Hood, Donna
From:Beam, Patricia
Sent:Tuesday, August 11, 2015 8:47 AM
To:Hood, Donna
Subject:FW: Iredell Rest Area, K-4908
Attachments:SKMBT_C28015081010050.pdf
FYI… The change in stream management by the contractor for this project falls within the temporary impact areas
already permitted.
Trish
From: Joe Coleman \[mailto:jcoleman@mtcreekinc.com\]
Sent: Monday, August 10, 2015 11:24 AM
To: Beam, Patricia
Cc: Daniel Lynch; Taylor, Mark
Subject: RE: Iredell Rest Area
Trish,
Please see attached revision of the water handling plan. STA 41+56 L1 is Site 1 and 15+59 L3 is Sites 2 and 3. We don’t
see the need to extend the limits of temporary stream impacts at either site.
Thanks,
Joseph E. Coleman |
Vice President
jcoleman@mtcreekinc.com | 828.695.7700
Construction Operations:
205 E Central Ave. | Catawba, NC 28609-9520
Office: (828) 241-2047 |
Fax: (828) 241-3642
www.mtcreekinc.com
From: Beam, Patricia
Sent: Thursday, August 06, 2015 8:41 AM
To: Taylor, Mark
Subject: RE: Iredell Rest Area
Mark,
At permit site 1, we are permitted for 47 feet of temporary impacts and at site 2, we are allowed 53 feet of temporary
impacts. The stations in the impact summary sheet in the permit reference 60+95 to 62+16-LNB-(Lt) for site 1 and
66+10 to 66+29-LSB- (Lt) for site 2, so I am not sure which sites are being referenced in the email below….
1
Please provide a plan sheet or sketch, so I can figure out what sites are being referenced… additionally, do their
proposed changed in stream management stay with those permitted temporary limits?
Thanks
Trish
From: Taylor, Mark
Sent: Tuesday, August 04, 2015 11:13 AM
To: Beam, Patricia
Cc: Ghitea, Theo
Subject: FW: Iredell Rest Area
Trish,
Please review and advise if this falls within the permits. Thanks for your help
J. Mark Taylor, P.E.
Resident Engineer
Division 12, Statesville
(704) 876.3543
From: Daniel Lynch \[mailto:dlynch@jrlynchandsons.com\]
Sent: Tuesday, August 04, 2015 7:42 AM
To: Taylor, Mark; Ghitea, Theo; Levan, Doy B
Cc: 'Mark Lynch'; 'Joe Coleman'; 'Don Phillips'
Subject: FW: Iredell Rest Area
Mark,
Can you let me know if the below revision to the Culvert sequence is acceptable? Mountain Creek will be mobilizing next
week to begin.
Thanks,
Daniel Lynch, PE
Jimmy R. Lynch & Sons, Inc.
307 S. Academy Street
Pilot Mountain, NC 27041
Office: 336-368-4047
Fax: 336-368-4613
Mobile: 336-362-9964
From: Joe Coleman \[mailto:jcoleman@mtcreekinc.com\]
Sent: Monday, August 03, 2015 5:38 PM
To: jmtaylor@ncdot.gov; mplyler@ncdot.gov
2
Cc: Daniel Lynch <dlynch@jrlynchandsons.com>
Subject: Iredell Rest Area
Gentlemen,
We will be building the culverts for JR Lynch and just wanted to clarify some items on the water handling plans and
make sure the DOT didn’t have any issues with them.
On 41+56.1 L1 we would like to locate the diversion pipe outside of the culvert footprint so we can construct both
barrels at one time. We will leave a short section of wall out for the diversion to penetrate, and pour it and the
accompanying roof after we switch water through the opposite barrel of the culvert extension.
On 15+59 L3, we would like to plan on pumping around to construct the floor and then install the diversion pipe on the
new floor and build the walls and the roof.
Let me know if you see any issues.
