HomeMy WebLinkAboutNC0026123_Environmental Assessment_19940427vjc4D 2(� /2 3
DIVISION OF ENVIRONMENTAL MANAGEMENT
April 27, 1994
MEMORANDUM
TO: Monica Swihart
FROM: Jason Doll
THROUGH: Carla Sanderson
Ruth Swanek
SUBJECT: Resubmitted Environmental Assessment
Proposed WWTP Expansion
City of Asheboro
Randolph County
The Instream Assessment Unit has reviewed the revised Environmental Assessment
from Black & Veatch. The revised EA is significantly improved and has been found to
address all of the concerns outlined in our corments on the original document, dated
March 14, 1994.
The revised EA outlines the facility's current pretreatment demands much better,
including efforts undertaken to deal with particular industrial users that have had high
mercury levels in the past. The new document still does not outline any future pretreatment
needs, but City officials have stated clearly that they have no current plans for recruitment
of new industries.
The revised document mentions the facility's internment problems in meeting toxicity
test limits. The EA states that continued pretreatment attention to mercury, and installation
of dechlorination equipment and tertiary filters should bring about improvement in this
area. There is not a great deal of detail in the EA regarding the efforts to pass toxicity tests,
but communication with the plant operator and the public utilities director have shown that a
substantive effort is under way to improve effluent toxicity.
The revised EA is most improved in its justification of increased flows and hydraulic
needs. It has good support information and explains clearly how the future flow
projections were developed. The document also outlines the city's efforts to reduce inflow
and infiltration, both present and future.
The schedule given for the expansion is more realistic than the one given in the original
EA, but it should be noted that the new schedule is very optimistic. It relies on the
assumptions that there will be no difficulties in the public notice period and that the city will
put the project out to bid before the NPDES permit is final.
Thank you for the opportunity to comment on this Environmental Assessment. Please
let me know if you need further information or if you have any questions or comments
pertaining to this matter.
cc: Coleen Sullins
Steve Bevington
Winston-Salem Regional Office
Central Files
v
DIVISION OF ENVIRONMENTAL MANAGEMENT
March 14,1994
MEMORANDUM
TO: Monica Swihart
THROUGH: Ruth Swanek '�
Carla Sanderson
FROM: Jason Doll
SUBJECT: Environmental Assessment
Proposed WWTP Expansions
City of Asheboro
The Instream Assessment Unit has reviewed the Environmental Assessment for the
expansion of the wastewater treatment plant operated by the City of Asheboro. The
document was found to be inadequate in several areas. It does not give enough
consideration to the alternative of relocating the discharge or address the adverse impacts of
the outfall at its current location. The document makes no mention of current industrial
users or future growth of such, and it gives no consideration to the resulting waste
characteristics caused by present and future industrial use. The document does not address
the facility's compliance problems, particularly with regard to effluent toxicity. The metals
limits given in the document are incorrect for the current discharge location. The document
does not adequately substantiate the plants hydraulic needs, nor does it give consideration
to alternative solutions in this area, and the schedule given for achieving improvements to
the facility is unrealistic. A discussion of the particular concerns follows.
L Effluent Toxicity and Discharge Impacts
The facility currently discharges to Hasketts Creek. According to USGS estimates
(#0210029550,1987) Hasketts Creek has a 7Q10 = 0.0 for both summer and winter and
30Q2 = 0.2 cfs. During critical flow periods the stream becomes 100% wastewater. The
average flow in the creek is 12.0 cfs, so during normal flows the stream will be over 50%
wastewater after the plants expansion to 9.0 MGD. The impact of the receiving stream
being dominated by waste flow is compounded by intermittent effluent toxicity. Since
1990 the facility has consistently failed one or more chronic toxicity tests annually. A
benthic macroinvertebrate study conducted by the Biological Assessment Group in
February,1990 found that Hasketts Creek above Asheboro's outfall rated "fair" but most
"...taxa either became rare or were completely eliminated below the discharge, indicating
severe stress in this portion of Hasketts Creek. The community structure below the
Asheboro discharge indicated that toxicity, not organic loading, was the cause of the
change in the invertebrate fauna."
The assessment of improvements to the facility should address effluent toxicity and
outline a mitigation strategy. Given that the low flows in Hasketts Creek are a large factor
in the discharge's adverse impacts, a much more thorough consideration should be given to
the alternative of relocating the discharge to the Deep River. The current document barely
mentions the option.
