Loading...
HomeMy WebLinkAbout20140192 Ver 1_Corrective Action Plan_20150928CORRECTIVE ACTION PLAN FOR Lower Big Hungry Mverc Dam Removal bite Henderson County, North Carolina Prepared for AGENCY REVIEW September 2015 Prepared by: AMo Gill Big Hungry River — Corrective Action Plan 17- Sep -15 Henderson County, NC McGill Associates, P.A. INTRODUCTION The Big Hungry River is a tributary of the Green River in the Broad River Basin. There are two historic dams in the lower reaches of the Big Hungry River (BHR), the lower of these is about 3/4 miles above the confluence with the Green River and the upper dam is about 3/4 miles above the lower. The Big Hungry River lower dam removal project is part of a larger project involving removal of both upper and lower dams. Both dams occur within the Green River Game Lands owned by the NC Wildlife Resources Commission. The dam removal project was initiated to enhance recreational opportunities on the BHR, remove aquatic migration barriers and eliminate hazards associated with both structures. Clean Water Act Section 404 and 401 permits were issued for the removal of the lower dam on May 7, 2014 and July 1, 2014 respectively. Construction commenced in February of 2015. The final portions of the lower dam were removed in early March 2015. This action resulted in a lowering of the base gradient of the river that caused an immediate headcut through accumulated sediment in the channel above the old dam. The sediment released from the project site as a result of this headcut led to the issuance of a Notification of Noncompliance with Permit from the USACE (March 26, 2015) and a Notice of Violation from NC DENR DWR (March 17, 2015). The Correction Action Plan (CAP) provided herein and attached materials are in response to the referenced notices issued to the NC Wildlife Resources Commission, Division of Engineering and Lands Management (Owner /Applicant) and Graham County Land Company, LLC (Contractor) in March 2015. McGill Associates, P.A. is the project engineer and is providing this response on behalf of the Owner and Contractor. Following the sediment release that occurred during an approximate 24 hour period between mid -day March 3, 2015 and mid -day March 4, 2015, staff members from NC DENR DWR and DEMLR conducted a site investigation of the Big Hungry River (BHR) below the project area of the lower dam removal project. Substantial volumes of sediment in the river, in excess of four feet in depth were observed. In response to the March 3 -4 event and subsequent communications with NCWRC, DWR, and other state and federal agencies, the Project Engineer initiated survey and planning efforts aimed at assessing the impacts and developing remedial action plans. This Corrective Action Plan (CAP) is submitted to the USACE and NC -DWR to describe how proposed remedial and restorative actions will bring the Big Hungry River, lower dam site, into compliance with Clean Water Act 404/401 permit conditions and to address the various other issues raised in the NOV's and Notification of Permit Noncompliance. Specific focus will be given to the following items: • Details to remove the unauthorized fill material • Short-term and long -term streambank and stream bed stabilization measures upstream of the dam to minimize further sediment destabilization • Stream restoration/enhancement activities downstream of the dam 2 Big Hungry River — Corrective Action Plan 17- Sep -15 Henderson County, NC McGill Associates, P.A. • Location of sediment disposal areas and details of how this sediment will be handled and stabilized • Proposed schedule to perform the corrective action tasks • Preparation of the final document detailing the performance of the remedial actions with supporting as -built drawings and photos A. REMOVAL OF UNAUTHORIZED FILL MATERIAL Following the sediment release that occurred during an approximate 24 hour period between mid -day March 3, 2015 and mid -day March 4, 2015, staff members from NC DENR DWR and DEMLR conducted a site investigation of the Big Hungry River (BHR) below the project area of the lower dam removal project. Substantial volumes of sediment in the river, in excess of four feet in depth were observed. The observed sediment deposition contributed to the issuance of a Notice of Violation to the project Applicant and Contractor that requires, among other things, the development of a Sediment Removal Plan and a Stabilization Plan for all involved areas of the BHR. In response to the March 3 -4 event and subsequent communications with NCWRC, DWR, and other state and federal agencies, the Project Engineer initiated survey and planning efforts aimed at assessing the impacts and developing remedial action plans. The results from the sediment impact analysis performed by McGill Associates are summarized below followed by an analysis of downstream sediment removal options: 1. Impact Analysis On -site Impacts: On -site impacts are those direct 404/401 impacts within the immediate area of the old lower dam and extending upstream for approximately 125 feet. These are temporary impacts associated with the access ramp constructed out of demolition rubble and soil, the temporary dam constructed out of Jersey Barriers, rubble and rock, and bank sloughing along the lower portion of the headcut channel. Off -Site Impacts: Off -site impacts were determined through a stream sediment study conducted March 20, 2015. The study involved an assessment of the BHR downstream of the lower