HomeMy WebLinkAbout20240318 Ver 1_High Point Stream Restoration AOI_20240221DEPARTMENT OF THE ARMY
U.S. ARMY CORPS OF ENGINEERS, WILMINGTON DISTRICT
WILMINGTON REGULATORY OFFICE
69 DARLINGTON AVENUE
WILMINGTON NORTH CAROLINA 28403
May 13, 2024
Regulatory Division
SAW-2024-00403
Ms. Melinda King
City of High Point
211 South Hamilton Street
Suite 206
High Point, North Carolina 27261
Via Email: Melinda. king@highpointnc.gov
Dear Ms. King:
This letter is in response to the Pre -Construction Notification (PCN) you submitted to
the Wilmington District, Raleigh on February 22, 2024, for a Department of the Army
Nationwide permit (NWP) verification. This project has been assigned the file number
SAW-2024-00403 and is known as Hamilton Avenue Stormwater Utility Upgrades. This
file number should be referenced in all correspondence concerning this project.
A review of the information provided indicates that the proposed work would include
the discharge dredged/fill material in 640 linear feet (0.036 acre) of stream. This
verification authorizes the permanent discharge of fill material into 448 linear feet (0.028
acre) stream channel and the temporary discharge of fill material into 192 linear feet
(0.008 acre) of stream channel to facilitate the installation of larger stormwater pipes
throughout the streets adjoining the stormwater outlet at Oakwood Cemetery and an
upgrade of the culverts within the cemetery to facilitate the increase discharge. The
project would also involve streambank stabilization on erosive streambanks at areas of
critical infrastructure, and realignment of channel flow to reduce erosion potential in
other areas of the project reach. The project area for this determination includes 14.32
acres which is illustrated on the enclosed site plans/maps, entitled Stream Restoration
0+00 TO 1+50, G-2 and Impact Sheets 1 through 4, dated November 2020, and Final
Design, Sheets G-1, G-2, and C-1 through C-13, dated January 2024. The
project/review area is located in the Boulding Branch (Hydrologic Unit Code:
030300030102) watershed, which is within the Cape Fear River basin; at 312 Qubein
Avenue, at Latitude 35.966270 and Longitude-80.007760; in High Point, Guilford
County, North Carolina.
We have determined that the proposed work is authorized by NWP 3 and NWP 13
pursuant to authorities under Section 404 of the Clean Water Act (33 U.S.0 § 1344).
The proposed work must be accomplished in strict accordance with the general permit
conditions, any regional conditions, the special conditions listed in this letter, the
application materials, and the enclosed plans. If the extent of the project area and/or
nature of the authorized impacts to waters are modified, a revised PCN must be
submitted to this office for written approval before work is initiated. Any violation of
permit conditions or deviation from your submitted plans may subject the permittee to
enforcement action.
This verification is valid until March 14, 2026, unless prior to this date the subject
NWP(s) is suspended, revoked, or is modified such that the activity no longer complies
with the terms and conditions of this NWP. If you commence or are under contract to
commence this activity before the date that the relevant NWP is modified or revoked,
you will have 12 months from the date of the modification or revocation of the NWP to
complete the activity under the present terms and conditions of this NWP.
Project Specific Special Conditions:
Suitable habitat for tricolored bat (Perimyotis subflavus) may be present at the
site. On September 14, 2022, the United States Fish and Wildlife Service
(USFWS) published a proposal in the Federal Register to list the tricolored bat as
endangered under the Endangered Species Act (ESA). The permittee
understands and agrees that all work associated with the clearing and removal of
trees and removal or modification of culverts must be completed prior to the
effective date of the final listing of this species in the Federal Register. Work
associated with the aforementioned activities not completed by the time must
cease and the permittee must contact Laura Meyer of the Corps at (919) 634-
1595 or laura.j.meyer usace.army.mil to determine if additional coordination
with the USFWS is required under Section 7 of the ESA prior to continuing work.
Activities subject to Section 404 (as indicated above) may also require an individual
Section 401 Water Quality Certification. You should contact the NC Division of Water
Resources (telephone 919-807-6300) to determine Section 401 requirements.
This NWP verification does not preclude the necessity to obtain any other Federal,
State, or local permits, licenses, and/or certifications, which may be required.
If you have any questions related to this verification or have issues accessing
documents referenced in this letter, please contact Laura Meyer, Regulatory Specialist
of the Raleigh at (919) 634-1595, by mail at the above address, or by email at
laura.j.meyer@usace.army. mi1.
Sincerely,
Z-a-a � ,�
Laura J. Meyer
Regulatory Specialist
Enclosures
Cc (w/enclosures)
Jason Steele, Freese and Nichols, Inc. (via Jason.Steele@freese.com)
Seren Homer, NCDWR (via seren.homer@deq.nc.gov)
W
J m
L.�
LLJ >
U)
O
W
LLJ
W
Q LC)
-F- N
U
�CN
0 N
O
CN
O r-
z N
cn Q -,,
N O
N Z ..
. N
N O >
m E O
Cn
O
Q O (n
u — O
Q I
0
co
0
�m
0
I >
�0
cncn
W
n
I
U
/N
U 0_
C/� 0
CN
_j
Ln
cn
N ~
�6>
E 0
Cn
0
QQ)co
U - 0
Q L_ J
INSTALL CONSTRUCTION
SAFETY FENCE AROUND \d STA 0+07.21
PROJECT LIMITS, TYP BEGIN 3-TIER ROCK WALL
SEE NOTE 5 AT END OF CULVERT HEADWALL
\ WITH GEOBAG WALL SYSTEM
V ABOVE AT 2:1 SLOPE.
STABILIZE AND VEGETATE
LIMITS OF DISTURBANCE
(SEE SHEET C-3 AND C-5)
i
EXISTING FENCE a
B4
PROPOSED STAGE Exempt
/ AND STOCKPILE AREA Present and
Ongoing Activity
/ 915.51 sq ft
LIMITS OF
GRAVES
PROPOSED
hwWM
/ CONSTRUCTION EXISTING STORM IN
ENTRANCE
BY TOTHERS BE REM D l I v I
�N
SILT FENCE, TYP
-,w`
STA -0+91
N\ SD LINE 2
JUNCTION BOX 1 _
N=807795.74 ---
' E=1701622.26 -
BY OTHERS
PROPOSED DROP INLET -
PROTECTION BY OTHERS
EROSION CONTROL NOTES:
STA 0+00.00 \
BEGIN CHANNEL REALIGNMENT S
CULVERT OUTFALL ELEV. 888.0
-PROPOSED HEADWALL BY OTHERS
�So C
r Zo 0 ft)
STA 0+00.00
PREFOR SC R /
� uffer Zone ROTE TION (T P) /
\�. Permanent
4\ �R' \ \ �Fill - Bould
/
�e�� � Basin &
\ C\ Channel
Realignme
23.5 Lf
\ PROP 58.12 sq ft
4.
S D LI
BY OTHERS
1. CONTACT THE DEMLR WINSTON-SALEM REGIONAL OFFICE 336-776-9800 AT LEAST
48 HOURS PRIOR TO COMMENCING THE LAND DISTURBING ACTIVITY.
2. EROSION AND SEDIMENTATION CONTROL MEASURES SHALL BE INSPECTED IN
ACCORDANCE WITH NCDEMLR AT LEAST ONCE EVERY 7 CALENDAR DAYS AND WITHIN
24 HOURS AFTER ANY STORM EVENT GREATER THAN 0.50 INCHES OF RAIN PER
24-HOUR PERIOD. SELF -INSPECTION FORM CAN BE FOUND AT
HTTP://DEQ.NC.GOV/ABOUT/DIVISIONS/
ENERGY-MINERAL-LAND-RESOURCES/EROSION-SEDIMENT-CONTROL/FORMS.
3. DESIGN COMPONENTS SHOWN ON PLANS MAY REQUIRE FIELD ADJUSTMENTS AT
DIRECTION OF ENGINEER.
4. ALL DEBRIS REMOVED DURING TRENCH EXCAVATION IS TO BE IMMEDIATELY HAULED
TO A PERMITTED OFF -SITE DISPOSAL LOCATION.
5. CITY OF HIGH POINT CONTACT PERSON RESPONSIBLE FOR MAINTENANCE:
MELINDA KING 336-883-3217
B2
Exempt
Present and
Ongoing Activity
67.4 sq ft
S2
Permanent
Geobag Wall
with Rock Toe
11.6 Lf 1
15.7 sq ft
0. SR ro i Dui_
• • N
STA 1 +45.65
END 3-TIER ROCK WALL WITH
GEOBAG WALL SYSTEM ABOVE
PROTECT
EXISTING SEWER
S3
JTED RIPRAP
Permanent
6
Fill - Grouted
Riprap
40.1 Lf
175.95 sq ft
6.51 cu yd
ING CHANNEL
CENTERLINE
Ilesod
B3
Exempt SED
Present and
Ongoing Activity E 1
1509.73 sq ft E R S
S6
Permanent
Geobag Wall
with Rock
Toe
8.9 Lf
5.26 sq ft
.04 cu yd
• • • '��
LIMITS OF
GRAVES
Ad\
Permanent
---
NCASE
S5
ONCRETE
Geobag Wall
AT ROCK
Permanent
SING
with Rock
SEE NOT
Geobag Wall
6.Toe
Lf
S4
with Rock
Toe
52 q
2.52 sq ft
STA 0+0 .65
BEGIN 2
TIER
RO
Permanent
77.1 Lf
.97
R ROCK W
0.5 cu ft
VE
Fill -Bank Grading
110.28 sq ft
3.9 Lf
4.08 cu yd
ALL SYSTEM
ABOVE
B1FALI
3.76 sq ft
Exempt
L
0.14 cu yd
Present and
Ongoing Activity
E
r 1065.0 sq ft
3
AND C - 5)
EARTHFILL AS REQUIRED TO -
MAINTAIN A MINIMUM 1' COVER
\
PROPOSED 91 LF OF 6' X 4'
BOX CULVERT @ 1.007
r� w
a/ CC)
Lj CC)
3 0o 0o
0
884 �U,�(,,
o`000�
U UOOZ(1JZ�
Q M 00 m
a/-=UcoWcoWco
w w
z q /-\
�00ED Z z z
+ u0 Q
X Iw Li •,
+ 00JLi V� V
CDo�_jZ� �o�o>
1 c0aLD�1na_Ma_z
Q�c~i��»�>r~
-- zILIzZa-za- X
8 8 0 v) rQ - - ./ - %-/
-1+00
STA 0+00
ELEV= 888.00
BEGIN PROPOSED
STREAM ALIGNMENT
0+00
NOTE: CONTRACTORS SHALL STAY
WITHIN THE SPECIFIED LATERAL
LIMITS AND SHALL NOT DISTURB
GRAVES. APPROVED EQUIPMENT
MATS SHALL BE USED TO PROTECT
ff, ALL GRAVES WITHIN 10 FT OF
EQUIPMENT. EXCAVATORS WITH TAIL
SWING SHALL NOT BE ALLOWED
DURING CONSTRUCTION.
NOTES:
1.
FINAL LOCATION OF CONSTRUCTED RIFFLES SHALL BE
VERIFIED IN FIELD AND APPROVED BY ENGINEER OF
RECORD.
2.
STONE FOR ROCK TOE SHALL BE APPROVED BY CITY
PRIOR TO INSTALLATION.
3.
CONTRACTOR SHALL TEMPORARILY STOP WORK DURING
BURIALS. CITY WILL PROVIDE 24-HOUR PRIOR NOTICE.
4.
IF ANY CEMETERY PROPERTY IS DAMAGED,
o
CONTRACTOR SHALL REPLACE AT NO COST TO OWNER.
+
5.
CONTRACTOR SHALL COORDINATE WITH CEMETERY
STAFF PRIOR TO INSTALLATION OF CONSTRUCTION
SAFETY FENCE TO VERIFY LOCATION AND DEPTH OF
N
WOODEN STAKES. (OFFICE PHONE NUMBER:
336-883-3408)
6.
INSTALL GROUTED RIPRAP TO PROTECT EXISTING
SEWER PIPE. GROUTED RIPRAP SHALL EXTEND FROM
v
EDGE OF PIPE WEST TO PROPOSED ROCK WALL AND
A MINIMUM OF 6 INCHES ON ALL SIDES OF PIPE.
7.
ENCASE SEWER PIPE IN CONCRETE AT LOCATION
WHERE IT RUNS UNDER PROPOSED ROCK WALL.
CONCRETE SHALL BE MINIMUM 6 INCHES THICK ON
ALL SIDES. EXTEND CONCRETE MINIMUM 1' PAST ROCK
WALL BOTH SIDES.
8.
REPLACEMENT OF STORMWATER PIPES IS PART OF A
SEPARATE PROJECT. WORK WILL BE COORDINATED
PRIOR TO CONSTRUCTION.
9.
IF UNMARKED HUMAN SKELETAL REMAINS ARE
ENCOUNTERED DURING CONSTRUCTION, THE PROVISIONS
OF NORTH CAROLINA GENERAL STATUTE CHAPTER 70,
ARTICLE 3 APPLY. CONSTRUCTION ACTIVITIES SHOULD
IMMEDIATELY CEASE, AND THE COUNTY MEDICAL
EXAMINER SHOULD BE CONTACTED.
900
PROPOSED HEADWALL
BY OTHERS
INV: 888.0
u. Q0
lq�_00
N 00
+
Qw
Ln W
EXISTING GRADE AT
\ PROPOSED CENTERLINE
PREFORMED SCOUR
PROTECTION PROPOSED
GRADE
EXISTING 48" PIPE
PROPOSED 40 LF OF
6' X 4' BOX CULVERT
@ 3.73% BY OTHERS
INV: 884.48
EXISTING CHANNEL GRADE
MATCH EXISTING GRADE WITH
SHIFTED CHANNEL ALIGNMENT
1+00
• •
• In
Permanent Impact - Channel
Realignment/Boulder Basin
Permanent Impact - Fill and Bank Grading
Permanent Impact - Rock Toe and Geobag Wall
Permanent Impact - Fill (Grouted Riprap)
Zone 1 Exempt Buffer Impact
Zone 2 Exempt Buffer Impact
UTa)
o .�
�0,
U C
Zw
-0-0
0 0
4) .N
(n&
2af
0
c
0
0
U
0
z
CN
N
z
N
0 \
�Z
N O
w ��
o wo -�
Oz z
~ `i�az0vi
N o - w
z Nwo 00
o
U wOfMNo:5
�mz'Ln�,a
Nw}o��
0 =MOM c
L_ w-wZ -
o
z 0
CJ w � � � 0
O 0C,�000
Z �of
0U no
�aazt=m
W%
J�
�O
N
0
W=
o4-
V
C° E
o
O U
NW
o0)�
Cnz r N
U
U 3
D \--
-
J I 1 3
'
c
Zocu �
N C�
0
w
U
O
Ln
+
�
r-I
Uj
z
O
00
�
z
�
Q
O
+
Z O
O.
O
O
z
U)
J
O
= W
Uj
_U
H
Q
LL
O
pC
�z
o
UO
Q
2i
w
LLJ
I
0�
DC
z
�
c
O
~
Q
LLJ
G
Q
�
o
co
J
co
N
m
N
O
z
a-Q
o
a0 =
W
0
OW 0)
o
z
z
W
y
w
U
-
U
z
co
Q
>
W
LL
U
U)
w
W
7
Q
J
1 0
}
m
�o 0
c
O - U
0 OC �
00-0
M
o
O
0 10' 20' 40'
L (n
co�-
°0
Q
SCALE IN FEET
HORIZONTAL
0
0 2' 4'
W
c
SCALE IN FEET
w
VERTICAL
a
o
IMPACT SHEET 1
FINAL DESIGN
SEQ.
Plot Dote: 1 /31 /2024 4:14 PM Plot By: 03807 Filename: N:\WTU\Drawings\CV-STREST-DT.dwg
m
3 a
U) >
Z O
Cr)
J
0-
�1>t
�a_
I
0
U
N �
~ C
V 3 O
i>t N
_j0\
cn 3�:
N �\
. N
N >
E U
0
cn
QQ)(n
U - O
Q L_ J
� STA 1 +89.73 OAKWOOD STA 6+61.18
BEGIN LAY BACK BANKS MEMORIAL STA 3+43.82 STA 5+30.98 END LAY BACK BANKS
PROPOSED °°°° AT 2:1 SLOPE. INSTALL PARK END 1-TIER ROCK WALL BEGIN LAY BACK BANKS B11 SLOPE. INSTALL
COIR MATTING AND PLANT AT 2:1 SLOPE. INSTALL
_ SD LINE 1 BLEND TO EXISTING WITH GEOBAG WALL SYSTEM ,oh Exempt TTING AND PLANT
BY OTHERS S10 O ABOVE AT 2:1 SLOPE COIR MATTING AND PLANT Q ' STA 5+40.06 Present and TO EXISTING
(SEE SHEET B8 Permanent BLEND TO EXISTING Ongoing Activity
O Exempt Fill -Riffle TRANSITION TO GRADING 55.35 sq ft EET - -5)
p (SEE SHEET C-4 AND C-5) Q S17
STA 2 Present and 21.1 Lf BANKS AT 2:1 SLOPE p0 Permanent CTED S19
Buffer Zone Ongoing Activity S AT 142.77 sq ft 0� (SEE SHEET C-4 AND C-5) p v Temporary
S9 66.18 s ft 7.93 cu d Fill -Riffle ss Grading - Coir
B5 Permanent 1EM
q 0 1 y S11 v v 20.5 Lf E 1 Matting
Exempt Fill - Riffle K BAG WALL Permanent B10 132.97 sq ft ss 123 Lf
Present and 20.4 Lf ABO EAT 2:1 SLOPE. Geobag Wall with GRADE BANKS AT Exempt 7.39 cu yd STA 6+23.45 152.23 sq
Present and �BEG 2n� Ongoing Activity 78.79 sq ft ILIZE A VEGETATE Rock Toe ILIZE WITH C Ongoing Activity b1b2.60 sq ft 4.38 cu yd SHEETIC-4 AND C-5 165 q gg 63.55 sq ft �0 Temporary •�S • N TRUCTEDf
) 12.65 sq ftdi PLANT VEGE y S ss ss
-ass 0.23 cu yd Exempt Grading - Coir RIFFL
.` _ Present and SHEET C - 4 S Matting "�•
k- C Ongoing Activity 29.7 Lf TE 1
} - 169.07 sq ft 32.61 sa ft
k
�k
/ Permanent
Fill - Boulder
Basin
14.0 Lf
70.6 sq ft
ST 3.92 cu yd �•�
P OUR
PROTECTION (TYP)
Buffer Zone 2 (20 ft)
INSTALL CONSTRUCTION
SAFETY FENCE AROUND
PROJECT LIMITS, TYP
SEE NOTE 5
O We 0
NOTE: CONTRACTORS SHALL STAY
U
WITHIN THE SPECIFIED LATERAL
LIMITS AND SHALL NOT DISTURB
GRAVES. APPROVED MATS OR
PLYWOOD SHALL BE USED TO
PROTECT ALL GRAVES WITHIN 10 FT 0
OF EQUIPMENT. EXCAVATORS WITH zw
TAIL SWING SHALL NOT BE
ALLOWED DURING CONSTRUCTION.
