
shall be prepared by the applicant and forwarded to the Corps and NOAA Fisheries for review and comment prior to
authorization of work." This coordination procedure has not been completed to date.
- Green sheet commitments in the FONSI indicate that ESA consultation would be completed before a 404 application
was submitted. The conclusions from this coordination are missing from the application.
Please provide the missing information within 30 days of receipt of this correspondence. The lack of response
within this timeframe will be considered a request to withdraw the application. If you have any questions please don't
hesitate to give me a call.
Thanks,
Brad
-----Original Message-----
From: Stanton, Tyler P [mailto:tstanton@ncdot.gov]
Sent: Wednesday, February 10, 2016 7:43 AM
To: Shaver, Brad E SAW <Brad.E.Shaver@usace.army.mil>; Herndon, Mason <mason.herndon@ncdenr.gov>; Lane,
Stephen <stephen.lane@ncdenr.gov>
Subject: [EXTERNAL] B-4929 PCN
The riparian wetlands were listed as non-riparian on the PCN and DMS request. I've attached the revised PCN pages and
we've submitted a revised DMS request, so you should see a revised acceptance letter from them soon. We'll update the
application on the website today or tomorrow.
Thanks,
Tyler
Tyler Stanton
Environmental Program Consultant
NCDOT, Natural Environment Section
919 707 6156 office
919 212 5785 fax
tstanton@ncdot.gov
1598 Mail Service Center
Raleigh, NC 27699-1598
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third
parties.