dam site for approximately 2850 linear feet as well as approximately 1850 linear feet upstream of the old impoundment limits above the lower dam. The assessment was conducted using 4 -foot and 7 -foot long sediment probes to measure depth and estimate average depth of depositional areas. The surface area of each depositional area was measured or estimated as well. Generally, pool areas consisted of one large sediment plume but riffle areas consisted of multiple smaller pockets of deposition in micro -pools or eddies within the riffle; the multiple smaller depositional areas within the riffles were aggregated into a single quantity for most riffles. GPS points were taken at the approximate center of each area evaluated. The locations are shown on figures (U1 -U2 and D1 -D2). Results of the evaluation are recorded in the attached table (T -1). 3 Big Hungry River — Corrective Action Plan Henderson County, NC 17- Sep -15 McGill Associates, P.A. Downstream Impacts: The downstream sediment evaluation area begins at the base of the waterfall below the old dam (station 0 +00) extending downstream about 2,850 linear feet (station 28 +50). The average slope of this reach is roughly 1.8 %. Every pool evaluated downstream of the lower dam contained large deposits of sediment. The composition of the sediment was predominantly medium to coarse sand mixed with a small amount of organic material. Along channel margins and backwater areas, particle size decreased and the sand was mixed with small amounts of silt and clay. Water clarity was high throughout the assessment area even in areas of high velocity. Most riffle sections contained multiple smaller sediment deposits as described above. There was sediment on the lower banks in places, but this was not measured. Within the 2,850 linear foot reach evaluated for sediment impact, 29 depositional areas were measured, 20 pools and 9 riffle /run areas, the total length of the measured areas was 1,047 linear feet. The total volume of sediment measured was 2,533 cubic yards. The volume of sediment measured per 1,000 feet of reach evaluated is about 889 cubic yards. The volume of sediment measured per 1,000 feet of reach measured is about 2,419 cubic yards. See below (Impact Assessment Analvsis) for a description of the difference between the length of reach measured and the length of reach evaluated. Upstream Impacts: The upstream evaluation area begins roughly 1,120 linear feet above the old dam (station 11 +20) and extends upstream for about 1850 linear feet (station 29 +50). The average slope of this reach is roughly 2.05 %. Every pool evaluated upstream of the backwater limits of the lower dam was filled with sediment of roughly the same composition as described for the downstream reach. Water clarity was high throughout this reach, no apparent difference from the downstream reach. Riffle sections contained scattered pockets of sediment but the frequency and size was somewhat reduced when compared to the downstream reach. Within the 1,790 linear foot reach evaluated, 13 depositional areas were measured, 9 pools and 4 riffle /run areas, the total length of the measured areas was 530 linear feet. The total volume of sediment measured was 1,138 cubic yards. The volume of sediment measured per 1,000 feet of reach evaluated is about 636 cubic yards. The volume of sediment measured per 1,000 feet of reach measured is about 2,147 cubic yards. See below (Impact Assessment Analvsis) for a description of the difference between the length of reach measured and the length of reach evaluated. Impact Assessment Analvsis: The sediment assessment performed by McGill Associates clearly shows that the BHR below the lower dam site is severely impacted by sediment deposition. The assessment also shows that the BHR is severely impacted by sediment above the limits of backwater behind the old lower dam. The degree to which pools are filled with sediment and the distribution of sediment in riffles and runs appears similar in the two reaches. The following method was used to compare the relative degree that the BHR is impacted by sediment between the upstream and downstream reaches. Estimated sediment 2 Big Hungry River — Corrective Action Plan Henderson County, NC 17- Sep -15 McGill Associates, P.A. volume per 1,000 feet of reach evaluated was determined by dividing the total volume of sediment measured by the length evaluated (2,533 yds. /2,850 lin.ft. for downstream and 1,137 yds. /1,790 lin.ft. for upstream). Estimated sediment volume Der 1,000 feet of reach measured was determined by dividing the total volume of sediment measured by the combined total length of the depositional areas measured (2,533 yds. /1,047 lin.ft. for downstream and 1,137 yds. /530 lin.ft. for upstream). This comparison shows a nearly 40% increase in sediment per linear foot of reach evaluated downstream vs. upstream. However, when considering that the upstream reach has a steeper average gradient (2.05% upstream to 1.8% downstream) and correspondingly fewer depositional areas per unit length (more riffles and shallow bedrock sections) than the downstream reach, a direct comparison of the amount of sediment trapped in depositional areas may be more appropriate. Such a comparison shows only a 13% increase in sediment per linear foot of measured depositional area downstream vs. upstream. Therefore, we believe the actual difference in the relative abundance of sediment between the two reaches to be closer to 13% than 40 %. The results of the instream sediment assessment seem to indicate that the entire section of the BHR from above the upper dam to at least 3,000 linear feet below the lower dam site is severely impacted by sediment and has been for some time. Direct evidence to support this is limited to two observations: 1. In a couple of the downstream pools there was a clearly visible organic layer with approximately 6 to 8 inches of sediment on top. This could indicate that the sediment below this organic layer may have existed prior to the March 3 -4 sediment release. 