Status Update
Onsite Landfill and SWMU-5 Reconfiguration Design
Venator Chemicals, LLC Facility
Harrisburg, NC
Facility ID: NCD 048 467 427-R2
Presented to: NCDEQ DWQ & DWM
Presented by: Venator/ERM
November 2023
1
Attendees
2
Roberto Scheller Senior Environmental Specialist - DWQ
Adam Ulishney Hazardous Waste Section Chief - DWM
Andrew Pitner Assistant Regional Supervisor - DWQ
Rob McDaniel Hydrogeologist – HWS
Sherri Stanley Branch Head – Solid Waste
Rose Pruitt Environmental Specialist – HWS
Claire Osborn Environmental Engineer – Solid Waste
Ori Tuvia Environmental Engineer, NPDES Permitting
Jonna Stein Harrisburg EHS manager
Michael Thomas Construction Project Manager
John Bonner Senior Project Leader North America
Kevin Robinson Harrisburg Plant Manager
Harry Carter, P.G. Project manager
Dave Wasiela, P.E. Technical Advisor
2
Completed Activities Landfill
3
Design finalized
Landfill
SWMU-5
Borrow area
Technical documents completed
Submitted application for permit to construct to DWM!
Submitted NOI Certification Form NCG01 & Financial Responsibility Form for Sediment and Erosion Control Plan
So that tree clearing activities can begin
3
4
4
5
5
Lagoon Liner Package
6
6
NPDES Completed Activities
7
Met with NC Division of Water Quality in August to review required information for permit mod
Completed SWMU-5 design
Submitted information required for permit modification today
7
Zoning Town of Harrisburg
8
Heritage Tree Survey updated for borrow area changes
Town of Harrisburg has requested that Venator submit a special use permit application
Application and fees to be hand delivered on Monday 12/4/23
Neighborhood meeting at Town Hall sometime in December
Presentation before Zoning Board in early January
Decision is made at that meeting
8
Next Steps
9
Awaiting comments on Site Suitability (Submitted March 2023)
Critical Path - Tricolored Bat: tree clearing must take place between Nov 15 – March 31st
Awaiting approval of Sediment and Erosion Control Plan (before tree clearing activities can begin)
Approximately 30 days. Clock started 11/8
Awaiting approval from Zoning Board
Awaiting comments on Solid Waste and NPDES permit applications
9
10
Questions?