HomeMy WebLinkAboutSWA000182_Cover Letter & Permit_20230222 oFtHc STATE�Ati ROY COOPER
Governor
ELIZABETH S.BISER
Secretary
DOUGLAS R.ANSEL NORTH CAROLINA
Interim Director Environmental Quality
February 22, 2023
Primax Properties,LLC
Attn: Marie McLucas, CFO
1100 East Morehead Street
Charlotte,NC 28204
Subject: Fast Track Authorization to Construct(ATC)Permit No.SWA000182
Steelpoint
Union County
Dear Mrs.McLucas:
The Division of Energy,Mineral and Land Resources received a complete"Authorization to Construct"
(ATC)Permit Application Form for the subject project on January 25, 2023 to be permitted under the
Post-Construction State Stormwater Fast Track Process. Staff have reviewed the application materials
and have determined that the project, as proposed,complies with the Stormwater Regulations set forth in
Rule 15A NCAC 02H.1043. We are hereby forwarding Authorization to Construct Permit No.
SWA000182 dated February 22, 2023,for the construction of the stormwater control measures (SCMs)
and built-upon area associated with the subject project.
This Authorization to Construct Permit does not constitute an approval of the project at its completion.
Approval of this project at completion will be based on Division review and approval of the final permit
application completed by a North Carolina licensed professional. It shall be the Permittee's and the
licensed professional's responsibility to ensure that the as-built project meets the appropriate stormwater
rules. Failure to comply may result in penalties in accordance with North Carolina General Statute §143-
215.6A through §143-215.6C and/or referral of the licensed professional to the appropriate North
Carolina licensing board.
This Authorization to Construct Permit shall be effective from the date of issuance until February 22,
2028 and does not supersede any other agency permit that may be required. The project shall be subject to
the conditions and limitations as specified therein.Failure to comply with these requirements will result
in future compliance problems. Please note that this Authorization to Construct Permit is not transferable
except after notice to and approval by the Division. The Division may require rescission and/or
revocation and reissuance of this permit.
This project will be kept on file at the Mooresville Regional Office. If you have any questions concerning
this permit,please contact Jim Farkas in the Central Office, at(919) 707-3646 orjim.farkas@ncdenr.gov.
Sincerely,
dui Q yaea'4 fikmw 5744"
zv-
,Douglas R. Ansel,Interim Director
Division of Energy,Mineral and Land Resources
Enclosures: Attachment A—Fast Track Construction Commencement Form
Application Documents
DES/jf: \\WaterResources\DEMLR-Stormwater\SW—Permits\SWA000182
cc: Kevin Caldwell,PE;GeoScience Group
Mark Griffin,Union County Building Inspections
NCDOT District Engineer
Zahid Khan,DEMLR
Mooresville Regional Office Stormwater File
E Q�� North Carolina Department of Environmental Quality I Division of Energy,Mineral and Land Resources
_ 512 North Salisbury Street 1 1612 Mail Service Center Raleigh,North Carolina 27699-1612
NORTH CAROHNA
ueeaement m 919.707.9200
Post-Construction Stormwater Management
ATC Permit No. SWA000182
STATE OF NORTH CAROLINA
DEPARTMENT OF ENVIRONMENTAL QUALITY
DIVISION OF ENERGY, MINERAL AND LAND RESOURCES
POST-CONSTRUCTION STORMWATER FAST TRACK PROCESS:
AUTHORIZATION TO CONSTRUCT (ATC) PERMIT
In compliance with the provisions of Article 21 of Chapter 143, General Statutes of North
Carolina as amended, and other applicable Laws, Rules and Regulations promulgated and
adopted by the North Carolina Environmental Management Commission, including 15A
NCAC 02H.1000 ("stormwater rules"),
PERMISSION IS HEREBY GRANTED TO
Primax Properties, LLC
Steelpoint
Near Beltway Boulevard, Indian Trail, Union County
FOR THE
construction of a fast track project and its associated stormwater control measures (SCMs) as
outlined in the approved Fast-Track application, site plan, and supporting documentation (the
"preliminarily approved documentation") as attached and/or on file with the Division of Energy, Mineral
and Land Resources (the "Division" or "DEMLR"). The preliminarily approved documentation is
incorporated by reference and are enforceable parts of this permit. This project is discharging to
receiving waters designated as North Fork of Crooked Creek, a class C water in the Yadkin Pee-Dee
River Basin and is to be designed in compliance with the provisions of 15A NCAC 02H.1000 and the
minimum design criteria (MDC) specified therein (the "stormwater rules") and enforced by the
Division.
This permit shall be effective from the date of issuance until February 22, 2028, and shall be subject
to the following specified conditions and limitations:
1. COMPLIANCE WITH THE STORMWATER RULES. The project and all SCMs (including
existing SCMs associated with the project) shall meet all applicable requirements of 15A NCAC
02H .1000 through .1062, including the Minimum Design Criteria (MDC), upon project
completion. This includes the following Sections of 15A NCAC 02H .1000:
.1003 Requirements that Apply to All Projects
.1017 NPDES MS4 and Urbanizing Areas: Post-Construction Requirements
.1043 Fast Track Permitting Process: Authorization to Construct
.1044 Fast Track Permitting Process: Final Permit
.1045 Requirements for Permit Transfers and Permit Renewals
.1050 MDC for All Stormwater Control Measures
.1051-.1062 MDC for Specific Stormwater Control Measures, as applicable
2. HIGHLIGHT OF SPECIFIC RULE REQUIREMENTS. The project shall comply with all
applicable provisions of the stormwater rules listed above. Some specific rule requirements to
be aware of include:
a. HIGH DENSITY REQUIREMENTS. The information provided in the application indicates
that this is a high density project and, as such, shall comply with all applicable high density
requirements of the stormwater rules.