2. All along the downstream reach there was extensive sediment deposition along the banks and inner -berm features at elevations above the water surface elevation at the time of the evaluation. Between the March 3 -4 sediment release and the March 20 sediment assessment there were not any precipitation events greater than 0.40 inches in 24 hours. This would appear to indicate that previous events delivered heavy sediment loads to the reach. 2. Sediment Removal Analysis Sediment Impact Assessment and Removal Plan Options: Following review and analysis of the instream sediment assessment performed both upstream and downstream of the lower BHR dam, it has become apparent that the BHR from the upper reaches of the old lake above the upper dam, downstream to the confluence with the Green River is a severely sediment stressed system. The sediment analysis did not extend upstream above the sediment wedge collected at the upper dam but it is likely that area will be sediment stressed as well. High 5 Big Hungry River — Corrective Action Plan Henderson County, NC 17- Sep -15 McGill Associates, P.A. sediment loads have been documented in the BHR and are well documented for the entire Green River watershed above Lake Adger. The NOV requires that a Sediment Removal Plan must be proposed but also requires that this plan should not be implemented until the entire area, including the area above the dam, is stabilized. We agree with this mandated sequence of events. Clearly it would not make sense to expend substantial resources and incur the environmental impacts associated with removing sediment below the lower dam when a single storm event could refill every pool in a short period of time. We have identified four substantial sources of sediment upstream of the impacted reach: 1. The BHR channel through the old lake bed immediately above the lower dam site, this reach is approximately 900 linear feet. 2. The large volumes of measured sediment in pools, riffles and runs above the old lower dam lake bed and below the upper dam. 3. The estimated 50,000 cubic yards of sediment currently held behind the upper dam, but apparently being released on a regular basis. 4. The high sediment load delivered from the 19 square mile watershed above the upper dam. A watershed with predominantly sandy loam soils, steep topography and a substantial amount of agricultural land use. A second issue with any sediment removal plan for the impact reach will be the environmental impacts necessary, simply to gain sufficient access to the sediment deposits with the equipment needed to implement the plan. Options considered for sediment removal include mechanical removal and hydraulic removal. Mechanical: Given the volume of sediment in this area and the need to minimize instream work (equipment in flowing water) it would be necessary to use fairly large tracked equipment to dig out the sediment. Additionally, off -road trucks would need to access each removal area to facilitate removal of sediment to a suitable disposal site. This operation would require the construction of a road down to the riparian area and then all along the riparian area. This would significantly disturb and alter the riparian zone along the right bank of the BHR for over 1,000 linear feet. In many areas isolating the sediment removal work area from flowing water would be extremely difficult without a much larger mobilization involving multiple cycles of coffer dam installation and removal, and this would be far from a perfect solution. Needless to say, the cost/benefit reality of such an operation would be hard to justify. Hvdraulic: This approach would offer some clear benefits over mechanical sediment removal, most notably it would eliminate the need to mechanically excavate a large portion of the impact reach. This approach would, however, also require the construction of an access road to and along the riparian zone. The hydraulically dredged or pumped sediment would have to be dewatered in the 0 Big Hungry River — Corrective Action Plan Henderson County, NC 17- Sep -15 McGill Associates, P.A. riparian zone and be loaded into trucks for removal offsite. The limiting factors for these operations include vertical lift and horizontal distance so the dewatering, stockpiling and loading operations would have to move down along the river with the dredging operation causing a substantial amount of disturbance. Focus Resources on Source Control: It is important to consider that the root cause of the sediment release is the fact that there are extremely large quantities of unconsolidated, highly erodible sediments behind both the lower and upper BHR dams. The watershed above the upper dam will also continue to produce large sediment loads well into the future. The best solution for the long term health of the BHR will be to remove or permanently stabilize in place the sediment behind both dams and restore a channel with