Loading...
HomeMy WebLinkAbout20140090 Ver 3_Outside footer drainage issue_20151027Wanucha, Dave From: Thomas, John T JR SAW <John.T.Thomas.JR@usace.army.mil> Sent: Tuesday, October 27, 2015 3:55 PM To: Euliss, Amy; Wanucha, Dave Subject: RE: U-2579B Station 628+65.50 Structure #10 Bent 2 outside footer drainage issue (UNCLASSIFIED) Classification: UNCLASSIFIED Caveats: NONE Yes I did include the temporary impacts that was included in the provide plan. -----Original Message----- From: Euliss, Amy [mailto:aeuliss@ncdot.gov] Sent: Tuesday, October 27, 2015 3:38 PM To: Thomas, John TJR SAW; Wanucha, Dave Subject: [EXTERNAL] RE: U-2579B Station 628+65.50 Structure #10 Bent 2 outside footer drainage issue (UNCLASSIFIED) Did you also include the temp. stream impacts? If so, should Dave as well so you're permits match? -----Original Message----- From: Thomas, John TJR SAW [mailto:John.T.Thomas.JR@usace.army.mil] Sent: Tuesday, October 27, 2015 3:37 PM To: Euliss, Amy; Wanucha, Dave Subject: RE: U-2579B Station 628+65.50 Structure #10 Bent 2 outside footer drainage issue (UNCLASSIFIED) Classification: UNCLASSIFIED Caveats: NONE I did do a mod letter for the 0.01 acre spring and had it put into the mail yesterday. I did this because the spring being in the flood plain of Smith Creek would most likely be captured as JD with the new WOUS rules. It was a easy fix to do a mod letter now so that it would not possibly become an issue later with the WOUS rules. John Thomas Raleigh Regulatory Field Office -----Original Message----- From: Euliss, Amy [mailto:aeuliss@ncdot.gov] Sent: Tuesday, October 27, 2015 3:27 PM To: Wanucha, Dave; Thomas, John TJR SAW Subject: [EXTERNAL] RE: U-2579B Station 628+65.50 Structure #10 Bent 2 outside footer drainage issue I meant to say spring, not stream. From: Euliss, Amy 1 Sent: Tuesday, October 27, 2015 3:22 PM To: Wanucha, Dave; Thomas, John TJR SAW (John.T.Thomas.JR@usace.army.mil) Subject: RE: U-2579B Station 628+65.50 Structure #10 Bent 2 outside footer drainage issue I think John is claiming jurisdiction over the stream, so we need to permit <0.01 acres of surface water. If he has already issued the 404 mod, then you might want to go ahead and issue so the 401 and 404 match up. John, What do you think? From: Wanucha, Dave Sent: Tuesday, October 27, 2015 3:14 PM To: Euliss, Amy Subject: RE: U-2579B Station 628+65.50 Structure #10 Bent 2 outside footer drainage issue Hi Amy, So no field mod needed then? Dave Wanucha Division of Water Resources Transportation Permitting Unit NC Department of Environmental Quality 336-776-9703 office 336-403-5655 mobile Dave.Wanucha@ncdenr.gov NC DEQ Winston Salem Regional Office 450 West Hanes Mill Road, Suite 300 Winston Salem, NC 27105 Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. From: Euliss, Amy Sent: Tuesday, October 27, 2015 8:29 AM To: Wanucha, Dave <dave.wanucha@ncdenr.gov>; Thomas, John TJR SAW (John.T.Thomas.JR@usace.army.mil) <John.T.Thomas.JR@usace.army.mil> Cc: Guy, Jeremy M<jmguy@ncdot.gov>; Panek, Lindsey F<Ipanek@ncdot.gov> Subject: RE: U-2579B Station 628+65.50 Structure #10 Bent 2 outside footer drainage issue We've had a change in plans. It would take 600', not 100', to make up the fall required to outlet the spring to the creek at the proper elevation. We will no longer need the temporary impacts to the bank of Smith Creek. Instead , we will put a temporary French drain to temporarily remove the water, and then fill the spring site around the spread footing with concrete. -Amy From: Euliss, Amy Sent: Monday, October 26, 2015 9:28 AM To: Wanucha, Dave; Thomas, John TJR SAW (John.T.Thomas.JR@usace.army.mil) Cc: Guy, Jeremy M; Panek, Lindsey F Subject: RE: U-2579B Station 628+65.50 Structure #10 Bent 2 outside footer drainage issue Attached is the official permit modification request. Let me know if you need anything else. Amy Euliss Division 9 Environmental Officer NCDOT 336 747 7802 office aeuliss@ncdot.gov 375 Silas Creek Parkway Winston Salem, NC 27127 cid: i mage001. png@01D10DA4.5CC88DA0 Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. From: Euliss, Amy Sent: Friday, October 23, 2015 2:25 PM To: Wanucha, Dave; Thomas, John TJR SAW (John.T.Thomas.JR@usace.army.mil) Cc: Guy, Jeremy M; Panek, Lindsey F Subject: FW: U-2579B Station 628+65.50 Structure #10 Bent 2 outside footer drainage issue We need to install a French drain from the spread footing to Smith Creek in order to remove the water from a spring that popped up during construction. This will result in @10' of temporary impacts to Smith Creek in an area where we're not permitted to work. This is needed for long term structural stability of the bridge. The area will be stabilized after the French drain installation. We're actively working on the bridge, and would like to proceed early next week. The work area will be isolated from the flowing water. Do we need to submit a permit mod, and if so, can we do so after the fact? I've drawn a red line on the plans and the structure plans which are attached. -Amy From: Panek, Lindsey F Sent: Friday, October 23, 2015 1:44 PM To: Euliss, Amy Cc: Guy, Jeremy M; Puckett, Lester L; Wyrick, Scott D; Riddick, Darryl M; Bennett, Andrew S; john.may@kci.com Subject: U-2579B Station 628+65.50 Structure #10 Bent 2 outside footer drainage issue Amy, On Structure #10 that is currently being constructed there appears to be a spring with a fair amount of water flow around the bridge pile that was driven on top of the spring. In order for the remaining spread footer construction to be completed and to alleviate the water flow in this area the Department would like to request permission to allow the contractor to install a one foot French drain running from the corner of the spread footing to the flowline of Smith Creek approximately 100 feet downstream(see attachment for location). The French drain would consist of 1 foot of #57 washed stone encapsulated in Geotextile. The outlet end of the French drain would consist of a 6" PVC outlet pipe. The work will require temporarily digging through the bank of Smith Creek, laying the outlet pipe, backfilling the creek bank, spreading a native seed mix and covering with Coir Fiber Mat. Disturbance of the stream bank should last no more than one day in duration. Please contact me if you have any questions. Thanks, Lindsey Panek Assistant Resident Engineer Division 9-Forsyth Construction Office: 336-747-7953 Fax: 336-761-2294 Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties. Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties. Classification: UNCLASSIFIED Caveats: NONE Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties. Classification: UNCLASSIFIED Caveats: NONE