HomeMy WebLinkAboutWQ0023678_Whites Mill Sewage Pummping Station Upgrades Application_20230724RECEIVED 4 "023 NCDEQ/DWR/NPDES REFERENCE NO. WHITES MILL SEWAGE PUMPING STATION UPGRADES Pump Station and Siphon Permit Application JULY 18, 2023 p Dewberry SUBMITTED BY Dewberry Engineers Inc. 9300 Harris Corners Pkwy Charlotte, NC 28269 704-625-5077 Ste. 220 ORIGINAL \A C A 9 '*",,,, O `,_' QPOFEssioti9��2,' SEAL 041334 ''y�N G. BUG�P -7/ 1$ /�3 TABLE OF CONTENTS COVER LETTER FORM SSEA 04-16 - SEWER SYSTEM EXTENSION APPLICATION PROJECT DESCRIPTION FIGURE 1 - WHITES MILL SEWAGE PUMPING STATION AND GRAVITY SEWER IMPROVMENTS FIGURE 2 - USGS MAP APPENDIX I - PRELIMINARY ENGINEERING REPORT APPENDIX II - WHITES MILL SEWAGE PUMPING STATION UPGRADES PUMP STATION CALCULATIONS APPENDIX III -WHITES MILL SEWAGE PUMPING STATION UPGRADES SIPHON CALCULATIONS APPENDIX IV - FLOOD INSURANCE RATE MAP �•_�� Dewberry July 18, 2023 NCDEQ/DWR Water Quality Permitting PERCS Unit 1617 Mail Service Center Raleigh, NC 27699-1636 Dewberry Engineers Inc. 704.509.9918 9300 Harris Corners Parkway, Suite 220 704.509.9937 fax Charlotte, NC 28269-3797 1 www.dewberry.com RE: Whites Mill Sewage Pumping Station Upgrades Dear Mr. Sir of Madam, Enclosed are one original and one copy of FORM SSEA 04-16, "Sewer Extension Application" for your review and approval. Also enclosed are: • Two sets of plans • Two copies of the project narrative • Two copies of the calculation report • Two copies of the PER • Two copies of the Specifications • A check for $480 (application fee) Please contact me if you have any questions. Sincerely, Stephen G. Buchanan, PE Senior Project Manager CC: Nawfal Shujaa — City of High Point Derrick Boone — City of High Point State of North Carolina Department of Environmental Quality DW-R Division of Water Resources 15A NCAC 02T .0300 — SEWER SYSTEM EXTENSION APPLICATION Division of Water Resources INSTRUCTIONS FOR FORM: SSEA 04-16 & SUPPORTING DOCUMENTATION Plans, specifications and supporting documents shall be prepared in accordance with, 15A NCAC 02T .0100, 15A NCAC 02T .0300, Division Policies and good engineering practices. Failure to submit all required items will necessitate additional processing and review time, and may result in return of the application. For more information, visit the Water Quality Permitting Section's collection systems website General — When submitting an application, please use the following instructions as a checklist in order to ensure all required items are submitted. Adherence to these instructions and checking the provided boxes will help produce a quicker review time and reduce the amount of requested additional information. A. One Original and One Copy of Application and Supporting Documents ® Required unless otherwise noted B. Cover Letter (Required for All Application Packages): ® List all items included in the application package, as well as a brief description of the requested permitting action. ➢ If necessary for clarity, include attachments to the application form. C. Application Fee (All New and Major Modification Application Packages): ® Submit a check or money order in the amount of $480.00 dated within 90 days of application submittal. ➢ Payable to North Carolina Department of Environmental Quality (NCDEQ). D. Sewer System Extension (Form: SSEA 04-16) Application (Required for All Application Packages): ® Submit the completed and appropriately executed application. ➢ If necessary for clarity or due to space restrictions, attachments to the application may be made. ❑ If the Applicant Type in Item I.2 is a corporation or company, provide documentation it is registered for business with the North Carolina Secre!M of State. ❑ If the Applicant Type in Item I.2 is a partnership or d/b/a, enclose a copy of the certificate filed with the Register of Deeds in the county of business. ® The project name in Item II.1 shall be consistent with the project name on the plans, specifications, flow acceptance letters, agreements, etc. ® The Professional Engineer's Certification on Page 6 of the application shall be signed, sealed and dated by a North Carolina licensed Professional Engineer. ® The Applicant's Certification on Page 6 of the application shall be signed in accordance with 15A NCAC 02T .0106(b). Per 15A NCAC 02T .0106(c), an alternate person may be designated as the signing official if a delegation letter is provided from a person who meets the criteria in 15A NCAC 02T .0106(b). E. Flow Tracking/Acceptance Form (Form: FTSE 04-16) (If Applicable): ® Submit the completed and appropriately executed Flow Tracking/Acceptance for Sewer Extension Permit Form from the owners of the downstream sewers and treatment facility. ➢ The flow acceptance indicated in form FTSE 04-16 must not expire prior to permit issuance and must be dated less than one year prior to the application date. ➢ Submittal of this application and form FTSE 04-16 indicates that owner has adequate capacity and will not violate G. 143-215.67(a). ➢ Intergovernmental agreements or other contracts will not be accepted in lieu of a project -specific FTSE 04-16. INSTRUCTIONS FOR FORM: SSEA 04-16 & SUPPORTING DOCUMENTATION Page 1 of 4 F. Engineering Plans (Required for All Application Packages): El Per 15A NCAC 02T .0305(b)(1), submit two sets of detailed plan sets that have been signed, sealed and dated by a North Carolina licensed Professional Engineer, and shall include at a minimum: ➢ Table of contents with each sheet numbered. ➢ A general location map with at least two geographic references and a vicinity map. ➢ Plan and profile views of the sewer extension as well as the proximity of the sewer extension to other utilities and natural features ➢ Detail drawings of all items pertinent to the sewer extension and pump stations. ➢ The location of all wells (including usage and construction details if available), streams (ephemeral, intermittent, and perennial), springs, lakes, ponds, and other surface drainage features within 100 feet of the project. ➢ Minimum separations required per 15A NCAC 02T.0305(f), and where separations cannot be maintained, alternative criteria per 15A NCAC 02T.0305(g). ➢ Minimum cover for sewer extensions required per 15A NCAC 02T.0305(f) must also be shown clearly on the plans. ® Plans shall represent a completed design and not be labeled with preliminary phrases (e.g., FOR REVIEW ONLY, NOT FOR CONSTRUCTION, etc.) that indicate they are anything other than final plans. However, the plans may be labeled with the phrase: FINAL DESIGN - NOT RELEASED FOR CONSTRUCTION. G. Specifications (Required for All Application Packages): ® Per 15A NCAC 02T .0305(b)(3), submit specifications that have been signed, sealed and dated by a North Carolina licensed Professional Engineer, and shall include at a minimum: ➢ Table of contents with each section/page numbered. ➢ Detailed specifications for all items pertinent to the sewer extension and pump stations ➢ Site Work (i.e., earthwork, clearing, grubbing, excavation, trenching, backfilling, compacting, fencing, seeding, etc.) ➢ Materials (i.e., force main, gravity, concrete, method of construction, etc.) ➢ Electrical (i.e., control panels, transfer switches, automatically activated standby power source, etc.) ➢ Means for ensuring quality and integrity of the finished product in accordance with the Minimum Design Criteria, including leakage and pressure testing for the sewer extension. ® Specifications shall represent a completed design and not be labeled with preliminary phrases (e.g., FOR REVIEW ONLY, NOT FOR CONSTRUCTION, etc.) that indicate they are anything other than final specifications. However, the specifications may be labeled with the phrase: FINAL DESIGN - NOT RELEASED FOR CONSTRUCTION. ® Specifications for standard equipment may only be omitted for municipalities with approved standard specifications, but the use of the standard specifications must be noted on each sheet of the plans. H. Engineering Calculations (All Application Packages): ® Per 15A NCAC 02T .0305(b)(2) and 15A NCAC 02T .0305(i)(1), submit engineering calculations that have been signed, sealed and dated by a North Carolina licensed Professional En ig neer, and shall include at a minimum: ➢ Friction/Total Dynamic Head calculations and system curve analysis (with one pump running, two pumps running, etc.) ➢ Pump selection information including pump curves, manufacturer's information, and recommended installation guidelines. ➢ Pump station cycle times and pump run times. ➢ Minimum velocities in the sewer extension in accordance with the Minimum Design Criteria ➢ Flotation calculations for all units constructed partially or entirely below grade (i.e. pump stations) Note that upon completion of the review process and prior to permit issuance, a request for the final plans and specifications will be requested on digital media (CD, DVD, Jump Drive, etc.) for our records. You will be notified when this information is requested, as the review may necessitate changes. INSTRUCTIONS FOR FORM: SSEA 04-16 & SUPPORTING DOCUMENTATION Page 2 of 4 I. Downstream Sewer Evaluations (All Application Packages) ® Per 15A NCAC 02T .0305(b)(2) and 15A NCAC 02T .0304(h)(1), submit engineering calculations that have been signed, sealed and dated by a North Carolina licensed Professional En ig neer, for receiving collection systems: ® For connection to a gravity sewer, submit: An evaluation of the gravity sewer based on peak flow from the proposed project and peak flows already tributary to the existing gravity sewer. Provide calculations and detail how existing peak flows were determined. ® For connection to a pump station, submit: An evaluation of the existing pump station to pump peak flow from the proposed project and peak flows already tributary to the existing pump station. Provide calculations and detail how existing peak flows were determined. ® For connection to a force main/low pressures sewer, submit: An evaluation of the existing system based on peak flows from the proposed project and peak flows already tributary to the existing system. In addition, evaluate the ability of each pump station tributary to the existing system to pump against additional head created by greater flows through the system. Evaluation may include alternative designs such as telemetry to coordinate pumping between pump stations (provided sufficient storage is available). Also include an evaluation of the discharge point of the existing force main/pressure sewer. J. Site Maps (All Application Packages): ® Submit an 8.5-inch x 11-inch color copy of a USGS Topographic Map of sufficient scale to identify the entire project area and closest surface waters. ➢ Location of the project (gravity sewer, pump stations & force main) ➢ Downstream connection points and permit number (if known) for the receiving sewer El Include a street level map showing general project area K Existing Permit (All Modification Packages): ❑ Submit the most recently issued existing permit. ❑ Provide a list of any items within the permit the Applicant would like the Division to address during the permit modification (i.e., permit description, flow allocation, treatment facility, etc.). L. Power Reliability Plan (If Applicable) ❑ Per 15A NCAC 02T .0305(h)(1), submit documentation of power reliability for pumping stations. ➢ This alternative is only available for average daily flows less than 15,000 gallons per day ➢ It shall be demonstrated to the Division that the portable source is owned or contracted by the applicant and is compatible with the station. The Division will accept a letter signed by the applicant (see 15A NCAC 02T .0106(b)) or proposed contractor, stating that "the portable power generation unit or portable, independently -powered pumping units, associated appurtenances and personnel are available for distribution and operation of this pump station." ➢ If the portable power source or pump is dedicated to multiple pump stations, an evaluation of all the pump stations' storage capacities and the rotation schedule of the portable power source or pump, including travel timeframes, shall be provided in the case of a multiple station power outage. (Required at time of certification) M. Final Environmental Document (If Applicable): ❑ Per 15A NCAC 02T .0105(c)(4), submit one copy of the environmental assessment and three copies of the final environmental document (i.e., Finding of No Significant Impact or Record of Decision). ❑ Include information on any mitigating factors from the Environmental Assessment that impact the design and/or construction of the subject sewer. N. Certificate of Public Convenience and Necessity (All Application Packages for Privately -Owned Public Utilities): ❑ Per 15A NCAC 02T .0115(a)(1) provide the Certificate of Public Convenience and Necessity from the North Carolina Utilities Commission demonstrating the Applicant is authorized to hold the utility franchise for the area to be served by the sewer extension, or ❑ Provide a letter from the North Carolina Utilities Commission's Water and Sewer Division Public Staff stating an application for a franchise has been received and that the service area is contiguous to an existing franchised area or that franchise approval is expected. INSTRUCTIONS FOR FORM: SSEA 04-16 & SUPPORTING DOCUMENTATION Page 3 of 4 O. Operational Agreements (Applications from HOA/POA and Developers for lots to be sold): ❑ Home/Property Owners' Associations ❑ Per 15A NCAC 02T .0115(c), submit the properly executed Operational Agreement (FORM: HOA 04-16). ❑ Per 15A NCAC 02T .0115(c), submit a copy of the Articles of Incorporation, Declarations and By-laws. ❑ Developers of lots to be sold ❑ Per 15A NCAC 02T .0115(b), submit the properly executed Operational Agreement (FORM: DEV 04-16). THE COMPLETED APPLICATION AND SUPPORTING DOCUMENTATION SHALL BE SUBMITTED TO: NCDEQ/DWR WATER QUALITY PERMITTING PERCS UNIT By U.S. Postal Service: 1617 MAIL SERVICE CENTER RALEIGH, NORTH CAROLINA 27699-1636 TELEPHONE NUMBER: (919) 807-6312 By Courier/Special Delivery: 512 N. SALISBURY ST. SUITE 925 RALEIGH. NORTH CAROLINA 27604 INSTRUCTIONS FOR FORM: SSEA 04-16 & SUPPORTING DOCUMENTATION Page 4 of 4 DWR State of North Carolina Department of Environmental Quality Division of Water Resources Division of Water Resources 15A NCAC 02T .0300 — SEWER SYSTEM EXTENSION APPLICATION SSEA 04-16 & SUPPORTING DOCUMENTATION Application Number: I. APPLICANT INFORMATION: (to be completed by DWR) 1. Applicant's name: City of High Point 2. Applicant type: ❑ Individual ❑ Corporation ❑ General Partnership ❑ Federal ❑ State ® Municipal 3. Signature authority's name: Derrick Boone per 15A NCAC 02T .0106(b) Title: Public Services Assistant Director 4. Applicant's mailing address: 211 South Hamilton Street, Suite 206 City: High Point State: NC Zip: 27261- 5. Applicant's contact information: Phone number: (336) 883-3279 Email Address: derrick.boonenhi¢hpointnc. og_v II. PROJECT INFORMATION: ❑ Privately -Owned Public Utility ❑ County 1. Project name: Whites Mill Sewage Pumping Station Upgrade 2. Application/Project status: ❑ Proposed (New Permit) ® Existing Permit/Project 3. If a modification, provide the existing permit number: WQ0023678 and issued date: April 12, 2004 4. If new construction but part of a master plan, provide the existing permit number: WQ00 5. County where project is located: Guilford County 6. Approximate Coordinates (Decimal Degrees): Latitude: 36.03153 o Longitude: -79.99456o III. CONSULTANT INFORMATION: 1. Professional Engineer: Stephen Buchanan, PE License Number: 041334 Firm: Dewberry Engineers Inc. Mailing address: 9300 Harris Corners Parkway, Suite 220 City: Charlotte State: NC Zip: 28269-3797 Phone number: (704) 625-5077 Email Address: sbuchanan(a)dewberry.com IV. WASTEWATER TREATMENT FACILITY (WWTF) INFORMATION: 1. Facility Name: Eastside WWTP Permit Number: NCO024210 Owner Name: City of High Point V. RECEIVING DOWNSTREAM SEWER INFORMATION: 1. Permit Number(s): W00014149 System Wide Collection System Permit Number(s): WQCS00010 Owner Name(s): City of High Point FORM: SSEA 04-16 Page 1 of 6 VI. GENERAL REQUIREMENTS 1. If the Applicant is a Privately -Owned Public Utility, has a Certificate of Public Convenience and Necessity been submitted? [:]Yes [:]No ®N/A 2. If the Applicant is a Developer of lots to be sold, has a Developer's Operational Agreement (FORM: DEV) been submitted? ❑ Yes ❑No ®N/A 3. If the Applicant is a Home/Property Owners' Association, has an Operational Agreement (FORM: HOA) been submitted? ❑ Yes ❑No ®N/A 4. Origin of wastewater: (check all that apply): ® Residential Owned ❑ Retail (stores, centers, malls) ❑ Car Wash ❑ Residential Leased ❑ Retail with food preparation/service ❑ Hotel and/or Motels ® School / preschool / day care ❑ Medical / dental / veterinary facilities ❑ Swimming Pool /Clubhouse ❑ Food and drink facilities ❑ Church ❑ Swimming Pool/Filter Backwash ❑ Businesses / offices / factories ❑ Nursing Home ❑ Other (Explain in Attachment) 5. Is/was an Environmental Assessment required under 15A NCAC O1 C? ❑ Yes ® No If yes, submit the appropriate final environmental document (FONSI, ROD, etc.) 6. Nature of wastewater: 100 % Domestic/Commercial % Other waste — specify: _ % Industrial (See 15A NCAC 02T .0103(20)) 7. Wastewater generated by project: 0 GPD (per 15A NCAC 02T .0114) Has a flow reduction been approved under 15A NCAC 02T .0114(f)? ❑ Yes ® No If yes, provide a copy of flow reduction approval letter 8. Summarize wastewater generated by project: Establishment Type Daily Design Flow ,,b No. of Units Flow Residential Properties 120 gal/day/bedroom 1,042 375,840 GPD School 15 gal/student 3,680 54,720 GPD gal/ GPD gal/ GPD gal/ GPD gal/ GPD Total 430,560 GPD a See 15A NCAC 02T .0114(b), (d). (e)(1) and (e)(2) for caveats to wastewater design flow rates (i.e., minimum flow per dwelling; proposed unknown non-residential development uses; public access facilities located near high public use areas; and residential property located south or east of the Atlantic Intracoastal Waterway to be used as vacation rentals as defined in G.S. 42A-4). b Per 15A NCAC 02T .0I 14(c), design flow rates for establishments not identified below shall be determined using available flow data, water using fixtures, occupancy or operation patterns, and other measured data. FORM: SSEA 04-16 Page 2 of 6 VIL GRAVITY SEWER DESIGN CRITERIA - 15A NCAC 02T .0305: 1. Summarize Gravity Sewer to be permitted: Size (inches) Length (feet) Material 8 26 DIP 12 1,566 HDPE 12 178 DIP 16 576 DIP VHI. PUMP STATION DESIGN CRITERIA — 02T .0305 & MDC (Pump Stations/Force Mains): COMPLETE FOR EACH PUMP STATION INCLUDED IN THIS PROJECT 1. Pump station number or name: Whites Mill Pump Station 2. Approximate Coordinates (Decimal Degrees): Latitude: 36.031676' Longitude:-79.994630' 3. What is the nearest 100-year flood elevation to the facility? 806.00 feet mean sea level. Source: FIRM Man Is any of the proposed project located within the 100-year flood plain? ❑ Yes ® No 4. If Yes, are the following items provided per 15A NCAC 02T .0305(e): Water -tight seals on all station hatches and manholes; and Control panels vents extend two feet above the 100-year flood plain elevation? ® Yes ❑ No ❑ N/A If No, what measures are being taken to protect them against flooding? 