appropriate dimension, pattern, and profile to move the high sediment loads that will emanate from the watershed. It may be appropriate to focus, in the near term, on stabilizing the area behind both dams and monitor the sediment deposition areas until all other work is complete. A reassessment of sediment removal options could be made at that time. Off -Site Sediment Mitigation: A fourth option would be to investigate potential off -site stabilization or sediment removal opportunities. The upper reaches of the BHR watershed contain numerous areas of intense agricultural activities in areas of highly erodible soils, while we are not aware of any specific sites at this time, it is understood that there are numerous areas in need of enhancement or stabilization efforts. Given the stated circumstances we propose the following to address the issues stated in the NOV and Notice of Noncompliance: A. Stabilize BHR channel upstream of the lower dam site for approximately 500 linear feet or an amount sufficient to prevent any future head cuts and to stabilize any unconsolidated sediment along the banks and active flood prone areas. B. Proceed with planning efforts for the removal of the upper BHR dam, removal of excess impounded sediment above the upper dam and stabilization of the BHR channel above the upper dam. C. Commence an investigation into various sediment removal /mitigation options, coordinate the findings with DWR and develop a plan for the most appropriate course of action. D. Monitor sediment levels in the BHR below and above the lower dam removal project area. 7 Big Hungry River — Corrective Action Plan Henderson County, NC 17- Sep -15 McGill Associates, P.A. B. SHORT AND LONG TERM MEASURES TO STABILIZE THE STREAM BED AND BANKS UPSTREAM OF THE LOWER DAM 1. Project Purpose & Description The purpose of this project is to reconstruct and stabilize eroded and unstable stream banks along the Big Hungry River (BHR) upstream of the recently removed lower dam structure. The severely eroded stream banks consist of exposed sediment deposits that were trapped behind the old dam and have eroded as the river has headcut above the old dam location. The proposed design is intended to reconstruct a stable channel for approximately 500 linear feet upstream of the old dam. The channel design is based on relevant upstream reference data and regional curve data. The project will involve the removal of instream sediment and stabilization of newly established streambanks using bioengineering and natural channel design approaches and techniques. The work described in this Corrective Action Plan (CAP) is urgent and necessary to prevent further sediment loss from the project area. The North Carolina Wildlife Resources Commission is the sponsor and responsible party for the project. Work on the site consists of repair and stabilization effort only, and is not considered natural channel restoration or enhancement work. However, some methods and approaches utilized in the proposed repairs are routinely applied in natural channel design efforts due to their ability to protect channel banks from shear stresses and the resultant erosion. All work in or near surface waters will be supervised by trained personnel from McGill Associates. 2. Site Description The project site consists of the area disturbed during the removal of the old lower dam, and a reach of the BHR extending approximately 500 linear feet upstream. The site also includes an access road from the end of Gallimore Road, approximately 1,500 feet to the old dam site and a graded ramp from the end of the access road down to the channel edge at the lower end of the project reach. A portion of the cul- de -sac at the end of Gallimore Rd. will be used for equipment and material staging as will an area at the lower end of the access road. The area immediately above the old dam contains large sediment deposits primarily along the left bank and further upstream sediment deposits are evident along the right bank. The channel bed also contains large quantities of sand with depths of greater than 7 feet in pools. A temporary dam was installed in the channel at the approximate location of the old dam following removal of the dam in early March of 2015. The purpose of the dam was to halt a rapid headcut through unconsolidated depositional Big Hungry River — Corrective Action Plan Henderson County, NC 17- Sep -15 McGill Associates, P.A. material. The temporary dam consists of several jersey barriers and concrete rubble from the dam demolition. The river has backed up by approximately 6 feet behind the temporary dam and this area is effectively trapping sediment. 3. Technical Approach Stabilization of the site and area above the dam will be accomplished as outlined in the attached plans. The area to be stabilized extends from the old dam site upstream for approximately 500 linear feet. This area consists of the construction access ramp at the old dam site and the temporary dam installed to abate the headcut and sediment loss on March 4, 2015. Above the access ramp, the BHR currently flows in a channel that has formed through deep sediment deposits. The depth of sediment in and adjacent to the existing channel tapers in an upstream direction. The primary goal of the design is to establish a stable, appropriately sized channel through the area of accumulated sediment, establish vertical grade control, and stable vegetated streambanks. The final plans are based on the following design