HomeMy WebLinkAbout20140545 Ver 1_DWR response_20150807
Ward, Garcy
From:Ward, Garcy
Sent:Friday, August 07, 2015 4:27 PM
To:Willis, Thomas C; tracey.l.wheeler@usace.army.mil; Daisey, Greg; Wilson, Travis W.;
Staples, Shane
Subject:RE: extraction of existing bridge piles on Bridge # 10, Dare County
Clay,
You have DWR’s approval to extract the piles during the in-water work moratorium as described in your e-mail given no
objections from the resource agencies. If the work cannot be accomplished as described below, please contact us as
additional approval may be required. Thanks.
Garcy Ward
Environmental Senior Specialist
Division of Water Resources
Washington Regional Office
Ph: 252-946-6481
E-mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to
third parties.
From: Willis, Thomas C
Sent: Monday, August 03, 2015 3:01 PM
To: tracey.l.wheeler@usace.army.mil; Ward, Garcy; Daisey, Greg; Wilson, Travis W.; Staples, Shane
Subject: extraction of existing bridge piles on Bridge # 10, Dare County
Agencies,
Corman construction has asked for permission to extract 12 timber piles and 2 steel H-piles associated with the south
bound lane. This will be done utilizing a vibratory hammer and each pile will take about 10 minutes. Do you all have any
objection to his proposal? They would like to conduct this work on Thursday or Friday of this week. I have attached a
map for a reminder of bridge location # 10, Pain Creek Canal, in Dare County.
Thanks,
Clay Willis
NCDOT – Division One
Environmental Supervisor
Office – 252-482-1876
Cell – 252-312-3692
tcwillis@ncdot.gov