2. Pretreatment and Industrial Users
The EA indicates 70% of the WWTP inflow comes from industrial / commercial users,
but makes no mention of what significant industrial users (SIUs) are presently in the
pretreatment program or what waste characteristics result from their inputs. Given the
facility's problems with intermittent effluent toxicity, the EA should outline current and
future pretreatment needs. The only justification given for the expansion is that flows to
the plant have been increasing. The EA says the increase to 9.0 MGD is based on
calculations derived from the city's growth rates in the 1980's, but gives no description of
the nature of that growth (i.e. industrial, commercial, domestic, zoo, etc.). The document
should outline any future industrial recruitment plans, in tics, and the associated waste
stream characteristics and treatment needs. These areas should also be addressed in terns
of secondary impacts.
A pretreatment inspection report conducted by the Winston-Salem Regional Office in
October 1993 expressed concerns over elevated mercury levels of 1 to 4 ppb coming from
the Eveready Battery Plant #2. Review of the facility's discharge monitoring reports has
shown detectable levels of mercury consistently each month well above the limit that would
be applied to the Hasketts Creek discharge (0.012 ug/1). The NPDES permit currently
requires monitoring for mercury, but a limit is scheduled to be phased in on April 1,1996.
The EA should outline plans to meet the limit, as well as outline plans to deal with other
toxic pollutants of concern, such as arsenic, with which the facility has had problems
historically.
3. Metals Limits.
The. "probable" metals limits given for the expanded facility in the EA are wrong. The
limits are from a speculative done by Instream Assessment in June 1991 which were for a
discharge to the Deep River and would by no means apply to Hasketts Creek where
there is no dilution during critical flow periods. Because the 7Q10 = 0 the limits at the
current discharge location would be equal to the instream water quality standards given in
15A NCAC 2B .0211, and are as follows:
Cadmium
2 ug/1
Chromium
50 ug/l
Residual Chlorine
17 ug/l
Nickel
88 ug/l
Lead
25 ug/l
Cyanide
5.0 ug/l
Mercury
0.012 ug/1
Arsenic
50 ug/1
Fluoride
1.8 mg/1
Essentially, there would be no less stringent limits or monitoring requirements than those
already given for the current 6.0 MGD flow. The limits in the EA would apply only if the
discharge were relocated to the Deep River.
4. Hydraulic Needs
The Environmental Assessment offers projected growth in flow as the justification for
plant expansion, but does little to substantiate the projection other than to say it is based on
growth rates in Asheboro from the 1980's. The document should go into much greater
detail as to how these projections were developed, and should also explain why they are
valid when applied to the next 30 years when economic and development trends may have
shifted significantly.
The document makes no mention of options such as analysis and abatement of inflow
and infiltration problems or the ,implementation of a water conservation program to reduce
water use and influent volume. These alternatives could prove to be more economical
methods to decrease the current hydraulic load, as well as future loads. The increased
capacity could eliminate or reduce the magnitude of expansion and the associated adverse
impacts and expenses. Such alternatives have been used very successfully in other projects
and should be given thorough consideration here.
5. Project Schedule
The schedule given in the Environmental Assessment is completely unrealistic, with
milestone dates given in parts of the document already past. The project will require a
modification to the NPDES permit. An application for the modification cannot be
submitted until an initial departmental Finding of No Significant Impact (FONSI) is drafted
and sent to the Department of Administration Clearinghouse for review. Once the FONSI
is completed and the NPDES permit modification request is made, the projected schedule of
issuance is at least 180 days (6 mos.). After the permit is finalized, a request for an
authorization to construct (A to C) may be submitted for review and approval. The review
period for an A to C is approximately 90 days. By our estimates the project is at about one
year, at least, from -having an approved A to C at this point. The EA should be updated to
reflect a more current, realistic timeline for completion of the expansion project.
6. Additional Limit Changes
In addition, the Environmental Assesment should take into account that studies being
conducted currently by the Instream Assesment Unit for the Cape Fear River Basin
Management Plan have indicated that the Deep River is experiencincing low dissolved
oxygen levels seasonally, often below the 5.0 mg/1 wateVuality standard. Our studies
have indicated eutrophication is playing a significant role in the low DO levels. As a result
of these documented water quality problems major facilities located in the Deep River
drainage are likely to receive nutrient limits as per the basinwide plan. The City of
Asheboro may wish to begin planning to meet these potential requirements and should
address such plans in the EA document.
