From:Euliss, Amy
Sent:Friday, October 09, 2015 2:10 PM
To:Wanucha, Dave; Thomas, John T JR SAW (John.T.Thomas.JR@usace.army.mil)
Cc:Mabe, David S; Suggs, Phillip H; Guy, Jeremy M
Subject:RE: project completion form BR 115 Pine Hall Road Stokes
Attachments:Pine Hall headcut.pdf; vein.pdf
Following the heavy rain, we had a head cut develop where we had installed the new pipe under Pine Hall Road. We
plan to install a vein to stabilize the channel. The slopes are VERY soupy, so we’re going to let things dry out a bit before
we do the repair. If we get in there now, we’ll make a much bigger mess than if we wait. I’ve attached a picture of the
channel, and a detail of the proposed repair. It’s the one labelled ‘step-pool’ in the vein.pdf. Let me know if you need
anything further from me.
-Amy
From: Euliss, Amy
Sent: Wednesday, September 30, 2015 3:05 PM
To: Wanucha, Dave; Thomas, John T JR SAW (John.T.Thomas.JR@usace.army.mil)
Subject: RE: project completion form BR 115 Pine Hall Road Stokes
Attached are before and after shots following @10 inches of rain.
From: Euliss, Amy
Sent: Monday, September 28, 2015 1:40 PM
To: Wanucha, Dave; Thomas, John T JR SAW (John.T.Thomas.JR@usace.army.mil)
Cc: Cvijetic, Bojan
Subject: project completion form BR 115 Pine Hall Road Stokes
We’ve completed the replacement of BR 115 on Pine Hall Road in Stokes County. A copy of the DWR completion form is
attached.
This low impact bridge replacement project was approved by the USACE via email on 6.28.13. We don’t have an Action
Id. in our files for the USACE.
Amy Euliss
NCDOT Division 9 Environmental Officer
375 Silas Creek Parkway
Winston Salem, NC 27127
336-747-7802 (work)