5. Finish grade elevation of the pump station: 812.50 6. Design flow of the pump station: 0.576 millions gallons per day (firm capacity) 7. Operational point(s) of the pump(s): 1,016 gallons per minute at 126 feet total dynamic head (TDH) 8. Number of pumps provided: 2 9. Number of pump cycles at average daily flow: 2 cycles per hour 10. Power reliability in accordance with 15A NCAC 02T .0305(h)(1): ® Standby power source or pump with automatic activation and telemetry - 15A NCAC 02T .0305(h)(1)(B)_ ➢ Required for all pump stations with an average daily flow greater than or equal to 15,000 gallons per day ➢ Must be permanent to facility Or if the pump station has an average daily flow less than 15,000 gallons per day: ❑ Portable power source with manual activation, quick -connection receptacle and telemetry - 15A NCAC 02T .0305(h)(1)(C) or ❑ Portable pumping unit with plugged emergency pump connection and telemetry - 15A NCAC 02T .0305(h)(1)(C): ➢ It shall be demonstrated to the Division that the portable source is owned or contracted by the applicant (draft agreement) and is compatible with the station. ➢ If the portable power source or pump is dedicated to multiple pump stations, an evaluation of all the pump stations' storage capacities and the rotation schedule of the portable power source or pump, including travel timeframes, shall be provided in the case of a multiple station power outage. FORM: SSEA 04-16 Page 3 of 6 VHI. PUMP STATION DESIGN CRITERIA (continued) 11. Summarize the pump station design elements: Design Element Plan Sheet Reference Specification Reference Power Reliability Source and Associated Elements C-201 26 36 23 Screened Wet Well Vent C-205 Check Valves, Gate Valves, etc. C-205 3331 11 Control Panel E-401 40 67 16 Restricted Access Elements (Fence, Wet Well Lock, etc) C-201 02 82 10 Audible and Visual Alarms E-401 Telemetry/SCADA E-401 40 63 43 Level Controls C-205 40 72 12 Weatherproof Sign with Required Information C-201 Air Relief Valves C-401 12. Summarize the force main to be permitted: Size (inches) Length (feet) Material High Elevation (feet) Discharge Elevation (feet) Pump -Off Elevation (feet) 8 152 DIP 852.25 806.37 787.72 10 780 DIP 852.25 806.37 787.72 10 4,526 PVC 852.25 806.37 787.72 13. Air release valve station locations per 15A NCAC 02T .03050): Air Release Valve # Station Plan Sheet Reference 1 17+21 C-305 2 23+68 C-307 3 29+23 C-308 4 38+80 C-310 5 and 6 50+48 and 60+69 C-313 and C-315 FORM: SSEA 04-16 Page 4 of 6 IX. SETBACKS & SEPARATIONS - (02B .0200 & 15A NCAC 02T .0305(f)): 1. Does the project comply with all separations found in 15A NCAC 02T .0305(1) & (g) ® Yes ❑ No ➢ 15A NCAC 02T.0305(f) contains minimum senarations that shall be Drovided for sewer systems: Setback Parameter* Separation Required Storm sewers and other utilities not listed below vertical 24 inches Water mains vertical -water over sewer including in benched trenches 18 inches Water mains(horizontal) 10 feet Reclaimed water lines vertical - reclaimed over sewer 18 inches Reclaimed water lines(horizontal - reclaimed over sewer 2 feet **Any private or public water supply source, including any wells, WS-I waters of Class I or Class II impounded reservoirs used as a source of drinking water 100 feet **Waters classified WS (except WS-I or WS-V), B, SA, ORW, HQW, or SB from normal hieh water or tide elevation and wetlands see item IX.2 50 feet **Any other stream, lake, impoundment, or ground water lowering and surface drainage ditches 10 feet Any building foundation 5 feet Any basement 10 feet Top slope of embankment or cuts of 2 feet or more vertical height 10 feet Drainage systems and interceptor drains 5 feet Any swimminq pools 10 feet Final earth grade vertical 36 inches ➢ 15A NCAC 02T.0305(g) contains alternatives where separations in 02T.0305(fl cannot be achieved. ➢ **Stream classifications can be identified using the Division's NC Surface Water Classifications webnage ➢ If noncompliance with 02T.0305( or ,g), see Section X of this application 2. Does the project comply with separation requirements for wetlands? (50 feet of separation) ❑ Yes [-]No ® N/A ➢ See the Division's draft separation requirements for situations where separation cannot be meet ➢ No variance is required if the alternative design criteria specified is utilized in design and construction ➢ As built documents should reference the location of areas effected 3. Does the project comply with setbacks found in the river basin rules per 15A NCAC 02B .0200? ❑ Yes ❑ No ® N/A ➢ This would include Trout Buffered Streams per 15A NCAC 2B.0202 4. Does the project require coverage/authorization under a 404 Nationwide or ❑ Yes ❑ No individual permits or 401 Water Quality Certifications? ➢ Information can be obtained from the 401 & Buffer Permitting Branch 5. Does project comply with 15A NCAC 021.0105(cl(6) (additional permits/certifications)? ® Yes ElNo Per 15A NCAC 02T.0105(c)(6), directly related environmental permits or certification applications are being prepared, have been applied for, or have been obtained. Issuance of this permit is contingent on issuance of dependent permits (erosion and sedimentation control plans, stormwater management plans, etc.). 6. Does this project include any sewer collection lines that are deemed "high -priority?" Per 15A NCAC 02T.0402, "high -priority sewer" means "any aerial sewer, sewer contacting surface waters, siphon, or sewer positioned parallel to streambanks that is subject to erosion that undermines or deteriorates the sewer. ® Yes ❑ No ➢ If yes, include an attachment with details for each line, including type (aerial line, size, material, and location). High priority lines shall be inspected by the permittee or its representative at least once every six -months and inspections documented per 15A NCAC 02T.0403(a)(5) or the permitee's individual System -Wide Collection permit. FORM: SSEA 04-16 Page 5 of 6 IN. CERTIFICATIONS: 1. Does the submitted system comply with 15A NCAC 02T, the Minimum Design Criteria for the Permitting of Pump Stations and Force Mains (latest version), and the Gravity Sewer Minimum Design Criteria (latest version) as applicable? ® Yes ❑ No If No, complete and submit the Variance/Alternative Design Request application (VADC 10-14) and supporting documents for review. Approval of the request is required prior to submittal of the Fast Track Application and supporting documents. 2. Professional Engineer's Certification: I, Stephen G. Buchanan, PE _attest that this application for (Professional Engineer's name from Application Item III.1.) Whites Mill Sewage Pumping Station Upgrade (Facility name from Application Item II.1.) has been reviewed by me and is accurate, complete and consistent with the information supplied in the plans, specifications, engineering calculations, and all other supporting documentation to the best of my knowledge. I further attest that to the best of my knowledge the proposed design has been prepared in accordance with this application package and its instructions, as well as all applicable regulations and statutes. Although other professionals may have developed certain portions of this submittal package, inclusion of these materials under my signature and seal signifies that I have reviewed this material and have judged it to be consistent with the proposed design. NOTE — In accordance with General Statutes 143-215.6A and 143-2I5.6B, any person who knowingly makes any false statement, representation, or certification in any application package shall be guilty of a Class 2 misdemeanor, which may include a fine not to exceed $10,000, as well as civil penalties up to $25,000 per violation. North Carolina Professional Engineer's seal, signature, and date: ��.``''"111C \A S O SEAL = ' = 041334 INE s i..................f!�rf..... .... :.....-.�.n..'... i••..4.`i. G BV 3. Applicant's Certification per ISA NCAC 02T .0106(b): / -7/1$l�3 I, Derrick Boone, Public Services Assistant Director attest that this application for (Signature Authority's name & title from Application Item I.3.) Whites Mill Sewage Pumping Station Upgrade (Facility name from Application Item II.1.) has been reviewed by me and is accurate and complete to the best of my knowledge. I understand that any discharge of wastewater from this non -discharge system to surface waters or the land will result in an immediate enforcement action that may include civil penalties, injunctive relief, and/or criminal prosecution. I will make no claim against the Division of Water Resources should a condition of this permit be violated. I also understand that if all required parts of this application package are not completed and that if all required supporting information and attachments are not included, this application package will be returned to me as incomplete. NOTE — In accordance with General Statutes 143-215.6A and 143-215.6B, any person who knowingly makes any false statement, representation, or certification in any application package shall be guilty of a Class 2 misdemeanor, which may include a fine not to exceed $1 O,O Ras well as civil penalties up to $25,000 per violation. Date: 7/18/23 FORM: SSEA 04-16 Page 6 of 6 Project Description Dewberry Engineers, Inc. has designed upgrades for the Whites Mill Sewage Pumping Station and downstream gravity sewer improvements to accommodate additional pumping capacity for the City of High Point. These improvements include replacing Whites Mill Pump Station with a new wetwell, pumps, valve vault, meter vault, standby generator, and force main. The downstream gravity sewer has been upsized to accommodate the additional pumping capacity as well as designing a new siphon across Oak Hollow Lake. Project area map is shown in Figure 1 and USGS map shown in Figure 2. An evaluation was performed in 2018 suggesting that the pump station was at capacity when comparing the average daily flow to the station's firm capacity. Additionally, during wet weather events, the station's wetwell water levels were high for extended periods of time. Due to concerns regarding the station capacity and based on discussions with field personnel and site visit conducted on May 19, 2021 with City of High Point staff, the City intends to upgrade the existing Whites Mill Pump Station and requested a PER that evaluates the capacity, upgrade alternatives and identifies possible downstream capacity limitations and alternatives to increase downstream capacity. Dewberry prepared a PER for the City of High Point and is included in Appendix I. The drainage basin that flows to Whites Mill Pump station is built out so there is no additional development which will connect to the pump station. The downstream gravity sewer is 12-inch diameter pipe that connects to an existing siphon which has a single 6-inch and single 8-inch line that carries the flow across Oak Hollow Lake to the Lake Forest Pump Station. The existing 6-inch and 8-inch siphon lines were installed in the 1970's and are laying on top of the lake bed. In the PER, a recommendation was made to add a third 8-inch siphon line. However, due to horizontal directional drill limitations a recommendation was made to abandon the existing siphon and install two new dual 12-inch HDPE lines using horizontal directional drilling. The new siphon lines will have more than sufficient capacity to handle flow from the upgrades at Whites Mill Sewage Pumping Station. Under peak flow and new pipe conditions the siphon can accommodate up to 2,025 gpm flow which exceeds what Whites Mill PS can pump. Analyzing future conditions to simulate degraded pipe and debris in the siphon lines show that the siphon can still accommodate 1,400 gpm capacity. To simulate these conditions a Hazen Williams C value of 90 was used. Siphon calculations are included in Appendix II. The upgrades proposed for Whites Mill Pump Station is going from 600 gpm capacity to 1,000 gpm which is an increase of 400 gpm. Based on this increase, Dewberry has used 0.576 MGD in Section VIII of the Pump Station Design Criteria in the Sewer System Extension Application (FORM SSEA 04-16). Pump station calculations are included in Appendix III. The downstream receiving pump station, Lake Forest Pump Station, has sufficient capacity to accommodate the increase in flows from Whites Mill PS. For additional information about Lake Forest Pump Station please refer to the PER in Appendix I. The majority of the proposed force main will be installed in the pavement along Oak Hollow Dr. and La Salle Dr. The force main will connect to a new gravity sewer manhole and 16-inch DIP sewer main to the new siphon lines. The siphon influent box was designed to expel as much air as possible from incoming flows and capture as many rocks, brick, sand, and gravel as possible prior to entering the siphon lines. A bypass pump connection has been added to the siphon box that will allow maintenance personnel to bypass pump into the secondary channel so that the main siphon line can be cleaned and pigged if clogged. A plug valve was added between the upstream manhole and siphon influent box to allow maintenance personnel to easily bypass pump the main influent siphon channel. 101 Dewberry C) z- 42j)�' WHITES MILL PUMP STATION CC LAJ 11� \A L-' `i HIGH PO1 H -E .4, WHITES MILL RD Deep' so 'D 6 \ i �_ L R -RD- LAo 0 950 86 NEW FORCE --j MAIN GRAVITY SEWER IMPROVEMENTS 01 a k LAKE FOREST 110W PUMP STATION 1ke LA SALLE DRIVE SIPHON 0' 500' 1000' 2000' 850 W/ LI SCALE: 1 1000' ffDewberry_ TITLE DATE REVISION SHEET NO. Dewberry Engineers Inc. USGS MAP 7/14/2023 9300 Harris Corners Parkway Suite 220 PROJECT PROJ. NO. DRAWING NO, 2 Charlotte, NC 28269-2618 WHITES MILL PUMPING STATION 50155072 704.509.9918 UPGRADE NC License No. F-0929 APPENDIX I WHITES MILL SEWAGE PUMPING STATION UPGRADES PRELIMINARY ENGINEERING REPORT Dewberry PREPARED FOR -ity of High Poin 211 S Hamilton High Point, NG 27/-u i 336 883 3194 PREPARED BY Dewberry 1610 Wycliff Road, Suite 410 Raleigh, NC 27607 Phone:919 8819939 NCBEIS- F-0929 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES TABLE OF CONTENTS Listof Figures................................................................................................................................................................ ul Listof Tables................................................................................................................................................................. iii Listof Attachments........................................................................................................................................................ ul Introduction....................................................................................................................................................................1 Purposeand Goals....................................................................................................................................................1 Background................................................................................................................................................................1 SewerCapacity Analysis................................................................................................................................................3 General......................................................................................................................................................................3 Methodologyfor Estimating Flows.........................................................................................................................3 CapacityEvaluation...................................................................................................................................................4 Whites Mill Sewage PS Sewer Capacity...............................................................................................................4 Receiving Sewer Capacity Analysis......................................................................................................................6 Lake Forest Sewage Pumping Station Sewer Capacity ........................................................................................8 AlternativesAnalysis....................................................................................................................................................10 Whites Mill Sewage Pumping Station Upgrades Alternatives Analysis....................................................................10 Alternative No. 1 — Construct a New Pumping Station........................................................................................10 Alternative No. 2 — Convert Existing Wet Well to a Submersible Pumping Station..............................................11 Alternative No. 3 — Install Larger Suction -lift Pumps...........................................................................................12 Downstream Receiving Sewers Upgrade Alternative Analysis................................................................................16 Alternative A — Upsizing Gravity Sewer...............................................................................................................16 Alternative B — New Force Main Along Lake.......................................................................................................16 Alternative C — New Force Main Parallel to Existing Gravity Sewer....................................................................17 LaSalle Drive Siphon..............................................................................................................................................21 OpenChannel Grinder Assembly........................................................................................................................21 SiphonPiping......................................................................................................................................................21 AccessRoad.......................................................................................................................................................21 Recommendations.......................................................................................................................................................23 PreliminaryProject Design......................................................................................................................................23 Whites Mill Sewage Pumping Station..................................................................................................................23 Downstream Receiving Sewers...........................................................................................................................23 LaSalle Drive Siphon..........................................................................................................................................23 LakeForest Pumping Station..............................................................................................................................23 ConstructionSchedule.............................................................................................................................................25 RequiredPermits.....................................................................................................................................................25 Opinion of Probable Construction Cost....................................................................................................................25 Dewberry ;; PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES LIST OF FIGURES FIGURE1: Project Aerial Map.......................................................................................................................................2 FIGURE 2: Whites Mill PS Alt 1 — Construct a New Pumping Station..........................................................................13 FIGURE 3: Whites Mill PS Alt 2 — Convert Existing Wet Well to a Submersible Pumping Station...............................14 FIGURE 4: Whites Mill PS Alt 3 — Install Larger Suction -Lift Pumps............................................................................15 FIGURE 5: Downstream Receiving Sewers Alt A — Upsizing Gravity Sewer...............................................................18 FIGURE 6: Downstream Receiving