objectives: • Locate and utilize existing natural channel Grade control to the extent practically feasible: The preferred design for this reach is one that allows the BHR to flow through the valley in a manner similar to the pre -dam condition of the early 1900's. The BHR both upstream and downstream of this reach is characterized by frequent bedrock control and deep pools, based on our analysis of the channel substrate below the sediment deposition, it appears this characteristic is present in this reach as well. The length of the project reach was determined based on natural grade control points identified at approximately 500 linear feet above the old dams location. The grade control at this location is covered by less than one foot of sediment, minimizing the risk of additional head cuts above this location. • Locate and utilize existing stable natural features to incorporate into design: Features such as vertical bank rock, vegetated natural ground, and large existing trees are incorporated into the design to anchor proposed cross sections to the extent practically feasible. • Avoid or minimize anv required cut in natural ground: There is a large amount of unconsolidated sediment adjacent to the existing channel that is masking the depth and shape of the underlying natural ground. Our objective is to locate and leave intact these previously existing natural features. This will involve field adjustments to the design where conditions are uncovered that don't fit with the current design. • Minimize the volume of sediment that will have to be moved: The final design for this reach incorporates a balance between practical feasibility and the ideal natural channel design. Perhaps the most significant cost will 9 Big Hungry River — Corrective Action Plan Henderson County, NC 17- Sep -15 McGill Associates, P.A. be associated with the moving and stabilization of the large volumes of sediment throughout the reach. • Locate areas on -site to be used for sediment disposal: There are two existing benches along this reach that are above the bankfull elevation, the feasibility of permanently disposing of excess sediment in these areas was investigated by a geotechnical engineer and the final design incorporates the engineers recommendations. Beyond these areas, sediment disposal will occur at an approved off -site disposal site. • Maintain low instream turbidity during various construction activities: Various approaches are incorporated into the final plan to be used individually and in concert to achieve this objective. These include a temporary crossing to facilitate access to the left bank of the BHR at the lower end and leaving the temporary dam constructed on March 4, 2015 in place until the final stage of construction, to facilitate settling and trapping of what sediment does get into the river. Accumulated sediment behind the temporary dam will be periodically removed and disposed of at a suitable upland location. 4. Design Summary The BHR at the project site has a drainage area of approximately 20 square miles that is predominantly forested with scattered pockets of low density residential and larger areas of agricultural use, particularly in the upper reaches of the watershed. The average water surface slope through the project reach is about 2 %. The bankfull width will range between 45 and 55 feet, bankfull cross sectional area will range from 145 to 165 square feet, and average depth will be approximately 3 feet. The design stream type will be a B -3 (using Rosgen terminology). The attached Final Plan provides details of our approach for design of the roughly 500 foot -long reach above the lower dam site. Given uncertainties regarding the location of buried bedrock grade control features and the precise location of the natural ground/unconsolidated sediment interface, we have built in limited alternatives and contingency measures into the design. As discussed during the April 8, 2015 meeting, these added design elements will allow for some on- the - ground adjustments to the stream design based on new information encountered during the construction phase. Every reasonable effort has been made to minimize uncertainty prior to construction, but these elements will allow the project to proceed with maximum efficiency. Typical channel dimensions shown in the plans are derived from regional curve data and refined using appropriate reference data from above the project reach. The plan view shows our intention to generally follow the existing flow path with minor variations to soften a couple of sharp bends and utilize existing bedrock outcroppings in the banks to the extent practicable. The plan view also shows locations for a 10 Big Hungry River — Corrective Action Plan Henderson County, NC 17- Sep -15 McGill Associates, P.A. temporary crossing, temporary dam and onsite locations for disposal of excess sediment. A longitudinal profile is provided that shows only an approximate average grade line for the proposed channel. The current profile is based on identified, assumed shallow bedrock ledges in the existing streambed. All bed features in the project reach are obscured by sediment and can only be identified using a probe rod. Consequently, we anticipate numerous minor adjustments to the plan will be necessary as we acquire more information about existing bed features during the construction phase. The plan is to minimize or avoid altogether the use of constructed grade control. A boulder cross vane grade