Loading...
HomeMy WebLinkAboutSWA000229_Construction Sequence_20231228 EROSION CONTROL SEQUENCE - STAGE 1 1. PRIOR TO BEGINNING ANY CONSTRUCTION.THE CONTRACTOR SHALL OBTAIN AND READ ALL PERMITS/APPROVALS NECESSARY TO COMPLETE THE CONSTRUCTION,INCLUDING BUT NOT LIMITED TO SITE PLAN APPROVAL,LAND DISTURBANCE PERMIT,NPDES PERMIT, CONSTRUCTION DRAWINGS APPROVAL,NCDOT DRIVEWAY PERMIT,NCDOT ENCROACHMENT AGREEMENTS,WATER PERMIT,SEWER PERMIT,ETC. CONTRACTOR TO RETAIN COPIES OF ALL PERMIT DOCUMENTS AND APPROVED PLANS ON THE JOBSITE THROUGHOUT CONSTRUCTION. READ AND COMPLY WITH ALL CONDITIONS OF ALL PERMITS. PERMIT DOCUMENTS SHALL BE CONSIDERED A PART OF THESE CONSTRUCTION DRAWINGS. 2. PRIOR TO BEGINNING ANY CONSTRUCTION,CONTRACTOR TO HOLD ONSITE PRECONSTRUCTION CONFERENCE WITH EROSION CONTROL INSPECTOR,CITY/TOWN/COUNTY INSPECTORS,NCDOT INSPECTOR AND OWNER/DEVELOPER AS REQUIRED. 3. INSTALL TEMPORARY SILT FENCE,AND HAVE IT INSPECTED BY THE NCDEQ INSPECTOR IF REQUIRED. 4. INSTALL TEMPORARY GRAVEL CONSTRUCTION ENTRANCE/EXIT AND TEMPORARY DRIVEWAY PIPE(IF ANY). 5. CLEAR ONLY THE MINIMUM NEEDED TO INSTALL THE STAGE 1 EROSION CONTROL MEASURES. INSTALL ALL EROSION CONTROL MEASURES SHOWN ON THE STAGE 1 EROSION CONTROL PLAN INCLUDING TEMPORARY SILT FENCE.STONE OUTLETS,DIVERSION BERMS/DITCHES, RISER/SKIMMER BASIN,ETC. PROMPTLY INSTALL DITCH LINERS,SPILLWAY LINER,AND SEED BASIN BERM,BASIN SLOPES,AND ALL DITCHES. 6. THE RISER/SKIMMER BASIN BERM SHALL BE ACCURATELY GRADED TO FUNCTION FOR THE PERMANENT WET DETENTION POND.INCLUDING THE CUTOFF TRENCH AND ANTI-SEEP COLLAR. THE RISER AND 0-RING GASKETTED RCP OUTLET PIPE SHALL BE ACCURATELY CONSTRUCTED AS PERMANENT STRUCTURES. REFER TO THE SCM PLAN/DETAILS SHEET FOR ADDITIONAL INFORMATION. THE PROJECT GEOTECHNICAL ENGINEER SHALL OVERSEE THE CONSTRUCTION OF THESE FEATURES AT THE TIME OF INITIAL SKIMMER BASIN CONSTRUCTION. 7. CONTACT EROSION CONTROL INSPECTOR TO REQUEST ONSITE INSPECTION OF STAGE 1 EROSION CONTROL MEASURES AND OBTAIN APPROVAL. 8. IT IS THE CONTRACTOR'S RESPONSIBILITY TO INSPECT ALL EROSION CONTROL MEASURES AFTER EACH RAINFALL EVENT.AND MAKE IMMEDIATE REPAIRS AS NEEDED. ALL SEDIMENT SHALL BE RETAINED ON THE JOBSITE THROUGHOUT CONSTRUCTION. ALL ADJACENT STREETS AND SIDEWALKS SHALL BE KEPT BROOM CLEAN. 