7 0
� O
U
s5 5 - SS S9-)IO3S 55 - 55' 000, o
i� z
f•••••.H•••••••••••••
•••••••••••••••
\ X
B6
Exempt
Present and
Ongoing Activity
3.60 sq ft
s5
��
/ ,
�9
�'
SCALE IN FEET
'.. �, CHANNEL ALIGNMEN
--
HORIZONTAL
- WITH FLOODPLAIN
ENCH
� _
�_-�
--
� 0
2' 4'
--BLEN s13 ING
�-__- -
- _ ,-
�'
/
- '-'-` (SEE Permanent A
D C-5)
�- -�
r i
SCALE IN FEET
- gg9 Excavation
-
/ /
-= / � ao
a
2
Permanent
VERTICAL
32 Lf
--__ - - 30.2 sq ft
i
� S16
S18
Temporary
S20
Permanent
Geobag
E
_
Temporary
p rY
rading - Coir
Fill - Riffle
all with
Rock Toe
---_
Grading - Coir ._,,_,_,
Matting
g
20.9 Lf
FINAL 11.4 Lf
OF
CONSTRUCTED
RIFFLES SHALL BE
�' ��' /'
/' ` '
•�• Matting
9.7 Lf
14.96 sq ft
107.34 s ft
5.96 cu yd
VERIFIE q
AND APPROVED
BY ENGINEER OF
/ /
"�
•�' 28.5 Lf
825s ft STA 6+42 52
0.96 cu d
RECOR y
.39.92%'�� q
BEGIN 1 -TIER ROCK WALL
EM BEGIN PROPOSED
CHANNEL ALIGNMENT
WITH FLOODPLAIN BENCH
STA 3+40.13
BEGIN 1 -TIER ROCK WALL
WITH GEOBAG WALL SYSTEM
ABOVE AT 2:1 SLOPE
STABILIZE AND VEGETATE
(SEE SHEET C-4 AND C-5)
Nr
B7
Exempt
EXI Present and
Ongoing Activity
C E 222.02 sq ft
LIMITS OF DISTURBANCE
ET E 7A
'
B12
Exempt
S12
Present and
Permanent
Ongoing Activity
MINIMUM
Grading and
5.76 sq ft
OF BANK
Geobag Wall with
PAVEMENT
Rock Toe
76 Lf
198.72 sq ft
20.24 cu yd
STA 5+ I J.55
s14 BEGIN LAY BACK BANKS STA 6+57.48
Permanent AT 2:1 SLOPE. INSTALL END 1-TIER ROCK WALL
and Geobag Wall
\ Fill -Rock Toe COIR MATTING AND PLANT WITH BANKS LAID BACK
•�• 43.2 Lf BLEND TO EXISTING ABOVE AT 2:1 SLOPE
56.45 sq ft (SEE SHEET C-4 AND C-5) BLEND TO EXISTING
5.74 cu yd (SEE SHEET C-4 AND C-5)
STA 4+77.06
END 1-TIER ROCK WALL
WITH GEOBAG WALL SYSTEM
ABOVE AT 2:1 SLOPE
STABILIZE AND VEGETATE
(SEE SHEET C-4 AND C-5)
Permanent Impact - Channel Realignment
Temporary Impact - Grading
Permanent Impact - Fill and Bank Grading
Permanent Impact - Rock Toe and Geobag Wall
Permanent Impact - Fill (Grouted Riprap)
Zone 1 Exempt Buffer Impact
Zone 2 Exempt Buffer Impact
XISTINO 48"
PIPE
Excavation
888
PROPOSED 40 LF OF
6' X 4' BOX CULVERT
@ 3,73% BY OTHERS
EXISTING GRADE AT
CONSTRUCTED RIFFLE
884
PROPOSED CENTERLINE
884
\
CONSTRUCTED
RIFFLE
I N V:
883.00
880
880
\
CONSTRUCTED RIFFLE
CONSTRUCTED
RIFFLE
PREFORMED SCOUR
w
-
PROTECTION PROPOSED
Z
w
--
876
GRADE
�_
EXISTING CHANNEL GRADE.
Z
_
876
J
MATCH EXISTING GRADE WITH
-
o
SHIFTED CHANNEL ALIGNMENT
a
w
CIO r-
\\
LriLn LnO
O�V0
LQ'L
LL
+
' ` w
Z
QWZ
Cnww
�Jw
Ln Lj_j M1
872
872
(V
CD
(V
0
w N O
D
w Q�
CD
L � __ 0
VI " - C)
Z ' 0 0
o ww ��
U J Of If
Cn 'COD
o Izmomw
LL.Z-�Z
M�oao
Do Z��
U w � O
O O N f o o 0
ch
Z N0- OU
_o
F-0-<M
WU
4
�O
N
O
W=
-`
o�
W
o�
V
Url-
(° E
ID°
y'
NW
o0)�
Cz r N
O 3
D � 3
-
z 0
C
0
W
U
Q
o
z
^J^
L.�
W
W
Op
z
0
0�
-
O
z
I-
Q
Ln
+
p
z
N
0./
02
p
z
���J
O
= W
w�
U
LL J
O
�
�z
O
Q
W
W
O
Q
I-
J
W
2
~
N
-'t
2
0
op
>
O
J
M
N
m
N
Z
Q
zz
=
w
O
LLJ
O
z
z
o
Y on
ul
(D
3
LO
U
z
H
Cn
Q
>
LLJ
LL
U
Z
Q
J
W a_
W
Q
LU
LL 0
}
m
- c
MO
i C M
m
oo(/)
U O_0
_C:M
O 0)O
•§
T)
L (n
.
ryM
W
J
Q
U
w
Cl)
Cn
LPL
O
z
W
> o
1+50 2+00 3+00 4+00 5+00 6+00 6+80 IMPACT SHEET 2
FINAL DESIGN SEQ.
Plot Dote: 1 /31 /2024 4:1 7 PM Plot By: 03807 Filencme: N:\SW\Drowings\OHWM PLANS.dwg
Al
01
3
�m
cn
X
I >
0
cncf)
W
cn
n
I
>
U p
/N
a (71-
C/� 20
. p N
J
D Ln
cn N ~
E U
cn
0
QQ)co
U — O
Q L_ J
[ = EXCAVATION
BELOW OHWM
[ = FILL BELOW
OHWM
GRADED SLOPE ABOVE
CULVERT HEADWALL BY
OTHERS
912
PROP GROUND -
908
904____
900
896 EX CULVERT TO
892 BE REMOVED BY
OTHERS
888 EX SEWER TO -
REMAIN IN SERVICE
884 -40 -20
912
908
904
900
896
892
888
884
880
d ►.
I IA AIT /lr
3-TIER STACKED
ROCK WALL
GROUTED RIPRAP
AROUND SEWER PIPE
SEE NOTE 5
EX GROUND 912
LIMIT OF 908
DISTURBANCE
0
STA 0+00
904
900
- 896
PROP 6'(H) x 41(V) CULVERT BY OTHERS 392
EE1tEOHWM -
888
BOULDER BASIN 40 884
AT CULVERT
OUTFALL
GRADE BACK BOTH BANKS AT MAX
2:1 SLOPE AND PLACE 4 LIFTS
CONSTRUCTED GEOBAG WALL SYSTEM
ABOVE STACKED ROCK WALL. PLACE
COIR MAT AND VEGETATE ABOVE
-40 -20 0 20 40
STA 0 + 1 2
PROP GROUND
908
-
-
904
—
900
896
892
888
LIMIT OF
GRAVESTONES /
LIMIT OF
- DISTURBANCE
GROUTED RIPRAP
884 AROUND SEWER PIPE
SEE NOTE 5
880 -40 -20
912
908
904
900 LIMIT OF
GRAVESTONES /
896 LIMIT OF
DISTURBANCE
892
888 GROUTED RIPRAP
884 AROUND SEWER PIPE
SEE NOTE 5
880
GRADE BACK BOTH BANKS AT MAX
2:1 SLOPE AND PLACE 4 LIFTS
912
908
904
900
896
892
888
884
880
CONSTRUCTED GEOBAG WALL SYSTEM 912
ABOVE STACKED ROCK WALL. PLACE
COIR MAT AND VEGETATE ABOVE 908
GEOBAG WALL (TYP)
EX GROUND 904
/7777:: 3-TIER STACKED
— ROCK WALL 900
— T — ----- — 896
LIMIT OF 892
25-YR ELEV. DISTURBANCE
OHWM
rp$W 9 _11 i 888
2-TIER STACKED 884
ROCK WALL
0 20 40 880
STA 0+25
GRADE BACK BOTH BANKS AT MAX
2:1 SLOPE AND PLACE 4 LIFTS
CONSTRUCTED GEOBAG WALL SYSTEM
ABOVE STACKED ROCK WALL. PLACE
COIR MAT AND VEGETATE ABOVE
GEOBAG WALL (TYP)
3-TIER STACKED EX GROUND
)ff I
ROCK WALL
PROP GROUND _
-40 -20 0
STA 0+38
Plot Dote: 1 /25/2024 1 :37 PM Plot By: 03807 Filename: N:\WTU\Drawings\CV-STREST-XS.dwg
25-YR ELEV.
OHWM
2-TIER STACKED
ROCK WALL
20
912
908
904
900
896
LIMIT OF
892
DISTURBANCE
888
884
40 880
908
904
900
896
892
888
884
880
GRADE BACK BOTH BANKS AT 2:1 NOTE: CONTRACTORS SHALL STAY
SLOPE AND PLACE 4 LIFTS WITHIN THE SPECIFIED LATERAL
CONSTRUCTED GEOBAG WALL SYSTEM LIMITS AND SHALL NOT DISTURB
ABOVE STACKED ROCK WALL. PLACE GRAVES. APPROVED MATS OR
-40 SEE NOTE 6 0
STA 0+50
LIMIT OF
GRAVESTONES / GRADE BACK BOTH BANKS AT 2:1
LIMIT OF SLOPE AND PLACE 4 LIFTS
DISTURBANCE CONSTRUCTED GEOBAG WALL SYSTEM
ABOVE STACKED ROCK WALL. PLACE
90810' MIN COIR MAT AND VEGETATE SLOPE
ABOVE GEOBAG WALL (TYP)
904
900 EX GROUND
896 —
PROP GROUND
892
888 3-TIER STACKED
ROCK WALL
884
880 -40 -20
LIMIT OF
DISTURBANCE
908
904
900 —
EX GROUND
896
PROP GROUND
892
888 3-TIER STACKED
884 I ROCK WALL
880 -40 -20
901
89_
892
888
884
880 -40 -20
0
STA 0+75
SLOPE 908 PLYWOOD SHALL BE USED TO
�P) 904 PROTECT ALL GRAVES WITHIN 10 FT
EX GROUND OF EQUIPMENT. EXCAVATORS WITH
- _
900 TAIL SWING SHALL NOT BE
ALLOWED DURING CONSTRUCTION.
896
LIMIT OF
25-YR ELEV. - DISTURBANCE 892
OHWM
888
2-TIER STACKED
ROCK WALL 884
I 880 NOTES:
20 40
908
904
LIMIT OF 900
DISTURBANCE
896
892
� 25-YR ELEV. OHWM
- - 888
2-TIER STACKED
ROCK WALL 884
20 40 880
GRADE BACK BOTH BANKS AT
2:1 SLOPE AND PLACE 4
LIFTS CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED 908
ROCK WALL. PLACE COIR MAT
AND VEGETATE SLOPE ABOVE
GEOBAG WALL (TYP) 904
0
STA 1 +00
EX GROUND
900
LIMIT OF
DISTURBANCE 896
892
25-YR ELEV. � OHWM 888
2-TIER STACKED
ROCK WALL 884
20 40 880
GRADE BACK BOTH BANKS AT 2:1
SLOPE AND PLACE 4 LIFTS
CONSTRUCTED GEOBAG WALL SYSTEM
ABOVE STACKED ROCK WALL. PLACE
COIR MAT AND VEGETATE SLOPE
I I Let 1111
`'L..
M
0
STA 1 +25
20
'1
011111111111111111
89_
892 -
888
884
880
-40
-20
0
STA 1 + 44
20
40
896
892
888
884
880
LIMIT OF 900
DISTURBANCE
896
EX GROUND 1892
'LEV. OHWM 888
TACKED 884
_L
40 880
1. ALL GRADED SLOPES SHALL BE
LINED WITH COIR MATTING PER THE
DETAIL.
2. ALL STACKED ROCK WALL WILL BE
BLENDED TO EXISTING GROUND AT
TOP OF ROCK TO LIMIT EROSION AT
TOP OF WALL.
3. PLACE SINGLE COIR WRAPPED LIFT
ABOVE STACKED ROCK WALL AS
REQUIRED
4. GEOBAGS WILL BE BUILT IN A
MANNER THAT BLENDS WITH
EXISTING BACKSLOPE. A MINIMUM OF
4 LIFTS (-2 FT ABOVE STONE) AT
-2:1 (H:V) SLOPE SHALL BE USED
UNLESS OTHERWISE SPECIFIED ON
PLANS. LIFTS CAN BE PLACED AS
STEEP AS 1.5:1 (H:V). MORE BAG
LAYERS MAY BE USED AT DIRECTION
OF ENGINEER.
5. GROUT RIPRAP BETWEEN STACKED
ROCK WALL AND EXISTING SEWER
PIPE TO PROTECT PIPE. EXTEND
GROUTED RIPRAP ABOVE AND ON
SOUTH SIDE OF PIPE FOR MINIMUM
OF 6 INCHES.
6. ENCASE SEWER PIPE IN CONCRETE
AT LOCATION WHERE IT RUNS
UNDER ROCK WALL. CONCRETE
SHALL BE MINIMUM 6 INCHES THICK
ON BOTH SIDES AND ABOVE PIPE.
EXTEND CONCRETE MINIMUM 1' PAST
ROCK WALL BOTH SIDES.
U c
zw
-0-0
c T
O
�af
0
c
0
0
U
O
Z
N
Z o
N
0 \
CD Z
w N O
1121
-�azo
N o Y O" w
Z N ! p -0 NO
0 a > L� a
wwcy
U J K M N ,:::)
c=�ziNa
In ~
cn c
0 �Zmo ;�
L'_ w-�Z
�L�0<
DO Z
U W _ = 5 O
0 o Lu
Z Lf)0-=
0
�a-< Fn
WU
J
�O
N
0
W=
��t
W
o�
V
U�
1E
y
O U
ors
MEW
aW
cn Z r N
3
-1
J I 3
'
c0
Z U
N c:�
0
-
a In � �
uj
U
Q
J
O
Lr)
w
z
+
00
Z
Q
0
z�
0
+
a2
� D
Cn
J
O
Vi
Lij
=wwu
�
z
o�
O
00
Q
W
w
0.N/
z
(/')
0
O
J
U
Q
co
CDc
J
coN
co
N
o
z
a
Q
o
m =
W
uW 0)
o
z
z
W
y
w
U
3:
c
U
z
coQ
>
w c/)
o6
o
H
w
W
Lu
7
~
a
o
z (n
J >
� U
}
m
_F0o
�U 6
o-�
oou,
U O1
c: c:
O
Ln
L (n
M
0 10 20'
°0
w_
Q
SCALE IN FEET
U
W
Cn
0
z
w
> o
IMPACT
SHEET
3
FINAL DESIGN
SEQ.
�m
X
I >
O
cncn
W
m
U)�
In
U N
min
U �t
a�
C/� o
_��
�iLn
cn
N ~
N Z 6
Q)
>
m�cn
0
QQ)co
U — O
Q L_ J
= EXCAVATION
BELOW OHWM
= FILL BELOW
OHWM
900
896
892
888
884
880
876
More
—40 —20 0 20 40
STA 2+00
896 EDGE OF PROP
892 PAVEMENT GROUND
896
892 EDGE OF
PAVEMENT
888
884 EX GROUND
880 —
876 —40
1 -TIER STACKED
ROCK WALL
-20
896 GRADE BANK AT
2:1 SLOPE. PLACE
892 COIR FIBER MAT
AND VEGETATE
888 (TYP)
884
880 EDGE OF EX GROUND -
PAVEMENT
876 PROP GROUND
872'-40 —20
EDGE OF GRADE BANK AT 2:1
PAVEMENT SLOPE. PLACE COIR
FIBER MAT AND
892 - VEGETATE. BLEND TO
EXISTING
888
884 — — — -- --- ---
EX GROUND
880—
876 GRADE FLOODPLAIN
BENCH AT 15:1 SLOPE.
872 PLACE COIR FIBER MAT
AND VEGETATE
868'-40 —20
GRADE BANK AT 2:1 SLOPE.
PLACE COIR FIBER MAT AND
VEGETATE (TYP)
------
25-YR ELEV. OHWM
EDGE OF
PAVEMENT 17
-
0 20 40
STA 2+50
GRADE BACK BANK AT 2:1 SLOPE AND
PLACE 4 LIFTS CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED ROCK
0
STA 3+00
0
STA 3+50
PROP GROUND
0
STA 4+00
20 40
GRADE BACK BANK AT 2:1 SLOPE
AND PLACE 4 LIFTS CONSTRUCTED
GEOBAG WALL SYSTEM ABOVE
STACKED ROCK WALL. PLACE COIR
MAT AND VEGETATE SLOPE ABOVE
GEOBAG WALL (TYP)
t��__EDGE OF
25-YR ELEV. PAVEMENT
� OHWM
-1 -TIER STACKED
-ROCK WALL
20 40
GRADE BACK BANK AT 2:1 SLOPE AND
PLACE 4 LIFTS CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED ROCK
WALL. PLACE COIR MAT AND VEGETATE
SLOPE ABOVE GEOBAG WALL (TYP)
—� EDGE OF
PAVEMENT
25-YR ELEV.
OHWM
1 -TIER STACKED
ROCK WALL
20 40
900
896
892
888
884
880
876
900
896
892
888
884
880
876
896
892
888
884
880
876
896
892
888
884
880
876
872
892
888
884
880
876
872
868
EDGE OF
PAVEMENT GRADE BANK AT 2:1
SLOPE. PLACE COIR
FIBER MAT AND
892 VEGETATE. BLEND
TO EXISTING
888
884-
880 EX GROUND
876 GRADE FLOODPLAIN
BENCH AT 15:1 SLOPE.
872 PLACE COIR FIBER MAT
AND VEGETATE
868'-40 —20
GRADE BANK AT 2:1
SLOPE. PLACE COIR
892 FIBER MAT AND
VEGETATE. BLEND
888 EDGE TO EXISTING
PAVEMENT
884 ----
25-YR ELEV.
880
876 GRADE FLOODPLAIN
r7 BENCH AT 15:1 SLOPE.