Sewers Alt B — New Force Main Along Lake.......................................................19 FIGURE 7: Downstream Receiving Sewers Alt C — New FM Parallel to Existing Gravity Sewer.................................20 FIGURE8: La Salle Drive Siphon Site Plan.................................................................................................................22 FIGURE 9: Recommended Improvements Plan..........................................................................................................24 LIST OF TABLES Table 1 - Whites Mill PS Metering data..........................................................................................................................4 Table 2 - Whites Mill PS Flow Rates for Design.............................................................................................................4 Table 3 - Gravity Sewer Upstream of Whites MITI PS.....................................................................................................5 Table 4 - Whites Mill PS Projected Firm Station Capacity ..............................................................................................6 Table5 - Flows Per Connection.....................................................................................................................................6 Table 6 - La Salle Drive Siphon Peak Hourly Flow estimate..........................................................................................7 Table 7 - La Salle Drive Siphon Capacity .......................................................................................................................7 Table 8 - Lake Forest PS Metering Data........................................................................................................................8 Table 9 - Lake Forest PS Flow Rates for Design...........................................................................................................9 Table 10 - Lake Forest PS Projected Firm Station Capacity ..........................................................................................9 Table 11 - Whites Mill PS Upgrade Alternative No. 1 Advantages/Disadvantages......................................................11 Table 12 - Whites Mill PS Upgrade Alternative No. 2 Advantages/Disadvantages......................................................12 Table 13 - Receiving Sewers Alternative A Advantages/Disadvantages......................................................................16 Table 14 - Receiving Sewers Alternative B Advantages/Disadvantages......................................................................17 Table 15 — Receiving Sewers Alternative C Advantages/Disadvantages.....................................................................17 Table 16 — Recommended Improvements — Opinion of Probable Construction Cost.................................................25 LIST OF ATTACHMENTS Appendix A Gravity Sewer Capacity Calculations.......................................................................................................27 Appendix B Siphon Capacity Calculations..................................................................................................................32 Appendix C Opinion Of Probable Construction Cost - Alternative 1............................................................................35 Appendix D Opinion Of Probable Construction Cost - Alternative 2............................................................................38 Appendix E Opinion Of Probable Construction Cost - Alternative A............................................................................41 Appendix F Opinion Of Probable Construction Cost - Alternative B...........................................................................43 Appendix G Opinion Of Probable Construction Cost - Alternative C..........................................................................45 Appendix H Opinion Of Probable Construction Cost - La Salle Drive Siphon............................................................47 ItDewberry LIST OF FIGURES iii PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES INTRODUCTION Dewberry Engineers Inc (Dewberry) has prepared this Preliminary Engineering Report (PER) for the City of High Point as part of the On -Call Agreement, dated April 2018. The Whites Mill Sewage Pumping Station (PS) is located near Oak Hollow Lake behind Tesa Court in High Point (See FIGURE i). The station is accessible via an access road from Tecumseh Street. An evaluation was performed in 2018 suggesting that the station is at capacity when comparing the average daily flow to the station's firm capacity. Additionally, during wet weather events, the station's wet well water levels are extremely high for extended periods of time. Due to concerns regarding station capacity and based on discussions with and a field visit conducted on May 19, 2021 with High Point staff, the City intends to upgrade the existing Whites Mill PS and requested a PER that evaluates the capacity, upgrade alternatives and identifies possible downstream capacity limitations and alternatives to increase downstream capacity. Purpose and Goals This PER evaluates the Whites Mill PS capacity needs to eliminate wet well surcharging and subsequent upgrade options to increase capacity. The PER further evaluates downstream impacts of increased station capacity to the downstream gravity sewers, the La Salle Drive Siphon and the Lake Forest Sewage Pumping Station. Background The Whites Mill PS station is a wet -pit, dry -pit suction -lift pumping station that was upgraded circa 2006. The variable speed, suction -lift pumps are installed below grade and requires confined space entry to access. The station includes a brick electrical building which houses power distribution, trailer -mounted generator, automatic transfer switch, control panel, drives, telemetry (cellular based) and other appurtenances. The pump model is Gorman -Rupp T4A3-B and was originally sized for 300 gpm at 80 feet of pressure; however, the belts and sheaves have since been modified to achieve a higher pump speed and capacity of approximately 600 gpm at 85 feet. When the station was upgraded in 2006, a new 8-inch force main was also installed and the discharge location was redirected to the 12-inch gravity sewer along Oak Hollow Drive. A bypass pump connection and a flow meter were also installed on the newer force main. The City reports that the bypass pump connection, which is located within a manhole, is inaccessible. The magnetic flow meter is operational and continuously monitors effluent wastewater flow. An evaluation was conducted in 2018, which was a high-level condition assessment to establish station condition, current output, and potential issues. The report suggested that the station is at capacity when comparing average daily flow to the pump station's firm capacity. Furthermore, recent wet weather flow data and site visits performed during such events suggest the pumps are undersized because the wet well water level approaches the top of wet well even though both pumps are operating in parallel. Wastewater from the Whites Mill force main is discharged to a gravity sewer on Oak Hollow Drive. This sewer is 12- inch diameter and was constructed circa 1973. This gravity sewer then discharges into the La Salle Drive Siphon. The La Salle Drive Siphon, which conveys wastewater across Oak Hollow Lake, discharges into the Lake Forest PS. In 2018, the La Salle Drive Siphon was evaluated for capacity and improvements to reduce potential clogging. The study recommended grinder installation and did not recommend any capacity improvements. The City completed a Sanitary Sewer System Master Plan in 2019. This plan evaluated system capacity based upon existing wastewater flows and projected future wastewater flows within 18-inch diameter sewers and larger and associated pumping stations. The Master Plan did not, however, consider either the Whites Mill PS service area or the Lake Forest PS service area as these smaller service areas did not meet the minimum sewer main size criteria. Therefore, a hydraulic model is not available for either the Whites Mill PS or the Lake Forest PS service areas and no recent gravity sewer flow meter data is available. Dewberry INTRODUCTION 1 WHITES MILL PS �i fl ` W PS , ._--V _ LJ f .. %-( ^ HH ES MJ� - I RD� '°1 0 Z 1• © m DISCHARGE MH — _..._...... 3 z m z u OAK HOLLOW ° 1 Q \`� % C`• ( �) LAKE ;� ' CD - __ L) . LA DnORA ora LADR 1 OAK HOLLOWLAKE O ! C w LEGEND LINETYPE DESCRIPTION - EX. GRAVITY SEWER EX. FORCE MAIN SANITARY SEWER MANHOLE PROPERTY LINES PS SEWAGE PUMPING STATION EXISTING SANITARY SEWER OUTSIDE OF PROJECT AREA Dewberry Dewberry Engineers Inc. I6f0 ,-urFROAD U ' X� cc OAK HOLLOW LAKE \ LA SALLE SIPHON ! PS LAKE FOREST PS FIG-1 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES SEWER CAPACITY ANALYSIS General The sewer capacity analysis identifies sewers/stations within the study limits that have limited capacity to convey peak hourly flows. The North Carolina Department of Environmental Quality (NCDEQ) Minimum Design Criteria (MDC) for Permitting of Gravity Sewers specifies that sewer capacities shall be designed for estimated ultimate tributary population. Additionally, it states that the capability of the downstream sewers to accept future flow made tributary to the collection system shall be evaluated. Accordingly, this analysis included evaluating the capacity at Whites Mill Sewage PS, the pipe capacity within the gravity sewer between the Whites Mill Force Main discharge manhole and the La Salle Drive Siphon and the capacity at the Lake Forest Sewage PS. Methodology for Estimating Flows Average daily and peak hourly wastewater flow was estimated by two methods. Flow Meter Data Method. The first method involved review of existing flow data as recorded at each station. The pumping stations collect flow data from an effluent magnetic flow meter on the station's force main. Therefore, it monitors wastewater pumped by the station and may not accurately represent the influent flow. As such, this approach is reasonable for collecting average daily flow data and peak hourly wet weather flow, unless the station's capacity is exceeded. If the station's capacity is exceeded, the peak hourly flow rate recorded by the effluent flow meter could be less than actual influent 'free flow' conditions. 2T/MDC Method. The second method involved a review of parcel data, water consumption data, flow criteria from the NC 2T Rules (15A NCAC 02T .0114) and NCDEQ minimum design criteria. The 2T criteria and water consumption data were used to establish average daily flow. The following 2T criteria were used: • Residential homes were assumed to have 3 bedrooms based upon review of online sales information around Oak Hollow Lake and generate 120 gallons per day per bedroom (gpd/BDR). Schools were assumed to generate 15 gpd/student based upon online information about the schools having cafeterias and gyms. The peak hourly flows were estimated using the peaking factor formula provided in NCDEQ's MDC for the Permitting of Pump Stations and Force Mains as shown below. Based upon census information for High Point, population density was assumed to be 2.6 people per home. PF = peaking factor Qphf _ 18 + NF Qphf = peak hourly flow (gallons per day) PF l d design daily (gallons per a Qddf $ + V r" Qddf = g .y flow (gllp day) P = service population (thousands) Using these two methods, the collection system capacity was evaluated as follows: 1. Pumping station capacity was assessed by comparing the projected peak hourly flow to the station's current firm capacity. The firm capacity was obtained from drawdown data provided by the City. 2. Gravity sewer capacity was assessed by comparing the calculated full -pipe capacity using the Manning equation and data from existing record drawings to the projected peak hourly flow. Appendix A includes a summary of these calculations by sewer section. 3. Siphon capacity was assessed by comparing the calculated capacity using the Hazen -Williams method to Dewberry SEWER CAPACITY ANALYSIS 3 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES assess frictional losses and from the effective available pressure head between the outlet elevation and inlet elevation of the siphon as shown on record drawings to the projected peak hourly flow. Appendix B includes detailed calculations for the siphon system. Capacity Evaluation Whites Mill Sewage PS Sewer Capacity 'FAK HOIJP! Y FLOW FSTIMATF USING FI OW MFTFR DATA MFTHOD The City provided hourly flow data for July 2021 and the daily flow data from August 24, 2018 through August 23, 2021. The minimum, average and peak flows gathered from this data are shown in the table below. Peak Hourly Flow 534 gpm 07/19/2021, 11:31:12 AM Average Daily Flow 172 gpm 8/24/2018 - 8/23/2021 Peak Daily Flow 463 gpm 02/06/2020 Furthermore, during the July 19, 2021 event, the station sustained a pumped flow rate of about 450-500 gpm between about 8:30 AM and 10:30 AM. During this time the wet well was also flooded to 12 to 14 feet deep indicating that the influent peak hourly flow is greater than the station's capacity/metered data and the system stored the excess wastewater during this time. Additionally, the peak hourly flow occurred during July when the schools were on summer break. Therefore, if an additional 96 gpm (3,680 students x 15 gpd/student x 2.5 peak factor / 1,440) is added to reflect flow when the schools are in session, the resulting estimated peak hourly flow during that event is 630 gpm. PEAK HOURLY FLOW ESTIMATE USING 2T/MDC METHOD The Whites Mill Sewage PS service area consists primarily of residential properties as well as three schools. The City reports that the pumping station's service area is essentially built -out and review of the GIS data indicates the same. There are approximately 1,042 residential properties and 3,860 students at the Southwest Guilford Elementary, Middle and High Schools according to NC Department of Public Instruction. The 2T Rules' minimum sewage flow rates for design were used to calculate the average daily flow rates for each type of land use within the service area. Peaking factors from NCDEQ MDCs were used to estimate peak hourly flow. The table below summarizes these calculations. Residential Properties 1,042 120 gpd / BDR 261 gpm 3.48 906 gpm Student Population 3,680 15 gal / student 38 gpm 2.5 96 gpm Total Tributary Flow - - 299 gpm 3.35 1,002 gpm ff Dewberry SEWER CAPACITY ANALYSIS 4 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES GRAVITY SEWER CAPACITY IMMEDIATELY UPSTREAM OF WHITES MILL SEWAGE PS While the Flow Meter Data Method suggests peak hourly flow in excess of 630 gpm and use of the 2T/MDC Method estimates 1,002 gpm of peak hourly flow, a comparison of these flows to the existing influent sewer capacity at the station was made to ascertain the system's ability to convey these higher flows. Furthermore, since flow meter data was not available for the influent sewers, the peak hourly flows through these pipes were estimated using the 2T/MDC Method. Two gravity flow sewers discharge to the station, one from the east and one from the west. These two sewers converge to a single pipe about 30-feet upstream of the station's wet well. The service area from the east consists of approximately 213 residential properties and flows to the station via an 8-inch gravity sewer that is parallel to the station's access road. The service area from the west consists of approximately 829 residential properties and 3,860 students at the Southwest Guilford Elementary, Middle and High Schools and flows to the station via a 12-inch gravity sewer. The following table summarizes estimated influent sewer capacity and the projected peak hourly flow through the sewers based upon Appendix A — Gravity Sewer Capacity Calculations. 8-Inch Influent Sewer Capacity from East 704 gpm 185 gpm 12-inch Influent Sewer Capacity from West 427 gpm* 817 gpm Combined Influent Capacity 1,069+ gpm** 1,002 gpm The 8-inch gravity sewer pipes immediately upstream of the station and flowing from the east are flowing 16% to 30% full based upon the Flow Meter Data Method and 24% to 5% full based upon the 2T/MDC Method. These gravity sewer pipes appear to have adequate capacity. The 12-inch gravity sewer pipes immediately upstream of the station and flowing from the west are flowing 76% to 82% full based upon the Flow Meter Data Method and 108% to 128% full based upon the 2T/MDC Method. Based on this information, the influent sewers from the west may have some limited capacity. The east and west pipes converge into an 8-inch gravity sewer that discharges into the wet well. This sewer is undersized. IDewberry SEWER CAPACITY ANALYSIS s PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES PROJECTED FIRM STATION CAPACITY The below table summarizes the results of the capacity analysis. Permitted Capacity per the City City Drawdown Testing Flow Meter Data Method 2T/MDC Method Combined Full -Pipe Capacity of Influent Sewers Based upon review of this table, the following observations are made: 310 gpm 410 gpm 534 gpm (630 gpm with schools) 1. The station's permitted capacity is less than the station's capacity. 1,002 gpm 1,069 gpm 2. The Flow Meter Data Method and 2T/MDC Method both indicate the station should have a firm capacity greater than current 410 gpm. 3. Using 2T/MDC Method, the station's firm capacity should be at least 1,002 gpm, which results in a total dynamic head condition of 125 feet via the existing 8-inch force main. Receiving Sewer Capacity Analysis The Whites Mill PS discharges wastewater through a force main to a gravity sewer that then flows to the La Salle Drive Siphon. The capacity of this gravity sewer and siphon were analyzed to identify limited capacity. GRAVITY SEWER PIPE CAPACITY (WHITES MILL PS TO LA SALLE DRIVE SIPHON) The Whites Mill PS pumps wastewater through 2,500 linear feet of 8-inch force main and discharges into a 12-inch gravity sewer a few hundred feet south of the Whites Mill Road and Oak Hollows Road intersection. As indicated in Appendix A, there are approximately 309 residential connections to the gravity sewer between the Whites Mill PS and the La Salle Drive Siphon. There is no metering data available immediately upstream of the siphon and therefore, in order to estimate the flow from these additional connections through the gravity sewer to the siphon, the Flow Meter Data Method and 2T/MDC Method were both used to make separate peak hourly flow estimates per residential connection. This resulted in 0.51 gpm per connection using Flow Meter Data Method and 0.87 gpm per connection using the 2T/MDC Method (reference Appendix A). Flow Meter Data Method 1,042 534 gpm 0.51 gpm 2T/MDC Method 1 0.87 gpm 0.87 gpm 10 Dewberry SEWER CAPACITY ANALYSIS 6 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Using as -built drawing data and the Manning equation, the full -pipe capacity of each sewer section was estimated. This data can be found in Appendix A. Generally, the full -pipe capacity of the existing sewer ranges from approximately 700 gpm to 1,300 gpm. The 12-inch gravity sewer pipes upstream of the siphon are flowing 42% to 95% full based the Flow Meter Data Method and 80% to 181 % full based on the 2T/MDC Method. These gravity sewer pipes appear to have adequate capacity based on Flow Meter Data Method and are exceeding full -pipe capacity by up to 81 % based on the 2T/MDC Method. In general, the remaining capacity is reduced the further it travels downstream towards the siphon. The most downstream 4,250 linear feet of gravity sewer has the least capacity, especially after the point where flow from approximately 114 additional residences discharges into the gravity sewer. The full -pipe capacity within this sewer section is exceeded by an average of 51 % with a maximum of 81 % based on peak hourly flows using the 2T/MDC Method. Based upon these findings, the gravity sewer is undersized. Therefore, the receiving sewers should be either upsized to accommodate the increased hydraulic loading or other alternatives considered that avoid upsizing the sewers while still allowing the downstream siphon and Lake Forest PS to receive the flow. I A GAI_I.F nR!