Thanks,
Joseph E. Coleman |
Vice President
jcoleman@mtcreekinc.com | 828.695.7700
Construction Operations:
205 E Central Ave. | Catawba, NC 28609-9520
Office: (828) 241-2047 |
Fax: (828) 241-3642
www.mtcreekinc.com
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
3
N.OIER REfEIENCE NO. SNFft NO.
C� f K-4908 EC-09/CONSTD9
/ MV SHfR NO.
PO.��W/.Y ORIGN HtDGU11C5
ENGMEFA ENGINEEII
CULVERT CONSTRUCTION SEQUENCE STA. 41 + 56.10 -Ll-
PHASE I PHASE II
7. CONSTRUCT STILLING BASIN (240 CYf. 4. REMOVE IMPERVIOUS DIKES A AND B, AND 24 INCH TEMPORARY PIPE, ALLOWING NORMAL FLOW THROUGH CULVERT.
2. CONSTRUCT IMPERVIOUS DIKES A AND B, AND INSTALL 24 INCH TEMPORARY PIPE, DIVERTING FLOW. 5. REMOVE STILLING BASIN.
3. CONSTRUCT PROPOSED CULVERT EXTENSION, FLOODPLAIN BENCH, AND INLEf CHANNEL IMPROVEMENTS. 6. COMPLEfE ROADWAY.
NPD 8y SAS 2001 NAD By SRS 2p07
STORAGE ]4 INCH
r140 CY� T�POMRY
PIPE
T
�\
�
�\
/ ��
\♦ /
�5 � T� '�
/ �c,/ �,/ �i �c�/
\ UIPERVIOUS ���
�� DIKE B �
\� ��
�\ \
O ��
� ��
�� � ��
� �� �`
�� � ��
�\F J
��
IMPERVIDUS `��\ `��\ �
OIKE A S
\
�
� � � ♦
% ��/�/ / j�%// ��`
/%//// /%/�// "_�
/� / /� / Fj"r�
/// j/
Fj f�
MOJER 0.FFE0.ENCE NO. SHEFf NO.
�yj K-4908 ec-ioicoxsrne
/ I � � ! ww snen vo.
0.0AOWAY �ESIGN NYpMUI1C5
CULVERT CONSTRUCTION SEQUENCE STA. 15 + 59.42 -L3- E�G��fEp E����A
PHASE I PHASE II
1. UiILIZE SKIMMER BASIN 8.1 AS SiILLING BASIN. 7�7���yy,�� 4. REMOVE IMPERVIOUS DIKES A AND B,AND 24 INCH TEMPORARY PIPE,ALLOWING NORMAL FLOW THROUGH CULVERT.
2. CONSTRUCT IMPERVIOUS DIKES A AND B, AND "'°T' ti�� � '°E, DIVERTING fLOW. 5. RETAIN SKIMMER BASIN 8.1 FOR ROADWAY CONSTRUCTION.
3. CONSTRUCT PROPOSED CULVERT EMENSION AND OUTLET CHANNEL IMPROVEMENTS. 6. COMPLEfE ROADWAY.
hov-
�y/d" �4h1-�� 2�° I � W ffN �
�j3 lm��� �'�- af ���v�' ���w-���-
N�3� SRS 2p07 NAp By SRS 2001
����� ` /����\
/ � '---- F3 ------'�--�—�� �1_---- \
� � /
/�
i� INCH
TEMPORA0.V / / /
PIPE / � Q UIPERVIOUS � / O
DIKE B
\ � �
/ v' `������ � ____� V) _
\ F3 �',,, ,— F--- --F3--
IMPFRVIOUS
DIKE A
��
/,
/
50 x 24 x 3 50 x 24 x 3
7.5 inch Skimmer 1.5 inch Skimmer
wiih 1.0 inch wi}h 1.0 inch
Orifice Diomefer Orifice Diometer
7 fr. weir 7 fr. weir
ID 8.1 ID 8.1