9. REFER TO THE NPDES PERMIT,WHICH REQUIRES THE CONTRACTOR TO PERFORM SELF-INSPECTIONS,KEEP AN ONSITE RAIN GAUGE,AND KEEP ONSITE INSPECTION RECORDS. 10. PROCEED TO THE STAGE 2 EROSION CONTROL SEQUENCE. EROSION CONTROL SEQUENCE-STAGE 2 1. DO NOT BEGIN STAGE 2 UNTIL ALL STAGE 1 MEASURES ARE IN PLACE. CONTRACTOR TO INSPECT AND REFURBISH ALL STAGE 1 EROSION CONTROL MEASURES AS NEEDED. 2. IT IS THE CONTRACTOR S RESPONSIBILITY TO INSPECT ALL EROSION CONTROL MEASURES AFTER EACH RAINFALL EVENT.AND MAKE IMMEDIATE REPAIRS AS NEEDED. ALL SEDIMENT SHALL BE RETAINED ON THE JOBSITE THROUGHOUT CONSTRUCTION. ALL ADJACENT STREETS AND SIDEWALKS SHALL BE KEPT BROOM CLEAN. 3. REFER TO THE NPDES PERMIT,WHICH REQUIRES THE CONTRACTOR TO PERFORM SELF-INSPECTIONS.KEEP AN ONSITE RAIN GAUGE.AND KEEP ONSITE INSPECTION RECORDS. 4. PERFORM DEMOLITION,THEN CLEAR AND GRUB THE SITE UP TO THE DISTURBANCE LIMITS SHOWN ON THE PLAN. 5. BEGIN SITE GRADING. PROVIDE TEMPORARY SEEDING IN ACCORDANCE WITH THE STABILIZATION TIME FRAMES SHOWN ON THE NPDES DETAILS. 6. INSTALL STORM PIPE SYSTEM AND TEMPORARY INLET PROTECTION. GRADE ALL PERMANENT SWALES'DITCHES,AND INSTALL DITCH LINERS. INSTALL PROPOSED UTILITIES. 7. ALL GRADING,COMPACTION.POND'BERM CONSTRUCTION, BUILDING PADS AND PROOFROLL SHALL BE OBSERVED BY THE PROJECT GEOTECHNICAL ENGINEER. SUBMIT GEOTECHNICAL CERTIFICATION OF POND BERM CONSTRUCTION TO OWNERCIVIL ENGINEER. 8. AFTER GRADING IS COMPLETE,THEN ESTABLISH PERMANENT GROUND COVER ON ALL DISTURBED AREAS,INCLUDING PAVING, LANDSCAPING,MULCH.AND ESTABLISH A DENSE STAND OF GRASS. ANY BARE SPOTS.EROSIVE RILLS OR EROSIVE SLOPES SHALL BE PERMANENTLY STABILIZED WITH AN EROSION CONTOL BLANKET AND GRASS(SEED, HYDROSEED OR SOD AS NEEDED). THE CONTRACTOR SHALL WATER ALL VEGETATION AS NEEDED FOR HEALTHY PLANTS AND GRASS UNTIL CONSTRUCTION IS COMPLETE AND APPROVED BY MUNICIPALITIES. 9. AFTER ALL AREAS ARE STABILIZED AND A DENSE STAND OF GRASS IS ESTABILSHED.THEN CONTACT EROSION CONTROL INSPECTOR FOR ONSITE INSPECTION. OBTAIN APPROVAL AND REQUEST PERMISSION TO CONVERT THE TEMPORARY SKIMMER BASIN INTO A PERMANENT WET DETENTION POND. 10. FOLLOWING APPROVAL,THEN REMOVE ALL REMAINING TEMPORARY EROSION CONTROL MEASURES(SILT FENCE,INLET PROTECTION. TEMPORARY DIVERSION DITCHES ETC.). REFER TO BASIN.POND CONVERSION SEQUENCE ON SHEET C4.03. 11. HOLD FINAL ONSITE INSPECTION WITH EROSION CONTROL INSPECTOR AND OBTAIN FINAL APPROVAL.