%/F SIPHC)N SFWER CARArITY The La Salle Drive Siphon is an inverted siphon that conveys sewer flows across Oak Hollow Lake to the Lake Forest PS. The siphon inlet and outlet chambers are located approximately 630 feet apart. There are two siphon pipes between the inlet and outlet chambers, a 6-inch and 8-inch ball and socket joint cast iron pipe laid across the Iakebed. The siphon chambers were, however, designed for three pipes across the lake. According to the 2018 study, the 6-inch siphon tends to clog with debris. To determine siphon capacity, the peak hourly flow must be estimated at the siphon and then compared against the available capacity for the siphon. As indicated in Appendix A, the peak hourly flow at the siphon is estimated to be approximately 789 gpm using the Flow Meter Data Method and 1,271 gpm using the 2T/MDC Method. See the table below: Whites Mill PS 629 gpm 1,002 gpm Additional Connections Estimated Flow at La Salle Drive Siphon 160 gpm 268 gpm 789 gpm 1,271 gpm Using the invert elevations and pipe diameter for each siphon pipe, the capacity was determined by setting the effective head to zero and solving for the flow variable. These calculations can be found in Appendix B. There is about 12.5 ft of head available for the siphon piping and this corresponds to a flow of about 370 gpm for the 6-inch siphon and about 790 gpm for the 8-inch siphon and a total of about 1,160 gpm combined. 6-inch Siphon Capacity 8-inch Siphon Capacity Total Capacity of La Salle Drive Siphon ff Dewberry 370 gpm 790 gpm 1,160 gpm SEWER CAPACITY ANALYSIS 7 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Based upon review of this data, the following observations are made: 1. There is adequate capacity within the siphon when both siphon pipes are free of any clogs and the peak hourly flow is 789 gpm based on metering data. 2. The siphon's capacity of 1,160 gpm is slightly below the peak hourly flow based upon the 2T/MDC Method resulting in a capacity of 1,270 gpm. 3. If the 6-inch siphon is clogged, there is insufficient capacity for the peak hourly flow regardless of which flow estimate method is used. Based upon these findings and discussions with the City, addition of a third siphon pipe is recommended. Lake Forest Sewage Pumping Station Sewer Capacity The Lake Forest Sewage PS capacity was analyzed to identify limited capacity. This included evaluating the peak hourly flow and firm station capacity. The peak hourly flow was determined using the provided metering data and from the 2T/MDC rules. This station is very similar in design to the Whites Mill PS. Both are dry -pit, wet -pit type stations using dry -prime, suction -lift pumps. The pumps are also variable speed, which means that the pump's capacity is adjusted to match influent flow. PEAK HOURLY FLOW ESTIMATE BASED UPON FLOW METER DATA METHOD The City provided metering data. Hourly flow data was provided for July 2021 and the daily flow data was provided from August 24, 2018 through August 23, 2021. The minimum, average and peak flows gathered from this data are shown in the table below. Average Hourly Flow 200 gpm 8/24/2018-8/23/2021 (Influent/Effluent) 247 gpm Peak Hourly Flow 664 gpm 07/19/2021, 09:30:14 AM (Influent(Effluent) 1,547 gpm 07/02/2021, 03:18:43 PM Average Daily Flow 233 gpm 8/24/2018-8/23/2021 Peak Daily Flow 832 gpm 05/21/2020 Based upon review of this data, the following observations are made: The station has extended periods of time without continuous pumping. (i.e.: it remains idle for some time between pump runs) Each pump is rated for a higher flow rate than the project peak hourly influent flow rate. As indicated in the table, an extreme wet weather event occurred in July 2021. Subsequent review of the wet well levels during this time indicate that they ranged from 4 to 9 feet with an average level of 5.9 feet during the month of July 2021. Therefore, this data suggests that the variable speeds pumps maintained pumping ff Dewberry SEWER CAPACITY ANALYSIS 8 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES capacity that met influent flow conditions because no surcharging had occurred PEAK HOURLY FLOW The Lake Forest Sewage PS service area includes the Whites Mill PS basin plus additional residential and commercial properties between the two stations. The La Salle Drive Siphon, which discharges wastewater to the station from the west, serves the Whites Mill PS basin and a portion of the Lake Forest basin. There is also a 12-inch gravity sewer to the east that conveys flow from additional residential and commercial properties. The 2T Rules for minimum sewage flow rates for design were used to calculate the daily flow rates for each type of land use within the service area. The peak hourly flow was determined as identified in Appendix A and summarized in the table below. Residential Properties Student Population Commercial Properties Total Tributary Flow 2,208 120 gpd / BDR 552 gpm 3.48 1,921 gpm 3,680 15 gal / student 38 gpm 2.5 96 gpm 30 82 gpm 2.5 205 gpm PROJECTED FIRM STATION CAPACITY The below table summarizes the results of the capacity analysis. 672 gpm - 2,222 gpm Permitted Capacity 1,250 gpm City Drawdown Testing 2,170 gpm Metered Peak Hourly Wet Weather Effluent Flow 1,547 gpm 2T/MDC Method 2,222 gpm Combined Full -Pipe Capacity of Influent Sewers 3,203 gpm Based upon review of this data, the following observations are made: The station's permitted capacity is less than the drawdown capacity. That station's firm capacity is nearly identical to the projected capacity using the 2T/MDC Method suggesting that a hydraulic upgrade of this station is not necessary. The combined influent sewer capacity (East 1,134 gpm + West 2,070 gpm) is greater than the pumping station capacity, which indicates that the existing sewers have sufficient capacity to convey the estimated peak hourly influent flows. It Dewberry SEWER CAPACITY ANALYSIS 9 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES ALTERNATIVES ANALYSIS The alternatives analysis included evaluating different upgrade options for the Whites Mill PS, downstream receiving sewers and the La Salle Drive Siphon. Whites Mill Sewage Pumping Station Upgrades Alternatives Analysis As discussed in greater detail in the Capacity Analysis Section, the pumps have insufficient capacity to meet the peak hourly flow to the station. Therefore, three potential alternatives were evaluated to increase the station's firm capacity. They are: Alternative No. 1 — Construct a New Pumping Station Alternative No. 2 — Convert Existing Wet Well to a Submersible Pumping Station Alternative No. 3 — Install Larger Suction -lift Pumps The three alternatives are described in greater detail below. Alternative No. 1 — Construct a New Pumping Station This alternative involves construction of a new wet well with submersible pumps, on the same parcel of land, and within close proximity of the existing station thereby allowing abandonment of the existing wet well and dry -pit. Refer to FIGURE z for site plan. This alternative includes the following improvements: Influent manholes and sewer to redirect flow to the new wet well Wet well with 75 HP duplex submersible pumps with a capacity of 1,000 gpm at 125 feet total dynamic head Valve vault with check valves and isolation valves Emergency bypass connection to the force main A short section of force main that connects to the existing 8-inch force main 1-ton jib crane to facilitate pump removal Pump control panel, variable frequency drives (VFDs) and automatic transfer switch within the existing electrical building Outdoor, sound attenuated 200 kW diesel generator with a fuel tank sized for 48 hours of operation at 100% load located away from the property line given the proximity of neighboring homes 480-volt, 300-amp electrical service and transformer A service disconnect in an enclosed breaker located on the exterior building wall A step-down transformer for 120-volt panelboard Driveway extension to the proposed wet well LED lighting and grounding ring installed Air conditioning system to maintain a conditioned space for the variable frequency drives. The new electrical installation will be compliant with the NEC and proper hazardous classifications under NFPA 820, with electrical design to alleviate conduit seal off fittings on the pump submersible cable. As indicated in Appendix C, the opinion of probable construction cost for this alternative is $1,900,000. Dewberry ALTERNATIVES ANALYSIS 10 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Some advantages and disadvantages for this alternative are as shown in Table 11 below. • Avoids long-term bypass pumping to 0 Longer construction duration facilitate construction • Requires expansion of site • Allows the existing station to remain in • Submersible pumps must be removed to service until the new station is ready to be be visually inspected placed into service • Provides all new facilities instead of relying on durability of rehabilitated structures • Eliminates need for confined space entry to service and maintain pumps Alternative No. 2 — Convert Existing Wet Well to a Submersible Pumping Station This alternative involves upgrading the existing station with the use of submersible pumps within the existing 8-foot diameter wet well structure. Refer to FIGURE 3 for site plan. This alternative includes the following improvements: Demolish existing concrete fillets in the wet well to fit submersible pump bases Install 75 HP submersible pumps with a capacity of 1,000 gpm at 125 feet total dynamic head Reconstruct wet well top such that a suitably sized hatch can be provided to access the pumps The existing suction pipe exiting through the side wall and into the pump chamber would be removed and the hole patched and made watertight. New cores would be required for each pump discharge leading to a new valve vault before connecting to the existing 8-inch force main. The interior surface of the wet well would be inspected and restored using an epoxy coating. The existing dry -pit pump chamber would no longer be needed and can be abandoned -in -place by filling with aggregate. 1-ton jib crane to facilitate pump removal A new pump control panel, variable frequency drives (VFDs) and automatic transfer switch within the existing electrical building Outdoor, sound attenuated 200 kW diesel generator with a fuel tank sized for 48 hours of operation at 100% load located away from the property line given the proximity of neighboring homes 480-volt, 300-amp electrical service and transformer A service disconnect in an enclosed breaker located on the exterior building wall A step-down transformer for 120-volt panelboard Replace the influent sewer As indicated in Appendix D, the opinion of probable construction cost for this alternative is $1,900,000. ff Dewberry ALTERNATIVES ANALYSIS 11 a PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Some advantages and disadvantages for this alternative are as shown in Table 12 below. • No expansion of site required 0 Requires long-term bypass pumping to facilitate construction • Shorter construction duration Submersible pumps must be removed to be visually inspected • Maximizes use of existing assets • Relies on structural integrity of the existing wet well Alternative No. 3 — Install Larger Suction -lift Pumps This alternative involves installing larger self -priming, suction lift pumps within the existing dry -pit. Refer to FIGURE 4 for site plan. To achieve a capacity of 1,000 gpm at 125 feet, 75 HP high -head pumps (e.g.: Gorman -Rupp V-Series) are necessary. These pumps are two -stage pumps with 76-inch height and a footprint of approximately 96-inches by 48-inches. The existing dry -pit chamber is 120-inches in diameter and 96-inches tall. Given the height and footprint of the V- Series pumps, they would not fit within the dry -pit chamber. Due to the physical limitations of fitting the larger, higher capacity pumps within the existing dry -pit pump chamber and the need for confined space entry to observe the pumps on a regular basis, Alternative 3 has been removed from further consideration. No opinion of probable cost has been prepared for this alternative. It Dewberry ALTERNATIVES ANALYSIS 12 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES \ P 10' ID WET WELL WITH SUBMERSIBLE PUMPS CHAINLINK FENCE —, TREELINE/BUFFER AREA 4' ID DOGHOUSE MH / 4' ID SSMH (TYP) J/ EXTEND SEWER FROM SS WEST TO NEW SSMH VALVE VAULT NEW EMERGENCY BYPASS CONNECTION WITH BLIND FLANGE AND ISOLATION VALVE ABANDON EX. WET WELL AND PUMP CHAMBER ABANDON EX. EMERGENCY BYPASS MH N o z 1 GENERATOR WITH WEATHERPROOF W r ENCLOSURE AND SUBBASE FUEL TANK W ��/ EXISTING GENERATOR BUILDING (n u— TO BE REUSED FOR PUMP VFDs, CONTROL PANELS, AND ELECTRICAL IMPROVEMENTS �r 8" FM GEN OAK HOLLOW LAKE i' z �` w .. cn CW7 J o Q 0 " aa. - a g cn z J F- i- CONNECT TO EXISTING 8" FM w > W F _ F- C7 = z 3 3 3 a EX. rM ME I LR VAUL I z C) i O FM - - . / N Z co (h C. z / o a -14 bill fi CULVEHT LL Upi� C W Z m at�o� .0 — FM w\w z Aa) MAW- a3i 0 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES „ o ABANDON EX. EMERGENCY BYPASS MH. \ C.'HAINLINK FENCE K i,.. ABANDON EX. PUMP CHAMBER OAK HOLLOW LAKE RELAY 12" SEWER TO WET WELL J REPLACE TOP SLAB OF WET WELL VALVE VAULT NEW EMERGENCY BYPASS CONNECTION WITH BLIND FLANGE AND ISOLATION VALVE 8" FM ' GENERATOR WITH WEATHERPROOF W r ENCLOSURE AND SUBBASE FUEL TANK W — s. • EXISTING GENERATOR BUILDING TO BE REUSED FOR PUMP VFDs, CONTROL PANELS, AND ELECTRICAL IMPROVEMENTS I GEN I }S w 3 LU at7u c. a � 3 � cn t + r N X W Cn w CONNECT TO EXISTING 8" FM > yit EX. FM METER VAU!,*' `� H w w 3 w ui C7 = z 2 U a 7 O d co FM // / a O z cl) w z o 0 u) AL X. CULVER1 ma a $mmm W m m LL UpiPC VO 2 .. W C�OQ xx N Ny aLL C1 N C FM �W Z n m A� 0 OAK HOLLOW LAKE ,,�y. Ar,0*000 L_•O PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES ABANDON EX. EMERGENCY BYPASS MH. (IIA/NI INK I-t_NCt INSTALL LARGER PUMPS WITHIN EX. PUMP CHAMBER�� REPLACE TOP SLAB OF PUMP CHAMBER I GEN RELAY 12" SEWER TO WET WELL VALVE VAULT - NEW EMERGENCY BYPASS CONNECTION WITH BLIND FLANGE AND ISOLATION VALVE 8" FM GENERATOR WITH WEATHERPROOF ENCLOSURE AND SUBBASE FUEL TANK EXISTING GENERATOR BUILDING TO BE REUSED FOR PUMP VFDS, CONTROL PANELS, AND ELECTRICAL IMPROVEMENTS _.. ,J l CONNECT TO EXISTING 8" FM ..k-TA Y 'J -_ W"W- O Z W Cn - w J EX, FP�I k1: 7! Fi VAC%i � �-?"` Ili' - _ Y ` •- -- i-M o O o N Z M H Z 0 � o a PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Downstream Receiving Sewers Upgrade Alternative Analysis Three alternatives were evaluated. They are: Alternative A — Upsizing Gravity Sewer Alternative B - New Force Main Along Lake Alternative C - New Force Main Parallel to Existing Gravity Sewer The following describes each alternative in greater detail. Alternative A — Upsizing Gravity Sewer This alternative involves upsizing the gravity sewer downstream of the Whites Mill PS from a 12-inch to 15-inch pipe to increase the capacity. Refer to FIGURE s for plan. The existing route's surface cover varies with about 2,300 feet of the 6,500 feet being within paved roadways and the remainder being cross country. It is assumed that the upsized gravity sewer will be installed parallel to the existing sewer and then the existing sewer will be abandoned in -place after the new gravity sewer is placed in service. The sewer piping would be installed via open -cut excavation. As indicated in Appendix E, the opinion of probable construction cost for this alternative is $3,000,000. The advantages and disadvantages for this alternative are as shown in Table 13 below. • Increases sewer capacity 0 Higher construction cost • New sewers are less susceptible to a Disruptive infiltration/inflow • Longer construction duration • Potential adjacent utility damage • Dewatering Alternative B — New Force Main Along Lake This alternative involves installing a new force main that follows along the lake extending from the Whites Mill PS until reaching the La Salle Drive Siphon. Refer to FIGURE 6 for plan. The new force main would be a 10-inch diameter, approximately 7,700 linear feet in length, with new combination air relief / vacuum relief valves installed at the high points. With this route, the Whites Mill PS operating point would be approximately 1,000 gpm at 120 feet of total dynamic head. This route will be primarily under non -paved surfaces with approximate depth of cover of 3 feet. Horizontal directional drills (HDD) would provide a cost savings at a few locations by reducing the total length of pipe installed. The remainder would be installed via open -cut excavation. As indicated in Appendix F, the opinion of probable construction cost for this alternative is $2,100,000. 19 Dewberry ALTERNATIVES ANALYSIS 16 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES The advantages and disadvantages for this alternative are as shown in Table 14 below. • The majority of pipe would be located on city - owned property reducing the need for easements • Avoids disruption to public roadways through residential areas • Avoids costly upsizing of gravity sewers • Eliminates cost of paving restoration • Reduces potential utility conflicts • More extensive environmental permitting • May need access easements to the force main at certain locations • Some force main sections may be subaqueous (i.e.: HDD crossings) • Air release valves in the backyards of the homes around the lake may increase potential odor complaints Alternative C — New Force Main Parallel to Existing Gravity Sewer This alternative involves installing a new force main that connects to the existing force main but then parallels the route of existing gravity sewer within the roadway to the La Salle Drive Siphon. Refer to FIGURE 7 for plan. The force main extension would be 10-inch diameter to reduce system pressure/pump horsepower while still exceeding the 2 feet per second minimum velocity requirement. Additional combination air relief / vacuum relief valves would be installed at the high points along the roadway. This route would be primarily under paved surfaces with approximate depth of cover of 3 feet. The sewer piping would be installed via open -cut excavation. As indicated in Appendix G, the opinion of probable construction cost for this alternative is $1,500,000. The advantages and disadvantages for this alternative are as shown in Table 15 below. • Avoids upsizing gravity sewers through residential areas • Less disruptive when compared to gravity sewer installation • Less pavement restoration from smaller trench excavation • Shorter construction duration ff Dewberry • Higher construction cost • Potential adjacent utility damage • Additional air release valves are necessary and they'd be located in the road increasing potential odor complaints ALTERNATIVES ANALYSIS 17 WHITESMILL PS'J / V L.y ! .-- J M— - j U) _ ___ (�.-� m N - M�v a� _ TES MILL RD fl - m z 1/0 r� 19 M 22 FM DISCHARGE MH ��" - - _:-—� C Z / ��❑ �ll�r u u c r� Zm F } l:D o z cn EX 12" GRAVITY SEWER NO ` ' IMPROVEMENTS Q �]' O `� OAK HOLLOW EX 8" FORCE MAIN NO L`�7\ ` ` LAKE —�-f �-- IMPROVEMENTS % 9 \ MH REPLACEMENT MH NO IMPROVEMENTS 5 1 % LA SALLE SIPHON PROPERTY LINES 6 / Q SEWAGE PUMPING STATION _ PS � \� t EXISTING SANITARY SEWER 4 OUTSIDE OF ALTERNATIVE ARFA LAKE FOREST PS Dewber Dewberry Engineers Inc. 2610WVCUFF ROAD SURE 410 RA r-§ .M -1 -11 SHEET NO. FIG-5 WHITES MILL PS z Lu m z Ps Z) WHITES e ui L F?