HomeMy WebLinkAbout20052116 Ver 2_More Info Letter_20170227K; Ira.
Water Resources
Environmental Quality
February 27, 2017
BOMA North Carolina LLC
Attn: Kory Reimann
1668 Ridge Point DR
Bountiful, UT 84010-1054
Subject: REQUEST FOR ADDITIONAL INFORMATION
Caleb's Creek Development
Dear Mr. Reimann:
ROY COOPER
Governor
MICHAEL S. REGAN
Secretary
S. JAY ZIMMERMAN
Director
DWR # 2005-2116 v2
Forsyth County
On January 26, 2017, the Division of Water Resources — Water Quality Programs (Division) received your
application dated January 4, 2017, requesting a 401 Water Quality Certification from the Division for your
project. The Division has determined that your application is incomplete and cannot be processed. The
application is on -hold until all of the following information is received:
1. Please provide the Division a copy of your response to the February 24, 2017 letter from the US
Army Corps of Engineers requesting additional information. [15A NCAC 02H .0502(c)]
2. Please submit your site plans on full plan sheets at a scale of no smaller than 1"=50' with
topographic contours shown. In addition, please provide an electronic copy to
sue.homewood@ncdenr.gov. If this project is to be proposed in phases you may provide detailed
site plans for Phase 1 and conceptual site plans for future phases. [15A NCAC 02H .0502(b)]
3. Please enumerate all wetland and stream impacts including fill slopes/dissipater pads/other
impacts on the site plan and clearly label impacts (Wetland/Stream Impact 1, etc.). The Division
recommends highlighting by hatching or shading all impacts areas for temporary impact areas and
permanent impact areas. [15A NCAC 02H .0502(g)]
4. Please provide a detailed engineering plan, profile view, and cross-section of all proposed culverts.
These drawings must include details regarding stream alignment in relation to pipe alignment, pipe
slope, pipe burial, and dissipater pad. [15A NCAC 02H .0502(b)]
State of North Carolina I Environmental Quality
450 W. Hanes Mill Road, Suite 300, Winston-Salem, North Carolina 27105
Phone: 336-776-98001 FAX: 336-776-9797
BOMA North Carolina LLC
DWR# 2005-2116 v2
Request for Additional Information
Page 2 of 4
Please clarify whether the Division of Energy, Mineral and Land Resources will require riprap within
any stream channels or wetlands as part of the Erosion & Sedimentation Control Plan or Dam
Safety plan approval. If riprap is required, please enumerate and clearly label the temporary and
permanent impacts on the site plan and submit a channel restoration detail for any temporary
impacts. Riprap must be located below the stream bed elevation. [15A NCAC 02H .0506(f)
6. Per conditions of the General Certifications "all culverts must be placed below the elevation of the
stream bed by one foot for all culverts with a diameter greater than 48 inches and 20 percent of
the culvert diameter for culverts having a diameter less than 48 inches." Please revise your plans to
meet this Condition or request an exemption from this Condition and provide justification for the
exemption request. [15A NCAC 02H .0506(b)(2) and .0502(b)]
7. Per conditions of the General Certifications, all work must be done "in the dry". Therefore,
dewatering methods will be necessary to temporarily dewater the stream channel during pipe
installation. Please provide a construction sequence that details the method of dewatering to be
utilized at the site and the sequence of construction events to be followed to ensure compliance
with this condition. In addition, please ensure that the location of the temporary impacts are
shown on the construction drawings and clearly indicated in the revised impact table. [15A NCAC
02H .0502(b)(3)]
8. Please provide a plan sheet that indicates the location of proposed stormwater measures for this
project. If this project is to be proposed in phases, please provide a stormwater management plan
approval for Phase 1 that includes information regarding stormwater treatment for all roadways as
well as residential/commercial built upon area. [15A NCAC 02H .0506(b)(5) and (c)(5)]
Pursuant to Title 15A NCAC 02H .0502(e), the applicant shall furnish all of the above requested information
for the proper consideration of the application. If all of the requested information is not received in writing
within 30 calendar days of receipt of this letter, the Division will be unable to approve the application and it
will be returned. The return of this project will necessitate reapplication to the Division for approval,
including a complete application package and the appropriate fee.
Please respond in writing within 30 calendar days of receipt of this letter by sending one copy of all of the
above requested information to my attention at the address below.
Please be aware that you have no authorization under the Water Quality Certification Rules for this activity
and any work done within waters of the state may be a violation of North Carolina General Statutes and
Administrative Code.
BOMA North Carolina LLC
DWR# 2005-2116 v2
Request for Additional Information
Page 3 of 4
Please contact me at 336-776-9693 or Sue. Homewood@ncdenr.gov if you have any questions or concerns.
Sincerely,
Sue Homewood
Winston-Salem Regional Office
cc: Perry Isner, Wetlands & Waters Inc (via email)
Jean Gibby, USACE Raleigh Regulatory Field Office (via email)
DWR WSRO 401 files
DWR 401 & Buffer Permitting Unit
BOMA North Carolina LLC
DWR# 2005-2116 Q
Request for Additional Information
Page 4 of 4