control detail is included in the plans if field conditions indicate one is required. Typical and design cross sections are provided to illustrate the general concept of this design. The primary challenge will be to stabilize and provide for permanent vegetation establishment on the extensive sediment deposits to be left along the reach. The design is to stabilize the streambanks adjacent to the sediment deposit with naturally vegetated, reinforced soil lifts. The base of the soil lifts will be rock or concrete rubble. If field conditions require additional toe armoring, a detail for boulder toe stabilization, with or without soil lifts above may be used. Existing bedrock has been identified in the stream banks throughout the reach. The design cross section ties to the existing bedrock in all locations where possible on outside meander bends. The plan includes a revegetation plan for all disturbed areas including the riparian corridor, sediment disposal areas, access road, and staging areas. The streambanks will be stabilized using live stakes along graded low banks (3 -feet c -c), live cuttings or bare -root whips in between soil lifts (continuous), and bare -root whips in the upper banks and sediment disposal areas (approximate 2 -feet c -c). All disturbed areas will be seeded with a native seed mix and temporary erosion control mix (see plans for mix and rate). Graded slopes above bankfull will be stabilized with a natural fiber, fully biodegradable erosion control mat, and areas along the access road may be hydroseeded. 5. Proposed Sequence of Construction The proposed Repair Plan is described in the attached construction plans and specifications. The general sequence of construction is explained here: 1. The contractor will mobilize onsite and install any additional erosion control measures or safety fence needed to properly protect the work area and surrounding areas from unintended erosion, sedimentation or disturbance. 2. The contractor will regrade water bars on access road to allow for sediment trapping and filtration of runoff prior to mixing with flow from upslope seeps and/or before discharge below the access road. 11 Big Hungry River — Corrective Action Plan Henderson County, NC 17- Sep -15 McGill Associates, P.A. 3. The contractor will remove sediment from the area behind the temporary dam upstream to the area of the temporary crossing. Sediment removed will be placed in a temporary containment area with adequate filtration to remove all visible sediment from any return water. Once the sediment is dewatered it will be removed to a stable disposal area and permanently stabilized. 4. The Contractor will install the temporary crossing at the approximate location specified on the plans. The crossing will consist of non - erodible material to provide a suitable crossing for construction equipment and allow passage of anticipated flows. Final design to be approved by Engineer based on site conditions at the time of construction. 5. The Contractor will prepare the sediment disposal area to accept excess material from the upstream channel grading. 6. The contractor will proceed to shape the design channel from the upstream end of the project area. Installation of all toe protection, grade control structures, and bank stabilization measures will be installed before proceeding downstream. 7. Contractor and Engineer will develop a plan to divert flow away from work area in the lower 100 linear feet of the project reach. Engineer will coordinate plan with Agencies. 8. All graded banks will be seeded and matted within 24 hours of finished grading. Finished grade is to be determined by the engineer. 9. The Contractor will continue working downstream until the limit of backwater from the temporary dam prevents work from proceeding further. 10. Contractor will install erosion control measures and confinement per the Drawings in the cul -de -sac of Gallimore road for temporary storage of excess sediment to be disposed of offsite. 11. Contractor will implement flow diversion plan and proceed to grade and stabilize the left bank to the lower end of the project reach. 12. Contractor will complete grading activities in sediment disposal area and stabilize all slopes and commence installation of all woody plant material. 13. Contractor will remove temporary stream crossing and clean out sediment storage area above temporary dam. 14. Contractor will remove temporary dam and complete grading and stabilization measures on the right bank at the lower end of the project reach. 15. Contractor will remove all excess sediment and debris from the riparian zone and haul to an approved offsite disposal area. 16. Contractor will complete installation of all woody plant material and complete all stabilization activities in the riparian corridor. 17. Contractor will remove all construction debris and stabilize the staging at the lower end of the access road. 18. Contractor will stabilize the access road and slopes above and below the road, all disturbed areas will be seeded and mulched according to the plans. 19. Contractor will monitor access road for stabilization and remove all silt fence and metal posts once road is permanently stabilized. 