872 PLACE COIR FIBER MAT
AND VEGETATE
888
884
880
EDGE OF EX GROUND
876 PAVEMENT PROP
GROUND
872 —40 —20
EDGE OF
PAVEMENT
888If
884
880 25-YR ELEV. �
876
872 —40
EDGE OF
PAVEMENT
888
E
884 *ROU
88o 25-YR ELEV-------
876 GRADE BANK AT
PLACE COIR FIBE
872 VEGE
868 —40
EX GROUP
PROF
GROUNC
—20
GRADE BACK BANK AT 2:1 SLOPE
AND PLACE CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED
ROCK WALL. EXTEND GEOBAG
LIFTS TO DAYLIGHT SLOPE.
EDGE OF
PAVEMENT
25-YR ELEV. ,
PROP 1 -TIER STA
GROUND ROCK WALL
0 20 40
STA 4+50
PROP -
GROUND
0
STA 5+00
GRADE BACK BANK AT 2:1 SLOPE
AND PLACE CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED
ROCK WALL. EXTEND GEOBAG
LIFTS TO DAYLIGHT SLOPE.
- - OHWM
1 -TIER STACKED
ROCK WALL
20
GRADE BANK AT 2:1 SLOPE.
PLACE COIR FIBER MAT AND
VEGETATE (TYP)
NOTE: CONTRACTORS SHALL STAY
WITHIN THE SPECIFIED LATERAL
LIMITS AND SHALL NOT DISTURB
GRAVES. APPROVED MATS OR
PLYWOOD SHALL BE USED TO
PROTECT ALL GRAVES WITHIN 10 FT
OF EQUIPMENT. EXCAVATORS WITH
TAIL SWING SHALL NOT BE
892 ALLOWED DURING CONSTRUCTION.
888
884
880
NOTES:
876
1. ALL GRADED SLOPES SHALL
872 BE LINED WITH COIR
MATTING PER THE DETAIL.
868 2. ALL STACKED ROCK WALL
:•,
- � 880
EX GROUND 876
40 872
888
EDGE OF
PAVEMENT 884
25-YR ELEV. OHWM 880
INSTALL 876
CONSTRUCTED RIFFLE
0 20 40
872
STA 5+50
GRADE BANK AT 2:1
SLOPE. PLACE COIR FIBER
KAAT Alvin \/F(;FTATF (TYP)
JD
EDGE OF
PAVEMENT
OHWM
-
0 20
STA 6+00
F1 -TIER STACKED ROCK WALL
AND GRADE BANK AT 2:1
40
M
■ ���
—20 0
STA 6+50
20
40
888
884
880
876
872
888
884
880
876
872
868
WILL BE BLENDED TO
EXISTING GROUND AT TOP
OF ROCK TO LIMIT EROSION
AT TOP OF WALL.
3. PLACE SINGLE COIR
WRAPPED LIFT ABOVE
STACKED ROCK WALL AS
REQUIRED
4. GEOBAGS WILL BE BUILT IN
A MANNER THAT BLENDS
WITH EXISTING BACKSLOPE.
A MINIMUM OF 6 LIFTS (-3
FT ABOVE STONE) AT -2:1
(H:V) SLOPE UNLESS
OTHERWISE SPECIFIED ON
PLANS. LIFTS CAN BE
PLACED AS STEEP AS 1.5:1
(H:V). MORE BAG LAYERS
MAY BE USED AT DIRECTION
OF ENGINEER.
U c
zw
-0-0
c T
0
a) .N
N
0
0
0
U
t
0
z
N
z
N
O
w N O
_�
M R
w �
�o-iA
oz z
ZON
N o Yo w
U
z Nwo 00
O nL
U w
i
�a
N�}oz�
O Z m
m
L_ z0oo
amo Q
OLj,-
O cn �00
��ZILI
coow�0
�aaz�m
W�
J
�O
N
0
W=
0�
W_
o�
V
U�
C°
y 0
c)U
o��
aW
MEW
cn Z r N
-c
J I 13
■
00
Z U
N c:�
0
W
U
Q
0—
0
W
OD
z
W
O
z
z�
Q
O
p
+
J
�N/j
V /
=wwu
z
of
0
k- z
00
Q
W
W
z�
p
0
J
U
Q
co
o
J
co
N
m
N
o
z
a-
Q
o
m=
w
o
U
z
z
w
y
w
U
U-
U x
U)
w
w
Lu
~
a
o
z cn
U
}
m
_F0o
0_0
O 0 o}'
U)
U O-0
c: c:
a)
O cm 0)
L (n
0 10 2 0'
°0
w�
Q
SCALE IN FEET
U
w
cn
c
0
z
w
> o
IMPACT
SHEET
4
FINAL DESIGN
SEQ.
Plot Dote: 1 /25/2024 4:33 PM Plot By: 03807 Filename: N:\WTU\Drawings\CV—STREST—XS.dwg
STANDARDS AND SPECIFICATIONS
11
1. BASEMAP INFORMATION IS FROM A TOPOGRAPHIC SURVEY PERFORMED BY STEWART, DATED NOVEMVER 11, 2018. ALL
COORDINATES ARE BASED ON NAD83 AND REALIZATION (2011) AND ALL ELEVATIONS ARE BASED ON NAVD 88.
2. LOCATIONS, ELEVATIONS, DIMENSIONS OF EXISTING UTILITIES, STRUCTURES, AND OTHER FEATURES ARE SHOWN ACCORDING
TO THE BEST INFORMATION AVAILABLE AT THE TIME OF PREPARATION OF THESE DRAWINGS, HOWEVER ARE NOT
PURPORTED TO BE ABSOLUTELY CORRECT. THE CONTRACTOR SHALL VERIFY LOCATIONS, ELEVATIONS, DIMENSIONS OF ALL
EXISTING UTILITIES, STRUCTURES, AND OTHER FEATURES AFFECTING THE WORK PRIOR TO CONSTRUCTION. THE CONTRACTOR
SHALL ASSUME FULL RESPONSIBILITY FOR ANY DAMAGE TO UTILITIES.
3. IN THE ABSENCE OF DETAILS OR SPECIFICATIONS IN THESE CONTRACT DOCUMENTS APPLICABLE DESIGN AND DETAILS
SHALL CONFORM TO GENERAL CONTRACT DOCUMENTS AND SPECIFICATIONS FOR THE CITY OF HIGH POINT.
4. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE REGULATIONS OF THE OCCUPATIONAL SAFETY AND HEALTH
ADMINISTRATION (OSHA).
5. BRACE UTILITY POLES AS REQUIRED TO MAINTAIN STABILITY OF THE POLES DURING CONSTRUCTION SUBSIDIARY TO WORK.
6. THE WORK SHALL MEET NCDEQ'S MINIMUM REQUIREMENTS PRESCRIBED IN TITLE 15A, SUB -CHAPTER 18C-WATER, TITLE
15A, SUB -CHAPTER 02T-WASTE NOT DISCHARGED TO SURFACE WATER, AND STORMWATER SUPPLIES.
7. CONTACT THE NORTH CAROLINA ONE -CALL CENTER AT 1-800-632-4949 A MINIMUM OF THREE DAYS AND A MAXIMUM
OF 10 DAYS BEFORE ANY EXCAVATION WORK IS CONDUCTED ASSOCIATED WITH THIS PROJECT SO AS TO AVOID UTILITY
DAMAGE.
8. EXISTING IMPROVEMENTS INCLUDING, BUT NOT LIMITED TO FENCES, DRIVEWAYS, SIDEWALKS, TRAFFIC SIGNS, MAIL BOXES
PAVEMENT, CURBS, UTILITY PIPELINES, AND DRAINAGE STRUCTURES WHICH ARE DAMAGED, REMOVED OR ALTERED TO
PERMIT INSTALLATION OF THE WORK SHALL BE REPAIRED OR REPLACED BY THE CONTRACTOR, AT THE CONTRACTOR'S
EXPENSE, IN THE SAME LOCATION AND IN CONDITION AS GOOD OR BETTER THAN THEY WERE FOUND.
EROSION CONTROL NOTES:
1. ALL CONSTRUCTION SHALL BE IN ACCORDANCE WITH STATE (NCDEQ) AND LOCAL REQUIREMENTS.
2. CONTACT THE DEMLR WINSTON-SALEM REGIONAL OFFICE, 336-776-9800, AT LEAST 48 HOURS PRIOR TO COMMENCING THE LAND
DISTURBING ACTIVITY.
3. THE INSPECTION AND MAINTENANCE OF THE EROSION PREVENTION MEASURES SHALL BE THE CONTRACTOR'S RESPONSIBILITY
THROUGHOUT ALL PHASES OF CONSTRUCTION. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO COMPLY WITH THE NCDEQ
REGULATIONS CONCERNING EROSION AND SEDIMENT CONTROL.
4. EROSION AND SEDIMENTATION CONTROL MEASURES SHALL BE INSPECTED IN ACCORDANCE WITH NCDEMLR AT LEAST ONCE EVERY 7
CALENDAR DAYS AND WITHIN 24 HOURS AFTER ANY STORM EVENT GREATER THAN 0.50 INCHES OF RAIN PER 24-HOUR PERIOD.
SELF -INSPECTION FORM CAN BE FOUND AT
HTTP:/DEO.NC.GOV/ABOUT/DIVISIONS/ENERGY- MINERAL- LAND- RESOURCES/EROSION -SEDIMENT-CONTROL/FORMS. REQUIRED REPAIRS
SHALL BE MADE IMMEDIATELY.
5. DESIGN COMPONENTS SHOWN ON PLANS MAY REQUIRE FIELD ADJUSTMENTS AT DIRECTION OF ENGINEER.
6. ERODED DITCHES/BANKS SHALL BE REPAIRED WITH A SUITABLE MATTING PER DETAIL.
7. CONTRACTOR TO USE A LAYDOWN/STAGING AREA AS SHOWN ON THE PLANS. IF ADDITIONAL AREAS ARE REQUIRED, CONTRACTOR IS
RESPONSIBLE FOR ACQUIRING THIS AREA AND PROVIDING THE REQUIRED EROSION CONTROL MEASURES.
8. TOTAL ACREAGE DISTURBED EQUALS APPROXIMATELY 1.3 ACRES.
9. CONTRACTOR SHALL INSTALL AND UTILIZE TEMPORARY CONSTRUCTION ENTRANCES PER DETAIL FOR ALL OFF -PAVEMENT ACCESS.
0
U
N
Z
N
0
N O
v =~
w .Q�
-owo�
oZ Z
(A o�Yo
U
Z
O wa> �a
w
c-) w��
N
o �Zmomw
LL_ Z-�z 0-
0
U W Z U
0 0 cf.)
��Z �ca�cno
�aaz�m
WIIA
J
mO
N
O
W
=
o�
W
or-
V
Ur-
CO
0
ID
zC_
O 0)N
(3NV
C/) Z r N
-tf
-3
J I
Cc:
Z O
N
0
0
cn a
10. CONTRACTOR SHALL INSTALL ALL EROSION CONTROL MEASURES AND DEVICES BEFORE LAND DISTURBING ACTIVITIES COMMENCE.
9.
THE CONTRACTOR SHALL REMOVE FROM THE PROJECT AREA ALL SURPLUS MATERIAL. THIS SHALL BE INCIDENTAL AND
NOT A SEPARATE PAY ITEM. SURPLUS MATERIALS FROM EXCAVATION INCLUDING DIRT, TRASH, ETC. SHALL BE PROPERLY
11. STANDARD SEDIMENT CONTROL DEVICES ARE TO BE FURNISHED, INSTALLED, AND MAINTAINED IN GOOD WORKING ORDER AT STORM
LiJ
DISPOSED OF AT AN ACCEPTABLE SITE. IF THE CONTRACTOR PLACES EXCESS MATERIAL IN THE AREAS WITHOUT
INLETS AS SHOWN ON THE PLANS AND AT THE DISCRETION OF THE ENGINEER TO ENSURE PROJECT SEDIMENT IS PROPERLY
U
PERMISSION, CONTRACTOR WILL BE RESPONSIBLE FOR ALL DAMAGE RESULTING FROM SUCH FILL AND CONTRACTOR SHALL
CONTROLLED WITHIN THE PROJECT LIMITS.
REMOVE MATERIAL AT ITS OWN COST.
J
12. CITY OF HIGH POINT CONTACT PERSON RESPONSIBLE FOR MAINTENANCE: MELINDA KING, 336-883-3215.
10.
THE DESIGN, INSPECTION AND MAINTENANCE OF THE EROSION PREVENTION MEASURES SHALL BE THE CONTRACTOR'S
RESPONSIBILITY THROUGHOUT ALL PHASES OF CONSTRUCTION. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO
w
Z
COMPLY WITH THE NCDEQ REGULATIONS CONCERNING EROSION AND SEDIMENT CONTROL.
0
O
11.
CONTRACTOR SHALL MAINTAIN SUITABLE CONSTRUCTION ACCESS FOR THE ENGINEER AND CITY OF HIGH POINT STAFF AT
Z
Z
ALL TIMES DURING CONSTRUCTION.
O
Q
LLJ
z
�
�
12.
CONTRACTOR SHALL BE RESPONSIBLE FOR KEEPING ALL EXISTING UTILITIES IN SERVICE DURING CONSTRUCTION,
O
0
Z
13.
CONTRACTOR SHALL PROVIDE CLOSURE PIECES FOR PIPELINE AS REQUIRED TO CONSTRUCT THE PROJECT, INCLUDING
=
THOSE REQUIRED FOR SPECIAL CONSTRUCTION PROCEDURES REQUIRED TO COORDINATE OWNER'S CHANGES TO THE
LD w
CI)
J
>
J
SEQUENCE OF CONSTRUCTION. ALL CLOSURE PIECES SHALL BE CONSIDERED A SUBSIDIARY COST TO THE PROJECT AND
u
w
u
<
WILL BE PROVIDED AT NO ADDITIONAL COST TO THE OWNER.
J
0
_
LLJ
14.
THE CONTRACTOR SHALL VIDEO ALL IMPACTED PROPERTY WITHIN THE CONSTRUCTION LIMITS PRIOR TO WORK. VIDEOS
�-- Z
Z
SHALL INCLUDE DATE NOTATION AND AUDIO IDENTIFICATION OF PROPERTY ADDRESS AND MAIN/LATERAL NAME. THIS PRE
00
Q
Lv
CONSTRUCTION VIDEO TAPING OF IMPACTED PROPERTIES SHALL BE CONSIDERED SUBSIDIARY WORK.
LLI
0
i
15.
THE CONTRACTOR IS RESPONSIBLE FOR KEEPING STREETS AND SIDEWALKS ADJACENT TO PROJECT FREE OF MUD AND
Z
DEBRIS FROM THE CONSTRUCTION.
O
co
I-
J
Q
TRAFFIC CONTROL NOTES:
_
1.
THE CONTRACTOR SHALL PROVIDE ADEQUATE WARNING SIGNS, LIGHTS, BARRIERS, RAILING, FLAGGERS, ETC., AND SHALL CONDUCT ALL
WORK IN ACCORDANCE WITH THE LATEST VERSION OF THE NCDOT "STANDARD SPECIFICATIONS FOR ROADS AND STRUCTURES," NCDOT
"ROADWAY STANDARD DRAWINGS MANUAL," MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD), AND THE NCDOT SUPPLEMENT TO
THE MUTCD (NCSMUTCD). THE CONTRACTOR SHALL POSSESS ONE COPY OF EACH OF THE ABOVE REFERENCED PUBLICATIONS. ANY
m
m
CONFLICTS FOUND BETWEEN THE NCSMUTCD AND THE MUTCD SHALL BE RESOLVED IN FAVOR OF THE MUTCD.
�
N
o
z d
Q
°ui
°
2.
THE CONTRACTOR SHALL CONDUCT OPERATIONS SO AS TO MAINTAIN AND PROTECT ACCESS FOR VEHICULAR AND PEDESTRIAN TRAFFIC,
o
TO AND FROM ALL PROPERTIES AFFECTED BY OPERATIONS.
o6
W
Q
w
of
w
H
W
3. UNLESS OTHERWISE REQUIRED, MATERIALS USED IN THE FABRICATION AND INSTALLATION OF CONSTRUCTION TRAFFIC CONTROL DEVICES
b
z
W
SHALL BE IN ACCORDANCE WITH THE APPLICABLE PROVISIONS OF THE MUTCD. WHEN TRAFFIC CONTROL DEVICES ARE NO LONGER
o
J
z Q
REQUIRED FOR TRAFFIC HANDLING IN THE INITIAL PHASE OF CONSTRUCTION REQUIRING THEIR USE, THEY MAY BE REUSED AT VARIOUS
LOCATIONS THROUGHOUT THE PROJECT PROVIDED THE DEVICE IS NOT DEFACED, IS STRUCTURALLY SOUND, CLEAN, AND OTHERWISE
m
o
J
CONFORMS TO THE ABOVE REQUIREMENTS.
J
Q
z
4.
ALL WORK ASSOCIATED WITH THE FURNISHING, INSTALLING, AND REMOVING OF PAVEMENT MARKINGS AND PAVEMENT MARKERS SHALL
o
BE PERFORMED IN ACCORDANCE WITH THESE CONTRACT DOCUMENTS AND THE LATEST PUBLICATION OF THE NORTH CAROLINA
w
DEPARTMENT OF TRANSPORTATION "STANDARD SPECIFICATIONS FOR ROADS AND STRUCTURES." AND "ROADWAY STANDARD DRAWINGS."
°
m
PERMANENT PAVEMENT MARKING SHALL BE ALKYD/MALEIC THERMOPLASTIC.
°'L
O U
O
cn >
5.
CONTRACTOR SHALL INSTALL AND MAINTAIN TRAFFIC CONTROL PLAN. CONTRACTOR SHALL MAINTAIN ONE (1) LANE OF TRAFFIC AT
°
w
ALL TIMES DURING CONSTRUCTION, UNLESS AUTHORIZED BY THE CITY OF HIGH POINT WITH PROPER ADVANCED NOTICE. FOR
°
w
TEMPORARY ROAD CLOSURE, ALL TRAFFIC CONTROL MEASURES AND PROCEDURES SHALL IMPLEMENT PROPER SAFEGUARDS. ALL
C -a
`n
BARRICADES, WARNING SIGNS, LIGHT DEVICES, ETC., FOR THE GUIDANCE AND PROTECTION OF TRAFFIC AND PEDESTRIANS, MUST
°.�
Q
CONFORM TO THE NCDOT MANTENANCE/UTILITY TRAFFIC CONTROL GUIDELINES.
W
cn
6.
CONTRACTOR TO ENSURE THAT ACCESS IS MAINTAINED TO ALL ACTIVE BUSINESSES DURING BUSINESS HOURS WHILE CONSTRUCTION IS
w r
N
UNDERWAY. CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING WITH AFFECTED BUSINESS OWNERS.
W
W
ZZ \
Ln
ccnn
>_
(V Q \
cn
W
p
>o
(mil Z ..
0
SHEET
E N
0
��cn
G-1
0
Q
FINAL DESIGN
SEQ.
Plot Date: 1 /25/2024 1 :34 PM Plot By: 03807 Filename: N:\STANDARD\STREAM SHEET SET FILES\GN-ALL- NOTE- 1 .dwg
0)
a
I
0
Z
CD
J
I
J
J
Q
I �
Z O
CD 00
/ rq
U) O
W
J
m
W �
U) >
O
W
LLJ
Cf) 75
n
Q
W
U �
N cf)
0
(f) ry O
� O\
Z Ln
cn Q N
N �\
N Z ..