[) z M\V�. '71 M m x • FM DISCHARGIF MH POTENTIAL HDD 30 im LOCATION 104 0 29 4 1 LI 1 0 :ili 28 POTENTIAL HDD LOCATICNI •26 OAK HOLLOW LAKE 23 Oq ro Irk 0 POI I N T lAt HDD I OCAT ION 22 2D 19 op OR 18 7 16 LA DORA DR 15 01 LA VISTA D14 • 14 IA VlSr,4 OAK HOLLOW OR LAKE 113 0 POTENTIAL HDD LOCATIONA • 12 z 0 a LEGENDDR LINETYPE DESCRIPTION 12" REPLACEMENT WITH 15" PIPE EX 12" GRAVITY SEWER NO IMPROVEMENTS 10 4 OAK HOLLOW LAKE EX 8" FORCE MAIN NO IMPROVEMENTS 9 3 MH REPLACEMENT 2 LA SALLE SIPHON MH NO IMPROVEMENTS PROPERTY LINES 0 7 PS SEWAGE SEWAGE PUMPING STATION P07FNIIAI HDD lOCAlION PS N." EXISTING SANITARY SEWER I LAKE FOREST PS I OUTSIDE OF ALTERNATIVE AREA Dewberry Dewtx-rry Engineers Inf- FIG-6 WHITES MILL PSLJ m CR .'' �""-.t c PS ,1 wH r i 6_i Pb ES MILL p G) Z 10*1 t" `• - — FM DISCHARGE MH - .00 (] (' I t► p ('j Z X Coll a. C - ' 10 CA Jr-Ll OAK HOLLOW LAKE r4 -. P a � sJ • � 5P Oyu\ DOgAlD fk 18 AA DORA DR OAKHOLLOW LAKE ' . �- �� O f. •� � Kra � a• '� o :4 LEGEND LINETYPE DESCRIPTION a+vo �1 12" REPLACEMENT WITH 15" PIPEvj EX 12' GRAVITY SEWER NO IMPROVEMENTS] y3 OAK HOLLOW '= :4 U. LAKE EX 8" FORCE MAIN NO IMPROVEMENTS 3 �.� C 8 2 5 LA SALLE SIPHON 7 g MH REPLACEMENT MH NO IMPROVEMENTS PROPERTY LINES Q SEWAGE PUMPING STATION PS ^EKE FOREST PS EXISTING SANITARY SEWER OUTSIDE OF ALTERNATIVE AREA �. Dewberry Dewberry Engineers Inc. 2610 WYCI.IFF ROAD SUITE 410 FIG-7 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES La Salle Drive Siphon Improvements to the La Salle Drive Siphon were previously investigated in 2018 and the analysis recommended installation of an open -channel grinder in a manhole upstream of the siphon inlet chamber, Given the increased capacity needs, the below summarizes the proposed updated improvements. This alternative includes the following improvements: Open -channel grinder suitable for flows up 1,800 gpm within 5-foot precast concrete chamber Upsize and adjust invert elevations for approximately 320 feet of gravity sewer immediately upstream of the siphon inlet chamber to increase capacity to the siphon and compensate for headlosses from the grinder 1-ton jib crane to facilitate grinder removal Third 8-inch siphon pipe across the lake using either ball and socket joint ductile iron or HDPE with anchor weights Clean existing 6-inch siphon pipe by sewer jetting and/or high -flow water flushing. If the siphon can also be dewatered, CCTV inspection is proposed to observe interior wall condition. If it cannot be dewatered, sonar inspection could be performed to confirm debris removal. 15-foot wide gravel access road to the La Salle Drive Siphon inlet chamber from La Salle Drive. 240/120V, single-phase, 100-amp electrical service from La Salle Drive to power grinder and provide telemetry Service entrance rated panelboard Electrical equipment rack Easements are anticipated for construction of the gravel driveway. As indicated in Appendix H, the opinion of probable construction cost for this alternative is $800,000. Open Channel Grinder Assembly The open -channel grinder will assist with shredding solids, debris and grease to reduce the likelihood of clogging within the siphon. The Muffin Monster Model 30005-032 as manufactured by JWC Environmental is an open -channel grinder that is suitable for flows up to 1,800 gpm. The grinder is equipped with a 32" cutter stack using 11-tooth cam cutters. It is paired with a 5 HP immersible motor and 304 stainless steel lifting bail, frame, guide rails and associated components. HYDRAULICS The expected headloss though the grinder is about 13 inches. The grinder is proposed to be installed between MH #2 and MH #3 and this section of gravity sewer is also within the limits required to be upsized from a 12-inch to a 15-inch diameter pipe. During peak hourly flow, the existing 12-inch sewer is flowing full and exceeding its capacity and the upsized 15-inch gravity sewer would flow about 55% full. The slope between MH #2 and MH #3 is about 0.62% and the inverts can be adjusted to overcome the added headloss from the new grinder. Siphon Piping A third siphon pipe would provide additional capacity for the siphon. The existing 6-inch and 8-inch siphon pipes were installed along the lakebed with ball and socket joints. Ball and socket joint pipe is recommended for the third siphon pipe. The pipe would be epoxy lined to extend its service life. Access Road Currently, the site is only accessible by foot or small all -terrain vehicle. Installation of a 15-foot wide gravel access road from La Salle Drive to the siphon influent box would allow vehicle access to the new grinder and existing siphon influent box to perform regular maintenance. The lot at 3902 La Salle Drive is an empty lot and an access road across this lot to the City -owned lake parcel is proposed. IDewberry ALTERNATIVES ANALYSIS 21 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES 15' WIDE GRAVEL ACCESS ROAD (ALTERNATIVE LOCATION) 4 R AND GRUB (30' WIDTH) I 15' WIDE GRAVEL ACCESS ROAD /I I TO SIPHON INFLUENT BOX OAK HOLLOW LAKE / / 3 IN -CHANNEL GRINDER WITHIN 5' MH I 15" GRAVITY SEWER (UPSIZED) 15' WIDE GRAVEL ACCESS ROAD 15' WIDE GRAVEL ACCESS ROAD AND 20' WIDE ACCESS EASEMENT EXISTING SIPHON INFLUENT BOX EXIS IING SIPHON PIPE OAK HOLLOW LAKE THIRD SIPHON PIPE (8" DIP W/BALL AND SOCKET JOINT OR EQUAL) zwLd W Z u O = a a CL 55 z Z) > g Un Z IL O w FW— J w (D can = Z w CD N z M � o 1w— Z O 0 ckf O a. bill IN 40 0 o oe-Fm LL mit Um rVro=m� C 3w�2m mt 0x W '� 2aQ tmv N LL c c w m A� 3 m 0 AMU. :oose• L!.!•Oq' PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES RECOMMENDATIONS Preliminary Project Design Based on the alternative analysis and discussions with City staff, the recommended improvements are as described below. Refer to FIGURE 9 for the recommended improvements plan. Whites Mill Sewage Pumping Station Alternative No. 1 — Construct a New Pumping Station is recommended for the following reasons: Results in a new station at the same cost as upgrading the existing station Risk of long-term bypass pumping failures during construction is eliminated Avoids risk of modifying existing concrete wet well The PS would use submersible pumps within a newly installed 10-foot diameter wet well. The firm station capacity would be 1,000 gpm. Downstream Receiving Sewers Alternative C — New Force Main Parallel to Existing Gravity Sewer is recommended for the following reasons: Avoids costly replacement of the existing sanitary sewer Lower construction cost The force main extension would be 10-inches in diameter with consideration of odor control valves on air release valves. La Salle Drive Siphon The following La Salle Drive Siphon improvements are recommended: Install a new grinder upstream of the siphon inlet chamber Add a third siphon pipe across Oak Hollow Lake Construct a new access road from La Salle Drive to the siphon inlet chamber Clean and inspect the 6-inch siphon pipe, which has a history of clogging. Lake Forest Pumping Station While no hydraulic improvements appear necessary, this station should be re -permitted for the projected higher influent flow/firm station capacity to accommodate increased flows from Whites Mill PS. 9 Dewberry RECOMMENDATIONS 23 WHITES MILL PS - (J L _ l4km z PS WHIT V (r1 1 gM�u A� " . (� SMIV RD �1 !i m m FM DISCHARGE Mom' -• C Z -•-» $ Cl j L__j N o IQ O o; =, z c N AS s� iAn \ OAK HOLLOW LAKE �p C Li 13 Do '•._." .. .P �R+g""R.. � JAI 6 LA DO RA DR.. \ c, � ( _ LA VISTA R'-LJ OAK HOLLOW oQ [`�A _R LAKE *• c�' o ~� LEGEND _J WC z LINETYPE DESCRIPTION '° 10" FORCE MAIN EX 12" GRAVITY SEWER NO IMPROVEMENTS O� yQ; IN -CHANNEL GRINDER WITHIN 5' MH ,mom EX. 8" FORCE MAIN NO 0 �- IMPROVEMENTS • MH REPLACEMENT THIRD SIPHON PIPE * (8" DIP W/BALL AND MH NO IMPROVEMENTS SOCKET JOINT OR EQUAL) 8 EXISTING SANITARY SEWER 5 LA SALLE SIPHON OUTSIDE OF ALTERNATIVE AREA \ / PROPERTY LINES T8 •�/`, SEWAGE PUMPING STATION / PS OAK HOLLOW NEW THIRD 8" SIPHON PIPE ACCESS ROAD TO SIPHON LAKE LAKE FOREST PS ~ Dewberry Dewberry Engineers Inc. 2610 YOULIFF ROAD FIG-9 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Construction Schedule A schedule has been prepared that identifies major milestones and an estimated project completion date for upgrades to the Whites Mill PS, downstream receiving sewers, and La Salle Drive Siphon improvements. The project phase durations are: Design Phase — January 2022 to June 2022 Permitting Phase — June 2022 to September 2022 Easement Acquisition Phase — May 2022 to October 2022 Bid and Award Phase — October 2022 to December 2022 Construction Phase — January 2023 to March 2024. Required Permits A list of anticipated permitting requirements for upgrading the Whites Mill PS, downstream receiving sewers and the La Salle Drive Siphon are as follows: NCDEQ Fast -Track Sewer Permit NCDEQ Division of Energy, Mineral and Land Resources Erosion and Sedimentation Control Plan Approval North Carolina Division of Water Resources (DWR), 401 Water Quality Certifications (WQC) Opinion of Probable Construction Cost The total opinion of probable construction cost (OPCC) is $4,400,000, including a 30% contingency. The OPCC is based on the recommendations and figures developed for this PER. See Table 16 below for overall OPCC for each of the project areas. Whites Mill PS Upgrade $ 2,100,000 $1,700,000 $ 2,500,000 Force Main Extension $1,500,000 $1,200,000 $1,800,000 La Salle Drive Siphon Improvements $ 800,000 $ 600,000 $ 1,000,000 Total Construction Cost $ 4,400,000 $3,500,000 $ 5,300,000 *The Association for the Advancement Cost Engineering (AACE) low and high values represent a 20%t accuracy. 0 Dewberry RECOMMENDATIONS 25 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Appendices It Dewberry RECOMMENDATIONS 26 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Appendix A Gravity Sewer Capacity Calculations '•. Dewberry RECOMMENDATIONS 27 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX A GRAVITY SEWER CAPACITY CALCULATIONS Sewer Slope & Caoacity Calculations usine 2T Rules for Flow Rate 6 = STA Rim In Out MH drop Depth Length Slope Pipe Dia Full Pipe Flow Aggregate of Flow Remaining Capacity O. a o LL LL to C 0 E " y G O. N p 0 LL O C 3 C a: U N O ) N C C COU w it w 3 to N v 0 a, E a C C U U Street Notes EAST TO WHITES MILL 1.43 9.15 -131.58 1.70% 8.00 in 8.00 in 709 gpm 1.02 mgd 185 gpm 0 0 Tecumseh @Access Rd HP18524, updated with survey data __. HP17305, updated with survey data 7 10+02.75 816.30 808.58E�8 7.15 185 gpm 0.27 mgd 213 6 8+71.17 811.73 804.914.88 0.03 6.85 185 gpm 0.27 mgd 524 gpm 0.75 mgd 26% 74% 0 gpm 0 0 0 Access Rd 5 7+25.42 808.86 801.95 801.61 0.34 7.25 -145.75 2.01% 8.00 in 771 gpm 1.11 mgd 185 gpm 0.27 mgd 586 gpm 0.84 mgd 24% 76% 0 gpm 0 0 0 Access Rd HP23577, updated with survey data 4 5+57.42 812.36 800.73 800.71 0.02 11.65 -168.00 0.52% 8.00 in 394 gpm 0.57 mgd 185 gpm 0.27 mgd 208 gpm 0.30 mgd 47% 53% 0 gpm 0 0 0 Access Rd HP22312, updated with survey data 3 2+99.17 808.58 799.58 799.54 0.04 9.04 -258.25 0.44% 8.00 in 360 gpm 0.52 mgd 185 gpm 0.27 mgd 174 gpm 0.25 mgd 284 gpm 0.41 mgd 52% 48% 0 gpm 0 0 0 Access Rd HP25745, updated with survey data 2 1+26.00 806.14 798.25 798.34 -0.09 7.80 -173.17 0.74% 8.00 in 469 gpm 0.68 mgd 185 gpm 0.27 mgd 39% 61% 0 gpm 0 0 0 Access Rd HP19181, updated with survey data 1 +27.00 809.85 797.87 797.07 0.80 12.78 -99.00 0.47% 8.00 in 375 gpm 0.54 mgd 185 gpm 0.27 mgd 189 gpm 0.27 mgd 49% 51% 0 gpm 0 0 0 Access Rd HP10528, updated with survey data 1 817 gpm WEST TO WHITES MILL 18 52+96.83 818.00 804.08 13.92 1 12.00 in 817 gpm 1.18 mgd 8291 3680 0 3 schools +829 residental connections (1042-213=829) 17 50+48.83 810.00 803.53 803.53 0.00 6.47 -248.00 0.22% 12.00 in 755 gpm 1.09 mgd 817 gpm 1.18 mgd -62 gpm -0.09 mgd 108% -8% 0 gpm 0 0 0 16 48+89.92 808.75 803.18 803.18 0.00 5.57 -158.91 0.22% 12.00 in 752 gpm 1.08 mgd 817 gpm 1.18 mgd -65 gpm -0.09 mgd 109% -9% 0 gpm 0 0 0 15 47+01.00 814.00 802.761 802.76 0.00 11.24 -188.92 0.22% 12.00 in 756 gpm 1.09 mgd 817 gpm 1.18 mgd -61 gpm -0.09 mgd 108% -8% 0 gpm 0 0 0 14 44+72.43 806.50 802.261 802.26 0.00 4.24 -228.57 0.22% 12.00 in 750 gpm 1.08 mgd 817 gpm 1.18 mgd -67 gpm -0.10 mgd 109% -9% 0 gpm 0 0 0 13 42+72.80 807.90 801.82 801.82 0.00 6.08 -199.63 0.22% 12.00 in 753 gpm 1.08 mgd 817 gpm 1.18 mgd -64 gpm -0.09 mgd 109% -9% 0 gpm 0 0 0 12 41+41.99 812.80 801.53 801.53 0.00 11.27 -130.81 0.22% 12.00 in 755 gpm 1.09 mgd 817 gpm 1.18 mgd -62 gpm -0.09 mgd 108% -8% 0 gpm 01 0 0 11 39+47.13 809.10 801.10 801.10 0.00 8.00 -194.86 0.22% 12.00 in 753 gpm 1.08 mgd 817 gpm 1.18 mgd -64 gpm -0.09 mgd 108% -8% 0 gpm 0 0 0 10 37+15.50 808.50 800.59 800.59 0.00 7.91 -231.63 0.22% 12.00 in 752 gpm 1.08 mgd 817 gpm 1.18 mgd -65 gpm -0.09 mgd 109% -9% 0 gpm 0 0 0 9 35+02.58 808.80 800.12 800.12 0.00 8.68 -212.92 0.22% 12.00 in 753 gpm 1.08 mgd 817 gpm 1.18 mgd -64 gpm -0.09 mgd 108% -8% 0 gpm 0 0 0 8 32+82.18 808.10 799.64 799.64 0.00 8.46 -220.40 0.22% 12.00 in 748 gpm 1.08 mgd 817 gpm 1.18 mgd -69 gpm -0.10 mgd 109% -9% 0 gpm 0 0 0 7 31+14.33 808.60 799.27 799.27 0.00 9.33 -167.85 0.22% 12.00 in 753 gpm 1.08 mgd 817 gpm 1.18 mgd -64 gpm -0.09 mgd 109% -9% 0 gpm 0 0 0 6 28+14.65 809.20 798.61 798.61 0.00 10.59 -299.68 0.22% 12.00 in 752 gpm 1.08 mgd 817 gpm 1.18 mgd -65 gpm -0.09 mgd 109% -9% -0.09 mgd, 108% -8% -0.09 mgd 109% -9% -0.23 mgd I -25% 0 gpm 01 0 0 5 26+70.34 813.80 798.29 798.29 0.00 15.51 -144.31 0.22% 12.00 in 755 gpm 1.09 mgd 817 gpm 1.18 mgd -62 gpm 0 gpm 0 0 0 4 24+15.57 816.30 797.73 797.73 0.00 18.57 -254.77 0.22% 12.00 in 752 gpm 1.08 mgd 817 gpm 1.18 mgd -65 gpm 0 gpm 0 0 0 3 22+71.75 809.37 797.97 797.92 0.05 11.45 -143.82 -0.17% 12.00 in 655 gpm 0.94 mgd 817 gpm 1.18 mgd -162 gpm 0 gpm 0 0 0 HP21335, updated with survey data 2 20+08.44 811.54 797.44 797.31 0.13 14.23 -263.31 0.18% 12.00 in 684 gpm 0.99 mgd 817 gpm 1.18 mgd -133 gpm -0.19 mgd 119% -19% 0 gpm 0 0 0 HP23660, updated with survey data 1 18+19.44 808.62 797.01 797.07 -0.061 11.55 -189.00 0.16% 12.00 in 639 gpm 0.92 mgd 817 gpm 1.18 mgd -178 gpm -0.26 mgd 128% -28% 0 gpm 0 0 0 HP30528, updated with survey data LAST MH TO WHITES MILL Wet Well (COMBINES EAST & WEST FLOWS FROM ABOVE) Flow is from East and West Calculated Above 1 +27.00 809.85 795.12 797.07 -1.95 12.78 1,002 gpm 1 1.44 mgd 1,002 gpm 1042 3680 0 Access Rd HP10528, updated with survey data 0 +00.00 811.34 796.95 811.34 -27.00 0.44% 12.00 in 1,0699pml 1.54 mgd 1,002 gpm 1.44 mgd 66gpml 0.10 mgd 94% 6% 1 0 gpm 0 01 0 Access Rd WW: updated with survey data; Per x11-8 Invin=790; Bot=783; Dewberry APPENDICES 28 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX A GRAVITY SEWER CAPACITY CALCULATIONS Sewer Slope & Capacity Calculatinns usine 2T Rules for Flow Rate O Rim In Out MH drop Depth 6.481 Length Slope 3.96% 0.20% Pipe Dia Full Pipe Flow Aggregate of Flow Remaining Capacity a o 94% OG E 3 S O M a:STA E 2' a N � IA E c M a 0 0 V O `� a, ) a o c y c " uo IOJ 1,002 gpm 1042 15 gpmI 17 3 gpm 4 W St _, v °o Y LAU 3680 0 0 � N c O E w E c 61 0 0 0 Street Notes Connections set equal to Total Effluent from White's Mill PS above EFFLUENT FROM WHITES MILL to LA SALLE DRIVE SIPHON 1,002 gpm 1.44 mgd 6% 30 6+86.001 844.40 837.92 8.00 in 12.00 in 1,082 gpm 725 gpm 819 gpm 1,017 gpm 1.46 mgd Oak Hollow Or oak Hollow Or Gravity Asbuilts show 8", 2006 FM records show as 12"; Need to confirm 12" 29 5+24.001 837.00 831.50 830.28 1.22 6.72 -162.00 1.56 mgd" 1,021 gpm 1.04 mgd; 1,028 gpm 1.18 mgd' 1,044 gpm 1.47 mgd 62 gpm 0.09 mgd 28 3+87.001 836.20 830.00 830.00 0.00 6.20 -1-37.00 1.48 mgd -304 gpm -0.44 mgd 142% -42% 8 gpm 9 0 O Oak Hollow Or 27 +00.001 842.20 828.99 828.38 0.61 13.82 -387.00 0.26% 12.00 in 1.50 mgd -225 gpm -0.32 mgd 127% -27% 16 gpm 18 0 0 Oak Hollow Or Stationing Changes at SSMH: Sta 0+00 U/P = Sta 26+32.13 D/S 26A 25+75.13 838.00 828.24 827.991 0.25 10.01 -57.00 0.25% 12.00 inj 795 gpm 1.14 mgd 1,044 gpm 1.50 mgd -250 gpm -0.36 mgd 131% -31% 1 0 gpm 0 0 0 X-Country 26B 24+64.63 831.20 827.25 827.25 0.00 3.95 -110.50 0.67% 12.00 in 1,312 gpm 1.89 mgd 1,044 gpm 1.50 mgd 268 gpm 0.39 mgd 80% 20% 0 gpm 0 01 0 x-Country Slope is labeled 0.50% in profile but based on stationing & inverts it is not 26C 22+84.63 835.00 826.34 826.34 0.00 8.66 -180.00 0.51% 12.00 in 1,140 gpm 1.64 mgd 1,044 gpm 1.50 mgd 96 gpm 0.14 mgd 92% 8% 0 gpm 0 0 0 x-country 26 20+96.71 838.90 825.40 825,40 0.00 13.50 -187.92 0.50% 12.00 in 1,134 gpm 1.63 mgd 1,050 gpm 1.51 mgd 84 gpm 0.12 mgd 93% 7% 6 gpm 7 0 0 Dantzler Ct • dantzler court to oak hollow IV 43-59 pg 11 25 18+09.69 829.20 823.84 823.84 0.00 5.36 -287.02 0.54% 12.00 in 1,182 gpm 1.70 mgd 1,054 gpm 1.52 mgd 128 gpm 0.18 mgd 89% 11% 3 gpm 4 0 0 Dantzler Ct @ Dantzler Rd 24 15+69.99 832.50 823.24 823.24 0.00 9.26 -239.70 0.25% 12.00 in 802 gpm 1.15 mgd 1,059 gpm 1.52 mgd -257 gpm -0.37 mgd 132% -32% 5 gpm 6 0 0 Dantzler Rd 23 11+70.22 836.20 822.24 822.24 0.00 13.96 -399.77 0.25% 12.00 in 802 gpm 1.15 mgd 1,067 gpm 1.54 mgd -265 gpm -0.38 mgd 1 133% -33%1 8 gpm 9 0 0 Dantzler Rd @ La Vera St 22 9+65.22 833.00 821.72 821.72 0.00 11.28 -205.00 0.25% 12.00 in 807 gpm 1.16 mgd 1,072 gpm 1.54 mgd -264 gpm -0.38 mgd 133% -33% 5 gpm 6 01 0 La Vera St @ San Fernando Dr 21 8+51.03 840,00 821.44 821.44 0.001 18.56 -114.19 0.25% 12.00 in 794 gpm 1.14 mgd 1,073 gpm 1.54 mgd -279 gpm -0.40 mgd 135% -35% 1 gpm 1 0 0 San Fernando Dr IV-41 20 6+91.68 848.50 821.04 821.04 0.00 27.46 -159.35 0.25% 12.00 in 803 gpm 1.16 mgd 1,075 gpm 1.55 mgd -272 gpm -0.39 mgd 134% -34% 3 gpm 3 0 0 San Fernando Or IV-41 19 4+35.651 840.50 820.40 820.40 0.00 20.10 -256.03 0.25% 12.00 in 802 gpm 1.15 mgd 1,075 gpm 1.55 mgd -274 gpm -0.39 mgd 134% -34% 0 gpm 0 0 0 x-country IV-41 18 2+04.35 825.00 819.541 819.54 0.00 0.40 0.00 0.00 5.46 4.55 7.76 -231.30 0.37% 12.00 in 978 gpm 1.41 mgd 1,076 gpm 1.55 mgd -99 gpm -0.14 mgd 110% -10% 1 gpm 1 0 0 x-country Iv-41 17 +00.00 822.50 818.35 817.951 -204.35 0.58% 12.00 in 1,223 gpm 1.76 mgd 1,175 gpm 1.69 mgd 48 gpm 0.07 mgd 96% 4% 99 gpm 114 0 0 x-country IV-37, IV-41,Stationing Changes at SSMH: Sta 0+00 U/P = Sta 9+38.42 D/S 16 5+36.07 824.50 816.74 816.741 -402.35 0.30% 12.00 in 879 gpm 1.27 mgd 111 .26 mgd' 1.26 mgd' 1,175 gpm 1.69 mgd -296 gpm -0.43 mgd 134% -34% 0 gpm 01 0 0 x-country Iv-37 15 1+97.97 828.00 815.73 815.731 12.27 -338.10 0.30% 12.00 in 876 gpm 1,175 gpm 1.69 mgd -299 gpm -0.43 mgd 134% -34% 0 gpm 0 0 0 X-Country IV-37 14 +00.00 828.60 815.14 815.14 0.00 13.46 -197.97 0.30% 12.00 in 875 gpm 1,209 gpm 1.74 mgd -334 gpm -0.48 mgd 138% -38% 34 gpm 39 0 0 La Vista Or @ Ponce De Leon Dr IV-37,IV-59; Stationing Changes at SSMH: Sta 0+00 U/P = Sta 9+38.00 D/S 13 6+85.001 828.70 814.52 814.52 0.00 14.18 -253.00 0.25% 12.00 inj 794 gpm 1.14 mgd 1,215 gpm 1.75 mgd -422 gpm -0.61 mgd 153% -53% 6 gpm 7 0 0 Ponce De Leon Dr IV-59 12 3+30.00 832.00 813.65 813.65 0.00 18.35 -355.00 0.25% 12.00 in 794 gpm 1.14 mgd 1,219 gpm 1.75 mgd -425 gpm -0.61 mgd 154% -54% 3 gpm 4 0 0 Ponce De Leon Dr IV-59 11 +00.00 832.83 812.84 812.84 0.00 19.99 -330.00 0.25% 12.00 in 794 gpm 1.14 mgd 1,235 gpm 1.78 mgd -441 gpm 1 -0.64 mgd 156% -56% 17 gpm 19 0 O Ponce De Leon Dr @ Oak Hollow Or Stationing Changes at SSMH: Sta 0+00 U/P = Sta 32+86.60 D/S 10 30+52.12 814.50 811.97 811.971 0.00 2.53 -234.48 0.37% 12.00 in 977 gpm 1.41 mgd 1,235 gpm 1.78 mgd -259 gpm -0.37 mgd 127% -27% 0 gpm 0 0 0 x-country IV-36 9 29+50.79 813.00 811.74 811.74 0.00 1.26 -101.33 0.23% 12.00 in 764 gpm 1.10 mgd 1,235 gpm 1.78 mgd -472 gpm -0.68 mgd 162% -62% 0 gpm 0 0 0 x-country IV-36 8 26+00.63 817.00 810.97 810.97 0.00 6.03 -350.16 0.22% 12.00 in 752 gpm 1.08 mgd 1,235 gpm 1.78 mgd -484 gpm -0.70 mgd 164% -64% 0 gpm 0 0 0 x-country IV-36 7 23+37.23 814.50 810.49 810.49 0.00 4.01 -263.40 0.18% 12.00 in 684 gpm 0.99 mgd 1,235 gpm 1.78 mgd -551 gpm -0.79 mgd 181% -81% 0 gpm 0 0 