12 Big Hungry River — Corrective Action Plan 17- Sep -15 Henderson County, NC McGill Associates, P.A. 6. Construction Monitoring Construction observation and monitoring will be provided by McGill Associates (Engineer) throughout the construction phase of the project. Personnel trained in stream restoration and natural channel design concepts will be onsite during critical phases of the construction and will be on -call during other times. The Engineer will produce work logs and progress reports on a regular basis. The Contractor will inform the Engineer when activities requiring the Engineer's approval are anticipated so that work can proceed without interruption. The Engineer will contact the permitting agencies if field conditions are encountered that require deviations from the plans beyond the scope described in this CAP and the Plans and Specifications. C. STREAM RESTORATION /ENHANCEMENT ACTIVITIES DOWNSTREAM OF THE LOWER DAM At the present time there are no planned restoration or enhancement activities for the BHR below the lower dam site. Based on observations over the past 6 months, the BHR below the lower dam site is generally stable despite the fact that large sediment accumulations remain within most pools along the reach. Section A (above) describes the sediment impacts and existing condition of the BHR above and below the lower dam project area. From the analysis performed and opinions expressed in the NOV, it is understood that remedial action downstream of the lower dam site is not advised until after both the lower and upper dam removal projects are concluded. It is also understood that restoration /enhancement activities downstream of the lower dam site involving construction equipment may do more harm than good to the ecosystem. Such activities would require access roads and staging areas in the riparian zone and on steep wooded slopes. The effectiveness of sediment removal activities is also in question and there would be a large short-term impact to instream habitat during any such operation. Given the stated issues, it is our recommendation that planning for any downstream restoration/enhancement activities be delayed until after completion of both upper and lower dam removal projects, at which time the need for such activities should be reassessed. D. SEDIMENT DISPOSAL PLAN The stream stabilization plan described under section B (above) outlines the current plan to remove and /or stabilize accumulated sediment behind the old lower dam. The construction phase for this plan is scheduled to commence in October 2015 and will involve grading and shaping in and adjacent to the existing channel above the lower dam to establish an appropriate bankfull channel and stabilize the graded streambanks in areas where bedrock is not present in the lower banks. Excess sediment removed from the channel and riparian areas will be relocated to an existing high bench on the left side of the BHR that extends approximately 300 linear feet upstream of the old dam location. A geotechnical study was conducted to determine the volume of 13 Big Hungry River — Corrective Action Plan Henderson County, NC 17- Sep -15 McGill Associates, P.A. additional sediment that could be supported on the existing bench and the appropriate method of stabilization. The attached construction plans detail the proposed grading and stabilization for this area. Additional excess sediment that cannot be disposed of on -site will be hauled off -site to an approved, permitted waste area. The contractor has indicated that the excess material will be hauled to the Henderson County landfill. E. SCHEDULE FOR PROPOSED ACTIVITIES The construction phase for the stabilization of the BHR above the lower dam site is scheduled to begin as soon as approvals are obtained from the USACE and NC DWR on the proposed plan. Also required prior to construction is approval of a contract change order from the State Construction Office. All approvals are anticipated by the end of September of 2015. Anticipated Project Timeline: 10 -5 -2015 — begin mobilization 10 -8 -2015 — begin river stabilization activities 11 -13 -2015 — complete river stabilization activities 11 -25 -2015 — complete final site stabilization activates including access road and staging areas 11 -30 -2015 — begin post construction monitoring for both river stability and site stabilization F. POST CONSTRUCTION AS -BUILT AND MONITORING Following construction activities, an as -built survey will be conducted for the project reach. The survey will consist of two representative cross sections at locations agreed upon by the agencies. Cross section locations will be marked in the field. Numerous photo points will be established with GPS points and angle of shot. WRC will develop plans for annual monitoring of the stabilized reach in connection with the ongoing upper dam removal project. 14 Graphic Scale (Feet) 0 25 50 100 SCALE IS APPROXIMATE CONTOUR INTERVAL: 20' SEDIMENT ASSESSMENT SITES UPSTREAM ANALYSIS SHEET U -1 MARCH 24, 201.5 Channel Shift to Right Bank +00 { F +00 5 +00 3 +00 11 +00 Limits of Backwa from Lower Dam 0400 3 +00 8+ Lower Dam - Removed BIG HUNGRY RIVER LOWER DAM SEDIMENT ASSESSMENT HENDERSON COUNTY NORTH CAROLINA 0 DATA SOURCES: 2010 AERIAL IMAGERY ACQUIRED THROUGH NC ONEMAP GEOSPATIAL PORTAL; LIDAR TOPOGRAPHY ACQUIRED , THROUGH NCDOT; SEDIMENT ASSESSMENT AREAS FIELD LOCATED USING HANDHELD GPS. I 1IMcG • A S S O C I A T E S ENVIRONMENTAL SERVICES 468 NEW MARKET BLVD. STE B BOONE, NC 28607 PH. (828) 386 -1920 ° ° ° ° S S Em Graphic Scale (Feet) 8�» 0 25 50 100 SCALE IS APPROXIMATE CONTOUR INTERVAL: 20' SEDIMENT ASSESSMENT SITES UPSTREAM ANALYSIS SHEET U -2 MARCH 24, 2015 ao. 1 ry 1 �O. BIG HUNGRY RIVER LOWER DAM SEDIMENT ASSESSMENT HENDERSON COUNTY NORTH CAROLINA 'T DATA SOURCES: 2010 AERIAL o IMAGERY ACQUIRED THROUGH ° NC ONEMAP GEOSPATIAL PORTAL; .'' LIDAR TOPOGRAPHY ACQUIRED ±'� THROUGHNCDOT; SEDIMENT Y;y j ASSESSMENT AREAS FIELD + LOCATED USING HANDHELD GPS. —AU ° A S S O C I A T E S McGill ENVIRONMENTAL SERVICES 468 NEWMARKET BLVD. STE B BOONS, NC 28607 PH. (828) 386 -1920 00 Graphic Scale (Feet) 0 25 50 100 SCALE IS APPROXIMATE CONTOUR INTERVAL: 20' SEDIMENT ASSESSMENT SITES DOWNSTREAM ANALYSIS SHEET D -1 MARCH 24, 2015 BIG HUNGRY RIVER LOWER DAM SEDIMENT ASSESSMENT HENDERSON COUNTY NORTH CAROLINA .