. N
cn
N O >
O
O
Q O (n
u — O
Q L� J
rl-
00
0
�m
p
>
cf)�
W
U�
m
U
/N
U'v
C
v) 0 O
� p N
�Ln
N ~
CN
N Z ..
a� a� >
E U
0
cn
QQ)cn
u — O
Q L7 J
INSTALL CONSTRUCTION
SAFETY FENCE AROUND \d STA 0+07.21
PROJECT LIMITS, TYP BEGIN 3-TIER ROCK WALL
SEE NOTE 5 AT END OF CULVERT HEADWALL
\ WITH GEOBAG WALL SYSTEM
V ABOVE AT 2:1 SLOPE.
STABILIZE AND VEGETATE
LIMITS OF DISTURBANCE
(SEE SHEET C-3 AND C-5)
,
EXISTING FENCE
PROPOSED STAGE
AND STOCKPILE AREA
PROPOSED
/ CONSTRUCTION
/ ENTRANCE EXISTING STORM DRAIN
/ OUTFALL TO BE REMOVED
BY OTHERS
SILT FENCE, TYP
C�f
wv
\\ / [2-7,
-� —5
STA-0+91��,
SD LINE 2
JUNCTION BOX
1
----
N=807795.74
E=1701622.26
BY OTHERS
�1000p
j9 \P
/ V J
PROPOSED DROP INLET
PROTECTION BY OTHERS
EROSION CONTROL NOTES:
i
STA 0+00.00
BEGIN CHANNEL REALIGNMENT 5
CULVERT OUTFALL ELEV. 888.0
PROPOSED HEADWALL BY OTHERS
�STA 0+00.00
PREFORMED SCOUR
t '\, PROTECTION (TYP)
LIMITS OF
GRAVES
0+
PROPOSED
SD LINE 2
BY OTHERS
900
1. CONTACT THE DEMLR WINSTON-SALEM REGIONAL OFFICE 336-776-9800 AT LEAST
48 HOURS PRIOR TO COMMENCING THE LAND DISTURBING ACTIVITY.
2. EROSION AND SEDIMENTATION CONTROL MEASURES SHALL BE INSPECTED IN
ACCORDANCE WITH NCDEMLR AT LEAST ONCE EVERY 7 CALENDAR DAYS AND WITHIN
24 HOURS AFTER ANY STORM EVENT GREATER THAN 0.50 INCHES OF RAIN PER
24-HOUR PERIOD. SELF -INSPECTION FORM CAN BE FOUND AT
HTTP://DEQ.NC.GOV/ABOUT/DIVISIONS/
ENERGY-MINERAL-LAND-RESOURCES/EROSION-SEDIMENT-CONTROL/FORMS.
3. DESIGN COMPONENTS SHOWN ON PLANS MAY REQUIRE FIELD ADJUSTMENTS AT
DIRECTION OF ENGINEER.
4. ALL DEBRIS REMOVED DURING TRENCH EXCAVATION IS TO BE IMMEDIATELY HAULED
TO A PERMITTED OFF -SITE DISPOSAL LOCATION.
5. CITY OF HIGH POINT CONTACT PERSON RESPONSIBLE FOR MAINTENANCE:
MELINDA KING 336-883-3217
STA 1 +45.65
END 3-TIER ROCK WALL WITH
GEOBAG WALL SYSTEM ABOVE
PROTECT EXISTING SEWER
WITH GROUTED RIPRAP
SEE NOTE 6
EXISTING CHANNEL
CENTERLINE
♦ _ -- ice.
PROPOSED
SD LINE 1
BY OTHERS
�- •-'��� LIMITS OF
\ GRAVES
ENCASE SEWER IN CONCRETE
AT ROCK WALL CROSSING
SEE NOTE 7
STA 0+04.65 STA 1 +45.97
BEGIN 2-TIER ROCK WALL END 2-TIER ROCK WALL WITH
AT END OF CULVERT HEADWALL GEOBAG WALL SYSTEM ABOVE
WITH GEOBAG WALL SYSTEM
ABOVE AT 2:1 SLOPE
STABILIZE AND VEGETATE
(SEE SHEET C-3 AND C-5)
NOTE: CONTRACTORS SHALL STAY
WITHIN THE SPECIFIED LATERAL
� LIMITS AND SHALL NOT DISTURB
GRAVES. APPROVED EQUIPMENT
MATS SHALL BE USED TO PROTECT
j ff, ALL GRAVES WITHIN 10 FT OF �
EQUIPMENT. EXCAVATORS WITH TAIL
SWING SHALL NOT BE ALLOWED
DURING CONSTRUCTION.
NOTES:
1.
FINAL LOCATION OF CONSTRUCTED RIFFLES SHALL BE
VERIFIED IN FIELD AND APPROVED BY ENGINEER OF
RECORD.
2.
STONE FOR ROCK TOE SHALL BE APPROVED BY CITY
PRIOR TO INSTALLATION.
3.
CONTRACTOR SHALL TEMPORARILY STOP WORK DURING
BURIALS. CITY WILL PROVIDE 24-HOUR PRIOR NOTICE.
4.
IF ANY CEMETERY PROPERTY IS DAMAGED,
o
CONTRACTOR SHALL REPLACE AT NO COST TO OWNER.
+
5.
CONTRACTOR SHALL COORDINATE WITH CEMETERY
STAFF PRIOR TO INSTALLATION OF CONSTRUCTION
115
SAFETY FENCE TO VERIFY LOCATION AND DEPTH OF
N
WOODEN STAKES. (OFFICE PHONE NUMBER:
336-883-3408)
6.
INSTALL GROUTED RIPRAP TO PROTECT EXISTING
=
SEWER PIPE. GROUTED RIPRAP SHALL EXTEND FROM
EDGE OF PIPE WEST TO PROPOSED ROCK WALL AND
A MINIMUM OF 6 INCHES ON ALL SIDES OF PIPE.
7.
ENCASE SEWER PIPE IN CONCRETE AT LOCATION
WHERE IT RUNS UNDER PROPOSED ROCK WALL.
CONCRETE SHALL BE MINIMUM 6 INCHES THICK ON
ALL SIDES. EXTEND CONCRETE MINIMUM 1' PAST ROCK
WALL BOTH SIDES.
8.
REPLACEMENT OF STORMWATER PIPES IS PART OF A
SEPARATE PROJECT. WORK WILL BE COORDINATED
PRIOR TO CONSTRUCTION.
9.
IF UNMARKED HUMAN SKELETAL REMAINS ARE
ENCOUNTERED DURING CONSTRUCTION, THE PROVISIONS
OF NORTH CAROLINA GENERAL STATUTE CHAPTER 70,
ARTICLE 3 APPLY. CONSTRUCTION ACTIVITIES SHOULD
IMMEDIATELY CEASE, AND THE COUNTY MEDICAL
EXAMINER SHOULD BE CONTACTED.
—1+00 0+00 1+00 1+ 50
Role]
0 10' 20' 40'
SCALE IN FEET
HORIZONTAL
0 2' 4'
SCALE IN FEET
VERTICAL
FINAL DESIGN
0
0
0
z
N
z
N
0 \
CZ
N O
w
U =~ �U
�owo�
oz z
~ �vi
N o v 0 w
z Nwo 00
o <> �a
ww
U - c' cz,
�wroF-
p m�
w-wZ
o
Z 0
0
O 00of
z ��0<cno
�am
Wu
J
00
N
0
W
Vo�
(1
y 0
ID
NW
o0)�
cZ r N
0
U 3
D
Z o
N C�
0
w
U
O
Q
L.f i
0-
r-I
uJ
z
O
00
Z
z
1O
Q
+
z0
0�
O
°2
O
z
��
�
J
O
= Lu
Lu
u
H
Q
LL
O
Or_
�z
7
O
U0
Q
w
Lu
z
�
c
O
~
Q
J
Lu
re
7
Q
op
o
J
M
N
m
N
O
z
a-Q
o
m=
w
oLLJ
U
Z
Z
W
y
ul
U
3:
cf)
U
Z
H
W
<
>
W
Q
LL
Q
Q
(If
U
cn
w
Lu
Lu
7
<
<
o
z
J >
1 U
}
m
Lu
cn
0
z
SHEET
SEQ.
C-1
Plot Dote: 1 /25/2024 1 :35 PM Plot By: 03807 Filename: N:\WTU\Drawings\CV—STREST—DT.dwg
rl-
0
00
0
�m
p
I >
� O
cf)�
W
V)
I a-
U
/N
U
v) 0 O
p N
Ln
cn N ~
CN
a� a� >
cn
0
QQ)cn
u - O
Q L7 J
STA 1 +90.42
PREFORMED SCOUR
PROTECTION (TYP)
� STA 1 +89.73 OAKWOOD
BEGIN LAY BACK BANKS MEMORIAL STA 3+43.82 STA 5+30.98
PROPOSED 000 0AT 2:1 SLOPE. INSTALL PARK END 1—TIER ROCK WALL BEGIN LAY BACK BANKS
SD LINE 1 COIR MATTING AND PLANT WITH GEOBAG WALL SYSTEM AT 2:1 SLOPE. INSTALL
BLEND TO EXISTING COIR MATTING AND PLANT
BY OTHERS (SEE SHEET C-4 AND C-5) O ABOVE AT 2:1 SLOPE BLEND TO EXISTING
O TRANSITION TO GRADING
BANKS AT 2:1 SLOPE O (SEE SHEET C-4 AND C-5)
STA 2+93.92 O p0
END LAY BACK BANKS AT 2:1 QC (SEE SHEET C-4 AND C-5)
SLOPE TRANSITION TO 1 —TIER
0s ROCK WALL WITH GEOBAG WALL O O
Q O
SSSYSTEM ABOVEAT 2:1 SLOPE. A GRADE BANKS AT 2:1 SLOPE
STABILIZE AND VEGETATE STABILIZE WITH COIR MATTING
O O
(SEE SHEETS C-4 AND C-5) O AND PLANT VEGETATION ss
—ss (SEE SHEET C-4 AND C-5) s � _s5
} � `•�'�• �S STA 4+77.92 /•/'�
'�. wadi,
:77�•�• S ss END PROPOSED �•�•
LOODPLAIN BENCH
LEN TO EXISTING
L Ll
NUY'.� ; * - EE SHEET C-4 AND C-5)
O❑
e`5
z 1___'
STA 5+40.06
BEGIN 20'
CONSTRUCTED
RIFFLE
SEE NOTE 1
ss
Ssy ss ss
CO'
NOTE: CONTRACTORS SHALL STAY
-)
/
WITHIN THE SPECIFIED LATERAL
E
STA 6+61.18
END LAY BACK
BANKS
LIMITS AND SHALL NOT DISTURB
AT 2:1 SLOPE.
INSTALL
GRAVES. APPROVED MATS OR
c
COIR MATTING
AND PLANT
PLYWOOD SHALL BE USED TO
� a)
BLEND TO EXISTING
PROTECT ALL GRAVES WITHIN 10 FT
0 c
(SEE SHEET C-4
AND C-5)
OF EQUIPMENT. EXCAVATORS WITH
ZU w
ass
TAIL SWING SHALL NOT BE
oT
,
—�5
ALLOWED DURING CONSTRUCTION.
7"—s—s—s—
0
STA 6+23.45
BEGIN 20'
uCONSTRUCTED
_Ss—sSs
_
--ISS -
y
L
SEE NOTE 1
z
.�
- -RIFFLE
HORIZONTAL —
�—
\
STA 1 +99.88
8so
�� ��� �� �/ '�� �� �� /�
,�
STA 6+42.52
�.
BEGIN 20'
STA 3+39.92
BEGIN 1 —TIER ROCK WALL
'
CONSTRUCTED
BEGIN PROPOSED
-
STA 5+ 15.55
RIFFLE
CHANNEL ALIGNMENT
LAY BACK BANKS
STA 6+57.48
SEE NOTE 1
--__—WITH
FLOODPLAIN BENCH
- �4+00 00 =
AT 2BEGIN
:1 SLOPE. INSTALL
END 1—TIER ROCK WALL
'—•—_
- � •�
WITH BANKS LAID BACK
INSTALL CONSTRUCTION
SAFETY FENCE AROUND
PROJECT LIMITS, TYP
SEE NOTE 5
—•— _,
- -
_ ��
.� COIR MATTING AND PLANT
BLEND TO EXISTING ABOVE AT 2:1 SLOPE
�,�•�'
-
(SEE SHEET C-4 AND C-5) BLEND TO EXISTING
STA 3+40.13
cp. i,i'�
C EM ETERYPs
(SEE SHEET C-4 AND C-5)
BEGIN 1 —TIER
ROCK WALL
�
/ •�•
STA 41—TIER 6ROCK
WITH GEOBAG
WALL SYSTEM
—.—•—.—.—•—
•��'�� Z
END
END WALL
ABOVE AT 2:1
STABILIZE AND
SLOPE
VEGETATE
EXISTING CHANNEL
WITH GEOBAG WALL SYSTEM
(SEE SHEET C-4
AND C-5)
CENTERLINE
PROVIDE 5 FT MINIMUM
2:1 SLOPE
STBAOBILI EAVE AT AND VEGETATE
BETWEEN TOP OF BANK
(SEE SHEET C-4 AND C-5)
AND EDGE OF PAVEMENT
LIMITS OF DISTURBANCE
0 2
y
—�
SCALE IN FEET
WNW
0 °'
� r ,
D � 3
`1
NOTES:
J
, 3
z o ,
1 .
FINAL LOCATION OF CONSTRUCTED RIFFLES SHALL BE
Q)
VERIFIED IN FIELD AND APPROVED BY ENGINEER OF
RECORD.
2.
STONE FOR ROCK TOE SHALL BE APPROVED BY CITY
PRIOR TO INSTALLATION.
3.
CONTRACTOR SHALL TEMPORARILY STOP WORK DURING
w
BURIALS. CITY WILL PROVIDE 24—HOUR PRIOR NOTICE.
V
4.
IF ANY CEMETERY PROPERTY IS DAMAGED,
0
CONTRACTOR SHALL REPLACE AT NO COST TO OWNER.
Q
z
5.
CONTRACTOR SHALL COORDINATE WITH CEMETERY
J
STAFF PRIOR TO INSTALLATION OF CONSTRUCTION
Lu
SAFETY FENCE TO VERIFY LOCATION AND DEPTH OF
W
WOODEN STAKES. (OFFICE PHONE NUMBER:
Z
336-883-3408)
0
0
6.
IF UNMARKED HUMAN SKELETAL REMAINS ARE
LI
ENCOUNTERED DURING CONSTRUCTION, THE
Z
Q
+
PROVISIONS OF NORTH CAROLINA GENERAL STATUTE
z O
<
CHAPTER 70, ARTICLE 3 APPLY. CONSTRUCTION
ACTIVITIES SHOULD IMMEDIATELY CEASE, AND THE
0
O
Z
COUNTY MEDICAL EXAMINER SHOULD BE CONTACTED.
_
0
J
892
r W
W
>
XISTINO 48"
PIPE
888
888
PROPOSED 40 LF OF
6' X 4' BOX CULVERT
@ 3,73% BY OTHERS
EXISTING GRADE AT
CONSTRUCTED RIFFLE
884
PROPOSED CENTERLINE
884
CONSTRUCTED
RIFFLE
I N V:
883.00
880
880
CONSTRUCTED RIFFLE
CONSTRUCTED
RIFFLE
PREFORMED SCOUR
w
—
876
PROTECTION PROPOSED
GRADE
EXISTING CHANNEL GRADE.
MATCH EXISTING GRADE WITH
876
Z
�_
J
w
Z
--
_
o
w
SHIFTED CHANNEL ALIGNMENT
a
0 0 0-
LnLn0
\\
co CO U
q 4 0
+ 0-
Z
��[if
�� a
QWZ
Lnww
872
�Jw
cnwm
872
1+50
2+00
3+00
4+00
5+00
6+00
LL
0 J
U
�
�Z
5
G
u 0
2i
Lu
I
mow/
0.
Z
�
0
co
Q
�
J
Lu
N
It
�:
2
0
op
O
J
M
N
m
N
O
z
Q
o
m 2
w
p
ow
U
Z
Z
W
y
ul
(D
3:
LO
U
Z
H
Cn
Q
>
Lu
FL
Lu
Lu�
Q �
o
z cn
Lu
U
LL
m
M 0
i C M
m
O O
O
U O-0,
_c:M
O 0)o
L (n
m
m �
w�
J
Q
U
w
cn
O
z
J.
W
> o
SHEET
6+80 C-2
FINAL DESIGN SEQ.
Plot Dote: 1 /25/2024 1 :36 PM Plot By: 03807 Filename: N:\WTU\Drawings\CV—STREST—DT.dwg
Al
01
3
�m
cn
x a)
1 >
cf)�
1J
cn n
I
>
U p
-�- /N
a
C/� 20
p N
Ln
cn
N ~
a)
a�6>
��cn
0
QQ)co
U — O
Q L- J
GRADED SLOPE ABOVE
CULVERT HEADWALL BY
OTHERS
912
PROP GROUND -
908
904 -
900
896 EX CULVERT TO
892 BE REMOVED BY
OTHERS
888 EX SEWER TO -
REMAIN IN SERVICE
884 -40 -20
LIMIT OF
912
GRAVESTONES /
LIMIT OF
DISTURBANCE
908
904
900
896
892
888
884
880
-40 -20
d ►.
EX GROUND 912
LIMIT OF 908
DISTURBANCE
0
STA 0+00
904
900
- 896
PROP 6'(H) x 4'(V) CULVERT BY OTHERS 392
OHWM
888
BOULDER BASIN 40 884
AT CULVERT
OUTFALL
GRADE BACK BOTH BANKS AT MAX
2:1 SLOPE AND PLACE 4 LIFTS
CONSTRUCTED GEOBAG WALL SYSTEM
ABOVE STACKED ROCK WALL. PLACE
c niR MAT ANn VFC;FTATF ARnVF
GEOBAG WALL (TYP)
PROP GROUND
2-TIER STACKED
ROCK WALL
GROUND -
EX
25-YR ELEV.
LIMIT OF
DISTURBANCE
OHWM
3-TIER STACKED
ROCK WALL
GROUTED RIPRAP
AROUND SEWER PIPE
SEE NOTE 5
BOULDER BASIN
PROP GROUND
908
-
-
904
—
900
896
892
888
LIMIT OF
GRAVESTONES /
LIMIT OF
- DISTURBANCE
GROUTED RIPRAP
884 AROUND SEWER PIPE
SEE NOTE 5
880 -40 -20
0
STA 0 + 1 2
20
GRADE BACK BOTH BANKS AT MAX
2:1 SLOPE AND PLACE 4 LIFTS
40
912
908
904
900
896
892
888
884
880
CONSTRUCTED GEOBAG WALL SYSTEM 912
ABOVE STACKED ROCK WALL. PLACE
COIR MAT AND VEGETATE ABOVE 908
GEOBAG WALL (TYP)
EX GROUND 904
/7777:: 3-TIER STACKED
— ROCK WALL 900
— T — ----- — 896
LIMIT OF 892
—T7725-YR ELEV. DISTURBANCE
OHWM
888
2-TIER STACKED 884
ROCK WALL
0 20 40 880
STA 0+25
GRADE BACK BOTH BANKS AT MAX
2:1 SLOPE AND PLACE 4 LIFTS
CONSTRUCTED GEOBAG WALL SYSTEM
ABOVE STACKED ROCK WALL. PLACE
COIR MAT AND VEGETATE ABOVE
GEOBAG WALL (TYP)
3-TIER STACKED EX GROUND
ROCK WALL
PROP GROUND =
25-YR ELEV.