0 x-Country IV-36 6 21+29.28 813.50 810.03 810.03 0.00 3.47 -207.95 0.22% 12.00 in 754 gpm 1.09 mgd 1,235 gpm 1.78 mgd -481 gpm -0.69 mgd 164% -64% 0 gpm 0 0 0 x-country IV-36 5 18+42.73 813.50 809.24 809.24 0.00 4.26 -286.55 0.28% 12.00 in 842 gpm 1.21 mgd 1,235 gpm 1.78 mgd -394 gpm -0.57 mgd 147% 47% 0 gpm 01 0 0 x-country 4 14+84.68 814.50 808.34 807.00 1.34 7.50 -358.05 0.25% 12.00 in 804 gpm 1.16 mgd 1,252 gpm 1.80 mgd -448 gpm -0.65 mgd 156% -56% 17 gpm 191 0 0 x-country 3 12+30.05 808.00 805.43 805.43 0.00 2.57 -254.63 0.62% 12.00 in 1,259 gpm 1.81 mgd 1,271 gpm 1.83 mgd -12 gpm -0.02 mgd 101% -1% 19 gpm 22 0 0 x-country 2 10+00.00 807.00 804.00 804.00 0.00 3.00 -230.05 0.62% 12.00 inj 1,264 gpm 1.82 mgd 1,271 gpm 1.83 mgd -7 gpm -0.01 mgd 101% -1% 0 gpm 0 0 0 x-country 1 9+10.00 807.30 801.24 801.00 0.24 6.30 -90.00 3.07% 12.00 in 2,807 gpm 4.04 mgd 1,271 gpm 1.83 mgd 1,536 gpm 2.21 mgd 45% 55% 0 gpm 0 0 0 x-Country La Salle Siphon Influent Box 0 2+81.75 810.00 787.80 787.80 0.00 22.20 -628.25 1,271 gpm 1.83 mgd 0 0 0 La Salle Siphon Effluent Box WEST TO LAKE FOREST (SIPHON FLOW) 2 2+81.75 810.00 787.80 787.80 0.00 22.20 281.75 1,271 gpm 1.83 mgd 1,271 gpm 1351 3680 0 Lake Forest Access Rd Equals Total Connections from Siphon Calculated Above 1 2+69.75 810.00 788.00 788.00 0.00 22.00 -12.00 -1.67% 12.00 in 2,070 gpm 2.98 mgd 1,271 gpm 1.83 mgd 799 gpm 1.15 mgd 61% 39% 0 0 0 Lake Forest Access Rd No invert out listed in record, assuming equals inv in from siphon 788.00 EAST TO LAKE FOREST (NON -SIPHON FLOW) 1.37 mgd 1.37 mgd 183 gpm 0.26 mgd 2 1+74.00 810.00 801.371 801.27 0.10 8.73 174.00 951 gpm 951 gpm 857 0 30 Lake Forest Access Rd 857 Residential Connections, 57 Commercial Properties 1 _+00.001 810.00 800.401 788.00 12.40 22.00 -174.00 0.50% 12.00 in 1,134 gpm 1.63 mgd 951 gpm 84% 16% 0 0 0 Lake Forest Access Rd No invert out listed in record, assuming equals inv in from siphon 788.00 TO LAKE FOREST (COMBINED EST & WEST FLOWS) 22.00 25.00 810.80 25.00 1.20% 2,222 gpm 3.20 mgd 2,222 gpm 2208 3680 30 Lake Forest PS Equals Connections from East and West Calculated Above 1 1 +25.001 810.001 788.001 788.001 0.001 36.00 r. 32,877 gpm 0 +00.00 810.80 787.70 787.70 47.33 mgd 2,222 gpm 3.20 mgd 30,655 gpm 44.13 mgd 7% 93% 0 0 0 Lake Forest PS Lake Forest Wet Well, bot = 783, pump off 785, HWLA=787.7, top 810.8 Residential Peaking Factor F 3.48 Residential Flow Per Connection: ; 0E6.8333333:gpm/connection 86991181gpm/connection of peak hourly flow Schools Peaking Factor 2.5 School Flow Per Student:gpm/connection of peak hourly flow Commerical Flow Per Connection: of peak hourly flow Manning n = Dewberry APPENDICES 29 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX A GRAVITY SEWER CAPACITY CALCULATIONS Sewer Slope & Capacity Calculations using Metering Data for Flow Rate o = STA Rim In Out MH drop Depth Length Slope Pipe Dia Full Pipe Flow Aggregate of Flow Remaining Capacity a c C �� 3 o E a o a C E o o . ; c ,° c f0 C o c cc c C N a o o c v+ f0 C o E E o 0 Street Notes EAST TO WHITES MILL 807.15 1.43 9.15 8.00 in 109 gpm 8.00 in 709 gpm 1.02 mgd 109 gpm 6D0 gpm 0.86 mgd 15% Tecumseh @Access Rd HP18524, updated with survey data Access Rd HP17305, updated with survey data Access Rd HP23577, updated with survey data 7 10+02.75 816.30 808.58 0.16 mgd 109 gpm 213 0 0 6 8+71.17 811.73 804.91 804.88 0.03 6.85 -131.58 1.7D% 0.16 mgd 85% 0 gpm 0 0 0 5 7+25.42 808.86 801.95 801.61 0.34 7.25 -145.75 2.01% 8.00 in 771 gpm 1 1.11 mgd 109 gpm 0.16 mgd 662 gpm 0.95 mgd 14% 86% 0 gpm 0 0 0 4 5+57.42 812.36 800.73 800.71 0.02 11.65 -168.00 0.52% 8.00 in 394gpml 0.57 mgd 109 gpm 0.16 mgd 284 gpm 0.41 mgd 28% 72% 0 gpm 0 0 0 Access Rd HP22312, updated with survey data 3 2+99.17 808.58 799.58 799.54 0.04 9.134 -258.25 0.44% 8.00 in 360 gpm 0.52 mgd 109gpml 0.16 mgd 250 gpm 0.36 mgd 30% 70% 1 0 gpm 0 0 0 Access Rd HP25745, updated with survey data 2 1+26.00 806.14 798.25 798.34 -0.09 7.80 -173.17 0.74% 8.00 in 469 gpm 0.68 mgd 109 gpm 0.16 mgd 360 gpm 0.52 mgd 23% 77% 0 gpm 0 0 0 Access Rd HP19181, updated with survey data 1 +27.00 809.85 797.87 797.07 0.80 12.78 -99.00 0.47% 8.00 in 375 gpm 0.54 mgd 109 gpm 0.16 mgd 265 gpm 0.38 mgd 29% 71% 0 gpm 0 0 0 Access Rd HP10528, updated with survey data WEST TO WHITES MILL 18 52+96.83 818.00 804.08 13.92 12.00 in 521 gpm 0.75 mgd 521 gpm 829 3680 0 3 schools + 829 residental connections (1042-213=829) 17 50+48.83 810.00 803.53 803.53 0.00 6.47 -248.00 0.22% 12.00 in 0 gpm 0.00 mgd 521gpml 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 01 0 16 48+89.92 808.75 803.18 803.18 0.00 5.57 -158.91 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 15 47+01.00 814.00 802.76 802.76 0.00 11.24 -188.92 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 14 44+72.43 806.50 802.26 802.26 0.00 4.24 -228.57 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 13 42+72.80 807.90 801.82 801.82 0.00 6.08 -199.63 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 12 41+41.99 812.80 801.53 801.53 0.00 11.27 -130.81 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 01 0 0 11 39+47.13 809.10 801.10 801.10 0.00 8.00 -194.86 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 10 37+15.50 808.50 800.59 800.59 0.00 7.91 -231.63 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 9 35+02.58 808.80 800.12 800.12 0.00 8.68 -212.92 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 8 32+82.18 808.10 799.64 799.64 0.00 8.46 -220.40 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 7 31+14.33 808.60 799.27 799.27 0.00 9.33 -167.85 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 6 28+14.65 809.20 798.61 798.61 0.00 10.59 -299.68 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 5 26+70.34 813.80 798.29 798.29 0.00 15.51 -144.31 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 4 24+15.57 816.30 797.73 797.73 0.00 18.57 -254.77 0.22% 12.00 in 0 gpm 0.00 mgd 521 gpm 0.75 mgd -521 gpm -0.75 mgd 0 gpm 0 0 0 3 22+71.75 809.37 797.97 797.92 0.05 11.45 -143.82 -0.17% 12.00 in 655 gpm 0.94 mgd 521 gpm 0.75 mgd 133 gpm 0.19 mgd 80% 20% 0 gpm 0 0 0 HP21335, updated with survey data 2 20+08.44 811.54 797.44 797.31 0.13 14.23 -263.311 0.18% 12.00 in 684 gpm 0.99 mgd 521 gpm 0.75 mgd 163 gpm 0.23 mgd 76% 24% 0 gpm 0 0 0 HP23660, updated with survey data 1 18+19.44 808.62 797.01 797.07 -0.06 11.55 -189.00 0.16% 12.00 in 639 gpm 0.92 mgd 521 gpm 0.75 mgd 117 gpm 0.17 mgd 82% 18% 0 gpm 0 0 0 HP10528, updated with survey data LAST MH TO WHITES MILL Wet Well (COMBINES EAST & WEST FLOWS FROM ABOVE) Flow is from East and West Calculated Above 1 +27.00 809.85 795.12 797.07 -1.95 12.78 631 gpm 0.91 mgd 631 gpm 1042 3680 0 Access Rd HP10528, updated with survey data 0 +00.00 811.34 796.95 796.95 811.34 -27.00 0.44% 12.00 in 1,069 gpm 1.54 mgd 631 gpm 0.91 mgd 438 gpm 0.63 mgd 59% 41% 0 gpm 0 0 0 Access Rd WW: Updated with survey data; Per XII-8 Invin=790; Bot=783; Dewberry APPENDICES 30 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX A GRAVITY SEWER CAPACITY CALCULATIONS Sewer Slope & Capacity Calculations using Metering Data for Flow Rate = C STA Rim In Out MH drop Depth Length Slope Pipe Dia Full Pipe Flow Aggregate of Flow Remaining Capacity 441 gpm 0.63 mgd 79 gpm 0.11 mgd 164 gpm 0.24 mgd O! 2 o e OD C 3 O E w K e?: 1 VI E C O . O " w C O c 0 a:0 . N C O rz v v '� E y cc U 0 O N YL = -o oo : N v7 - N f0 C O E a E U Street Notes EFFLUENT FROM WHITES MILL to LA SALLE SIPHON 631 gpm 0.91 mgd 631 gpm 1042 3680 0 Connections set equal to Total Effluent from White's Mill PS above 30 6+86.001 844.40 837.92 -837.92 6.48' 8.00 in 12.00 in 12.00 in 1,082 gpm 725 gpm 819 gpm 640 gpm 0.92 mgd' 9 gpm 17 0 0 Oak Hollow Or 29 5+24.00 837.00 831.50 830.28 1.22 6.72 -162.00 3.96% 1.56 mgd 1.04 mgd 1.18 mgd 642 gpm 646 gpm 655 gpm 0.92 mgd 0.93 mgd 0.94 mgd 59% 89% 80% 82% 41% 2 gpm 11% 5 gpm 20% 9 gpm 18% 0 gpm 50% 1 0 gpm 4 0 0 Oak Hollow or Gravity Asbuilts show 8", 2D06 FM records show as 12"; Need to confirm 12" 28 3+87.00 836.20 830.00 830.00 0.00 6.20 -137.00 0.2D% 9 0 0 Oak Hollow or 27 +00.00 842.20 828.99 828.38 0.61 13.82 -387.00 0.26% 18 0 0 oak Hollow or Stationing Changes at SSMH: Sta 0+00 U/P = Sta 26+32.13 D/S 26A 25+75.13 838.00 828.24 827.99 0.25 10.01 -57.00 0.25% 12.00 in 795 gpm 1.14 mgd 655 gpm 0.94 mgd 139 gpm 0.20 mgd 0 0 0 x-Country 26B 24+64.63 831.20 827.25 827.25 0.00 3.95 -110.50 0.67% 12.00 in 1,312 gpm 1.89 mgd 655 gpm 0.94 mgd 656 gpm 0.94 mgd 50% 0 0 0 X-Country Slope is labeled 0.50% in profile but based on stationing & inverts it is not 26C 22+84.63 835.00 826.34 826.34 0.00 8.66 -180.00 0.51% 12.00 in 1,140 gpm 1.64 mgd 655 gpm 0.94 mgd 484 gpm 0.70 mgd 58% 42% 0 gpm 0 0 0 X-country 26 20+96.71 838.90 825.40 825.40 0.D0 13.50 -187.92 0.50% 12.00 in 1,134 gpm 1.63 mgd 659 gpm 0.95 mgd 475 gpm 0.68 mgd 58% 42% 4 gpm 7 0 0 Dantzler Ct ' dantzler court to oak hollow IV 43-59 pg 11 25 18+09.69 829.20 823.84 823.84 0.00 5.36 -287.02 0.54% 12.00 in 1,182 gpml 1.70 mgd 661 gpm 0.95 mgd 521 gpm 0.75 mgd 56% 44% 2 gpm 4 0 0 Dantzler Ct @ Dantzler Rd 24 15+69.99 832.50 823.24 823.24 0.D0 9.26 -239.70 0.25% 12.00 in 802 gpm 1.15 mgd 664 gpm 0.96 mgd 138 gpm 0.20 mgd 83% 17% 3 gpm 6 01 0 Dantzler Rd 23 11+70.22 836.20 822.24 822.24 0.00 13.96 -399.77 0.25% 12.00 in 802 gpm 1.15 mgd 669 gpm 0.96 mgd 133 gpm 0.19 mgd 83% 17% 5 gpm 9 0 0 Dantzler Rd @ La Vera St 22 9+65.22 833.00 821.72 821.72 0.00 11.28 -205.00 0.25% 12.00 in 807 gpm 1.16 mgd 672 gpm 0.97 mgd 136 gpm 0.20 mgd 83% 17% 3 gpm 6 0 0 La Vera St @ San Fernando Dr 21 8+51.03 840.00 821.44 821.44 0.00 18.56 -114.19 0.25% 12.00 in 794 gpm 1.14 mgd 672 gpm 0.97 mgd 121 gpm 0.17 mgd 85% 15% 1 gpm 1 0 0 San Fernando Dr IV-41 20 6+91.68 848.50 821.04 821.04 0.00 27.46 -159.35 0.25% 12.00 in 803 gpm 1.16 mgd 674 gpm 0.97 mgd 129 gpm 0.19 mgd 84% 16% 2 gpm 3 0 0 San Fernando or IV-41 19 4+35.65 840.50 820.40 820.40 0.00 20.10 -256.03 0.25% 12.00 in 802 gpm 1.15 mgd 674 gpm 0.97 mgd 128 gpm 0.18 mgd 84% 16% 0 gpm 01 0 0 x-country IV-41 18 2+04.35 825.00 819.54 819.54 0.00 5.46 -231.30 0.37% 12.00 in 978 gpm 1.41 mgd 674 gpm 0.97 mgd 303 gpm 0.44 mgd 69% 31% 1 gpm 1 0 0 x-country IV-41 17 +00.00 822.50 818.35 817.95 0.40 4.55 -204.35 0.58% 12.00 in 1,223 gpm 1.76 mgd 733 gpm 1.06 mgd 490 gpm 0.71 mgd 60% 40% 59 gpm 114 0 0 X-country IV-37, IV-41,Stationing Changes at SSMH: Sta 0+00 U/P = Sta 9+38.42 D/S 16 5+36.07 824.50 816.74 816.74 0.00 7.76 -402.35 0.3D% 12.00 in 879 gpm 1.27 mgd 733 gpm 1.06 mgd 146 gpm 0.21 mgd 83% 17% 0 gpm 0 0 0 x-country IV-37 15 1+97.97 828.00 815.73 815.73 0.00 12.27 -338.10 0.30% 12.00 in 876 gpm 1.26 mgd 733 gpm 1.06 mgd 143 gpm 0.21 mgd 84% 16% 0 gpm 0 0 0 X-country IV-37 14 +00.00 828.60 815.14 815.14 0.D0 13.46 -197.97 0.30% 12.00 in 875 gpm 1.26 mgd 753 gpm 1.08 mgd 122 gpm 0.18 mgd 86% 14% 20 gpm 39 0 0 La Vista or @ Ponce De Leon Dr IV-37,IV-59; Stationing Changes at SSMH: Sta 0+00 U/P = Sta 9+38.00 D/S 13 6+85.00 828.70 814.52 814.52 0.D0 14.18 -253.00 0.25% 12.00 in 794 gpm 1.14 mgd 757 gpm 1.09 mgd 37 gpm 0.05 mgd 95% 5% 4 gpm 7 0 0 Ponce DeLeon or IV-59 12 3+30.00 832.00 813.65 813.65 0.00 18.35 -355.00 0.25% 12.00 in 794 gpm 1.14 mgd 759 gpm 1.09 mgd 35 gpm 0.05 mgd 96% 4% 2 gpm 4 0 0 Ponce De Leon or IV-59 11 +00.00 832.83 812.84 812.84 0.00 19.99 -330.00 0.25% 12.00 in 794 gpm 1.14 mgd 768 gpm 1.11 mgd 26 gpm 0.04 mgd 97% 3% 10 gpm 19 0 0 Ponce De Leon Or @ Oak Hollow Dr Stationing Changes at SSMH: Sta 0+00 U/P = Sta 32+86.60 D/S 10 30+52.12 814.50 811.97 811.97 0.00 2.53 -234.48 0.37% 12.00 in 977 gpm 1.41 mgd 768 gpm 1.11 mgd 208 gpm 0.30 mgd 79% 21% 0 gpm 0 0 0 x-country IV-36 9 29+50.79 813.00 811.74 811.74 0.D0 1.26 -101.33 0.23% 12.00 in 764 gpm 1.10 mgd 768 gpm 1.11 mgd -5 gpm -0.01 mgd 101% -1% 0 gpm 0 0 0 X-country IV-36 8 26+00.63 817.00 810.97 810.97 0.00 6.03 -350.16 0.22% 12.00 in 752 gpm 1.08 mgd 768 gpm 1.11 mgd -17 gpm -0.02 mgd 102% -2% 0 gpm 0 0 0 X-country IV-36 7 23+37.23 814.50 810.49 810.49 0.00 4.01 -263.40 0.18% 12.00 in 684 gpm 0.99 mgd 768 gpm 1.11 mgd -84 gpm -0.12 mgd 112% -12% 0 gpm 0 0 0 X-country IV-36 6 21+29.28 813.50 810.03 810.03 0.00 3.47 -207.95 0.22% 12.00 in 754 gpm 1.09 mgd 768 gpm 1.11 mgd -14 gpm -0.02 mgd 102% -2% 0 gpm 0 0 0 x-country IV-36 5 18+42.73 813.50 809.24 809.24 0.00 4.26 -286.55 0.28% 12.00 in 842 gpm 1.21 mgd 768 gpm 1.11 mgd 73 gpm 0.11 mgd 91% 9% 0 gpm 0 0 0 X-country 4 14+84.68 814.50 808.34 807.001 1.34 7.50 -358.05 0.25% 12.00 in 804 gpm 1.16 mgd 778 gpm 1.12 mgd 26 gpm 0.04 mgd 97% 3% 10 gpm 19 0 0 X-country 3 12+30.05 808.00 805.43 805.43 0.00 2.57 -254.63 0.62% 12.00 in 1,259 gpm 1.81 mgd 789 gpm 1.14 mgd 469 gpm 0.68 mgd 63% 37% 11 gpm 22 0 0 X-country 2 10+00.00 807.00 804.00 804.00 0.00 3.00 -230.05 0.62% 12.00 in 1,264 gpm 1.82 mgd 789 gpm 1.14 mgd 474 gpm 0.68 mgd 62% 38% 0 gpm 0 0 0 X-Country 1 9+10.00 807.30 801.24 801.00 0.24 6.30 -90.00 3.07% 12.00 in 2,807 gpm 4.04 mgd 789 gpm 1.14 mgd 2,018 gpm 2.90 mgd 28% 72% 0 gpm 0 01 0 x-country La Salle Siphon Influent Box 0 2+81.75 810.00 787.80 787.80 0.00 22.20 -628.25 789 gpm 1.14 mgd 0 gpm 0 0 0 La Salle Siphon Effluent Box WEST TO LAKE FOREST (SIPHON FLOW) 2 2+81.75 810.00 787.801 787.80 0.00 22.20 281.75 789 gpm 1.14 mgd 789 gpm 1351 3680 0 Lake Forest Access Rd Equals Total Connections from Siphon Calculated Above 1 2+69.75 810.00 788.001 788.00 0.00 22.00 -12.00 -1.67% 12.00 in 2,070 gpm 2.98 mgd 789 gpm 1.14 mgd 1,280 gpm 1.84 mgd 38% 62% 0 gpm 0 0 O Lake Forest Access Rd No invert out listed in record, assuming equals inv in from siphon 788.00 EAST TO LAKE FOREST (NON -SIPHON FLOW) 2 1+74.00 810.00 801.37 801.27 0.10 8.73 174.00 645 gpm 0.93 mgd 645 gpm 857 0 30 Lake Forest Access Rd 857 Residential Connections, 57 Commercial Properties 1 +00.00 810.00 800.40 788.00 12.40 22.00 -174.00 0.50% 12.00 in 1,134 gpm 1.63 mgd 645 gpm 0.93 mgd 489 gpm 0.70 mgd 57% 43% 0 gpm 0 0 0 Lake Forest Access Rd No invert out listed in record, assuming equals inv in from siphon 788.00 TO LAKE FOREST (COMBINED EST & WEST FLOWS) 1 1 +25.001 810.001 788.001 788.001 0.001 22.001 25.001 1,434 gpm 2.06 mgd 1,434 gpm 2208 3680 30 Lake Forest PS Equals Connections from East and West Calculated Above 0 1 +00.001 810.801 787701 1 787.701 810.80 -25.001 1.20% 36.00 in 32,877 gpm 47.33mgdl 1,434 gpm 2.06 mgd 31,443 gpm 45.26 mgd 4% 96% 0 gpm 01 01 0 1 Lake Forest PS Lake Forest Wet Well, bot = 783, pump off 785, HWLA=787.7, top 810.8 Residential Peaking Factor N/A Residential Flow Per Connection: 0.513436 gpm/connection of peak hourly flow Schools Peaking Factorl 2.5 School Flow Per Student: 0.026042 gpm/connection of peak hourly flow Commerical Flow Per Connection: 6.833333 gpm/connection of peak hourly flow Manning n = 0.013 Dewberry APPENDICES 31 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Appendix B Siphon Capacity Calculations '•.� Dewberry RECOMMENDATIONS 32 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX B - SIPHON CAPACITY CALCULATIONS Headloss/Capacity Calculation for Siphons/Pressure Sewer Flow (gpd) 532,800 To determine max capacity between two elements, Flow (gpm) 370 GOAL SEEK by setting cell E35 to B8 value by Flow (cfs) 0.8 changing B3 value Discharge Exit Elevation 788.47 Upstream Entrance Elevation 801.0 Available Head (ft) 12.53 C Factor (for pipe) Pipe Segment Diameter (in) Quantity K factor (for fittings) Head Loss (ft) Velocity (fps) Pipe 6 628 feet 100 12.0 4.20 Rounded Entrance 6 1 0.25 0.1 4.20 11.25 Degree Bend 6 0 0.04 0.0 4.20 22.5 Degree Bend 6 0 0.05 0.0 4.20 45 Degree Bend 6 0 0.20 0.0 4.20 90 Degree Bend 6 0 0.30 0.0 4.20 90 Degree Long Radius Bend 6 0 0.20 0.0 4.20 90 Degree Reducing Elbow 6 0 0.05 0.0 4.20 Plug - Eccentric - full bore 6 0 0.50 0.0 4.20 Knife Gate Valve - Metal Seat 6 0 0.20 0.0 4.20 Gate Valve - Resileant Seat 6 0 0.30 0.0 4.20 Wye Scenario 1 6 0 0.75 0.0 4.20 Wye Scenario 2 6 0 0.50 0.0 4.20 Wye Scenario 3 6 0 3.00 0.0 4.20 Wye Scenario 4 6 0 0.30 0.0 4.20 Wye Scenario 5 6 0 0.50 0.0 4.20 Standard Tee - Straight thru 6 0 0.30 0.0 4.20 Standard Tee - Run to Side Outlet 6 0 0.75 0.0 4.20 Standard Tee - Side Outlet 6 0 0.50 0.0 4.20 Still Water Exit 6 1 1.00 0.3 4.20 Reducer 6 0 0.25 0.0 4.20 other 6 0 feet 100 0.0 4.20 628 feet Total Head Loss Through Systeml 12.3 The following equation calculates and overall Manning 'n' value which includes the pipe and fittings hf = 4.66 n2 Length Q2 / Diam 16/3 based upon Q in cfs, and diameter in feet Resultant n value = 0.0124 Dewberry APPENDICES 33 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX B - SIPHON CAPACITY CALCULATIONS Headloss/Capacity Calculation for Siphons/Pressure Sewer Flow (gpd) 1,137,600 To determine max capacity between two elements, Flow (gpm) 790 GOAL SEEK by setting cell E35 to B8 value by Flow (cfs) 1.8 changing B3 value Discharge Exit Elevation 788.47 Upstream Entrance Elevation 801.0 Available Head (ft) 12.53 C Factor (for pipe) Pipe Segment Diameter (in) Quantity K factor (for fittings) Head Loss (ft) Velocity (fps) Pipe 8 628 feet 100 12.0 5.05 Rounded Entrance 8 1 0.25 0.1 5.05 11.25 Degree Bend 8 0 0.04 0.0 5.05 22.5 Degree Bend 8 0 0.05 0.0 5.05 45 Degree Bend 8 0 0.20 0.0 5.05 90 Degree Bend 8 0 0.30 0.0 5.05 90 Degree Long Radius Bend 8 0 0.20 0.0 5.05 90 Degree Reducing Elbow 8 0 0.05 0.0 5.05 Plug - Eccentric - full bore 8 0 0.50 0.0 5.05 Knife Gate Valve - Metal Seat 8 0 0.20 0.0 5.05 Gate Valve - Resileant Seat 8 0 0.30 0.0 5.05 Wye Scenario 1 8 0 0.75 0.0 5.05 Wye Scenario 2 8 0 0.50 0.0 5.05 Wye Scenario 3 8 0 3.00 0.0 5.05 Wye Scenario 4 8 0 0.30 0.0 5.05 Wye Scenario 5 8 0 0.50 0.0 5.05 Standard Tee - Straight thru 8 0 0.30 0.0 5.05 Standard Tee - Run to Side Outlet 8 0 0.75 0.0 5.05 Standard Tee - Side Outlet 8 0 0.50 0.0 5.05 Still Water Exit 8 1 1.00 0.4 5.05 Reducer 8 0 0.25 0.0 5.05 other 8 0 feet 100 0.0 5.05 628 feet Total Head Loss Through System 1 12.5 The following equation calculates and overall Manning 'n' value which includes the pipe and fittings hf = 4.66 n2 Length Q2 / Diaml6/3 based upon Q in cfs, and diameter in feet Resultant n value = 0.0126 Dewberry APPENDICES 34 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Appendix C Opinion Of Probable Construction Cost - Alternative 1 Dewberry RECOMMENDATIONS 35 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX C - OPCC - ALTERNATIVE 1 CONSTRUCT A NEW PUMPING STATION Quantity No. Basis Description Unit Cost Total Cost Units ARCHITECTURAL Replace Door 1 LS $ 7,000 $ 7,000 $ 7,000 CIVIL Ex Sewage PS Demolition 1 LS $ 20,000 $ 20,000 8" DIP Force Main 100 LF $ 200 $ 20,000 8" Plug Valve w/ Valve Box 1 EA $ 4,500 $ 4,500 Fittings 550 LBS $ 12 $ 6,600 8" Coupling 1 EA $ 2,500 $ 2,500 15" PVC Gravity Sewer 150 LF $ 175 $ 26,000 8" PVC Gravity Sewer 100 LF $ 150 $ 15,000 SSMH, 5' ID, 12'-14' Depth 3 EA $ 11,000 $ 33,000 Yard Hydrant 1 EA $ 1,500 $ 1,500 2" PE Water Service 100 LF $ 45 $ 4,500 Temporary Sewage Bypass Pumping 1 LS $ 10,000 $ 10,000 Clearing and Grubbing 1 LS $ 1,000 $ 1,000 Chain -Link Fence 400 LF $ 80 $ 32,000 Bollard 6 EA $ 800 $ 4,800 Unsuitable Material Excavation and Backfill with No. 57 Ston 20 CY $ 75 $ 1,500 Rock Excavation (Mechanical) 75 CY $ 400 $ 30,000 Gravel Driveway Restoration 960 SY $ 30 $ 29,000 Combination Air Relief and Vacuum Relief Valve Assembly 1 EA $ 15,000 $ 15,000 Emergency Bypass Pumping Connection 1 EA $ 15,000 $ 15,000 10' Diameter Wet Well 1 EA $ 70,000 $ 70,000 Valve Vault 1 EA $ 20,000 $ 20,000 Wet Well - Epoxy Coating 800 SF $ 60 $ 48,000 Tapping Sleeve and Valve Assembly 1 LS $ 4,500 $ 4,500 8-inch Insert Valve 1 LS $ 4,000 $ 4,000 Asphalt Paving 50 TON $ 250 $ 13,000 ABC Roadway Subbase 80 TON $ 40 $ 3,200 Silt Fence 900 LF $ 5 $ 4,500 $ 439,000 MECHANICAL Submersible Sewage Pumps (75 HP) with Rails & Base 1 EA $ 164,000 $ 160,000 Valve Vault - Plug Valve 2 EA $ 3,500 $ 7,000 Valve Vault - Check Valve 2 EA $ 10,000 $ 20,000 Valve Vault - Piping (including Fittings) 