Thank you for the opportunity to comment on this Environmental Assesment. Please
let me know if you need further information or if you have any questions or comments
pertaining to this matter.
cc: Coleen Sullins
Steve Bevington
Winston-Salem Regional Office
Central Files
WHOLE EFFLUENT TOXICITY TESTING OISELF-MONITORING SUMMARY] Tuc,Fcbl5,1994
VACILI'IY REOVIREMIUI17 YrAR JAN Min MAR APR M JI
PGE
ARCADIAN CORI4)RAIION PERM CIIR LIMA.6%
90 -
-
-
-
-
-
--
--
-
-
-
-
N(7gXX13727=1 ftin:.N1092 rnvPwnry: Q PIP A JAN APR JN. OCT
N.ComP:Single
91 -
-
-
-
-
-
-
-
-
-
-
-
Comny:NliWHANOVIiR Re& :WIRO 5,IbI,.iu:CI'I:I7
92 --
--
-
PASS
-
-
PASS
-
-
LATE
PASS
-
I'H:0.28 Sgeel.l
93 PASS
-
--
PASS
--
--
PASS
-
-
PASS
-
-
7QIQ,.27.2 IWC(%): 1.6 °
W PASS
AR('IIP.R DANII'3ti MIDLAND (Y)l001 MiRM: 24HR AC MONK LC50(FmD OR MYS1D)
g0 FAIL(
FAIU
FAILmy
61.2f
bl
-
PASSI
-
-
PASSI
-
-
NC0027065/001 13,in:8/IN3 Fmgnney:Q OCI'IAN APR 1IIL
NnnComP:
91 m
PASSI
PASSI
m
--
-
>501
._
_.
NOND
•-
-
Counly:nRUNSWICK Region: WIRO Suhhasin: CPF17
92 M
79.21
--
33.01
-
-
>1001
-
-
>1001
-
-
PF:,1,502 SM(ial
93 >tm
-
-
>1001
-
-
Am
-
--
>SD.01
-
-
7QIMODA1. IW('(%): n.03 oomr:
B4
ARIXNE HOSIERY MIJ. 1HiRM CIIR LIM: 8.0%
90 m
m
FAIL
m
m
FAIL
m
m
FAIL
m
m
m
NV"7927A81I netamlif1/89 FmPmwy: Q 1'n' A MAR JIINSITIIEC
NImCmmP:
91 m
FAIL
PASS
PASS
-
m
-
-_
FAIL
m
m
FAIL
Couni, 111IRKli Reµm,.: ARO Suldvsin: (I1132
92 m
m
PASS
-
--
PASS
---
-
PASS
--
-
FAIL
-
I'F: O.W75 SPr•Inl
93 FAIL
Nl
FAIL.PASS
--
--
H
---
---
PASS
---
-
PASS
7010:0.13 IWC(%1:8.19 Hither.
W
ASHEBORO WWII' Pl;RM CIIR I.IM:W%
Y 90 -
FAIL
PASS
-
-
PASS
--
-
PASS
-
-
FAIL
N(IM261!3AN11 Ilegim9/1293 Fu sen,y:Q PA' A MAR IIINSIiI OF.17
Nm0,a.,:SINGI.I(
.91 PASS
-_
FAIL
PASS
-
PASS
---
-
PASS
-
-
PASS
Ciunly:RANDOLP11 Regiml:WSRO SYbhusln:011n9
92 -
-
PASS
-
-
FAIL
PASS
-
PASS
-
-
PASS
IT 6a S"W
SO _-
--
PASS
-
-
PASS
._
-
PASS
-
-
nl
7QIQ 0.00 IWCI'J4: MN) unler
94 JeAZL
ASIROLINECORK MO(MAH OR AI'MONO FPIS
m -
'--
63.2
--
-"
-'-
--
-'
-
-'
W=146W. 1 Begin:5/ISM9 1i,,ency: 5 OW0-
Pnnnly:G1IIl,lY)RU Ih•, WSIIO Snldwrin( ITT2
02 •-
---
--
--
--
-
--
-
-
-
-
19;. 51r. U1
03 ...
...
--.
_.
...
...
...
.---
1111,1 II IYI 1\1'1'1'S1 11YI IY1 x4,
1Is
AIK'IPERM CIIR I.IM"AI%
80 ._
...
...
...
--.
...
.-.
_-
---
--.
--
-
N( WROH5,1/(KI 6•Bin:IPIN2 Imryenry: Q PA! A MAR ION SET DEC
NuoCom,Single
91 --
--
---
--
--
--
---
--
--
---
-
V,Iu.1y:1A)RSY'lll Regi.m:WSRO Snhhnsin:YAD(M
92 --
-
-
--
-
--
-
-
-
-
H
IT IL1010 Fm,gm
W -
---
H
-
---
H
---
--
H
H
7QIO: 0.05 IWC(%):90.32 Ihder:
94
AORORA W WIP TERM AC I.IM:NO AC (FMID) Q P/F
B0
N('002I5310101 Segin:2/INI 1'mlwsuy: Q I'? A MAR IIIN SEP DRC
NuuCnmP:
91
Cnunly:nlUlR'DR'1' Reginn:WARO Subhosin:TAR07
92
1-11:0.12 % rdnl JOC:.WA)0-9/IN4 NO TOX RI:Q
03
7QI0t 0.0 IW('(%):100.0 Oh r.