- 7777-
AL =11 OHWM
2-TIER STACKED
ROCK WALL
-40 -20 0 20
STA 0+38
Plot Dote: 1 /25/2024 1 :37 PM Plot By: 03807 Filename: N:\WTU\Drawings\CV-STREST-XS.dwg
MENEM
1 -I
EVAN
off • ���
888 GROUTED RIPRAP
884 AROUND SEWER PIPE
SEE NOTE 5
880
912
908
904
900
896
LIMIT OF
DISTURBANCE 892
888
884
40 880
908
904
900
896
892
888
884
880
GRADE BACK BOTH BANKS AT 2:1 NOTE: CONTRACTORS SHALL STAY
SLOPE AND PLACE 4 LIFTS WITHIN THE SPECIFIED LATERAL
CONSTRUCTED GEOBAG WALL SYSTEM LIMITS AND SHALL NOT DISTURB
ABOVE STACKED ROCK WALL. PLACE GRAVES. APPROVED MATS OR
-40 SEE NOTE 6 0
STA 0+50
LIMIT OF
GRAVESTONES / GRADE BACK BOTH BANKS AT 2:1
LIMIT OF SLOPE AND PLACE 4 LIFTS
DISTURBANCE CONSTRUCTED GEOBAG WALL SYSTEM
ABOVE STACKED ROCK WALL. PLACE
908 COIR MAT AND VEGETATE SLOPE
ABOVE GEOBAG WALL (TYP)
904
900 EX GROUND
896 —
PROP GROUND
892
888 3-TIER STACKED
ROCK WALL
884
880 -40 -20
LIMIT OF
DISTURBANCE
908
904
900 —
EX GROUND
896
PROP GROUND
892
888 3-TIER STACKED
884 I ROCK WALL
880 -40 -20
901
89_
892
888
884
880 -40 -20
0
STA 0+75
SLOPE 908 PLYWOOD SHALL BE USED TO
�P) 904 PROTECT ALL GRAVES WITHIN 10 FT
OF EQUIPMENT. EXCAVATORS WITH
-EX GROUND
900 TAIL SWING SHALL NOT BE
ALLOWED DURING CONSTRUCTION.
896
LIMIT OF
- DISTURBANCE 892
25-YR ELEV.
OHWM
888
2-TIER STACKED
ROCK WALL 884
I I 880 NOTES:
20 40
908
904
LIMIT OF 900
DISTURBANCE
896
892
� 25-YR ELEV. OHWM
— — 888
2-TIER STACKED
ROCK WALL 884
20 40 880
GRADE BACK BOTH BANKS AT
2:1 SLOPE AND PLACE 4
LIFTS CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED 908
ROCK WALL. PLACE COIR MAT
AND VEGETATE SLOPE ABOVE goo
GEOBAG WALL (TYP)
0
STA 1 +00
EX GROUND
900
LIMIT OF
DISTURBANCE 896
892
25-YR ELEV. � OHWM 888
2-TIER STACKED
ROCK WALL 884
20 40 880
GRADE BACK BOTH BANKS AT 2:1
SLOPE AND PLACE 4 LIFTS
CONSTRUCTED GEOBAG WALL SYSTEM
ABOVE STACKED ROCK WALL. PLACE
COIR MAT AND VEGETATE SLOPE
���
--- MENEM
-
. • ,
I I Let 1111
`01111
0
STA 1 +25
20
- -'-
-
-
89MEMO
892 -
888
884
880
-40
-20
0
STA 1 + 44
20
896
OF -
R A 892
LIMIT OF
900
DISTURBANCE
896
EX GROUND 892
LEV. OHWM 888
TACKED 884
L
40 880
1. ALL GRADED SLOPES SHALL BE
LINED WITH COIR MATTING PER THE
DETAIL.
2. ALL STACKED ROCK WALL WILL BE
BLENDED TO EXISTING GROUND AT
TOP OF ROCK TO LIMIT EROSION AT
TOP OF WALL.
3. PLACE SINGLE COIR WRAPPED LIFT
ABOVE STACKED ROCK WALL AS
REQUIRED
4. GEOBAGS WILL BE BUILT IN A
MANNER THAT BLENDS WITH
EXISTING BACKSLOPE. A MINIMUM OF
4 LIFTS (-2 FT ABOVE STONE) AT
-2:1 (H:V) SLOPE SHALL BE USED
UNLESS OTHERWISE SPECIFIED ON
PLANS. LIFTS CAN BE PLACED AS
STEEP AS 1.5:1 (H:V). MORE BAG
LAYERS MAY BE USED AT DIRECTION
OF ENGINEER.
5. GROUT RIPRAP BETWEEN STACKED
ROCK WALL AND EXISTING SEWER
PIPE TO PROTECT PIPE. EXTEND
GROUTED RIPRAP ABOVE AND ON
SOUTH SIDE OF PIPE FOR MINIMUM
OF 6 INCHES.
6. ENCASE SEWER PIPE IN CONCRETE
AT LOCATION WHERE IT RUNS
UNDER ROCK WALL. CONCRETE
SHALL BE MINIMUM 6 INCHES THICK
ON BOTH SIDES AND ABOVE PIPE.
EXTEND CONCRETE MINIMUM 1' PAST
ROCK WALL BOTH SIDES.
0 10 20'
SCALE IN FEET
O
0
U
O
Z
N
Z o
N
0 \
CD Z
w N 2
�I w
0.aZ0
N o
o
Y"w
Z Ln o 0
0 a > L� a
ww
U JK N
�M.zaiNa
NwroM�~
0 �Zmo ;�
LA-w-�Z
�LLoQo
�o Z of
(�W� =,O
0 oNF,000
Z ��c<�s
0
Ta-< m
WU
J
�O
N
0
W=
-`
o�
V
U�
C° E
y
1 U
NW
ors
cZ r N
�
3
U
D \-- 3
-C
J 1 3
'
1
cU
Z U
N c:�
0
Lr� a -3::
w
U
Q
J
w
z
Op
Z
QN
z O
L.f.
°2
O
U)
J
=W
W
U
� J
O
�
�z
00
Q
w
0./
z
O�
J
Q
op
o
J
co
N
co
N
o
z
a-
Q
o
m=
w
o
o 0)
o
z
z
W
y
w
U
�
L
U 7
z
u>
Q
>
w �
o
0
0
U X
H
w
W
Lu
7
~
a
o
z
1 >
1 U
}
m
W
D
0
z
SHEET
C-3
FINAL DESIGN SEQ.
�m
cn
X Q)
I >
0
cncn
W
m
In
U p
/N
a
C/� So
,2� N
Ln
cn N ~
N Z 6
Q)
>
��cn
O
QQ)co
U — O
Q L_ J
� •
r
—tee
900
896
892
888
—
EDGE OF
PAVEMENT
—
884
EX GROUND
880
876
—40
896
892 EDGE OF
PAVEMENT
888
884 EX GROUND
880 —
876 —40
—20 0
STA 2+00
PROP
GROUND
1 -TIER STACKED -
ROCK WALL
—20
1 -TIER STACKED
ROCK WALL
-20
896 GRADE BANK AT
2:1 SLOPE. PLACE
892 COIR FIBER MAT
AND VEGETATE
888 (TYP)
884
880 EDGE OF EX GROUND
PAVEMENT
876 PROP GROUND
872 —40 —20
EDGE OF GRADE BANK AT 2:1
PAVEMENT SLOPE. PLACE COIR
FIBER MAT AND
892 - VEGETATE. BLEND TO
EXISTING
888
884 — — — -- --- ---
EX GROUND
880—
876 GRADE FLOODPLAIN
BENCH AT 15:1 SLOPE.
872—PLACE COIR FIBER MAT
AND VEGETATE
868'-40 —20
20
GRADE BACK BANK AT 2:1 SLOPE AND
PLACE 4 LIFTS CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED ROCK
WALL. PLACE COIR MAT AND VEGETATE
SLOPE ABOVE GEOBAG WALL (TYP)
40
25-YR ELEV. OHWM
EDGE OF
PAVEMENT -
0 20 40
STA 2+50
GRADE BACK BANK AT 2:1 SLOPE AND
PLACE 4 LIFTS CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED ROCK
0 20 40
STA 3+00
GRADE BACK BANK AT 2:1 SLOPE
AND PLACE 4 LIFTS CONSTRUCTED
GEOBAG WALL SYSTEM ABOVE
STACKED ROCK WALL. PLACE COIR
MAT AND VEGETATE SLOPE ABOVE
GEOBAG WALL (TYP)
EDGE OF
25-YR ELEV. PAVEMENT
OHWM � -
1 -TIER STACKED
ROCK WALL
0 20 40
STA 3+50
PROP GROUND
0
STA 4+00
GRADE BACK BANK AT 2:1 SLOPE AND
PLACE 4 LIFTS CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED ROCK
WALL. PLACE COIR MAT AND VEGETATE
SLOPE ABOVE GEOBAG WALL (TYP)
—� EDGE OF
PAVEMENT
25-YR ELEV.
OHWM
1 -TIER STACKED
ROCK WALL
20 40
900
896
892
888
884
880
876
900
896
892
888
884
880
876
896
892
888
884
880
876
896
892
888
884
880
876
872
892
888
884
880
876
872
868
EDGE OF
PAVEMENT
GRADE BANK AT 2:1
SLOPE. PLACE COIR
FIBER MAT AND
892—VEGETATE.
BLEND
TO EXISTING
888
884-
880
EX
GROUND
GRADE FLOODPLAIN
876
BENCH AT 15:1 SLOPE.
PLACE COIR FIBER MAT
872
AND VEGETATE
868
40 —20
GRADE BANK AT 2:1
SLOPE. PLACE COIR
892 FIBER MAT AND
VEGETATE. BLEND
888EDGE TO EXISTING
PAVEMENTii
884 ---- __
25-YR ELEV.
880 —
876 GRADE FLOODPLAIN
BENCH AT 15:1 SLOPE.
872 PLACE COIR FIBER MAT
AND VEGETATE
888
884
880
EDGE OF EX GROUND
876 PAVEMENT PROP
GROUND
872 —40 —20
EDGE OF
PAVEMENT
888
884
880 25-YR ELEV. �
876
872 —40
EDGE O4GROUN
PAVEME
888
E
884880 25-YR ELEV.876 GRADE BANK AT
PLACE COIR FIBE
872VEG868 —40
EX GROUP
PROF
GROUNC
—20
PROP
GROUND
0
STA 4+50
PROP
GROUND
0
STA 5+00
GRADE BACK BANK AT 2:1 SLOPE
AND PLACE CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED
ROCK WALL. EXTEND GEOBAG
LIFTS TO DAYLIGHT SLOPE.
EDGE OF
PAVEMENT
25-YR ELEV. ,
1 -TIER STA
ROCK WALL
20 40
GRADE BACK BANK AT 2:1 SLOPE
AND PLACE CONSTRUCTED GEOBAG
WALL SYSTEM ABOVE STACKED
ROCK WALL. EXTEND GEOBAG
LIFTS TO DAYLIGHT SLOPE.
- -17-
OHWM
1 -TIER STACKED
ROCK WALL
20
GRADE BANK AT 2:1 SLOPE.
PLACE COIR FIBER MAT AND
VEGETATE (TYP)
NOTE: CONTRACTORS SHALL STAY
WITHIN THE SPECIFIED LATERAL
LIMITS AND SHALL NOT DISTURB
GRAVES. APPROVED MATS OR
PLYWOOD SHALL BE USED TO
PROTECT ALL GRAVES WITHIN 10 FT
OF EQUIPMENT. EXCAVATORS WITH
TAIL SWING SHALL NOT BE
892 ALLOWED DURING CONSTRUCTION.
888
884
880
NOTES:
876
1. ALL GRADED SLOPES SHALL
872 BE LINED WITH COIR
MATTING PER THE DETAIL.
868 2. ALL STACKED ROCK WALL
- � 880
EX GROUND 876
40 872
888
EDGE OF
PAVEMENT 884
25-YR ELEV. _ OHWM 880
INSTALL 876
CONSTRUCTED RIFFLE
0 20 40
872
STA 5+50
GRADE BANK AT 2:1
SLOPE. PLACE COIR FIBER
KAAT Alvin \/F(;FTATF (TYP)
JD
EDGE OFPAVEMENT
OHWM
0 20
STA 6+00
F1 -TIER STACKED ROCK WALL
AND GRADE BANK AT 2:1
40
XPROP
D
GROUND
SLOPE. PLACE COIR MAT.
OHWM —
EDGE OF
PAVEMENT
2:1 SLOPE.
R MAT AND
:TATE (TYP)
—20 0
STA 6+50
20
40
888
884
880
876
872
888
884
880
876
872
868
WILL BE BLENDED TO
EXISTING GROUND AT TOP
OF ROCK TO LIMIT EROSION
AT TOP OF WALL.
3. PLACE SINGLE COIR
WRAPPED LIFT ABOVE
STACKED ROCK WALL AS
REQUIRED
4. GEOBAGS WILL BE BUILT IN
A MANNER THAT BLENDS
WITH EXISTING BACKSLOPE.
A MINIMUM OF 6 LIFTS (-3
FT ABOVE STONE) AT -2:1
(H:V) SLOPE UNLESS
OTHERWISE SPECIFIED ON
PLANS. LIFTS CAN BE
PLACED AS STEEP AS 1.5:1
(H:V). MORE BAG LAYERS
MAY BE USED AT DIRECTION
OF ENGINEER.
U �
zw
-0-0
c T
0 N
(n01
a� a
0
c
0 1020'
SCALE IN FEET
0
0
U
t
0
z
N
z
N
O
Li N O
_�
w �
�o-iA
oz z
N o Yo w
U
z Nwo 00
O ww
U w
i�a
NEr('oz�
w� �
O ,Zmomw
LL_
�L�Qo
o
�o Z
U w � � O
O O cn 00 0
z (n0-]--<cno
�aaz�m
WU
J
�0
N
0
W=
0�
W_
o�
V
U�
C°
y 0
O U
� o�
azNV
cnFmi Z r N
J I 13
■
00
Z U I
N c:�
0
n�a�
w
U
Q
D_
w
z
00
Z
QN
z O
0.
0
/'�
J
_ ui
W
U
LL. J
O�
k-z
CC
G
"0
Q
w
i
z
0�
J
Q
0
z
W
0
O
O
+
N
z
0
U
W
0
U
co
o
co
J
coN
co
N
o
z
a-
Q
o
m=
w
o
o 0)
O
z
z
w
y
w
0
3:c
U �
z
cn
Q12�
>
w Cn
LL
0�
U X
W
w
W
Lu
~
a
o
z cn
U
}
m
W
D
cn
0
z
SHEET
C-4
FINAL DESIGN SEQ.
Plot Dote: 1 /25/2024 1 :37 PM Plot By: 03807 Filename: N:\WTU\Drawings\CV—STREST—XS.dwg
0
00
0
�m
0 N
I >
� O
LLJ
U
In
U r4,)
/N
N
v) 0 O
� p N
N ~
CN
a� a� >
E U
0
cn
QQ)cn
U — O
Q L_ J
NOTES"
1. GRADE AREA OF INSTALLATION AS SHOWN ON PLANS.
REMOVE ALL ROCKS AND OTHER OBSTRUCTIONS SO THE
MATERIAL WILL HAVE DIRECT CONTACT WITH SOIL.
2. BAGS ARE TO BE FILLED ONSITE WITH MODERATE DRAINED
MATERIAL TO BE APPROVED BY ENGINEER. FOLLOW BAG
FILLING PROCEDURE FROM ENVIROLOK, FLEX MSE, DELTALOK
OR APPROVED EQUIVALENT.
3. GEOBAG WALL LAYERS SHOULD BE SOLID AND UNIFORM.
FLATTEN GEOBAGS WITH HAND TAMPER OR EQUIVALENT AFTER
PLACEMENT AND BEFORE PROCEEDING WITH CINCHING,
TWINING, AND STAKING.
4. APPLY VERTICAL BAG STABILIZER ACCORDING TO INSTALLATION
INSTRUCTIONS FROM ENVIROLOK, FLEX MSE, DELTALOK OR
APPROVED EQUIVALENT.
5. TIGHTEN VERTICAL BAG STABILIZER THROUGHOUT THE
CINCHING AND TWINING PROCESS. REFER TO MANUFACTURER
INSTALLATION INSTRUCTIONS.
6. APPLY SEED AND VEGETATION ACCORDING TO WALL SYSTEM
MANUFACTURER'S INSTRUCTIONS.
7. GEOBAGS WILL BE BUILT IN A MANNER THAT BLENDS WITH
EXISTING BACKSLOPE. A MINIMUM OF 6 LIFTS (-3FT ABOVE
ROCK WALL) AT — 1.5:1 (H:V) SLOPE UNLESS OTHERWISE
SPECIFIED ON PLANS. MORE BAG LAYERS MAY BE USED AT
DIRECTION OF ENGINEER.
EXISTING TREES TO
REMAIN UNLESS
SPECIFIED ON THE
PLANS OR DIRECTED I I
BY THE ENGINEER
EXISTING
GROUND
II
PLATIPUS ANCHORS
SEE STACKED
WALL DETAIL
3' PLATIPUS
ANCHOR OR
APPROVED
EQUIVALENT
(NOT USED ON
FILL SECTIONS)
WRAP GEOGRID
FABRIC AROUND
BAG AND PROVIDE
OVERLAP
PLATIPUS ANCHOR TO
BE RUN THROUGH
OVERLAP IN GEOGRID
FABRIC, IN BETWEEN
BAGS TO AVOID
PUNCTURING THE BAG
TRIM ROOTS AS NECESSARY
TO PLACE GEOBAG ON SOIL
COIR FABRIC KEYED
UNDER TOP BAG AND
STAPLE TO FILL
0.5' MAX
VARIES TO MEET EXISTING GRADE
�1
LIVE PLANT MATERIAL (SEE
PLANTING TABLE) BETWEEN
COURSES
WRAP GEOGRID FABRIC
AROUND BAGS, EVERY OTHER
ROW
PLACE BAG ANCHOR DEVICE
EVERY ROW TO CONNECT
BAGS TOGETHER, PER
MANUFACTURER GUIDANCE
GEOBAG ANCHORING AND
WRAPPING DETAIL
PLATIPUS ANCHOR
EVERY FOURTH BAG
(APPROX. 8')
PLACED IN BETWEEN
BAGS TO AVOID
PUNCURING
(NOT USED ON FILL
SECTIONS)
GEOGRID FABRIC WRAP AND
SECURED TO EXISTING BANK
WITH PLATIPUS ANCHOR.