15 LF $ 150 $ 2,300 Wet Well Piping 60 LF $ 250 $ 15,000 Replace HVAC System 1 EA $ 30,000 $ 30,000 Sump Pump for FM Meter Vault 1 LS $ 3,000 $ 3,000 1-ton Jib Crane 1 LS $ 25,000 $ 25,000 2C $ 2,000 Dewberry APPENDICES 36 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX C - OPCC - ALTERNATIVE 1 CONSTRUCT A NEW PUMPING STATION Quantity Description No. Units Basis Unit Cost Total Cost STRUCTURAL Concrete Equipment Pad - New Generator 2 CY $ 2,000 $ 4,000 Jib Crane Support 2 CY $ 1,000 $ 2,000 $ 6,000 ELECTRICAL Demolition 1 LS $ 3,000 $ 3,000 Service Entrance (300A, N4X) 1 EA $ 22,500 $ 23,000 ATS (480V, 300A, N12) 1 EA $ 30,000 $ 30,000 New Generator (200kW) 1 EA $ 225,000 $ 230,000 VFDs (480V, 75hp, N12) 2 EA $ 42,188 $ 84,000 480V Panelboard 1 EA $ 15,000 $ 15,000 Lighting Panelboard Transformer 1 EA $ 5,250 $ 5,300 120V Panelboard 1 EA $ 7,500 $ 7,500 Lighting 4 LS $ 1,688 $ 6,800 Grounding 1 LS $ 15,000 $ 15,000 Conduit & Wire & Duct Bank 1 LS $ 100,000 $ 100,000 Misc. Electrical 1 LS $ 65,000 $ 65,000 $ 685,000 I&C Demolition 1 LS $ 2,000 $ 2,000 Pump Control Panel 1 EA $ 50,000 $ 50,000 Telemetry 1 EA $ 30,000 $ 30,000 Instruments 1 EA $ 10,000 $ 10,000 92,000 ALLOWANCES 3rd Party Testing 1 LS $ 15,000 $ 15,000 $ 15,000 Subtotal $ 1,406,000 Mobilization 5% $ 70,000 General Conditions 10% $ 141,000 Contingency 30% $ 422,000 Total Opinion of Probable Construction Cost $ 2,100,000 AACE Class 4 Capital Cost Range: Low -20% $ 1,700,000 High 20% $ 2,500,000 Dewberry APPENDICES 37 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Appendix D Opinion Of Probable Construction Cost - Alternative 2 Dewberry RECOMMENDATIONS 38 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX D - OPCC - ALTERNATIVE 2 CONVERT EXISTING WET WELL TO A SUBMERSIBLE PUMPING STATION Quantity No. Units Basis Description Unit Cost Total Cost ARCHITECTURAL Replace Door 1 LS $ 7,000 $ 7,000 $ 7,000 CIVIL Ex Sewage PS Demolition 1 LS $ 15,000 $ 15,000 Ex Conc Fillet Demolition 1 LS $ 7,000 $ 7,000 15" PVC Gravity Sewer 30 LF $ 400 $ 12,000 8" DIP Force Main 80 LF $ 200 $ 16,000 8" Plug Valve w/ Valve Box 1 EA $ 4,500 $ 4,500 Fittings 550 LBS $ 12 $ 6,600 8" Coupling 1 EA $ 2,500 $ 2,500 Temporary Sewage Bypass Pumping 1 LS $ 150,000 $ 150,000 Bollard 6 EA $ 800 $ 4,800 Unsuitable Material Excavation and Backfill with No. 57 Stone 5 CY $ 75 $ 380 Gravel Driveway Restoration 960 SY $ 30 $ 29,000 Combination Air Relief and Vacuum Relief Valve Assembly 1 EA $ 12,000 $ 12,000 Emergency Bypass Pumping Connection 1 EA $ 15,000 $ 15,000 Valve Vault 1 EA $ 20,000 $ 20,000 Wet Well - Epoxy Coating 800 SF $ 60 $ 48,000 Tapping Sleeve and Valve Assembly 1 LS $ 4,500 $ 4,500 8-inch Insert Valve 1 LS $ 5,000 $ 5,000 Asphalt Paving 50 TON $ 250 $ 13,000 ABC Roadway Subbase 80 TON $ 40 $ 3,200 Silt Fence 900 LF $ 5 $ 4,500 $ 373,000 MECHANICAL Submersible Sewage Pumps (75 HP) with Rails & Base 1 EA $ 164,000 $ 160,000 Valve Vault - Plug Valve 2 EA $ 2,500 $ 5,000 Valve Vault - Check Valve 2 EA $ 10,000 $ 20,000 Valve Vault - Piping (including Fittings) 15 LF $ 150 $ 2,300 Wet Well Piping 60 LF $ 150 $ 9,000 Replace HVAC System 1 EA $ 30,000 $ 30,000 Sump Pump for FM Meter Vault 1 LS $ 3,000 $ 3,000 1-ton Jib Crane 1 LS $ 25,000 $ 25,000 $ 254,000 STRUCTURAL Replace Wet Well Top and Add Hatch 1 LS $ 12,000 $ 12,000 Concrete Equipment Pad - New Generator 2 CY $ 1,000 $ 2,000 Jib Crane Support 2 CY $ 700 $ 1,400 $ 16,000 Dewberry APPENDICES 39 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX D - OPCC - ALTERNATIVE 2 CONVERT EXISTING WET WELL TO A SUBMERSIBLE PUMPING STATION Quantity No. Units Basis Description Unit Cost Total Cost ELECTRICAL Demolition 1 LS $ 17,000 $ 17,000 Service Entrance (300A, N4X) 1 EA $ 22,500 $ 23,000 ATS (48OV, 300A, N12) 1 EA $ 30,000 $ 30,000 New Generator (200kW) 1 EA $ 225,000 $ 230,000 VFDs (480V, 75hp, N12) 2 EA $ 42,188 $ 84,000 480V Panelboard 1 EA $ 15,000 $ 15,000 Lighting Panelboard Transformer 1 EA $ 5,250 $ 5,300 120V Panelboard 1 EA $ 7,500 $ 7,500 Lighting 4 LS $ 1,688 $ 6,800 Grounding 1 LS $ 15,000 $ 15,000 Conduit & Wire & Duct Bank 1 LS $ 100,000 $ 100,000 Misc. Electrical 1 LS $ 65,000 $ 65,000 $ 599,000 I&C Demolition 1 LS $ 2,000 $ 2,000 Pump Control Panel 1 EA $ 50,000 $ 50,000 Telemetry 1 EA $ 30,000 $ 30,000 Instruments 1 EA $ 10,000 $ 10,000 $ 92,000 ALLOWANCES 3rd Party Testing 1 LS $ 5,000 $ 5,000 $ 5,000 Subtotal $ 1,346,000 Mobilization 5% $ 67,000 General Conditions 10% $ 135,000 Contingency 30% $ 404,000 Total Opinion of Probable Construction Cost $ 2,000,000 AACE Class 4 Capital Cost Range: Low _20% $ 1,600,000 High 20% $ 2,400,000 Dewberry APPENDICES 40 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Appendix E Opinion Of Probable Construction Cost - Alternative A Dewberry RECOMMENDATIONS 41 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX E - OPCC - ALTERNATIVE A UPSIZE GRAVITY SEWER Quantity No. Units Basis Description Unit Cost Total Cost CIVIL Ex Gravity Sewer Pipe Abandonment 150 CY $ 300 $ 45,000 Ex Sanitary Sewer Manhole Abandonment 34 EA $ 1,500 $ 51,000 Clearing and Grubbing 1 AC $ 5,000 $ 5,000 Unsuitable Material Excavation and Backfill with No. 57 Stone 575 CY $ 75 $ 43,000 Rock Excavation (Mechanical) 300 CY $ 400 $ 120,000 Asphalt Paving - Trench Restoration 210 TON $ 250 $ 53,000 ABC Roadway Subbase 420 TON $ 40 $ 17,000 Discharge Manhole - Epoxy Coating 300 SF $ 35 $ 11,000 15" PVC Gravity Sewer 5,815 LF $ 175 $ 1,000,000 15" DI Gravity Sewer 1,435 LF $ 200 $ 290,000 SSMH, 4' ID, 0'-6' Depth 9 EA $ 5,000 $ 45,000 SSMH, 4' ID, 6.01-8' Depth 6 EA $ 5,500 $ 33,000 SSMH, 4' ID, 8.01-10' Depth 2 EA $ 6,000 $ 12,000 SSMH, 4' ID, 10.01-12' Depth 2 EA $ 6,500 $ 13,000 SSMH, 4' ID, 12.01-14' Depth 5 EA $ 7,000 $ 35,000 SSMH, 4' ID, 14.01-16' Depth 1 EA $ 7,500 $ 7,500 SSMH, 4' ID, 16.01-18' Depth 0 EA $ - $ - SSMH, 4' ID, 18.01-20' Depth 3 EA $ 8,500 $ 26,000 SSMH, 4' ID, 20.01+' Depth 2 EA $ 12,000 $ 24,000 Silt Fence 9,900 LF $ 5 $ 50,000 Silt Fence Outlet 15 EA $ 150 $ 2,300 Class 2 Rip Rap 100 SY $ 75 $ 7,500 Rolled Erosion Matting 16,500 SY $ 5 $ 83,000 Wattles 165 EA $ 100 $ 17,000 Dewatering Silt Bag 2 EA $ 2,000 $ 4,000 Construction Entrance 2 EA $ 2,600 $ 5,200 Temp Stream Crossing 5 EA $ 10,000 $ 50,000 $ 2,050,000 ALLOWANCES 3rd Party Testing 1 LS $ 45,000 $ 45,000 $ 45,000 Subtotal $ 2,095,000 Mobilization 5% $ 105,000 General Conditions 5% $ 105,000 Contingency 30% $ 629,000 Total Opinion of Probable Construction Cos $ 3,000,000 AACE Class 4 Capital Cost Range: Low -20% $ 2,400,000 High 20% $ 3,600,000 Dewberry APPENDICES 42 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Appendix F Opinion Of Probable Construction Cost - Alternative B Dewberry RECOMMENDATIONS 43 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX F - OPCC - ALTERNATIVE B NEW FORCE MAIN ALONG LAKE Quantity No. Units Basis Description Unit Cost Total Cost CIVIL 10" PVC Force Main 5,075 LF $ 90 $ 460,000 10" DI Force Main 500 LF $ 110 $ 55,000 10" HDD Force Main 2,065 LF $ 225 $ 460,000 Fittings 2,000 LBS $ 5 $ 10,000 Clearing and Grubbing 20 AC $ 5,000 $ 100,000 Unsuitable Material Excavation and Backfill with No. 57 Stone 250 CY $ 75 $ 19,000 Rock Excavation (Mechanical) 125 CY $ 400 $ 50,000 Asphalt Paving - Trench Restoration 5 TON $ 250 $ 1,300 ABC Roadway Subbase 10 TON $ 40 $ 400 Combination Air Relief and Vacuum Relief Valve Assembly 4 EA $ 12,000 $ 48,000 Discharge Manhole - Epoxy Coating 225 SF $ 35 $ 7,900 Silt Fence 11,160 LF $ 5 $ 56,000 Silt Fence Outlet 15 EA $ 150 $ 2,300 Class 2 Rip Rap 150 SY $ 75 $ 11,000 Rolled Erosion Matting 12,390 SY $ 5 $ 62,000 Wattles 190 EA $ 100 $ 19,000 Dewatering Silt Bag 2 EA $ 2,000 $ 4,000 Construction Entrance 5 EA $ 2,600 $ 13,000 Temp Stream Crossing 4 EA $ 10,000 $ 40,000 $ 1,419,000 ALLOWANCES 3rd Party Testing 1 LS $ 15,000 $ 15,000 $ 15,000 Subtotal $ 1,434,000 Mobilization 5% $ 72,000 General Conditions 5% $ 72,000 Contingency 30% $ 430,000 Total Opinion of Probable Construction Cos $ 2,100,000 AACE Class 4 Capital Cost Range: Low -20% $ 1,700,000 High 20% $ 2,500,000 Dewberry APPENDICES 44 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Appendix G Opinion Of Probable Construction Cost - Alternative C Dewberry RECOMMENDATIONS 45 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX G - OPCC - ALTERNATIVE C NEW FM PARALLEL TO EXISTING GRAVITY SEWER Quantity No. Units Basis Description Unit Cost Total Cost CIVIL 10" PVC Force Main 5,000 LF $ 120 $ 600,000 10" DI Force Main 500 LF $ 150 $ 75,000 Fittings 4,000 LBS $ 5 $ 20,000 Clearing and Grubbing 1 LS $ 2,500 $ 2,500 Unsuitable Material Excavation and Backfill with No. 57 Stone 245 CY $ 75 $ 18,000 Rock Excavation (Mechanical) 125 CY $ 400 $ 50,000 Asphalt Paving - Trench Restoration 305 TON $ 250 $ 76,000 ABC Roadway Subbase 610 TON $ 40 $ 24,000 ABC Access Road 70 TON $ 40 $ 2,800 Combination Air Relief and Vacuum Relief Valve Assembly 4 EA $ 12,000 $ 48,000 Discharge Manhole - Epoxy Coating 225 SF $ 35 $ 7,900 Silt Fence 2,150 LF $ 5 $ 11,000 Silt Fence Outlet 5 EA $ 150 $ 750 Class 2 Rip Rap 100 SY $ 75 $ 7,500 Rolled Erosion Matting 3,583 SY $ 5 $ 18,000 Wattles 36 EA $ 100 $ 3,600 Dewatering Silt Bag 4 EA $ 2,000 $ 8,000 Construction Entrance 1 EA $ 2,600 $ 2,600 Traffic Control 1 LS $ 30,000 $ 50,000 $ 1,026,000 ALLOWANCES 3rd Party Testing 1 EA $ 45,000 $ 45,000 $ 45,000 Subtotal $ 1,071,000 Mobilization 5% $ 54,000 General Conditions 5% $ 54,000 Contingency 30% $ 321,000 Total Opinion of Probable Construction Cost $ 1,500,000 AACE Class 4 Capital Cost Range: Low -20% $ 1,200,000 High 20% $ 1,800,000 Dewberry APPENDICES 46 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES Appendix H Opinion Of Probable Construction Cost - La Salle Drive Siphon Dewberry RECOMMENDATIONS 47 PRELIMINARY ENGINEERING REPORT WHITES MILL SEWAGE PUMPING STATION UPGRADES APPENDIX H - OPINION OF PROBABLE CONSTRUCTION COST LA SALLE DRIVE SIPHON tity Description No. Basis Unit Cost Total Cost Units CIVIL 15-inch PVC Gravity Sewer 320 LF $ 150 $ 48,000 SSMH, 4' ID, 0'-6' Depth 2 EA $ 5,000 $ 10,000 SSMH, 5' ID, 0'-6' Depth 1 EA $ 9,000 $ 9,000 8-inch DI Siphon Pipe (Ball and Socket Joint) Protecto 401 680 LF $ 160 $ 110,000 8" M-Flex Coupling 7 EA $ 3,732 $ 25,000 Clearing and Grubbing 1 AC $ 7,670 $ 7,700 Driveway Curb Cut 1 EA $ 3,000 $ 3,000 Gravel Access Road (6" ABC) 800 CY $ 50 $ 40,000 Silt Fence 1,650 LF $ 5 $ 8,300 Silt Fence Outlet 4 EA $ 150 $ 600 Rolled Erosion Matting 2,670 SY $ 5 $ 13,000 Dewatering Silt Bag 1 EA $ 2,000 $ 2,000 Construction Entrance 1 EA $ 2,600 $ 2,600 Precast Concrete Grinder Vault 1 EA $ 12,000 $ 12,000 Fence 80 LF $ 70 $ 5,600 Clean Siphon 680 LF $ 10 $ 6,800 Solids Disposal 1 TON $ 500 $ 500 Inspect Siphon 680 LF $ 30 $ 20,000 $ 324,000 MECHANICAL Muffin Monster (Model #30005-024) 1 EA $ 94,900 $ 95,000 1-ton Jib Crane 1 EA $ 16,300 $ 16,000 $ 111,000 STRUCTURAL Electrical Equipment Pad 2 CY $ 700 $ 11400 Jib Crane Support 2 CY $ 700 $ 1,400 $ 3,000 ELECTRICAL Service Entrance Panelboard 1 EA $ 14,375 $ 14,000 Conduit & Wire & Duct Bank 1 LS $ 17,250 $ 17,000 Canopy/Equipment Rack 1 EA $ 9,200 $ 9,200 Misc. Electrical 1 LS $ 5,750 $ 5,800 $ 46,000 I&C SCADA & RTU 1 EA $ 15,000 $ 15,000 15,000 EASEMENTS 20' Wide Access Easement - 3900 La Salle Dr 2,865 SF $ 3 $ 8,600 30' Wide Temporary Construction Easement - 3900 La Salle Dr 4,185 SF $ 2 $ 8,400 $ 17,000 Subtotal $ 516,000 Mobilization 5% $ 26,000 General Conditions 5% $ 26,000 Contingency 30% $ 155,000 Total Opinion of Probable Construction Cost $ 800,000 AACE Class 4 Capital Cost Range: Low -20% $ 600,000 High 20% $ 1,000,000 Dewberry APPENDICES 48 APPENDIX II WHITES MILL SEWAGE PUMPING STATION UPGRADES PUMP STATION CALCULATIONS • ,Ron � ►,•••,, ew err Wastewater Lift Station Force Main Design Calculations Project Name: Whites Mill Sewage Pumping Station Upgrades Location: High Point, NC Designed By: Parrott Hood, El Checked By: Stephen Buchanan, PE Date: July 18, 2023 Project/GWO No.: 50155072 Wastewater Lift Station Force Main Project Summary Project Name: Average Daily Flow (gpd): Pump Operational Point No. 1 (flow@tdh) Pump Manufacturer: Model Number: Impeller Diameter: Horse Power: Voltage: Force Main Diameter (in): Force Main Length (ft): Whites Mill Sewage Pumping Station Upgrades 430,560 1056gpm @ 124ft Flygt NP 3202 HT3-458 310 mm 70 460 10 7,630 2 Wastewater Flow Calculations Establishment Unit Value (Gal/Day /Unit) Unit Type # of Units Discharge GPD Residential (To NEWWTF) 360 Residence 0 0 Residential (all other Treatment Facilities) 210 Residence 0 0 Barber Shops 50 Chair 0 0 Beauty Shops 125 Booth or Bowl 0 0 Business - General & Office 25 Employee per shift 0 Business - Factories Excluding Industrial Waste 25 Employee per shift 0 0 Business or Factories w/showers or food preparation 35 Employee per shift 0 0 Business - Warehouse 100 Loading bay 0 0 Business - Warehouse Self Storage (not including Caretaker Residence) 1 Unit 0 0 Churches without kitchens, day care, or camps 3 Seat 0 0 Churches with kitchens 5 Seat 0 0 Churches providing day care or camp 25 Person (child+employee) 0 0 Fire or Rescue without on -site staff 25 Person 0 0 Fire or Rescue with on -site staff 50 Person per shift 0 0 Food & Drink - Banquet Dining Hall 30 Seat 0 0 Food & Drink - Bars, Cocktail Lounges 20 Seat 0 0 Food & Drink - Caterers 50 100 sf floor space 0 0 Food & Drink - Restaurants, Full Service 40 Seat 0 0 Food & Drink - Restaurants, Single Service Articles 20 Seat 0 0 Food & Drink - Restaurants, Drive-in 50 car space 0 0 Food & Drink - Restaurants, Carry out only 50 100 sf floor space 0 0 Food & Drink - Institutions, Dining Halls 5 meal 0 0 Food & Drink - Deli 40 100 sf floor space 0 0 Food & Drink - Bakery 10 100 sf floor space 0 0 Food & Drink - Meat Dept., Butcher, Fish Market 75 100 sf floor space 0 0 Food & Drink - Specialty Food Stand or Kiosk 50 100 sf floor space 0 0 Hotels/Motels/B&B without in -room cooking facilities 120 Room 0 0 Hotels/Motels/B&B with in -room cooking facilities 175 Room 0 0 Hotels/Motels- Resort Hotels 200 Room 0 0 Hotels/Motels- Cottages, Cabins 200 Unit 0 0 Laundries (Self -Service) 500 Machine 0 0 Medical or Dental offices 250 Practitioner per shift 0 0 Medical - Veterinary offices without boarding 250 Practitioner per shift o 0 Medical - Veterinary, Kennels, with boarding 20 Pen, Cage, Kennel, Stall 0 0 Medical - Medical Hospitals 300 Bed 0 0 Medical - Mental Hospitals 150 Bed 0 0 Medical - Convalescent, Nursing, Rest Homes without Laundry 60 Bed 0 0 Medical - Convalescent, Nursing, Rest Homes w/ Laundry 120 Bed 0 0 Medical - Residential Care Facilities 60 Person 0 0 Parks & Rec. - Campgrounds w/comfort station but without water & sewer hookup 75 Campsite 0 0 Parks & Rec. - Campgrounds with water & sewer hookup 100 Campsite 0 0 Parks & Rec. - Campground Dump Station facility 50 Space 0 0 Parks & Rec. - Construction, Hunting, or Work camps with flush toilets 60 Person 0 0 Wastewater Flow Calculations Establishment Unit Value (Gal/Day Unit Type # of Units Discharge GPD Parks & Rec. - Construction, Hunting, or Work camps with chemical or portable toilet 40 Person 0 0 Parks & Rec. - Parks with Restrooms 250 Plumbing Fixture 0 0 Parks & Rec. - Summer camps without food prep or laundry facilitates 30 Person 0 0 Parks & Rec. - Summer camps with food prep and laundry facilitates 60 Person 0 0 Parks & Rec. - Swimming Pools, Bath Houses, Spas 10 Person 0 0 Public Access Restrooms 325 Plumbing Fixture 0 0 Schools - Preschools & Daycares 25 Person (child+employee) 0 0 Schools with Cafeteria, Gym, & Showers 15 Student 0 0 Schools with Cafeteria 12 Student 0 0 Schools without Cafeteria, Gym, & Showers 10 Student 0 0 Schools, Boarding 60 erson (student+employee 0 0 Service Stations, Gas Stations 250 Plumbing Fixture 0 0 Car Wash Facilities (if recycling water, see Rule .0235 of 2T regulations) 1200 Bay 0 0 Sports Centers - Bowling 50 Lane 0 0 Sports Centers - Fitness, Exercise, Karate, Dance 50 100 sf floor space 0 0 Sports Centers - Tennis, Racquet ball 50 court 0 0 Sports Centers - Gymnasium 50 100 sf floor space 0 0 Sports Centers - Golf Course with only minimal food service 250 Plumbing Fixture 0 0 Sports Centers - Country Clubs 60 Member or Patron 0 0 Sports Centers - Mini Golf, Putt -Putt 250 Plumbing Fixture 0 0 Sports Centers - Go -Kart, Motorcross 250 Plumbing Fixture 0 0 Sports Centers - Batting Cages, Driving Ranges 250 Plumbing Fixture 0 0 Sports Centers - Marinas without Bathhouse 10 Slip 0 0 Sports Centers - Marinas with Bathhouse 30 Slip 0 0 Sports Centers - Video Game Arcades, Pool Halls 250 Plumbing Fixture 0 0 Stadiums, Auditoriums, Theatres, Community Centers 5 Seat 0 0 Stores, Shopping Centers, Malls & Flea Markets Auto, Boat, RV dealerships/showrooms with restrooms 125 Plumbing Fixture 0 0 Convenience Stores, with Food Preparation 60 100 sf floor space 0 0 Convenience Stores, without Food Preparation 250 Plumbing Fixture 0 0 Flea Markets 30 Stall 0 0 Shopping Centers and Malls with Food Service 130 1000 sf 0 0 Stores and Shopping Centers without Food Service 100 1000 sf 0 0 Transportation Terminals - Air, Bus, Train, Ferry, Port & Dock 5 Passenger 0 0 Other- 0 Other- 0 Other- 0 Other - See attached supplemental PER 430,560 From 15A NCAC 02T .0114 Average Daily Flow (gallons per day) 430,560 Actual Measured Flow Data (Source) I Average Daily Flow (gallons per day) 450,000 Design Pumping Flow Rate Peaking Factor Calculation Service Area Population 4,722 Peak Factor = 18 + SIP 4+�P Calculated Peak Factor = 3.3 Design Peak Factor = 3.3 Determine Minimum Pump Rate Average Daily Flow 430,560 GPD Peak Flow 1,407,042 GPD Minimum Pumping Rate Required 977 GPM Design Pumping Rate 1 1,000 GPM Cycle Time & Wet Well Geometry Target Cycles Per Hour ADF = 299 gpm Pumping Rate = 1,000 gpm Time = 30.0 min. Target Cycles Per Hour = 2.0 Check Cycles Per Hour: OK Check Cycles Per Hour: OK Determine Wet well Diameter Required Volume = Pick Wet Well Diameter = Pick Wet Well Cycle = Volume in Cycle = 6288 Gallons Ft Vert. Ft Gallons 8.5 4.0 1 1698 Vertical Datum Used: JNAVD 88 Determine Wet Well Invert & Float Elevations Wet well Dia. = 8.5 Ft Top Elev = 812.50 Gnd Elev = 812.00 Lowest SS Invert In =1 795.99 larm = 793.72 ag On = 792.72 sad On = 791.72 umos Off = 787.72 Bottom Invert Elev* =1 786.72 *As required to meet manufacturer's req'd submergence Meets Minimum 1' Below Lowest Pipe Invert? OK s Pumping Station Piping Design Pump Station Piping Inside the Wetwell Design Pump Rate (gpm) = 1,000 Pick Wet Well & Valve Vault Nominal Piping Size (in) = 8.00 Pump Station Piping Material = DIP PC 350 Wet Well Pipe Diameter (in) = 8.55 Velocity (fps) = 5.59 Meets Minimum Velocity Requirement? OK Meets Maximum Velocity Requirement? OK Force Main & Piping Design I Off -Site Force Main Data Design Pump Rate (gpm) = 1,000 Select Force Main Size (in) = 10 Velocity (fps) = 4.1 Meets Minimum Velocity Requirement? OK Meets Maximum Velocity Requirement? OK Required Pump? Use Non -Clog Pum Line Length (ft) = 7,630 Account for Minor Losses = 5% Equiv Length (ft) = 8,012 Connection Point: ITo Existing Sewer Manhole Pump Station Piping Data Design Pump Rate (gpm) = Pick Wet Well & Valve Vault Piping Size (in) = F Velocity (fps) = Meets Minimum Velocity Requirement? Meets Maximum Velocity Requirement? 