HomeMy WebLinkAboutNC0022406_Appx C_Source Characterization_20150909Drilling Procedures
Drilling Techniques
In general, deep borings were advanced using mud rotary or 6'/4 inch inner diameter (ID) hollow
stem augers (HSAs) to collect environmental/geotechnical samples. Once refusal was
encountered using the mud rotary or smaller ID HSAs, then 8 or 10 inch diameter roller or tri-
cone drilling bits were advanced to one to two feet below refusal (when feasible) to install the 6
inch PVC outer casing (details provided in Well Installation Procedures below). If unable to
create a one to two foot socket in the bedrock (e.g. swelling clays) for casing installation using
mud rotary, then 8'/4 inch inner diameter (ID) HSAs were utilized for outer casing installation.
Once grout was allowed to cure for approximately 24 hours, HQ or PQ coring tools was utilized
to advance the borehole approximately 15 ft below bottom of outer casing (depending on the
depth of the Partially Weathered Rock (PWR) transition zone. Boreholes were then reamed
with a 4 or 5 inch diameter roller or tri-cone bit to allow for 2 inch diameter monitoring well
installation.
Bedrock borings were installed using same drilling techniques as detailed above except the
borehole was advanced approximately 50 ft into component rock. In select locations where
bedrock borings were paired with deep borings, wells were double cased (telescoped) to
eliminate potential mixing of zone being monitored in the deep boring and zone being monitored
in the bedrock boring if the casing could not be advanced to and socketed in bedrock. In some
cases to simplify, a 6 in outer casing was installed as mentioned above to PWR, and then
boring was advanced to bedrock below outer casing using a 5 7/8 roller or tri-cone bit to set a 4
or 5 inch outer casing. Once grout was allowed to cure for approximately 24 hrs the boring was
advanced 50 ft below the bottom of the 5 in outer casing. Boring was then reamed using a 4
inch diameter roller or tri-cone bit as described above and monitoring well installed.
Shallow borings were advance using 4 % inch or 6'/4 inch ID HSAs to a termination depth
based on observations made during advancement of the deep boring and monitoring well was
installed. Monitoring well installation is described in greater detail in the Well Installation
Procedures.
Shallow Monitoring Well Installation Procedures
Shallow monitoring wells were installed to monitor the regolith aquifer zone or ash and are
identified with an "S" (shallow) or "SL" (shallow lower) qualifier in the well nomenclature. If the
regolith zone was observed to be relatively thick or more than one water bearing zone was
encountered during drilling, a second shallow monitoring well was installed to monitor the lower
water bearing zone and was identified as the SL well. Shallow monitoring wells were installed
at the Site using either hollow stem auger (HSA) or mud rotary (roller or tri-cone bit) drilling
techniques. Shallow monitoring wells were installed to monitor regolith aquifer or if installed in a
dam, wells were installed to monitor the phreatic surface within the ash basin(s). Each shallow
well was constructed with ten feet (ft) to fifteen ft of two inch diameter schedule 40 PVC 0.012-
inch slotted pre -packed screen and schedule 40 PVC riser to grade or above grade if needed.
A #2 filter pack sand was placed one to two feet above the pre -packed screen, bentonite was
placed one to two feet above the sand pack, and borehole was completed to grade with grout
via positive displacement method (tremmie grouting). If the boring was in an access path or
roadway the well was completed at the surface with a flush mount well cover and locking well
cap. If the boring was located off access paths and roadways the well was completed at the
surface with a four inch above grade protective casing with lock and bollards to protect the
monitoring well.
Deep Monitoring Well Installation Procedures
Deep monitoring wells were installed to monitor the transition zone (if present) and are identified
with a "D" (deep) qualifier in the well nomenclature. Deep monitoring wells were installed using
either HSA or mud rotary drilling techniques to approximately one to two feet below refusal
where a six inch diameter schedule 40 PVC outer casing was installed to seal off the
overburden. Grout utilized for outer casing installation was allowed to cure for approximately 24
hours then boring was advanced approximately fifteen feet below the bottom of the outer casing
using HQ or PQ coring tools. Rock cores were logged in accordance with the Field Guide for
Rock Core Logging and Fracture Analysis by Midwest GeoSciences Group and cores were
photographed. Each deep well was constructed with five ft of 2 inch diameter schedule 40 PVC
0.012-inch slotted pre -packed screen and schedule 40 PVC riser to grade or above grade if
needed. A #2 filter pack sand was placed one to two feet above the pre -packed screen,
bentonite was placed one to two feet above the sand pack, and borehole was completed to
grade with grout via tremmie grouting method. If the boring was in an access path or roadway
the well was completed at the surface with a flush mount well cover and locking well cap. If the
boring was located off access paths and roadways the well was completed at the surface with a
four inch above grade protective casing with lock and bollards to protect the monitoring well.