{ J O O k00 a DATA SOURCES: 2010 AERIAL IMAGERY ACQUIRED THROUGH NC ONEMAP GEOSPATIAL PORTAL; LIDAR TOPOGRAPHY ACQUIRED THROUGH NCDOT; SEDIMENT ASSESSMENT AREAS FIELD LOCATED USING HANDIIELD GPS. A S S O C I A T E S I jMcG ENVIRONMENTAL SERVICES 468 NEWMARKET BLVD. STE B BOONE, NC 28607 PH. (828) 386 -1920 Graphic Scale (Feet) 0 25 50 100 SCALE IS APPROXIMATE CONTOUR INTERVAL: 20' SEDIMENT ASSESSMENT SITES DOWNSTREAM ANALYSIS SHEET D -2 MARCH 24, 2015 BIG HUNGRY RIVER LOWER DAM SEDIMENT ASSESSMENT HENDERSON COUNTY NORTH CAROLINA DATA SOURCES: 2010 AERIAL IMAGERY ACQUIRED THROUGH NC ONEMAP GEOSPATIAL PORTAL; LIDAR TOPOGRAPHY ACQUIRED THROUGH NCDOT; SEDIMENT ASSESSMENT AREAS FIELD LOCATED USING HANDHELD GPS. JMcG• A S S O C I A T E S ENVIRONMENTAL SERVICES 468 NEWMARKET BLVD. STE B BOONE, NC 28607 PH. (828) 386 -1920 STREAM SEDIMENT STUDY -MARCH 20, 2015 Table T -1 Location relative to Evaluated Measured Area Lower Dam Length Length Width Depth Cu. Ft. Cu. Yds. Max Depth Notes 1 Downstream 20 20 20 3.5 1400 51.9 7 Pool beneath large falls - old dam to right side of channel. 2 Downstream 20 12 20 1.5 360 13.3 4.5 Pool beneath large falls -old dam to left side of channel. 3 Downstream 70 70 10 1.5 1050 38.9 Run section bordered by boulder outcropping. 4 Downstream 190 100 23 3 6900 255.6 Long pool. 5A Downstream 310 25 45 3 3375 125.0 6 Deep chute along left side of channel. Wide boulder garden: shallow sediment (-1 ") in high velocity zones; 5B Downstream 350 45 35 1.5 2363 87.5 deeper sediment deposition (^3') in eddies of rocks. Section with vegetated bars and chutes: deeper sediment 6A Downstream 440 40 30 0.75 900 33.3 3 deposition in eddies and shallow sediments in high velocity zones. 6B Downstream 515 10 10 2 200 7.4 Pool along right side of channel. 7 Downstream 610 15 5 1 75 2.8 Right side of channel area of deposition. 8 Downstream 680 18 10 1.5 270 10.0 Right side of channel area of deposition. 9 Downstream 745 12 25 1.7 510 18.9 Center of channel area of deposition (run). 10 Downstream 880 100 35 2.5 8750 324.1 Long pool. 11 Downstream 1100 35 10 1 350 13.0 Pool 12 Downstream 1140 10 20 1 200 7.4 Shallow pool. 13 Downstream 1170 25 15 1.5 562.5 20.8 Deposition in center of channel in run section. 14 Downstream 1210 18 12 1.5 324 12.0 Shallow pool. 15 Downstream 1275 40 12 1.2 576 21.3 Boulder garden section with intermittent pockets of sediment. 16A Downstream 1450 30 10 1 300 11.1 Pool above falls. 16B Downstream 1500 12 10 1.5 180 6.7 Pool below falls. 17 Downstream 1580 50 30 2.5 3750 138.9 Long pool. 18 Downstream 1660 12 8 1 96 3.6 Pool 19 Downstream 1760 40 12 2.5 1200 44.4 Pool 20 Downstream 1860 18 25 2.5 1125 41.7 5 Pool in gorge section. 21 Downstream 1935 60 30 5 9000 333.3 8 Pool below gorge section. 22 Downstream 2070 30 20 1.5 900 33.3 3 Pool 23 Downstream 2180 65 40 5 13000 481.5 7+ Long pool. 24 Downstream 2445 40 20 1.5 1200 44.4 Intermittent pockets of sediment in bouldery section. 25 Downstream 2565 30 15 3 1350 50.0 5 Pool 26 Downstream 2850 65 25 5 8125 300.9 7+ Long pool. DOWNSREAM TOTAL 2850 1047 68391 2533.0 PAGE 1 volume of sediment per foot of reach evaluated =1138 yards / 1790 lin.ft. = 0.64 yards /ft evaluated volume of sediment per foot of reach measured =1138 yards / 530 lin.ft. = 2.15 yards /ft evaluated Percent Difference Downstream vs Upstream Evaluated: 0.89 yards /ft - 0.64 yards /ft = 0.25 yards /ft / .064 yards /ft = 39% increase Measured: 2.42 yards /ft - 2.15 yards /ft = 0.27 yards /ft / 2.15 yards /ft = 13% increase PAGE 2 Location Relative to Evaluated Measured Area Lower Dam Length Length Width Depth Cu. Ft. Max Depth Notes A Upstream 1120 12 20 1.5 360 13.3 3 Pool B Upstream 1220 8 10 1 80 3.0 Pool C Upstream 1350 10 10 1 100 3.7 Run D Upstream 1610 30 20 1.5 900 33.3 Pool E Upstream 1760 110 30 2.5 8250 305.6 7+ Long pool. F Upstream 1900 85 25 2.7 5738 212.5 7+ Long pool. G Upstream 2240 30 15 1.3 585 21.7 Pool Two areas of deposition in channel between riffles and boulder H Upstream 2310 10 10 1.5 150 5.6 sections. I Upstream 2360 20 8 1.5 240 8.9 small pool J Upstream 2400 80 35 3 8400 311.1 7+ Long pool. K Upstream 2540 40 40 2.5 4000 148.1 6 Pool L Upstream 2820 15 8 1 120 4.4 Run M Upstream 2910 80 15 1.5 1800 66.7 2.5 Run UPSTREAM TOTAL 1790 530 30723 1137.9 ANALYSIS Downstream volume of sediment per foot of reach evaluated = 2533 yards / 2850 lin.ft. = 0.89 yards /ft evaluated volume of sediment per foot of reach measured = 2533 yards / 1047 lin.ft. = 2.42 yards /ft evaluated volume of sediment per foot of reach evaluated =1138 yards / 1790 lin.ft. = 0.64 yards /ft evaluated volume of sediment per foot of reach measured =1138 yards / 530 lin.ft. = 2.15 yards /ft evaluated Percent Difference Downstream vs Upstream Evaluated: 0.89 yards /ft - 0.64 yards /ft = 0.25 yards /ft / .064 yards /ft = 39% increase Measured: 2.42 yards /ft - 2.15 yards /ft = 0.27 yards /ft / 2.15 yards /ft = 13% increase PAGE 2