PLACE ANCHOR HORIZONTALLY
EVERY FOURTH BAG (APPROX.
8 FT).
MATCH PRE CONSTRUCTION
CONTOURS
GEOBAG WALL SYSTEM — BLEND TO EXISTING SECTIONS
CROSS SECTION
INSERT 2
GEOBAG
ANCHOR
DEVICES
PER BAG
GEOBAG WALL
(ONLY 2 ROWS
SHOWN FOR
CLARITY)
EXISTING
STREAM BANK
WALL SYSTEM PLAN
iirIAi
EXISTING GROUND
-1— I
NATIVE
MATERIAL
COMPACTED
TO 95%
DENSITY
TYPICAL GEOBAG
—PROPOSED GRADING
f-
� , 1
f
GEOGRID TIE BACK
�7
MINIMUM 24"
THICK APPROVED
FREE —DRAINING
BACKFILL (MAY
BE AVAILABLE
ON —SITE) AS
APPROVED BY
ENGINEER.
SNORKEL
BAG CLOSED WITH UV
RESISTANT ZIPTIE
\G SEAM
COIR FABRIC KEYED
UNDER TOP BAG AND
STAPLE TO FILL
2
�1
LIVE PLANT MATERIAL (SEE
PLANTING TABLE) BETWEEN
COURSES
MATCH PRE
SEE STACKED CONSTRUCTION
WALL DETAIL CONTOURS
GEOBAG WALL SYSTEM — FILL SECTIONS
CROSS SECTION
GEOBAG WALL SYSTEM
(ENVIROLOK, FLEX MSE, DELTALOK, OR EQUIVALENT
NOT TO SCALE
�a)
U C
Z w
-0-0
ET
0
.N
(n0,
0
C
FINAL DESIGN
0
0
U
0
Z
N
Z CD
\ 0
w O
>�-
m
w Q�
�owo�
Oz z
��aZON
N � w
Z N
O <L
U w����a
N
m
O �Zmomw
oQo
o
z~
U w _ � � O
O oUnE'-0o�
Z u�u< LnZ)
9
F-- 0-
W�
J
wO
N
0
W=
-`
o
W
o441
V
c� r`
z
y
c)U
ors
aNV
cn Z r` N
3
-C
J 1 3
'
cU
Z U
N c:�
0
w
U
Q
w
z
Op
Z
QN
z O
L.f.
O
(D
(n
J
= w
w
>
U
u- J
O
�
�z
UO
Q
2i
w
i
z�
Ou)
I—
CJ
G
Q
2
J
Q
W
0
�
p
N
N
co
O
coN
J
m
N
O
z
a-Q
o
ui
O
z
z
Y
Q
>
w
z
co
H
c
LL
c
c
c�
U
I
cn
w
W
fy_
~
a
o
z CO
J
� U
}
m
w
cn
cn
O
z
SHEET
SEQ.
C-5
w
J
Q
U
LL
w
> O
Plot Dote: 1 /25/2024 1 :37 PM Plot By: 03807 Filename: N:\WTU\Drawings\CV—STREST—DT1.dwg
r-
0
00
0
3
°m
o
>
0
cnc/)
w
m
cn g
d
U r7
/N
N
V O
r) N
LO
N ~ �
�
N Z ..
N N >
cn
O
Q (n
U = o
Q I� I
O
00
0
�m
0
I >
�0
cf)cn
w
I n
>
U r7
/N
0)�
(n O O
L N
J �
cn
N ~ �
a� a� >
m E 0
0
Q Q) V)
Q L� J
EXISTING BANKLINE
III —III COIR FIBER MATTING
(SEE DETAIL)
BACKFILL OR CUT SLOPE III
AT 2H:1 V. FILL OF NATIVE „
MATERIAL COMPACTED TO 95% III —III- 12 —18 FABRIC OVERLAP
DENSITY OR EXISTING SOIL. �y
-IIIIIIIIIIIII 'L
IIIIIIIIIIIIIII +
II -III
EXISTING NATIVE
GROUND IIIIII—� 1' MIf
-IIIIIII I-
-1 I II I II 1I
POROUS EROSION CONTROL
BACKFILL (NCDOT #5 STONE)
=1 I IIIIIII� I
NON —WOVEN T-I 11I I I11=1 I II I II I i=1 I II I II
GEOTEXTILE FILTER
FABRIC
GEOBAG WALL, TYP.
ADD BAGS AS NEEDED TO TIE INTO
EXISTING GRADE. SEE DETAIL.
N,
MINIMUM EXPOSED DIMENSIONS 2'(H)x1'(V)
STACKED ROCK WALL
STREAM BED INVERT
TOE RIPRAP
SIZE STONE TO CLASS B
FOOTER STONE BURIED TO EXISTING J NON —WOVEN GEOTEXTILE
STREAM INVERT FILTER FABRIC
1 ONE- TIER ROCK WALL WITH GEOBAGS
NOT TO SCALE
EXISTING BANKLINE
COIR FIBER MATTING
(SEE DETAIL)
IIII III_ 12"-18" FABRIC OVERLAP
III IIIIII-I
�IIIIIIIIIIIIII �
BACKFILL OR CUT SLOPE III
AT 2H:1 V. FILL OF NATIVE (-
MATERIAL COMPACTED TO 95%
DENSITY OR EXISTING SOIL.
I IIIII I I-
-I I II I II
�IIII 1I
=1 I IIIII 11=
III-IIII ��� i
NON —WOVEN GEOTEXTILE III —III O�o�o 0
FILTER FABRIC O O
IIIII-III- ����
—III—III o O O O O
-IIIIII-III_
EXISTING NATIVE IIIIII=III- o�jo���
GROUND
II I=III=III=III=III- �������
POROUS EROSON CONTROL=III ,III
BACKFILL (NCDOT #5 STONE)III-III �IIIIII
FOOTER STONE
BURIED TO EXISTING
STREAM INVERT
GEOBAG WALL, TYP.
ADD BAGS AS NEEDED TO
TIE INTO EXISTING GRADE.
SEE DETAIL.
STACKED ROCK WALL
MINIMUM EXPOSED
1' MIN DIMENSIONS IS 2H, 1' V.
z STREAM BED
INVERT
N
N
TOE RIPRAP
III- 1 SIZE STONE TO
II -III- CLASS B
1-IIII � IIII
NON —WOVEN
GEOTEXTILE FILTER
FABRIC
THREE- TIER ROCK WALL WITH GEOBAGS
NOT TO SCALE
BACKFILL OR CUT SLOPE AT
2H:1 V. FILL OF NATIVE
MATERIAL COMPACTED TO 95%
DENSITY OR EXISTING SOIL.
NON —WOVEN GEOTEXTILE
FILTER FABRIC I
-I1
EXISTING NATIVE GROUND
POROUS EROSION CONTROL
BACKFILL (NCDOT #5 STONE)
END ROCK
WALL BY
KEYING INT
BANK AT 4
DEG, MIN E
T
A `
VV
RIPRAP
CLASS B
EXISTING BANKLINE
COIR FIBER MATTING
(SEE DETAIL)
12"-18" FABRIC OVERLAP
GEOBAG WALL, TYP.
ADD BAGS AS NEEDED TO TIE INTO EXISTING GRADE. SEE
DETAIL.
STACKED ROCK WALL
MINIMUM EXPOSED DIMENSIONS IS 2' H, 1' V.
1' MIN
_IIII O o O
STREAM BED INVERT
IIIII I ��� N
r -
III III—IIII - �� N� TOE RIPRAP SIZE STONE TO CLASS B
IIIIII-III o�oo
_II I I I IIIIIIIIII-III
- IIIIIIIIIIIIIIIIII—III 1III- NON —WOVEN GEOTEXTILE
i IIII11
FILTER FABRIC
FOOTER STONE BURIED TO
EXISTING STREAM INVERT
TWO- TIER ROCK WALL WITH GEOBAGS
NOT TO SCALE
M r-P'1r ATIA1/I Tirn nr M/-\/-%I/
FLOW
STACKED ROCK WALL
NOT TO SCALE
END ROCK WALL
BY KEYING INTO
BANK AT 45 DEG,
MIN 6'
kVVIII I IVV L/'11\VL V/'1rJ
BETWEEN STONES
PLAN VIEW
NOTES:
1.
STACKED ROCK WALL SHALL HAVE 2 OR
3 TIERS ONE (1) TIER ABOVE
THE FOOTER TIER.
2.
STACKED ROCK WALL CAN BE
STACKED WITH A SLOPE BETWEEN 0.5:1
(H:V) AND 2:1 (H:V) STEEP.
3.
MINIMUM STACKED STONE SIZE
FOR ROCK
WALL 3'(L) X 2.5'(W) X 2'(H).
THE STRUCTURE STONE MUST
BE BLOCKY,
ANGULAR, AND STACKABLE.
4.
NON —WOVEN GEOTEXTILE FILTER FABRIC SHALL BE NCDOT APPROVED
WEIGHT OF 90Z.
5.
GEOBAG SIZE WILL BE 5.5" H
x 2'2" L X
1'3" W. SEE DETAIL.
U �
s
U c
Z W
-0-0
ET
0
.N
�0,
0
c
FINAL DESIGN
0
0
U
(V
z CD
N
O c\O Z
W N O
D
oZ Z
N oig: YOUw
z N w p p
o ww
U Ofmz��a
M C/) LE �
O �Zmomw
L� Z—�z a
'y o 0
U w O
p 0 cn [i f
z �a-0��o
�aazt__m
WU
JN
�0
O
W
�`
=
o4-
W
or-
V
Ur-
�■
o
U
MEO
r--
Z r N
aNV
cn
o 3
D
cn3
-
J
■
Z 0 Iv I
Nc:�
0
Un3a3:
LJJ
U
Q
J
LU Z
Op
Z QN
z O ry
°2 O
u)
J
_0
= w LJJ
>
U
LL J
O �
� Z
00 Q
LJJ
i
Z
O�
I—
Q
Q
(110-11
LLJ
Z
Lei
CD
Q
Lij
o
co
co
N
J
m
N
O �
z
a-Q
0
Im
inLu
O
00
z
z
LLJu0
Q
>
w
z
H
ILL
0
10
10
1 c�
0
cn
w
w
Lu
2
Q
�
U
E
}
m
w
cn
cn
O
z
SHEET
SEQ.
C-7
_F0o
O_ 0
O c En0
U O_0
c c:m
a)
a�
o
�mu)
m �
w T
J
Q
U
cn
}
LL
E
w
> O
Plot Date: 1 /25/2024 1 :37 PM Plot By: 03807 Filename: N:\WTU\Drawlngs\CV-STREST-DT1.dwq
0
00
0
�m
N
O N
I >
O
cn
cn W
m
cn�
In
UI�
cn 0 O
� p N
Ln
cn
N ~
a� a� >
E U
cn
O
QQ)cn
u - O
Q L- J
TOP OF BANKFULL
T/Nn nE- oAKII/M II 1
STF
STONE IMPERVIOUS DIKE
IMPERVIOUS FABRIC
STONE FILLING FINE
FLOW `
Z�
CHANNEL BOTTOM
CROSS SECTION
1'
FLOW
BEDDING MATERIAL
STONE FILLING MEDIUM
BEDDING MATERIAL
BASE OF
STREAM
STONE IMPERVIOUS DIKE
PLAN VIEW
GEOTEXTILE FILTER
FABRIC
STONE IMPERVIOUS DIKE
PROFILE
KAIN SECURE IMPERVIOUS FABRIC
UNDER TOP LAYER OF SANDBAGS
13' MIN.
SANDBAGS
SECURE IMPERVIOUS FABRIC WITH STONE FILLING
FINE
SANDBAG IMPERVIOUS
DIKE PROFILE
NOTE:
1. THE STRUCTURE SHALL BE USED FOR
DIVERTING AND PUMPING ONLY. THE STRUCTURE
SHALL BE RELOCATED OR REMOVED ONCE
PUMPING/DIVERTING IS COMPLETE.
2. EITHER TYPE OF IMPERVIOUS DIKE (SANDBAG
OR STONE) MAY BE USED.
CHANNEL
A AIr\M AS
SANDBAG IMPERVIOUS DIKE
CROSS SECTION
1 IMPERVIOUS DIKE
NOT TO SCALE
IN
'11 1 IAI(` AACn11 IAA
T3'MIN.
NOTE:
1. USE NO. 5 OR NO. 57 STONE FOR
SEDIMENT CONTROL STONE.
2. PROVIDE STABILIZED OUTLET TO
STREAM BANK.
3. WOOD PALLETS MAY BE USED IN LIEU
OF STONEA ND GEOTEXTILE AS
DIRECTED. A SUFFICIENT NUMBER OF
PALLETS MUST BE PROVIDED TO
ELEVATE THE ENTIRE SPECIAL STILLING
BASIN ABOVE NATURAL GROUND.
EXISTING GROUND
DRAINAGE GEOTEXTILE
PUMP HOSE
MAINTENANCE REQUIREMENTS: 15' MINIMUM
1. THE SPECIAL STILLING BASIN SHALL BE DISPOSED OF
AND REPLACED WHEN IT IS 3/4 FULL OF SEDIMENT OR
WHEN IT IS IMPRACTICAL FOR THE BAG TO FILTER THE
SEDIMENT OUT AT A REASONABLE FLOW RATE.
2. THE INLET OF THE BAG SHOULD BE INSPECTED
PERIODICALLY FOR DAMAGE AND/OR BLOCKAGE.
3 SEDIMENT CONTROL STONE SHALL BE REPLACED IF
DAMAGED BY HIGH FLOWS OR BAG FAILURE. 1 SPECIAL STILLING BASIN
NOT TO SCALE
IMPERVIOUS DIKE (SAND F T\/nr I/N,A,AIN
PROPOSED CHANN
CHANNEL
PIPE DIVERSION CROSS SECTION
IMPERVIOUS DIKE
SEE DETAIL
MAIN PUMP
(BASEFLOW)
3ED 24" CPP
FLOW
8" OF SEDIMENT CONTROL
STONE
FLOOD PLAIN
_\ STREAM
VI I/�IVIVLL
BOTTOM PIPE DIVERSION PROFILE
NOTE:
1. PIPE MUST HAVE POSITIVE DRAINAGE WHEN USING
DIVERSION (0.3% TO 2.0% PIPE SLOPE IS
RECOMMENDED)
CONSTRUCTION AREA (250' MAX)
(LOCATION VARIES WITHIN THE PUMP AROUND AREA)
IMPERVIOUS DIKE
y
SPECIAL STILLING
SEDIMENT PUMP SEE DETAIL THIS
AS REQUIRED
PUMP -AROUND DIVERSION PLAN VIEW
PUMP—AROUND/PIPE DIVERSION
NOT TO SCALE
OUTFALL ONTO GDOT RIPRAP TYPE 3
3AS1 N
HEET
NOTE:
1. CHANNEL SHALL BE MATTED WITH COIR FIBER
MATTING PRIOR TO THE CLOSE OF EACH WORK DAY.
2. IF FINAL CHANNEL GRADING HAS NOT BEEN
PERFORMED, TEMPORARILY SECURE COIR MATTING
WITH STAKES OR ROCK
FINAL DESIGN
0
0
0
Z
WU
J
�O
N
0
W=
-`
Vo�
C°
0
o
O U
NW
ors
cn r N
3
-C
J 1 13
■
O
Z Iv I
0
0
LJJ
U
Q z
� O J
V) Q
LJJ z 0 [--
0 0 Lij
W Q
z
�0Q z�
o� � 00
0-
C� (n J Q ~
= w L1J > Z
0_j
�z W �
O Q ry �z
2i mow/
I LLJ
z -:>:: !>:
O Wo
Li
co
O
N
J
m
N
z
z
a-
Q
o
o
O
Z
z
LLJ
.e -0
LD
Z
H
cn
Q
>
W N
H
li
I
p
p
U
I—
cn
w
w
7
Q
o
z 0
U
1
}
m
-Fuo
c
� N �
O O j
O
U O-0
M
a)
O cm a)
L§(n
L (n
m "•—
m-
w—
J
Q
U
w
W
c
O
z
W
> o
SHEET
C-9
Plot Dote: 1 /25/2024 1 :37 PM
Plot By: 03807 Filename: N:\WTU\Drawings\CV—STREST—DT2.dwg
CONSTRUCTION SEQUENCE
GENERAL
1. OBTAIN ALL APPLICABLE PERMITS.
2. PRIOR TO SCHEDULING THE PRE —CONSTRUCTION MEETING, THE EROSION AND
SEDIMENT CONTROL SURETY MUST BE SUBMITTED TO THE CITY OF HIGH POINT,
EROSION AND SEDIMENT CONTROL (E&SC) PERMIT AND A NCGO100000
CERTIFICATE OF COVERAGE (COC) MUST BE OBTAINED BEFORE ANY LAND
DISTURBING ACTIVITIES OCCUR.
3. AFTER THE PRE —CONSTRUCTION MEETING IS HELD, THE CONTRATOR CAN INSTALL
E&SC MEASURES ONLY. THIS INCLUDES BUT IS NOT LIMITED TO CONSTRUCTION
ENTRANCE, TEMPORARY SILT FENCE, SPECIAL SEDIMENT FENCE, AND INLET
PROTECTION. CLEAR ONLY AS NECESSARY TO INSTALL THESE MEASURES.
4. THE CONTRACTOR SHALL CONDUCT SELF —INSPECTIONS OF THE EROSION AND
SEDIMENTATION CONTROL MEASURES AND COMPLETE THE FOLLOWING COMBINED
SELF —INSPECTION FORM FOUND ON THE DEMLR WEBSITE
(HTTP: /DEQ.NC.GOV/ABOUT/DIVISIONS/ENERGY— MINERAL— LAND— RESOURCES/
EROSION—SEDIMENT—CONTROL/FORMS). E&SC INSTALLATION AND MAINTENANCE
LOG, A RAIN GAUGE, COPY OF CITY OF HIGH POINT SIGNED PLANS ONSI TE,
REVISED SIGNED PLANS, NPDES LOG, AND CONSTRUCTION BOX MUST BE
PRESENT AND EASILY ACCESSIBLE ONSI TE. ALL EROSION AND SEDIMENT CONTROL
PRACTICES SHALL BE CHECKED FOR STABILITY AND OPERATION WEEKLY, AND
WITHIN 24 HOURS OF EVERY RAIN EVENT OF GREATER THAN 0.5 INCHES. ANY
NEEDED REPAIRS SHALL BE MADE IMMEDIATELY TO MAINTAIN MEASURES AS
DESIGNED. MAINTENANCE OF THE EROSION AND SEDIMENT CONTROL MEASURES
SHALL BE AS DESCRIBED IN PLANS.
5. INSTALL PUMP AROUND AS DESCRIBED BELOW. PUMP AROUND WORK AREA
DURING CONSTRUCTION ACTIVITIES.
