Duke Energy Progress (DEP)
Barker Laydown Yard
Site Preparation
Scope of Work
11/06/2023
Mow the site and install gravel per Approved Erosion Control Plan to include:
1. Duke Energy Progress (DEP)will obtain and pay for the following permits:
1. Cumberland County Special Use Permit
2. Cumberland County Site Plan
3. NCDEQ Erosion and Sediment Control
4. NCDEQ low-density Stormwater Permit
5. NCDOT Driveway Permit
2. No work may start on the site until all the required permits have been obtained.
3. Furnish and install the "Temporary Construction Entrance."
4. Install the silt fence. Clear/mow only enough area to install the silt fence.
5. Clear only the area at and around all "Sediment and Erosion Control Devices" (Silt Fence
Outlets, etc.).
6. Install the "Sediment and Erosion Control Devices".
7. Install Temporary Seeding.
8. Mow the site.
9. Install and compact ABC stone on top of the existing grade and ensure positive drainage
across the site.
10. Install Permanent Seeding.
11. "Sediment and Erosion Control Devices" shall be maintained through completion of the
project. The contractor shall make any repairs as necessary to the Sediment and Erosion
Control Devices"throughout the duration of his contract for the project. The contractor
shall keep all sediment on site.
12. The contractor shall keep Braxton Road free of soil, stone, and debris from the
construction site. It shall be the responsibility of the contractor to remove any soil, stone,
and debris deposited onto the roadway by sweeping, washing or by other methods.
Page 1 of 2
No. E22007101
Page 2 of 2
13. The contractor shall inspect all "Sediment and Erosion Control Devices" at least once
weekly. The contractor shall also inspect all the "Sediment and Erosion Control Devices"
after each rainfall of 1 inch or more within 24 hours after the rain has stopped. A rain
gauge shall be installed at the project site to facilitate rainfall monitoring. In North
Carolina, at each inspection of the "Sediment and Erosion Control Devices", the contractor
is required to complete the "Stormwater Inspections for General Permit NCG010000-Land
Disturbing Activities form and post it in the permit box located on site.
14. The contractor, in North Carolina, shall conduct self inspections for erosion and
sedimentation control and complete the self-inspection report for land disturbing activity
form as required by NCGS 113A-54.1 after each phase of the approved erosion and
sedimentation control plan is implemented. This form shall be maintained on-site to be
available at all times.