1,000 8 6.38 OK > 2 FPS OK < 8 FPS Item Number of Fittings L/D Ratio Equivalent Length 45 bend 90 bend 22.5 bend Branch Tee Flow Check valve Plug Valve 16 0.00 3 30 60.00 9 0.00 1 60 40.00 1 135 90.00 1 17 11.33 0.00 0.00 0.00 Equivalent Fitting Length (ft) = Wet Well & Valve Vault Piping Length (ft) = Total Equivalent Pump Station Pipe Length (ft) = Equivalent Off -Site Diameter Length (ft) = 201 37 238 706 Total Equivalent Force Main Length (ft) = 8,717 9 Force Main & Piping Design Force Main Data and Velocity Check Design Pump Rate (gpm) = 1,000 Select Force Main Size (in) = 10.00 Set Mimimum Velocity Desired (fps) = 3.00 Set Maximum Velocity Desired (fps) = 8.00 Velocity (fps) = 4.09 Meets Minimum Velocity Requiremen OK Meets Maximum Velocity RequiremeF OK Required Pump? Use Non -Clog Pump Sludge Multiplier (Mx)= 1 Force Main Length(s) Section Length (feet) Pipe Diameter inches Maximum Elevation ft 1 2,300 8.00 845.00 2 4,620 10.00 852.25 3 900 10.00 852.25 FM Low Point 787.72 Total 7,820 Minor Head Losses in Pipe Sections by Hazen Williams Formula Section 1 2 3 Nominal Diameter (inches) 8.00 10.00 10.00 Pipe Material DIP PC 350 PVC C900 DR V DIP PC 350 Pipe Diameter (in) 8.55 9.42 10.58 Discharge (gpm) 1,000 1,000 1,000 Velocity (ft/s) 5.59 4.60 3.65 Length (ft) 2300.00 4620.00 900.00 New Pipe or Old PipE New Pipe New Pipe New Pipe Hazen Williams Friction Coefficient 125 140 125 Minor Losses (ft) 32.69 33.21 4.53 Minor Losses with Sludge Multipler 32.69 33.21 4.53 New Pipe or Old PipE Old Pipe Old Pipe Old Pipe Hazen Williams Friction Coefficient 100 120 100 Minor Losses (ft) 49.42 44.18 6.85 Minor Losses with SI 49.42 44.18 6.85 Force Main Equivalent Length by % Loss Line Length (ft) = 7,820 Account for Minor Losses = 5% Equiv Length (ft) = 8,211 Force Main Equivalent Length by Minor Loss Calculations Section Length (ft) Pipe Diameter in Minor Losses (in feet of head 1 2,300 8.00 32.69 2 4,620 10.00 33.21 3 900 10.00 4.53 Fittings 1.45 Total FM 7,820 70.44 Total Equivalent Force Main Length (ft) = 7,890 Total Dynamic Head High Point on Force Main = 852.25 Lowest Point on Force Main = 787.72 Total Static Head = 64.53 Head Loss Due to Friction = 71.89 Total Dynamic Head (TDH) = 136.42 Check Detention Time in Force Main at ADF Length of Force Main = 7,820 Feet Volume of Force Main (Section 1 Dia) = 23,322 Gallons Cycles to Pump 10.40 Cycles Minutes of Detention = 82.4 Minutes Hours of Detenion in FM 1.37 Hours Meets Maximum Detention Time? OK 10 Pump Selection Force Main Diameter (in) = 10 Equivalent Force Main Length (ft) = 7,890 Highest Point on Forcemain (ft) = 852.25 Staic Head (ft) = 64.53 Hazen -Williams C Factor = 1 125.00 Minimum Required Pump Rate (GPM) = 977 Design Pumping Rate (GPM) = 1000 Total Dynamic Head (ft) = 136.42 Pressure Head "Only Pressure at Connection Proposed Head at Static "All On" Pump "Only Pump Velocity GPM Connection Proposed Head TDH Station (fps) Head "All On„ (feet) (feet) (feet) Pump Station On" TDH (feet) On" (feet) (feet) 0 64.53 N/A 65 0.0 183 400 64.53 N/A 74 1.6 158 800 64.53 N/A 99 3.3 137 1200 64.53 N/A 138 4.9 117 1600 64.53 N/A 190 6.5 99 2000 64.53 N/A 254 8.2 80 2400 64.53 N/A 330 9.8 58 Pump Manufacturer: Flygt Model Number: NP 3202 HT3-458 Impeller Diameter: 1310 mm Horsepower: 170 Voltage: 1460 ill Pump and Force Main System Curve 350 300 250 - 200 U. 150 100 50 N —*—Pump Head s All On System TDH —mom 1 Pump On 0 500 1000 1500 2000 2500 3000 Flow (GPM) 12 Station Operation Check Proposed Operational Point: 1,056 GPM @ 1 124 TDH Check Wet well Cycle Times Wetwell Wetwell Wetwell Wetwell Diameter Area Cycle Volume (feet) (gal / VF) (ft) (gal) 8.5 424 4.0 1697 Fill = Wetwell Volume = 5.7 minutes ADF Run = Wetwell Volume = 2.2 minutes Pump Rate - ADF Total = 7.9 minutes Cycle Time = 7.6 Cycles / Hour Meets Minimum Cycle Time? OK Meets Maximum Cycle Time? OK 13 Buoyancy Calculations Wetwell Outside Dimensions 9.50 Feet Wetwell Inside Dimensions 8.50 Feet Wetwell Top Slab Elevation 812.50 Feet Wetwell Invert Elevation 786.72 Feet Extended Base Slab Diameter 11.50 Feet Extended Base Slab Thickness 1.00 Feet Top Slab Thickness 0.50 Feet Calculate Total Volume of Wet well Structure Volume of Wetwell Riser Sections = 1826 cf Volume of Wetwell Extended Base = 104 cf Total Volume of Wetwell Structure = 1930 cf L;aicuiate i otai volume or water uispiacea H2O Displaced = (Volume of Wetwell Structure) * (62.4 Ibs/cf) H2O Displaced 120447 Ibs Calculate Weiqht of Wet well Components Section Total Ht Weight Top Slab Thickness ft. 0.50 5316 Riser - Total Vertical Ft. 25.78 54668 Base Slab Thickness (ft.) 1.00 15580 Total 27.28 175565 Total Weight of Concrete in Wetwell 75565 Ibs. Calculate Submerged Weight of Soil Above Extended Base/Footing Total Area of Extended Base 104 sf Total Area of Wetwell Riser 71 sf Area of Extended Base less Wet well 33 sf Height of Soil Above Extended Base 25 ft Volume of Soil Above Extended Base 834 cf Weight of Soil Above Extended Base (estimated) 1 120 Ibs/cf Total Weight of Soil Above Extended Base 1 100068 Ibs/cf Flotation Protection Required Weight of Concrete and Weight of Soil Above Extended Base: 175633 Ibs Weight of Water Displaced By Wetwell: 120447 Ibs Flotation Protection Required? NO 14 APPENDIX III WHITES MILL SEWAGE PUMPING STATION UPGRADES SIPHON CALCULATIONS Siphon Calculations Friction Head Calculations Hazen Williams hf = 0.002083' L' (100/C)11.85' ((gpmA1.85)/(dA4.8655)) HAZEN & WILLIAMS FORMULA North Siphon Line L = 790.4 feet (length of line + all equivalent lengths) L = 790.4 feet (length of line + all equivalent lengths) (New Pipe) C = 130 (Hazen & Williams Friction Factor) (Old Pipe) C = 90 (Hazen & Williams Friction Factor) gpm = 1,271 gpm (flow rate) 1.83 MGD gpm = 1,271 gpm (flow rate) 1.83 MGD d = 10.656 in (pipe diameter) d = 10.656 in (pipe diameter) hf = 5.61 feet 2.43 psi hf = 11.07 feet 4.79 psi Pipe Velocity Pipe Velocity Q 1271 gpm Q 1271 gpm Diameter 10.656 in Diameter 10.656 in Area 0.62 ft' Area 0.62 ft' Q 2.83 ft/sec Q 2.83 ft/sec V 4.57 ft/sec V 4.57 ft/sec Siphon Minimum Velocity Check OK Siphon Minimum Velocity Check OK Upstream Invert Elevation 803.91 Upstream Invert Elevation 803.91 Downstream Invert Elevation 790.55 Downstream Invert Elevation 790.55 Static Head 13.36 Static Head 13.36 Is Static Head > Friction Head? OK Is Static Head > Friction Head? OK South Siphon Line L = 790.4 feet (length of line + all equivalent lengths) L = 790.4 feet (length of line + all equivalent lengths) (New Pipe) C = 130 (Hazen & Williams Friction Factor) (Old Pipe) C = 90 (Hazen & Williams Friction Factor) gpm = 1,271 gpm (flow rate) 1.83 MGD gpm = 1,271 gpm (flow rate) 1.83 MGD d = 10.656 in (pipe diameter) d = 10.656 in (pipe diameter) hf = 5.61 feet 2.43 psi hf = 11.07 feet 4.79 psi Pipe Velocity Pipe Velocity Q 1271 gpm Q 1271 gpm Diameter 10.656 in Diameter 10.656 in Area 0.62 ft' Area 0.62 ft' Q 2.83 ft'/sec Q 2.83 ft'/sec V 4.57 ft/sec V 4.57 ft/sec Siphon Minimum Velocity Check OK Siphon Minimum Velocity Check OK Upstream Invert Elevation 803.41 Upstream Invert Elevation 803.41 Downstream Invert Elevation 790.55 Downstream Invert Elevation 790.55 Static Head 12.86 Static Head 12.86 Is Static Head > Friction Head? OK Is Static Head > Friction Head? OK Siphon Calculations - Maximum Capacity Friction Head Calculations Hazen Williams hf = 0.002083 - L- (100/C)A1.85 ' ((gpmA1.85)/(dA4.8655)) HAZEN & WILLIAMS FORMULA Norm aipnon Line L = 790.4 feet (length of line + all equivalent lengths) (New Pipe) C = 130 (Hazen & Williams Friction Factor) gpm = 2,025 gpm (flow rate) 2.92 MGD d = 10.656 in (pipe diameter) hf = 13.27 feet 5.75 psi Pipe Velocity Q 2025 gpm Diameter 10.656 in Area 0.62 ft2 Q 4.51 ft'/sec V 7.29 ft/sec Siphon Minimum Velocity Check OK L = 790.4 feet (length of line + all equivalent lengths) (Old Pipe) C = 90 (Hazen & Williams Friction Factor) gpm = 1,400 gpm (flow rate) 2.02 MGD d = 10.656 in (pipe diameter) hf = 13.24 feet 5.73 psi Pipe Velocity Q 1400 gpm Diameter 10.656 in Area 0.62 ft' Q 3.12 ft'/sec V 5.04 ft/sec Siphon Minimum Velocity Check OK Upstream Invert Elevation 803.91 Upstream Invert Elevation 803.91 Downstream Invert Elevation 790.55 Downstream Invert Elevation 790.55 Static Head 13.36 Static Head 13.36 Is Static Head > Friction Head? OK Is Static Head > Friction Head? OK aoum aipnon Line L = 790.4 feet (length of line + all equivalent lengths) L = 790.4 feet (length of line + all equivalent lengths) (New Pipe) C = 130 (Hazen & Williams Friction Factor) (Old Pipe) C = 90 (Hazen & Williams Friction Factor) gpm = 1,975 gpm (flow rate) 2.84 MGD gpm = 1,375 gpm (flow rate) 1.98 MGD d = 10.656 in (pipe diameter) d = 10.656 in (pipe diameter) hf = 12.67 feet 5.49 psi hf = 12.80 feet 5.54 psi Pipe Velocity Pipe Velocity Q 1975 gpm Q 1375 gpm Diameter 10.656 in Diameter 10.656 in Area 0.62 ft2 Area 0.62 ft2 Q 4.40 ft/sec Q 3.06 fN/sec V 7.11 ft/sec V 4.95 ft/sec Siphon Minimum Velocity Check OK Siphon Minimum Velocity Check OK Upstream Invert Elevation 803.41 Upstream Invert Elevation 803.41 Downstream Invert Elevation 790.55 Downstream Invert Elevation 790.55 Static Head 12.86 Static Head 12.86 Is Static Head > Friction Head? OK Is Static Head > Friction Head? OK APPENDIX IV WHITES MILL SEWAGE PUMPING STATION UPGRADES FLOOD INSURANCE RATE MAP STATE OF NORTH CAROLINA FIRM PANEL LOCATOR DIAGRAM ROC,unia AM 1 carm" i--Z50,1fRV - DATUM INFORMATION The pro}ctlm mood n Vic wsM,al— d Mon man war the Nonh ca drat State Plene IFIPSZONE 32W1 The hor]soMN datam was Me NonM Amehran Dann d 1983. GRS80 ellipsool DAaerrss n dMun Nlgad. w'opdion. or Uni—sal Tranavalse Mwoatz mats wed n the Modscllon of FIRMS for Adjacent nandicMns may M— n .ogre pos8lonN d8erancee , Cap faNees woes haadgtronal Dwagalles Those dmrancsa do no affect she ill—acy d ones FIRM All morel t- m His mop ae in U.S S—ey Feet. wive 1 U.S. Survey Foot • 12 937 Metals Food Mevsbom m that map are Maancad M the North Amecian Verticalw Dan of 19M (NAVO 88) These flood en,maonrs me,, b, complied W sirudae and Panel aleva— Mereno7tl to the calm raNica denim M —We oflaet beN,Sen NAVD 88 antl the NNmal Geodao Vertical Dann of 1929 (NGVD 29) Me been commod I. — NorM Caman, col-, This onall ores #,m appledl io iM NGVD 29 flood NevNnm snit waa - Mv— M V du -- of Mp sMewob swvno FIRM The offset, so each county Wen m this FIRM panel n Itvwn , me vemral Men dh , table bab. Vsma a county hosgary W e Iloodsp source wM nmewsed NGVD 29 Rood! elevasom — concAeq ndvgMW offset tsar bten caksilesed antl applied ding the csew d Ma saelise M. FIRM. Sea SW 6.1 d she wmlpw"V Flood aaurarce Stud, repot to obtain f,nher =a— on the pan _ of akvNho, between NAVD W ant NGVD 29 To dNan c,, rM eNval,m, desa,pl,on, arch locagn reor — TOM beach meld, shown on, this mop. P.— coMacl Me Node Carolina, Geodetic Survey at the address Mown babe, You may also cora,a the Information Service, Branch d sat National Geodatc Suave, N (3011 T1g.,W a ms ib--a DepJAMM,— y -Y Norm Caolaa Geodetc Survey Coast' Avalage VenIW D— Offset Table R VAaN C 27 SVeN i _ Rag) 7 -3 27Ti01 (919)733-3836 iXOo-l==ratj y All aceam, bated n one Flood Hazard Data Table babe wale eluded by aewad rrMtptls useq fob savvy. 00rer Mod laud date shown on sat map may have been carved way aaher e=•oeaM _y,hs on .- detaiaq Rivalaa ananY Mona hMonn m ImModnl9 wu NuOhad by Vase aWyses a Mm ccrnad n me Flood =a—, Study report FLOOD HAZARD DATA TABLE Roo° " N1tl" II.N LM,Np1a Dstnce Fran t%ANaal Deco aa6rasrd Sesame Co. :a1Mn Food OscMge 110DYta1 encroachnars Bade , Section Satin (ell YNaa.$. ,,,am 1 Lo." Downsesanlo Zvow Tesese 'e WEST FORK DEEP MVER (STREAM NO. 2) 6106 610,600' NA we I 32D 6116 1 61/.800' NA 809.7 16o 6138 613,8W' NA 814.4 176 81,M 614,562' NA 816.2 32D ' Fait—i,npM WEST FORK DEEP NM TMMRARY NO. 2 (STREAM ND. 8) 012 1,150T NA 809.6 125 025 2.570 T NA 816.5 50 ' Fait abve rroMAM t Feet about IrnMal Road �•.. wR. w AYT E O Thhs dgaa Flood Inseams Rae Map (FIRM) was wMpced Mrwgl, a undue cooperasve panmranip between the State of Nonh Carolina Prot the Federal Emergency Management Agency (FEMA). The State of With Cambia. has f W,—tad a lore, ]elm appl lh offlo00plan management to decease Me costs a abonned with lloodng Th' is demonNreled by the Slates commitment to map flow]plan areas A the local level. As a par] of ]his MM. Me Nate of Node caoloa has jorree m a Coopxaing Technical State agnaerrtnl wide FEMA to Produce arm matntauh this dgVa FIRM. www.ncfloodmaps.com low: ZONE X , 1. • M j I" � ' 11• � I'. M i LONE AE ZONF X �� I , r:li ..' s 11,' '. '� I ICI, In •1. MI �I ` .. '_ ' ,' e fa ' � ♦' 70NE AE Z lOmtF z J ZONF: AF. •s A .� .ZONE% ZONE X •.. T • ` •.` ....._ _ • • i ` . ; �_ / l••l� A�1 •'ZONE AE I of ,,. � :I 11. I +,7;a •J� �w-- '� / ZONE �J 7 —„ 2DNE X eb 000 ME' Tots mop Is to use n ...Ma.O ion Na— Flood In-- Program fl does rp aize ssaov insiMMy aN areas NElec, n flooding Pany hom bca md drsge sources small The communky map retain" stvwbf be ­w for Passible hyaaad or addsionse noon hax.d m onmal— To ocan more detailed nrormladm n smw ­M BMs Pines Elavet]ans (BFEI) ends Peodneys vat bow detmmined uew, hie —lped to chnwe me, Flood Prank, FloOoway Oita. Inn. patted Flood Hated DNS. a Summary d Stvne , ENVaon, table, onmil aG wMn me Food nwnme SW , (FIS, lop. Mal accorrpaMes ors FIRM Usem ,hoed he ,wale met BFE. Mown on Me FIRM npreem rounded whdrlod ekvaams These BFE, are,mended for flood p n loV puryoses -1 and — roe be used as to sea source d Mm se—crl nlamabm Ac=wdegtY. food serum dats Presented In the Fie upon Mwq he dlitad m rpyuncbon wM ma FIRM for P-1 d =amMaon a floodwan mahapemenl Bamowes of IeEuls" Iloodiays — m the FIRM la noodea ,dews s1W,ed by dewed —.1wero conM - al cross —I and misnoo4led between nos, Mtaom The fi—ys woe based on hYtradc cm,idenlm, wM M Wd 10 ngunemems d oat f,tslon,l Flood mini nce Pmtram Fwodway wgms ant doer pMnent IloodwaY data rot noodnt rounds atuded DY detabd mSMads as wit as rnprM�rKldaclalMarA w1dDa W noodnp scan, s1Wad by knktl ONas memeoa ert proNded n ow F sod pautanra Study (FS) report to bps n m The F S reps, e. linos. msttu=bms n, delemunep S IloodwaY usmt rmF __hmsM —, la lio log aWetl by Nmnd deeded napgd, r 91 NOTES TO USERS Chen Gees not in Spada Flood Hazard Areas may be wotecteo by Rood cc tr alrachMM Rita to Sedbn 44 -Flood Nolectron Maaawea d Vat Fbotl Inseanp Study repot sat hMonnabm on flood contra eaucluras m M s unsddm I Data ass,, rRomNm and gaos,,a e, data wed 10 develop Mrs FIRM wee ohlemed hom aw,abns. ndudap ton mncroan9 local comon—yl,asl at We and fMM` lg.—, aide ooe, sources The wM_ base M ors FIRM is venal vnegery acgaed by Gudrord County The Came Paod of mbaotw to the mnagery M 2003 trdd�Niol and geospabal data snpplatl by the local CwnmmnYf sal ,tali met FEMA base map speasicaY>m con —ed the waare i source for de -op mom of Ito base map See geospaal _Mdaa to the assoaaed o9w, FIRM for cods—, maonma— abwl Dose map w—ailm Basal map Manures Nwwn on ma map such w corppae wits, lie Dosed on the mos, ,n— dale "a avalabk al Me time of pudhoallm Cheaper In IM corporate INMb MY I1a ni of—,, 0, Nnce I. nap re, pars MaP wars shwa =anwh the nd —" c,1-- oflnat or webne m varty eareM mhbnwns d lendcmonal bomdeas and base nap feNMaes Tots map may roman roads that was rot the F, ea n a hytraulc Tam d sheama where ro new hytraJc model was creased easy ton wotladgn d Ma staNw,d forma FIRM 1 TOT —FEET ZONL X Thb mop reflects more deaaded and lol"ile ehaap cha,nal conflgraalons men Ihme shevm m the weviws FIRM for Me Iunsdl,t— The food tams ant Inodways that wale liana M FIRM a her been Ned to aegmn io IheN now stream aired hour s RM m pnvnou lido Y camel cmameF PM ley Fbla M) Data leeks n the Flood axti awns As a roaun. 0e bow lilt llsuran=e t di repay, Iwhoh s shorn, nl IN, l ap nytrauac dNS) may refleM stream tmanml dsta,ne, Vat tldfer hour vial is Nnosvn m ttns map Please Misr to she sepalaely Forded Map bras% for an, ,M­ map CO the county showmp the layout a map pawls. canmmM map repository aOMessas, art a Lntq d Cenmmdea table = i,, Natrona Flood Imean2 Program does fo each community as well p, hang of the worts m whhcb each comm_y is nceted X You have gNNipls abouh We map a ,vasnon, carvnsg the NNmml Flood Maaace Nopam fin gemrel. please cat t - M - FEMA MAP (1-11"-336-2627) or vlsd ton FEW weDNb al Mto (Iwww fame. my M ac=ohMnOaswn9 Flood In ..— SlWy rort epLetts of Mop Re (LOMR) a Latta of Map Ann—m- ILOMAI revisng portion, of den pawl. and dpeal vaspns of fMs FIRM may be, avaaabk Vna the Node, callow- FbppMln MWpty P.W— wabsd N Mb lhvw-w.rncflP9drn,oa col o corsad the FEMA Map SaM ice Ghee a 1 A 21W9616 for ireamamm m NI Mated woduda as,ocatad wM His FIRM The FEMA MW Servce C,Mer met' Nato lea reached by Fu N Td0D3W%4 And as women M Mn.Nw-ww.msc Tema ow —FEET U.—ME, Im ilford County xlrwratW Areas 370111 830000 FEET ... �O FEET MAP REPOSITORY ReMbaslYq dMp Rpossmw m M,ps_.nr a MMMh EFFECTIVE DATE OF FLOOD INSURANCE RATE MAP PANEL DUNE 18, 2a07 EFFECTIVE D M(S) OF REV,SX)NMS, TO THIS PANEL Formnmsl CapmwsenM pmtpaneyede nep.—bneC.,Mp--weelovedn K Fam nsn,.eFe snpY raper b urn wnsamw b daMttn-Me s woo nwrmce n areMtble n nn aoMrnwory. con rpm pen. ve No1n exam OnYlan d E,mpe,cY Meuoevrcr, w Me Nnpne Flood kwrwae P,mO'am a hie ,pewee done mnaars a wenaes: NC DMsim>�EnememY MamspnMehh�..,h.w...Iw rrmw.NsameFMwbaO.. µ,ur�Proa„n LEGEND SPECIAL FLOOD HAZARD AREAS (SFHAS) SUBIECT TO INUNDATION RY THE 1% ANNUAL CHANCE FLOOD Tile I% amual chance flood (1DOyear Mad), also Iaovrrl as the base MmM flood, Is e flood a has a 1% chance of beat egsalad a eYeeaee m a y 9ncn year. The Swill Flood Hated Area a the — NOhttY to Boodng by sre 1% amual chance Mod. Areas n Special Food Nano ncude Zones a, AE, AM, All, AR, A", v, and VE. The Base Food ELI— n Vile wa 'Wa s elenlbn d the 1% amlal tl� Mod. ZONE A hip Base Flood Ekvabon EeemWed. ZONE AE Base Flood Ek,adon determined. AM Flood depths of 1 M 3 fee (Imply allies Of pmdq): Base Flood Season, dMerrn—, ZOME AO Flood deon of 1 In 3 feet (usually skeet fbw an 0cipeq tenk); ine aw dww dsteral d. Far auras of ahwat lan MOEYq, vaoWm also derernlred. ZONE AR SpaTal Flood NerarC Area formeN wr10eOM hates se 1% anon chance Mod by a Mad coned system that wa su iatoonMy tlemtae0. Zone AR nObee, that she lamer Mod coned ,,,tern h bent reshnM n pm,nde 11MemOn ham the 1% arobal chance a gnaw Bond. ZONE A" Area N be prele0ee hen 1% annals dance Mod by a FeGea flood wobadbn system u,de tontruNon; no= Flood Ei—dons deasmwe. ZONE w Caatai Bond me wan van M horse (ware aim); Bade Flood Eevabons determined FLOODWAY AREAS IN ZONE AE The Modvay is she chaaene of a sbenh beds any adlacent Modpimn aea that muss be kept five of elic—chnrd so sat the I%anmat Mace. Mon ran be camel wahaA sAisaraal adrea,es N Mod he h. OTHER FLOOD AREAS ZOME X Area of 0.2% anual thane Rood: carers d 1% ambal cane Mod with aere9e dep0a d lees Math 1 low a wan tlranape aeon Ness Ma 1 squaw mk: lilt area wdvcled by levees hen 1% anmW Hance Mod. OTHER AREAS ZOMEIt enadaan—te—de02%en'llms novallan. ZONED Albn— wood swards an, undWrmrW,bit 0oddde ® COASTAL WRIER RESOURCES SYSTEM (CERS) AREAS OTHERWISE PROTECTED AREAS (OPAS) Calls Mess Add OVa, are nenail bowel Move or adleoet M Special Food 1laead Area. - 1%ase-divehm Boodwanonmlan, 01 anal— lkodoien boadaY —. flmpwry boaMsay fine D be edgy ..................... a,sad—bond, eoedaY dndN soeoN Fkm rants Ann Taw s d balder �1`T�SPKFie— I —in, spew hips HaoM limn d Mean Bee Rpd eenions, Mon aswa n,m saocac. 513 ^-�^^ Base flood Besaaa,n soap hears; aeaeonnke• IE1981h Ea¢ Fboa EMeen was Mae uMdm — me. sAMm n • rateecew sae ramM Anevn veaat Irmp d wee O� Gass swvaon lie Cnow.wa madealm ,alaaat0 W m, Ham Amaaar boom d v .P�. oz-u10 19831aA0 e3) 4 ll6 1d0onaer "nMa `Tnmwme tNnaalr and mis, mho 17 1477 W FEET 25061p10da Yaaw: HprM Caalau Sale plane cmaenee glen (FD4dE 3200, Sbt Ap Nap e3 eel) OM5510 sbzh em aea 6saNhp sa,m _urn (see apaMalo, n _ „ pebm—liclmdesnanwne) BM5510O Rona Gpaebe Swvn be,M mot Ina avWnnan n Me Naen lryarrnalion swum d Ma Faha pwMer -MIS area Mae Dees NDRTN MAP SCALE 1• - 600• V : 6.000) as m hit 1: �t Tin 'nv FJ1P PANEL 7803J FIRM ° FLOOD INSURANCE RATE MAP NO)RI II ('AIMLIIA PANEL 7803 � =.Flnoe.r«,FinaMp.mF1 cOMMUMTy f,I EMU IVfF'% I � � I O O7 I a+p Mumw i` a Cig EFFECTIVF.DATE MAPNUMBER JUNE 18.2007 3710780300J a Q � pee••^' State of North Carolina n,........