6. IMMEDIATELY HAUL ALL CONSTRUCTION DEBRIS TO OFF —SITE DISPOSAL LOCATION.
7. SEDIMENT SHALL BE REMOVED FROM BEHIND THE SILT FENCE WHEN IT BECOMES
0.5 FEET DEEP.
8. DISTURBED AREAS SHALL BE STABILIZED AS SOON AS POSSIBLE. ALL AREAS
WITH SLOPES STEEPER THAN 3:1 OR SLOPES GREATER THAN 50 FEET IN LENGTH
SHALL BE STABILIZED WITHIN 7 DAYS. ALL OTHER AREAS THAT DO NOT MEET
THE CRITERIA REQUIRING STABILIZATION WITHIN 7 DAYS SHALL BE STABILIZED
WITHIN 14 DAYS. THIS MAY INCLUDE MOST AREAS WHERE PIPING AND PAVING
ACTIVITIES WILL TAKE PLACE.
9. AFTER ALL LAND DISTURBING ACTIVITIES ARE COMPLETE AND THE SITE IS
STABILIZED, ALL TEMPORARY MEASURES SHALL BE REMOVED, INCLUDING SILT
FENCE, SILT FENCE STONE OUTLETS, CURB INLET PROTECTION, AND ANY OTHER
APPROVED EROSION CONTROL MEASURES. PERMANENT SEEDING, MULCHING, AND
LANDSCAPING SHALL BE APPLIED TO ALL DISTURBED AREAS WITHIN 30 WORKING
DAYS OR 120 CALENDAR DAYS (WHICHEVER IS SHORTER) FOLLOWING
COMPETITION OF CONSTRUCTION.
10. EROSION CONTROL MEASURES TO COMPLY WITH NPDES PERMIT NCGO10000 IN
RELATION TO STORMWATER INSPECTION.
11. WHEN THE PROJECT IS COMPLETE, THE PERMITTEES SHALL CONTACT DEMLR TO
CLOSE OUT THE E&SC PLAN.
HARDWARE CLOTH (J" — I"
MESH OPENINGS) OVER
DEWATERING HOLES
2"
TEMPORARY SEDIMENT POOL
0
1' MIN — 2' MAX. oCJo d"�r�4.
NCDOT #57 —
WASHED STONE
12"
rDEWATERING x--CONCRETE BLOCK
2 x 4 WOOD STUDS
(AS REQUIRED FOR
LATERAL SUPPORT)
CONCRETE BLOCK
MAINTENANCE NOTES:
1. BLOCK AND GRAVEL
INLET PROTECTION
SHALL BE MAINTAINED
PER THE NCDOT
EROSION AND
SEDIMENT CONTROL
MANUAL.
2. REPLACE THE #57
WASHED STONE AS
NEEDED TO ALLOW
WATER TO DRAIN
THROUGH THE DEVICE
BETWEEN RAINFALL
EVENTS
u u
-
2 x 4 WOOD STUDS
(AS REQUIRED FOR
EF
LATERAL SUPPORT)
NOTES:
1. ENSURE THAT DRAINAGE AREAS DO
NOT EXCEED
1 ACRE
o
s
PER INLET.
2. KEEP THE HEIGHT OF
AND NO GREATER THAN
THE BARRIER
24 INCHES.
AT LEAST 12
INCHES
0
NCDOT #57
3. IF NEEDED, PLACE 2
OPENINGS FOR LATERAL
x 4 WOOD STUDS THROUGH
SUPPORT.
BLOCK
o
—P�
�'a � o� 000a, 4�
o
Q�
O �o'ocrn >wov o vw� o ooaAB ooe.
WASHED STONE
4. THIS PRACTICE MUST
FILL MATERIAL AND MUST
FILL SLOPES.
NOT BE USED
NOT DIVERT
NEAR THE EDGE OF
WATER OVER CUT OR
2:1 SLOPE, GRAVEL
FILTER
CITY OF HIGH POINT ISSUED 2-17-09 INLPRO BG.DWG
NORTH CAROLINA REVISIONS STANDARD DRAWING FOR
ENGINEERING SERVICES DEPARTMENT BLOCK AND GRAVEL INLET PROTECTION 608.01
APPROVED.. FAR 1AA1?;Y 2� , 20Z
7- FOR STORM DRAIN INLETS
DIRECTOR
U c
zw
-0-0
000 .
0
c
0
0
0
Z
WU
J
�O
N
O
W=
-`
Vo�
(1 E
y ID°
NW
o0)�
cf)Z r N
J I 3
■
00
Z
N c:�
0
W
U
N
Q
z
0
V)
L LJ
z
0
Q
00
W
0�
-
LLJ
D
z
�0Q
0�
z�
o�
00
C�
W
J Q
~
2 w
Lu
U
z
LO J
00
0
z
0
Q
LJ
Lu
r
Z
LLJ
z
0
W
QQ
W
LLJ
J
C,n
PUMP AROUND:
co
O
J
00
1. INSTALL DIVERSION PUMP, DISCHARGE LINE, AND OUTLET PAD.
N
N
2. INSTALL SEDIMENT PUMP AND SPECIAL STILLING BASIN AT LOCATION OF
o 1—Q
o
z
z
z
ui
0
DOWNSTREAM IMPERVIOUS DIKE.
o6
w
Q
w
�
w
� N
=
LL
c
c
c
�
10
3. INSTALL UPSTREAM IMPERVIOUS DIKE UPSTREAM OF ACTIVE CONSTRUCTION AREA
w
W w
AND BEGIN PUMPING/DIVERTING OF THE MAINSTREAM FLOW.
W
o
z
J >
1 U
4. INSTALL DOWNSTREAM IMPERVIOUS DIKE DOWNSTREAM OF ACTIVE CONSTRUCTION
AREA AND INITIATE PUMPING OF SEDIMENT —LADEN WATER FROM CONSTRUCTION
m
AREA AS NEEDED.
0
0
5. AT END OF EACH WORK DAY, COVER NATURAL STREAM BANKS WITH COIR
F0 o
MATTING. REMOVE IMPERVIOUS DIKES AND DIVERSION PIPE FROM STREAMS TO
c:,�
N °'
ALLOW NATURAL FLOW.
o
0 a�
00 0�
o U)
6. UPON COMPLETION OF WORK, REGRADE STREAM BED AND BANKS AS SPECIFIED
0 0
IN PLANS. REMOVE EROSION CONTROL MEASURES FROM WITHIN CREEK BED.
c
STABILIZE WITH TEMPORARY AND PERMANENT SEED MIX AND STRAW MULCH.
C�
>
REVEGETATE ACCORDING TO PLANTING PLAN.
N D
L �
UI�
�0�(n
"
7. STABILIZE AND PROTECT FROM EROSION RESULTING FROM OFFSITE RUNOFF
J
.Q N
WITHIN 7 DAY DURATION.
L
N
W
co
/ \
Ln
ccnn
LPL
cn N
W
>o
SHEET
aa>
Ecn
o
Q LT-- J
FINAL DESIGN
SEQ.
Plot Dote: 1 /25/2024 1 :38 PM Plot By: 03807 Filename: N:\WTU\Drawings\CV—STREST—DT2.dwg
0
STEP 1:
EXCAVATE A 6" x 6" TRENCH. DRIVE STEEL
POSTS 18" INTO GROUND DOWNHILL OF THE
TRENCH.
MAX. 8'
BETWEEN
POSTS
STEP 4:
BACKFILL THE TRENCH WITH #57
CLEAN STONE TO ANCHOR THE
BOTTOM OF THE SILT FENCE SO THAT
RUNOFF IS FORCED TO GO THROUGH THE
FENCE AND CANNOT GO UNDER IT.
F
STEP 2:
ATTACH WIRE FENCE TO POSTS AND
EXTEND THE BOTTOM OF THE FENCE
INTO THE EXCAVATED TRENCH BOTTOM.
HEIGHT -
MAX. 3'
MIN. 2'
5' STEEL POSTS
DANCE NOTES:
IPORARY SILT FENCE MUST BE MAINTAINED
_ t THE NCDOT EROSION AND SEDIMENT
CONTROL MANUAL.
AT A MINIMUM, REMOVE AND DISPOSE OF ALL
SILT ACCUMULATION WHEN THE DEPTH REACHES
2 OF THE HEIGHT OF THE GEOTEXTILE. DO NOT
UNDERMINE DURING CLEANOUT.
CITY OF HIGH POINT ISSUED 2-17-09
NORTH CAROLINA REVISIONS
ENGINEERING SERVICES DEPARTMENT
APPROVED..RY.
................:2.14 .....................
DIRECTOR
ORAN,
HIGH
POLYE
E
NORTH CAROLINA
Environmental Quality
SECTION
STEP 3:
ATTACH THE FILTER FABRIC TO THE WIRE
FENCE AND EXTEND THE BOTTOM OF THE
FILTER FABRIC INTO THE TRENCH BOTTOM.
WIRE FENCE "HOG WIRE"
(14 GUAGE WITH MAX. MESH
SPACING= 6 INCHES)
FILTER FABRIC
SEE SPECIFICATIONS
FOR MATERIAL
BOTTOM OF WIRE FENCE AND
FILTER FABRIC BURIED 6"
IN EXCAVATED TRENCH BACKFILLED
WITH #57 STONE.
STEEL POST DRIVEN
18" INTO GROUND
NOTES:
1. BOTTOM OF FILTER FABRIC MUST BE PLACED IN TRENCH AND
SECURED BY BACKFILLING THE TRENCH WITH #57 STONE.
2. DO NOT INSTALL SILT FENCE WHERE FLOWS ARE
CONCENTRATED.
3. WOODEN POSTS NOT ALLOWED.
4. STEEL POSTS SHALL WEIGH 1.33 LB/LF.
STANDARD DRAWING FOR
TEMPORARY SILT FENCE
FOR EROSION CONTROL
OF TREE DIAMETER
TREE PROTECTION ZONES
SILTFENCE.DWG
600.00
SHEET 1 OF 1
Page:
CITY OF HIGH POINT ISSUED 2-17-09 SILTFENCEOUT.DWG
NORTH CAROLINA REVISIONS STANDARD DRAWING F 0 R
ENGINEERING SERVICES DEPARTMENT TEMPORARY SILT FENCE WITH STONE OUTLET 600.01
APPROVED..>R�141?Y�,20.0,�
�,.- FOR EROSION CONTROL
.............................................
DIRECTOR SHEET 1 OF 1
IRE TREE PROTECTION ZONE RADIUS
GOOD
PROTECTION
BETTER
PROTECTION
BEST
PROTECTION
10 FEET
12 FEET
20 FEET
15 FEET
18 FEET
30 FEET
20 FEET
24 FEET
40 FEET
25 FEET
30 FEET
50 FEET
NOTES:
1. Leave critical areas (such as flood plains, steep slopes and
wetlands) with desirable trees in their natural condition or only
partially cleared.
2. Select trees to be preserved before siting roads, buildings or
other structures.
3. Minimize trenching in areas with trees. Place several utilities
in the same trench.
4. Prohibit or restrict access to tree protection zones(TPZ). Post
"Keep Out" signs on all sides of fencing and do not store
construction equipment or materials in TPZ.
5. Monitor trees using a professional or train your staff to monitor
tree health during and after construction on a regular, frequent
basis.
6. Assign a crew member to weekly TPZ fence integrity checks.
Repair and replace TPZ fencing as needed.
MAINTENANCE:
1. Prune any damaged trees. In spite of precautions, some
damage to protected trees may occur. In such cases, repair any
damage to the crown, trunk, or root system immediately.
2. Repair roots by cutting off the damaged areas and painting
them them with tree paint. Spread peat moss or moist topsoil
over exposed roots.
3. Repair damage to bark by trimming around the damaged area,
taper the cut to provide drainage and paint with tree paint.
4. Cut off all damaged tree limbs above the tree collar at the trunk
or main branch. Use three separate cuts to avoid peeling bark
from healthy areas of the tree.
FINAL DESIGN
O
0
U
L
O
Z
N
Z O
N
O \
cD Z
w N O
U =~
mowo(7)
oz z
U)
Y O
LLJ
Z LLJ 0 0
O
U
Z N
— w g
O �Zmom�
LL z—�z a
ao
z
U LLJ
O O N 0 0 0
Z Ln U) o
d Q Z m
WU
J
�O
N
O
W=
-`
o�
W
0�
V
Url-
(0E
o
IDU
0 0 0)
ILI (3NV
Cf) Z r N
FMI
0 3
D \-- 3
J I 13
'
z 0 o
N c�
0
LC) a -3::
w
U
Q
z
0
V)
W
z
0<
00
W
0.
—
W
0
Z
0
Q
z
o2
00
0-..0
��
C/)
<
2 w
w
U
z
LLLJ
ry
00
00
0
Q
W
c
w
r
z
i
ry
LLJ
Z
I`
0
C/)
QQ
W
LLJ
J
C,n
V I
00
O
M
N
J
m
N
z
zz a-Q
oLLJ
�LL1
o
LLJ
00
Z
Z
.e
LD
Cl)
Z
H
Cn
Q
>
W N
c)
LL
c)
c)
0�
10 1~
H
w
W
LU
7
~
a
o
Z Cf)
J
U
m
c
0
'mecca
O — U
� N �
0 c u,
o �
U 0-0
ccca
0 �0
L (n
cv � •—
m �
W
J
Q
U
w
C0
CO
Cnn
LPL
O
z
W
> o
SHEET
C-11
MOE
Plot Dote: 1 /25/2024 1 :38 PM Plot By: 03807
Filename: N:\WTU\Drawings\CV—STREST—DT2.dwg
y
0
00
0
�T
�m
N
0 70
I >
d
Cf) U7
IJ
ry
>n
U I�
N
N
J \
/ LO
N ~ \
N z
a�
>>
�E0
O
Q�w
Q J
GROUND STABILIZATION AND MATERIALS HANDLING PRACTICES FOR COMPLIANCE WITH
THE NCG01 CONSTRUCTION GENERAL PERMIT
Implementing the details and specifications on this plan sheet will result in the construction
activity being considered compliant with the Ground Stabilization and Materials Handling
sections of the NCG01 Construction General Permit (Sections E and F, respectively). The
perm ittee shall comply with the Erosion and Sediment Control plan approved by the
delegated authority having jurisdiction. All details and specifications shown on this sheet
may not apply depending on site conditions and the delegated authority having jurisdiction.
SECTION E: GROUND STABILIZATION
Required Ground Stabilization Timeframes
Stabilize within this
Site Area Description
many calendar
Timeframe variations
days after ceasing
land disturbance
(a) Perimeter dikes,
swales, ditches, and
7
None
perimeter slopes
(b) High Quality Water
7
None
(HQW) Zones
(c) Slopes steeper than
If slopes are 10' or less in length and are
3:1
7
not steeper than 2:1, 14 days are
allowed
-7 days for slopes greater than 50' in
length a nd with slopes steeper tha n 4:1
-7 days for perimeter dikes, swales,
(d) Slopes 3:1 to 4:1
14
ditches, perimeter slopes and HQW
Zones
-10 days for Falls Lake Watershed
-7 days for perimeter dikes, swales,
(e) Areas with slopes
ditches, perimeter slopes and HQW Zones
flatter than 4:1
14
-10 days for Falls Lake Watershed unless
there is zero slope
Note: After the permanent cessation of construction activities, any areas with temporary
ground stabilization shall be converted to permanent ground stabilization as soon as
practicable but in no case longer than 90 calendar days after the last land disturbing
activity. Temporary ground stabilization shall be maintained in a manner to render the
surface stable against accelerated erosion until permanent ground stabilization is achieved.
GROUND STABILIZATION SPECIFICATION
Stabilize the ground sufficiently so that rain will not dislodge the soil. Use one of the
techniques in the table below:
Temporary Stabilization
Permanent Stabilization
• Temporary grass seed covered with straw or
• Permanent grass seed covered with straw or
other mulches and tackifiers
other mulches and tackifiers
• Hydroseeding
• Geotextile fabrics such as permanent soil
• Rolled erosion control products with or
reinforcement matting
without temporary grass seed
• Hydroseeding
• Appropriately applied straw or other mulch
• Shrubs or other permanent plantings covered
• Plastic sheeting
with mulch
• Uniform and evenly distributed ground cover
sufficient to restrain erosion
• Structural methods such as concrete, asphalt or
retaining walls
• Rolled erosion control products with grass seed
POLYACRYLAMIDES (PAMS) AND FLOCCULANTS
1. Select flocculants that are appropriate for the soils being exposed during
construction, selecting from the NC DWR List of Approved PAMS/Flocculonts.
2. Apply flocculants at or before the inlets to Erosion and Sediment Control Measures.
3. Apply flocculants at the concentrations specified in the NC DWR List of Approved
PAMS/Flocculonts and in accordance with the manufacturer's instructions.
4. Provide ponding area for containment of treated Stormwater before discharging
offsite.
5. Store flocculants in leak -proof containers that are kept under storm -resistant cover
or surrounded by secondary containment structures.
EQUIPMENT AND VEHICLE MAINTENANCE
1. Maintain vehicles and equipment to prevent discharge of fluids.
2. Provide drip pans under any stored equipment.
3. Identify leaks and repair as soon as feasible, or remove leaking equipment from the
project.
4. Collect all spent fluids, store in separate containers and properly dispose as
hazardous waste (recycle when possible).
5. Remove leaking vehicles and construction equipment from service until the problem
has been corrected.
6. Bring used fuels, lubricants, coolants, hydraulic fluids and other petroleum products
to a recycling or disposal center that handles these materials.
LITTER, BUILDING MATERIAL AND LAND CLEARING WASTE
1. Never bury or burn waste. Place litter and debris in approved waste containers.
2. Provide a sufficient number and size of waste containers (e.g dumpster, trash
receptacle) on site to contain construction and domestic wastes.
3. Locate waste containers at least 50 feet away from storm drain inlets and surface
waters unless no other alternatives are reasonably available.
4. Locate waste containers on areas that do not receive substantial amounts of runoff
from upland areas and does not drain directly to a storm drain, stream or wetland.
5. Cover waste conta iners at the end of each workday a nd before storm events or
provide secondary containment. Repair or replace damaged waste containers.
6. Anchor all lightweight items in waste containers during times of high winds.
7. Empty waste containers as needed to prevent overflow. Clean up immediately if
containers overflow.
8. Dispose waste off -site at an approved disposal facility.
9. On business days, clean up and dispose of waste in designated waste containers.
PAINT AND OTHER LIQUID WASTE
1. Do not dump paint and other liquid waste into storm drains, streams or wetlands.
2. Locate paint washouts at least 50 feet away from storm drain inlets and surface
waters unless no other alternatives are reasonably available.
3. Contain liquid wastes in a controlled area.
4. Containment must be labeled, sized and placed appropriately for the needs of site.
5. Prevent the discharge of soaps, solvents, detergents and other liquid wastes from
construction sites.
PORTABLE TOILETS
1. Install portable toilets on level ground, at least 50 feet away from storm drains,
streams or wetlands unless there is no alternative reasonably available. If 50 foot
offset is not attainable, provide relocation of portable toilet behind silt fence or place
on a gravel pad and surround with sand bags.
2. Provide staking or anchoring of portable toilets during periods of high winds or in high
foot traffic areas.
3. Monitor portable toilets for leaking and properly dispose of any leaked material.
Utilize a licensed sanitary waste hauler to remove leaking portable toilets and replace
with properly operating unit.
