Good Afternoon,
We received additional information for your application for a new Fast-Track ATC post-construction stormwater permit
on 5/5/2023. At this time, the submission is not administratively complete and cannot be accepted for review in its
current condition. Please provide the following submittal items by close of business on 5/18/2023 so that we may accept
the project and begin the review process, otherwise, the project will be returned as administratively incomplete.
2x hard copies of the Application Form (or pages) with the following corrections made (A complete application is
required per 15A NCAC 02H .1043(3)(a)):
Part D3 – The Applicant listed in Section D1 of the Application is different than the Current Property
Owners (Stancil Builders, Inc. is a different entity than the Stancil estate, et al.). Please indicate that the
Applicant, Stancil Builders, Inc., is the developer (as they are developing the property on behalf of the
Current Property Owners.
Part D4 – Please provide the names and contact information for each property owner (you may either
attach additional pages as needed, modify the form, or squeeze the information onto the provided
lines).
NOTE: This is an administra?ve completeness review, not a detailed engineering review, there may be other issues that
may be brought up during the engineering review.
If these items are received within the s?pulated ?meframe, we can accept the project and begin the review process.
Once accepted, reviews under the Fast-Track permi?ng process can take up to 30 calendar days per statute (one of our
two reviewer posi?ons is currently vacant).
Hard copies should be mailed to the following address:
For FedEx/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640M
Raleigh, NC 27604
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
If you have any ques?ons, please contact Jim Farkas at jim.farkas@ncdenr.gov or 919-707-3646.
Thank you,
Jim Farkas
State Stormwater Engineer
1
North Carolina Department of Environmental Quality
Office: (919) 707-3646
Jim.farkas@ncdenr.gov
From: Farkas, Jim J
Sent: Tuesday, April 18, 2023 11:57 AM
To: timstrickland@stancilbuilders.com; freddiestancil@stancilbuilders.com; keith.roberts@timmons.com; Ryan
Wadsworth <Ryan.Wadsworth@timmons.com>
Cc: Joyner, Melissa <melissa.joyner@ncdenr.gov>
Subject: Stancil Farms in Angier, Harnett County
Good Morning,
We received your application for a new Fast-Track ATC post-construction stormwater permit on 4/13/2023. At this time,
the submission is not administratively complete and cannot be accepted for review in its current condition. Please
provide the following submittal items within 30 calendar days (by close of business on 5/18/2023) so that we may
accept the project and begin the review process, otherwise, the project will be returned as administratively incomplete.
2x hard copies of the Application Form (or pages) with the following corrections made (A complete application is
required per 15A NCAC 02H .1043(3)(a)):
Part F – Please complete this portion of the application, initialing the provided submittal items.
Per the provided property deeds, the property to be permitted is owned by Mr. & Mrs. Fred Stancil and
Mr. & Mrs. Alex Stancil. Please revie the application to either list these individuals as the permittees or
include them as property owners. It is noted that the Stancil’s are associated with the applicant,
however they are distinct entities and this needs to be reflected on the form.
1x original signed and notarized/sealed hard copy of Parts G & H of the Application. 2x original signed hard
copies of this form are required and only one was provided (the other copy appears to be a photocopy).
NOTE: This is an administra?ve completeness review, not a detailed engineering review, there may be other issues that
may be brought up during the engineering review. While not required for administra?ve completeness, the following
items were noted during review:
The cul-de-sac of Road H may be located within the vegetated setback for the nearby surface water (it is unclear
at this scale if it is within or outside of the setback since it is very close to the edge of the setback). If it is within
the vegetated setback, please move it outside of the vegetated setback.
If these items are received within the s?pulated ?meframe, we can accept the project and begin the review process.
Once accepted, reviews under the Fast-Track permi?ng process can take up to 30 calendar days per statute (one of our
two reviewer posi?ons is currently vacant).
Hard copies should be mailed to the following address:
For FedEx/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640M
Raleigh, NC 27604
2
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
If you have any ques?ons, please contact Jim Farkas at jim.farkas@ncdenr.gov or 919-707-3646.
Thank you,
Jim Farkas
State Stormwater Engineer
North Carolina Department of Environmental Quality