Bedrock Monitoring Well Installation Procedures
Bedrock monitoring wells were installed to monitor fractured bedrock and are identified with a
"BR" qualifier in the well nomenclature. These wells are screened across water bearing
fractures within competent bedrock. Bedrock monitoring wells were installed using either HSA
or mud rotary drilling techniques to approximately one to two feet below component bedrock
where a six inch diameter schedule 40 PVC outer casing was installed to seal off the
overburden. Grout utilized for outer casing installation was allowed to cure for 24 hours then
boring was advanced approximately fifty feet below the bottom of the outer casing using HQ or
PQ coring tools. Rock cores were logged in accordance with the Field Guide for Rock Core
Logging and Fracture Analysis by Midwest GeoSciences Group and cores were photographed.
Packer testing was performed on select fractures observed in the rock cores. Screen interval
was selected based on observations made during coring activities and multiple packer test
results. Each bedrock well was constructed with five ft of 2 inch diameter schedule 40 PVC
0.012-inch slotted pre -packed screen and schedule 40 PVC riser to grade or above grade if
needed. A #2 filter pack sand was placed one to two feet above the pre -packed screen,
bentonite was placed one to two feet above the sand pack, and borehole was completed to
grade with grout via tremmie grouting method. If the boring was in an access path or roadway
the well was completed at the surface with a flush mount well cover and locking well cap. If the
boring was located off access paths and roadways the well was completed at the surface with a
four inch above grade protective casing with lock and bollards to protect the monitoring well.
Soil Sampling Procedures
For nested monitoring wells, the deep boring was utilized for characterization of subsurface
material and collection of environmental and/or geotechnical samples for lab analyses. Standard
Penetration Testing (SPT) was conducted utilizing split -spoon sampling techniques at five foot
increments with an 18-inch split -spoon sampler. Any environmental and/or geotechnical
samples not able to be collected in the deep well were collected in either the shallow or bedrock
well that was paired with the deep well. Geotechnical samples consisted of undisturbed (Shelby
tube) samples (natural moisture content, grain size with hydrometer, hydraulic conductivity, and
specific gravity), sorption samples (Kd/HFO), mineralogy, and index property samples (natural
moisture content and grain size with hydrometer). Environmental sampling for soils consisted of
Total Inorganic compounds (TI) and Total Organic Carbon (TOC) and environmental sampling
for ash consisted of TI, TOC, and Synthetic Precipitation Leaching Potential (SPLP). In
situations where there was a single well to installed, as many samples as possible were
collected in that boring, but if it was not feasible to collect the necessary samples a second
boring (geotechnical boring) was advanced within five ft of the original boring to obtain the
remaining samples.
Sampling equipment was decontaminated between each sample interval in the same borehole
as well as between each boring. Sampling equipment was first rinsed with tap water, washed
with a water-liquinox mix and then rinsed a final time with deionized water. All downhole
equipment utilized during boring/well installation (i.e.; augers, drill rods, split spoons, etc.) were
decontaminated between each borehole to eliminate potential cross contamination between
boreholes. A decontamination pad was constructed for field cleaning of downhole tooling.
Downhole tooling was decontaminated using a high temperature, high pressure steam cleaner
followed by rinsing with potable water.
Hydrogeologic Evaluation Testing
To better characterize hydrogeologic conditions, falling and constant head tests, packer tests,
and slug tests were performed. Data collected from these tests will be used in the groundwater
modeling.
At select deep/bedrock well locations, horizontal permeability tests (falling or constant head
tests) were performed just below refusal in the upper bedrock (transition zone if present). At
select shallow/deep/bedrock locations, vertical and horizontal permeability tests were conducted
above refusal in varying hydrostratigraphic units.
Packer testing was conducted in bedrock borings at select fractures based on observations
made during drilling and the rock cores. In general, a double packer system was utilized with
generally five to teen feet of separation between packers and a single packer system was
utilized to perform a shut in permeability test at the bottom of the borehole.
Slug tests were completed in each monitoring well installed to assess hydraulic conductivity.
Slug tests were conducted in accordance with requirements of the NCDENR Memorandum
titled, "Performance and Analysis of Aquifer Slug Tests and Pumping Tests Policy", dated May
31, 2007.
Drilling and Installation Variances
Variances from Groundwater Assessment Work Plan
Source Characterization
As Proposed
ompleted
1
Well AB-7SL
Eliminated
Thickness of ash not sufficient to allow installation of
second well screened in ash.
2
Wells AB-4S/SL/D/BR
Relocated
Proposed location was un-compacted ash that could
not support drilling equipment.
3
Boring AB-2SA, AKA AB-2GTB
Added
Added to collect environmental (TI & TOC) and UD
_
samples. Abandoned.
4
Boring AB-3GTB
Added
Added to collect geotec samples. Abandoned.
Boring AB-5GTB
Added
Added to collect environmental samples (TI, TOC,
5
V
I
SPLP), and flush bottom and open hole permeability
I
tests. Abandoned.
Boring AB-6GTB
Added
Added to collect environmental samples (TI, TOC,
6
SPLP, UD) and flush bottom and open hole
permeability tests. Abandoned.
7
Boring AB-9GTB
Added
Added to collect environmental samples (TI, TOC)
Borings AB-1 S/D, AB-2S/D, and AB-
Wells moved to upstream crest of
and geotec samples. Abandoned.
Change required to facilitate drill rig access.
8
3S/D to be installed on downstream
ash basin dam.
crest of ash basin dam.