EARTHEN STOCKPILE MANAGEMENT
1. Show stockpile locations on plans. Locate earthen -material stockpile areas at least
50 feet away from storm drain inlets, sediment basins, perimeter sediment controls
and surface waters unless it can be shown no other alternatives are reasonably
available.
2. Protect stockpile with silt fence installed along toe of slope with a minimum offset of
five feet from the toe of stockpile.
3. Provide stable stone access point when feasible.
4. Stabilize stockpile within the timeframes provided on this sheet and in accordance
with the approved plan and any additional requirements. Soil stabilization is defined
as vegetative, physical or chemical coverage techniques that will restrain accelerated
erosion on disturbed soils for temporary or permanent control needs.
NORTH TH CAROLI NA
En viron m en ter I[Quality
CLEANLY Ovim stl' vm
ow
�Pr
sm
CTY.
ONSITE CONCRETE WASHOUT
STRUCTURE WITH LINER
gV"TTM Od
L�TIIAL LZAT�1 1N i1E111
a THE COMCKM VAS"M STAUCTUM SHALL
K H WANn WHO THE LOD AIUM
Sou AEACIE= = OF THE iTN�T1AES
31CUMNETE WA HMIT s,RUCTUE IEEtIS M K
CLEARY MAN= VITH SllAMGE NOi1116 OCVICIwr
i
4SAIMM (Tv.)
OR !TARE=
MIZk
LOCATMN OETE711RIEO Or
CLEANLY "mum SISRAW
�aTUAL
NOW DEVICE QrXLW MW
L THE Cu1CIETE WASHOUT
STRUCTUM SHALL K NWAMM
WIN" THE Ma At WM SOLID
MACHU 73K OF THE iTRUCT#EEi
CAPACITY To PNOVIOE AOFaAATE
CAPACITY V"" A 00I
19 Or
ABOVE GRAD W1L=UT
MGT SCALE
STRUCTURE
CONCRETE WASHOUTS
1. ❑o not discharge concrete or cement slurry from the site.
2. Dispose of, or recycle settled, hardened concrete residue in accordance with local
and state solid waste regulations and at an approved facility.
3. Manage washout from mortar mixers in accordance with the above item and in
addition place the mixer and associated materials on impervious barrier and within
lot perimeter silt fence.
4. Install temporary concrete washouts per local requirements, where applicable. If an
alternate method or product is to be used, contact your approval authority for
review and approval. If local standard details are not available, use one of the two
types of temporary concrete washouts provided on this detail.
5. ❑o not use concrete washouts for dewatering or storing defective curb or sidewalk
sections. Stormwater accumulated within the washout may not be pumped into or
discharged to the storm drain system or receiving surface waters. Liquid waste must
be pumped out and removed from project.
6. Locate washouts at least 50 feet from storm drain inlets and surface waters unless it
can be shown that no other alternatives are reasonably available. At a minimum,
i nsta II protectio n of storm d ra i n i n let(s) closest to the washout which cou Id receive
spills or overflow.
7. Locate washouts in an easily accessible area, on level ground and install a stone
entrance pad in front of the washout. Additional controls maybe required by the
approving authority.
8. Install at least one sign directing concrete trucks to the washout within the project
limits. Post signage on the washout itself to identify this location.
9. Remove leavings from the washout when at approximately 75% capacity to limit
overflow events. Replace the tarp, sand bags or other temporary structural
components when no longer functional. When utilizing alternative or proprietary
products, follow manufacturer's instructions.
10. At the completion of the concrete work, remove remaining leavings and dispose of
in an approved disposal facility. Fill pit, if applicable, and stabilize any disturbance
caused by removal of washout.
HERBICIDES, PESTICIDES AND RODENTICIDES
1. Store and apply herbicides, pesticides and rodenticides in accordance with label
restrictions.
2. Store herbicides, pesticides and rodenticides in their original containers with the
label, which lists directions for use, ingredients and first aid steps in case of
accidental poisoning.
3. ❑o not store herbicides, pesticides and rodenticides in areas where flooding is
possible or where they may spill or leak into wells, stormwater drains, ground water
or surface water. If a spill occurs, clean area immediately.
4. Do not stockpile these materials onsite.
HAZARDOUS AND TOXIC WASTE
1. Create designated hazardous waste collection areas on -site.
2. Place hazardous waste containers under cover or in secondary containment.
3. Do not store hazardous chemicals, drums or bagged materials directly on the ground.
NCGO I GROUND STABILIZATION AND MATERIALS HANDLING
EFFECTIVE: 04/01/19
FINAL DESIGN
U
E
U_
C C
C C
C aU
o
T
(nv
0
C
O
0
U
O
Z
v
(V
Z C)
N
O to ZF
W (V O
U S~
a/ �C)WQpN
O Z Z
W => a Z 0
N o�Yo�'w
(� N
Z NWo 00
O
U Jd �NC]O
LLJ�Z10 CL
O omW
LL.
UW��~O
O o
000QZZ
Z N�� U N Q
� a- F-
WU
J
wO
N
v
W=
W0�
v�
V
U E
oo
FNV
r, z
a�
i O M w
CO
z I
NCB
0
W
U
�
Q
z
0
C/)
W
Z
0Q
0Q
11�LJ
WQ
Z
�0
z_J
o�
00
a
�
0_
U)J
Q
~
T LU
OJ
�
��
Z
u
Q
LLJ
W
�Z
LLJ
Z
O
Wo
~
J
I LOO 0,
LLJ
(f)
Q
V)
3
N
N
00
o
co
N
J
m
z
<o
°o_
WW
o
o
Z
Z
Y
Q
W N
Z
H
W
>
~
�
U
LL
0
U)
W
W
�
o
z
LU
U
1
m
�o
27'
O - U
� O N
O I
O
U O!
�r-M
a)
O 0)O
Co �.�
w�
J
Q
U
W
in
D
CO
LL
0
z
LU
> o
SHEET
C-12
Plot Date: 1 /25/2024 1:38 PM Plot By: 03807 Filename: N:\WTU\Drowings\CV-STREST-DT2.dwg
r-
0
00
0
U)
�T
M
o 70
I >
a
Cf) U7
IJ
>n
U
3 �
N
V(Z)
J \
LO
N ~ \
4/_
N Z
a)
>v
�E0
0
Q�w
Q J
PART III
SELFANSPECTION, RECORDKEEPING AND REPORTING
SECTION A: SELF -INSPECTION
Self -inspections are required during normal business hours in accordance with the table
below. When adverse weather or site conditions would cause the safety of the inspection
personnel to be in jeopardy, the inspection may be delayed until the next business day on
which it is safe to perform the inspection. In addition, when a storm event of equal to or
greater than 1.0 inch occurs outside of normal business hours, the self -inspection shall be
performed upon the commencement of the next business day. Any time when inspections
were delayed shall be noted in the Inspection Record.
Frequency
Inspect
(during normal
Inspection records must include:
business hours)
(1) Rain gauge
Daily
Daily rainfall amounts.
maintained in
If no daily rain gauge observations are made during weekend or
good working
holiday periods, and no individual -day rainfall information is
order
available, record the cumulative rain measurement for those un-
attended days (anc this will determine if a site inspection is
needed). Days on which no rainfall occurred shall be recorded as
"zero." The permittee may use another rain -monitoring device
approved by the ❑ivbion.
(2) E&5C
At least once per
1. Identification ofthe measures inspected,
Measures
7 calendar days
2. Date and time of the inspection,
and within 24
3. Name of the person performing the inspection,
hours of a rain
4. Indication of whether the measures were operating
event? 1.0 inch in
properly,
24 hours
5. Description of maintenance needs for the measure,
b. Description, evidence, and date of corrective actions taken.
(3) Stormwatc r
At least once per
1. Identification of the discharge autfalls inspected,
discharge
7 Calendar days
2. Date and time of the inspection,
autfalls (SDCs)
and within 24
3. Name of the person performing the inspection,
hours of a rain
4. Evidence of indicators of stormwater pollution such as oil
event > 1.0 inch in
sheen, floating or suspended solids or discoloration,
24 hours
5. indication of visible sediment leaving the site,
6. Description, evidence, and date of corrective actions taken.
(4) Perimeter of
At least once per
If visible sedimentation is found outside site limits, then a record
site
7 calendar days
of the following shall be made:
and within 24
1. Actions taken to clean up or stabilize the sediment that has left
hours of a rain
the site limits,
event > 1.0 inch in
2. Description, evidence, and date of corrective actions taken, and
24 hours
3, An explanation as to the actions taken to control future
releases.
(5) Streams or
At least once per
If the stream or wetland has increased visible sedimentation or a
wetlands onsite
7 calendar days
stream has visible increased turbidity from the construction
or offsite
and within 24
activity, then a record of the following shall be made:
(where
hours of a rain
1. Description, evidence and date of corrective actions taken, and
accessible)
event? 1.0 inch in
2. Records of the required reports to the appropriate Division
24 hours
Regional Office per Part III, Section C, Item (2)(a) of this permit.
(6) Ground
After each phase
1. The phase of grading (installation of perimeter E&5C
stabilization
of grading
measures, clearing and grubbing, installation of storm
measures
drainage facilities, completion of all land -disturbing
activity, construction or redevelopment, permanent
ground cover).
2. Documentation that the required ground stabilization
measures have been provided within the required
tirneframe or an assurance that they will be provided as
soon as possible.
NOTE: The rain inspection resets the required 7 calendar day inspection requirement.
PART III
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION B: RECORDKEEPING
1. E&SC Plan Documentation
The approved E&SC plan as well as any approved deviation shall be kept on the site. The
approved E&SC plan must be kept up-to-date throughout the coverage under this permit.
The following items pertaining to the E&SC plan shall be kept on site and available for
inspection at all times during normal business hours.
Item to Document
Documentation Requirements
(a) Each E&SC measure has been installed
Initial and date each E&SC measure on a copy
and does not significantly deviate from the
of the approved E&SC plan or complete, date
locations, dimensions and relative elevations
and sign an inspection report that lists each
shown on the approved E&SC plan.
E&SC measure shown on the approved E&SC
plan. This documentation is required upon the
initial installation of the E&SC measures or if
the E&SC measures are modified after initial
installation.
(b) A phase of grading has been completed.
Initial and date a copy of the approved E&SC
plan or complete, date and sign an inspection
report to indicate completion of the
construction phase.
(c) Ground cover is located and installed
Initial and date a copy of the approved E&SC
in accordance with the approved E&SC
plan or complete, date and sign an inspection
plan.
report to indicate compliance with approved
ground cover specifications.
(d) The maintenance and repair
Complete, date and sign an inspection report.
requirements for all E&SC measures
have been performed.
(e) Corrective actions have been taken
Initial and date a copy of the approved E&SC
to E&SC measures.
plan or complete, date and sign an inspection
report to indicate the completion of the
corrective action.
2. Additional Documentation to be Kept on Site
In addition to the E&SC plan documents above, the following items shall be kept on the
site and available for inspectors at all times during normal business hours, unless the
Division provides a site -specific exemption based on unique site conditions that make
this requirement not practical:
(a) This General Permit as well as the Certificate of Coverage, after it is received.
(b) Records of inspections made during the previous twelve months. The permittee shall
record the required observations on the Inspection Record Form provided by the
Division or a similar inspection form that includes all the required elements. Use of
electronically -available records in lieu of the required paper copies will be allowed if
shown to provide equal access and utility as the hard -copy records.
3. Documentation to be Retained for Three Years
All data used to complete the a-NOI and all inspection records shall be maintained for a period
of three years after project completion and made available upon request. [40 CFR 122.41]
PART II, SECTION G, ITEM (4)
DRAW DOWN OF SEDIMENT BASINS FOR MAINTENANCE OR CLOSE OUT
Sediment basins and traps that receive runoff from drainage areas of one acre or more shall use outlet structures that withdraw water from the surface when these devices need to be drawn down
for maintenance or close out unless this is infeasible. The circumstances in which it is not feasible to withdraw water from the surface shall be rare (for example, times with extended cold weather).
Nan -surface withdrawals from sediment basins shall be allowed only when all of the following criteria have been met:
(a) The E&SC plan authority has been provided with documentation of the non -surface withdrawal and the specific time periods or conditions in which it will occur. The non -surface withdrawal
shall not commence until the E&SC plan authority has approved these items,
(b) The non -surface withdrawal has been reported as an anticipated bypass in accordance with Part III, Section C, Item (2)(c) and (d) of this permit,
(c) Dewatering discharges are treated with controls to minimize discharges of pollutants from stormwater that is removed from the sediment basin. Examples of appropriate controls include
properly sited, designed and maintained dewatering tanks, weir tanks, and filtration systems,
(d) Vegetated, upland areas of the sites or a properly designed stone pad is used to the extent feasible at the outlet of the dewatering treatment devices described in Item (c) above,
(e) Velocity dissipation devices such as check dams, sediment traps, and riprap are provided at the discharge points of all dewatering devices, and
(f) Sediment removed from the dewatering treatment devices described in Item (c) above is disposed of in a manner that does not cause deposition of sediment into waters of the United States.
PARTIII
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION C: REPORTING
1. Occurrences that Must be Reported
Permittees shall report the following occurrences:
(a) Visible sediment deposition in a stream or wetland.
(b) Oil spills if:
• They are 25 gallons or more,
• They are less than 25 gallons but cannot be cleaned up within 24 hours,
• They cause sheen on surface waters (regardless of volume), or
• They are within 100 feet of surface waters (regardless of volume).
(C) Releases of hazardous substances In excess of reportable quantities under Section 311
of the Clean Water Act (Ref: 40 CFR 110.3 and 40 CFR 117.3) or Section 102 of CERCLA
(Ref: 40 CFR 302.4) or G.S. 143-215.85.
(d) Anticipated bypasses and unanticipated bypasses.
(e) Noncompliance with the conditions of this permit that may endanger health or the
environment.
2. Reporting Timeframes and Other Requirements
After a permittee becomes aware of an occurrence that must be reported, he shall contact
the appropriate Division regional office within the tmeframes and in accordance with the
other requirements listed below. Occurrences outside normal business hours may also be
reported to the Department's Environmental Emergency Center personnel at (800)
858-0368.
Occurrence
Reporting Timeframes (After Discovery) and other Requirements
(a) Visible sediment
■
Within 24 hours, an ❑raI or electronic notification.
deposition in a
e
Within 7 calendar days, a report that contains a description of the
stream or wetland
sediment and actions taken to address the cause of the deposition.
Division staff may waive the requirement for a written report on a
case -by -case basis.
■
If the stream is named on the NC 303(d) list as impaired for sediment -
related causes, the permittee may be required to perform additional
monitoring, inspections or apply more stringent practices if staff
determine that additional requirements are needed to assure compliance
with the federal or state impaired -waters conditions.
(b) Oil spills and
9
Within 24 hours, an oral or electronic notification. The notification
release of
shall include information about the date, time, nature, volume and
hazardous
location of the spill cr release.
substances per Item
1(b)-(e) above
(c) Anticipated
*
A report at least ten days before the date of the bypass, if possible.
bypasses [40 CFR
The report shall include an evaluation of the anticipated quality and
122.41(m)(3)]
effect of the bypass.
(d) Unanticipated
•
Within 24 hours, an oral or electronic notification.
bypasses [4e CFR
e
Within 7 calendardays, a report that includes an evaluation of the
122.41(m)(3)]
and effect of the bypass.
(e) Noncompliance
•
_quality
Within 24 hours, an oral or electronic notification.
with the conditions
e
Within 7calendar days, a report that contains a description of the
of this permit that
noncompliance, and its causes; the period of noncompliance,
may endanger
including exact dates and times, and if the noncompliance has not
health or the
been corrected, the anticipated time noncompliance is expected to
environment[40
continue; and steps taken or planned to reduce, eliminate, and
CFR 122.41(1)(7)]
prevent reoccurrence of the noncompliance. [40 CFR 122.41(I)(6).
■
Division staff may waive the requirement for a written report on a
case -by -case basis.
NCGO I SELF -INSPECTION, RECORDKEEPING AND REPORTING
. K"A
NORTH CAROLI NA
i ��I )-)
s r
,ItS:a -;Environmental Quality
ors*
EFFECTIVE: 04/01/19
y
U
E
U_
C C
C C
a'0
C a)
C,
FINAL DESIGN
T
U)C)n
ai a)
0
C
0
O
O
Z
v
N
Z o
N
0 c0 z
4J cN O
V 2 ~ �
H W
O Z Z
Y O V N
Z N - M C)No
0 ww
V z - w a
�Wro��
0 �ZmoM
� LZ-�z a
o
�o Z �
U W i7_ Zo
0 0(,�000
000QZZ
Z N� r Ut/'!p
=aaz�m
WU
J
�0
N
v
W=
W
v�
V
U (D E
Z
0o'i
Door
o r,
Z (n
CO
z I
C 0-0
W
U
�
Q
z
0
(n
0-
Cf)
_J
LLJZ
0Q
I—
0
p
W
O�
-
LLJ
0
z
_J
Z
0
00
a
0
Cn
J Q
~
=wW��z
of
�/
00
_
G
C/')
00
Q
LLJO
W
�Z
LLJ
Z
::�i_
0
w
Q
J
LLJ
L)
Q
()
0 d,
3
N
N
00
O
co
N
J
m
N
Z
Z �_
o
m0
Lw
o
Z
Z
Y -0
N
Z
H
W
Q
>
W ~
�
LL
0
IU
U)
w
W
� �
z
o
Cl)
J >
1 U
m
�o
c
MU
L C: N
0-- U
� O N
0000
00-0
a)
o ��
U)
L (n
m-0-
w�
J
Q
U
w (n
D
� LL
w
z > o
SHEET
C-13
Plot Date: 1 /25/2024 1:38 PM Plot By: 03807 Filename: N:\WTU\Drowings\CV-STREST-DT2.dwg
Compliance Certification Form
File Number: SAW-2024-00403 County: Guilford
Permittee: City of High Point, Ms. Melinda King
Project Name: Hamilton Avenue Stormwater Utility Upgrades
Date Verification Issued: 5/13/2024
Project Manager: Laura Meyer
Upon completion of the activity authorized by this permit and any mitigation required by
the permit, sign this certification and return it to the following address:
US ARMY CORPS OF ENGINEERS
Wilmington District
Attn: Laura Meyer
Raleigh
3331 Heritage Trade Drive Suite 105
Wake Forest, North Carolina 27587
or
laura.j.meyer@usace.army.mil
Please note that your permitted activity is subject to a compliance inspection by a U. S.
Army Corps of Engineers representative. Failure to comply with any terms or conditions
of this authorization may result in the Corps suspending, modifying or revoking the
authorization and/or issuing a Class I administrative penalty, or initiating other
appropriate legal action.
hereby certify that the work, and mitigation (if applicable), authorized by the above
referenced permit has been completed in accordance with the terms and conditions of
the said permit including any general or specific conditions.
Date Authorized Work Started:
Completed:
Describe any deviations from permit (attach drawing(s) depicting the deviations):
*Note: The description of any deviations on this form does not constitute approval by the Corps.
Signature of Permittee
Date