94
0AKINSVILLIi\\WW PERM CIIR LIM: 3. 1%
-
90 PASS
---
-
m
PASS
-
PASS
-
-
PASS
--
-
NOI12."61MI negin:7/I/89 Imlwclry: Q P71; A JAN APR IIIL OCT
NnnComP:
91 PASS
-
-
bl
M
PASS
PASS
-
-
PASS
-
-
Caunty:Mf10110.1. Regilm:ARO Subbadn: FRB06
92 PASS
-
-
FAIL
PASS
-
PASS
-
-
PASS
-
-
PF:0.075 5"1.1
0 FAIL
PASS
-
PASS
-
-
PASS
-
-
PASS
-
-
7QI0:3.6 IWCI%0.12 dole':
94
IIANDAG. INC. PERM: 2411R AL' IJM 9117h (FOID)
90 c30'
66.1'
33.3'
253-
>100X
>100%
m
NONE.
42.5-
56.42-
12.43-
11.4'
NCfX111121N00t Orgin:9/IN3 F.,o,ua'Y: Q Pn' 611-:131 MAY AIIGNOV
NanCu.p:SINGIJi
et 12.2-
16.3•
23.8'
17.3-
10.87'
NONE.
64.42-
74.52-
NONE.
>100.
4.69'
10.51'
('nnm,011ANVII J J! Re9imI: RR(Suhlmsim:TAR01
92 7.054-
2.67•
>100.
>I00'
40.61-
>100'
28.72•
70.71-
22.53'
12.94-
10.51'
>100•
I'F: VAR Sm601
93 12.07-
85.58'
M
20.31.
17.88•
72.01-
>100'
>100'
PASSISIG
FAILI
PASSI
--
7QI6:0.(XI IW('f%1: 101m Onh:
W
IIA.M: I'I:JtM('1 lR LIb1:21%.
PO --
--
-
--
--
-
-
-
-
-'
LATE
bl
NOXH 01-11AXII Ile,mAWI0111 lia•lwlxy: Q P/I' A 1'1-11 MAY AIIG NOV
N.... I „P:
01 PASS
TABS
_.
._
PASS
-
-_
PASS
-.
...
FAIL
PASS
Caunly I)ON(T)MOR Region: ARO Suh in: I44D02
92 -
WE
PASS
-
PASS
-
-
PASS
-
-
FAILFAIL
FAIL
111g40 N,6.1
0 PASS
PASS
-
-
PASS
-
-
PASS
-
-
PASS
-
11110'J111 I\1'I'I'GI'11 )O Ih,nt
04
C Lon><svlive fnilurcn =.igni0awm nmY+Is"'I " Y Pre IINO Dam Avnilshlc
IJNPJ41)
1'IiIlM=1'ennil Regnin•nwm I.IiIb A,hninixlmlivrl<1mf-l'nrgol Pmqurnry=Mnnilminafmrlueney:Q.Qunnerlyl M.Munlhly;nM-OlmonlhlY;SA-Semiannunlly;A-Annunlly;OWD. Only when disehnrging;D. Diseuminued munituri.,Pquilnmenr, IS. Cundwting independent study
negin=l5m nxmlh rc'rvircJ 7QI(I=Raxeiving xlnam low Dow rrilMrm lcLs) A=�uanedY mmnimring inrrcaxa la nmmbly upon sinl.•Ic fnilurc Mon1lM llul lacing must lxrur-es. JAN.AI'R,IIILDCI' NnnCnnIII = C'nrmnt CumPli.eu Requimmenl
M'=Pcmnm'JOuwfMGD) OV('%=lnMmam wmle armrvmmli,m IMF =I dNil ehmnir mxl AC=Acme CIIN=Chmnic
U.w Nmmian: (- Pa01evJ Minnow: s - Vcrmd olnrin sn.: nw - MvmiJ sbrinm: (l1V - C11mm n1u : P - M,mallw of maned swlrcnmee nl hiXlwml rmneenlmliml: nl-11,K." Iry I1nM Ao Tus Gmno: hl . and Ial
Reaming Numtinn:---=Uam nm rcgvircd:NR-Nvl mPnnuJ:O-Ocginning of Qumler 1eF.eilily Activity Smlus:I- Innnive. N-Newly issucifnmmlmc);11. Alive butnm dielmrgingtt-Muiedam nI.H.1c fur nmmh in 4,..Iiun SIG=ORCsignlnurcnmJeJ
4
qzt
A�l
aA