Page 1 of 4
Post-Construction Stormwater Management
ATC Permit No. SWA000182
b. PROJECT AREA. The attached site plan depicts this project as a phased project with a
project area of 723,372 square feet. The locations of all SCMs, streams, wetlands, buffers,
and vegetated setbacks are shown on the site plan.
c. VEGETATED SETBACKS. A vegetated setback shall be provided adjacent to surface
waters per the requirements of Rule 15A NCAC 02H .1003(4) , G.S. 143-214.7(b2)(2) as
amended by Session Law 2018-145 and other applicable stormwater rules to which the
project is subject.
d. RECORDED DOCUMENT REQUIREMENTS. The stormwater rules require the following
documents to be recorded and must be submitted to obtain the final permit as stated in
15A NCAC 02H.1044:
i. Deed restrictions and protective;
ii. Access and/or easements;
iii. Operation and maintenance agreement;
iv. If a final plat is recorded, it must include a reference to the recorded operation and
maintenance agreement;
v. Deeds for individual lots with a reference to the deed restrictions and protective
covenants.
e. OPERATION AND MAINTENANCE. During the term of the ATC, all operation and
maintenance for the project shall follow the Erosion Control Plan requirements until the
Sediment-Erosion Control devices are converted to SCMs. Once the devices are
converted to SCMs, the permittee shall provide and perform the operation and
maintenance necessary, as listed in the recorded operation and maintenance agreement,
to assure that all components of the permitted on-site stormwater system function at the
intended design condition.
f. NO ALTERNATIVES TO THE MDC. The project shall not propose an alternative design,
nor shall it claim an exemption from the MDC based on vested rights, a waiver or a
Director's Certification.
g. SOLAR FARMS. In order for the solar panels to be considered a pervious surface, all of
the recommendations of Chapter E-4 of the Stormwater Design Manual must be met. This
includes providing either a minimum disconnection length between each row of panels
equal to the width of each panel row or horizontal gaps between individual modules on the
panel, which allows the disconnection length to be no less than 80% of the panel width.
3. ATC PERMIT ADMINISTRATION. In accordance with 15A NCAC 02H .1043 and .1044, the
following administrative procedures shall apply:
a. PROJECT AREA CHANGES. If the project area changes, then this ATC permit shall be
rendered null and void and the project must either apply for a new ATC or standard permit.
b. LICENSED PROFESSIONAL. A licensed professional of record must be maintained for
the duration of the project and who will prepare, certify, and submit the as-built package to
obtain the final permit. If another licensed professional is retained before the project is
complete, then an updated guaranty must be submitted. The original licensed professional
is required to inform the Division that they are no longer associated with the project.
c. CHANGES TO THE PROJECT NAME, PERMITTEE NAME OR CONTACT
INFORMATION: The permittee shall submit a completed Permit Information Update
Application Form to the Division within 30 days to making any one of these changes.
Page 2of4
Post-Construction Stormwater Management
ATC Permit No. SWA000182
d. TRANSFER. This permit is not transferable to any person or entity except after notice to
and approval by the Director. Neither the sale of the project, in whole or in part, nor the
conveyance of common area to a third party constitutes an approved transfer of the ATC
stormwater permit. The permittee is responsible for compliance with all permit conditions
until such time as the Division approves the transfer request. If the project is sold without
notification to DEMLR, then this ATC permit shall be rendered null and void, the project will
be out of compliance, and construction will not be allowed until a new standard permit
application is submitted and approved for the project.
e. TRANSFER REQUEST. To transfer this permit, either submit a new ATC application form
(with all required items) or apply for a standard stormwater permit through the standard
permitting process. Full or partial designers' certifications must be completed and
submitted with the new ATC application or the new standard permit application for any
SCMs that were already completed under the ATC. The transfer request must include the
appropriate application, documentation and the processing fee as outlined in 15A NCAC
02H.1045(2). This request must be submitted within 90 days of the permit holder meeting
one or more of the following:
i. A natural person who is deceased;
ii. A partnership, limited liability corporation, corporation, or any other business
association that has been dissolved;
iii. A person or entity who has been lawfully and finally divested of title to the property
on which the permitted activity is occurring or will occur through foreclosure,
bankruptcy, or other legal proceeding.
iv. A person or entity who has sold the property, in whole or in part, on which the
permitted activity is occurring or will occur;
f. RENEWAL. This ATC permit may be renewed by providing a renewal application with all
required items at least 180 days prior to the expiration date of this permit. The renewal
request must include the appropriate application, documentation and the processing fee as
outlined in 15A NCAC 02H.1045(3).
g. EXPIRATION. If the ATC permit expires, the project shall be considered out of
compliance, and thus shall be disqualified from renewal through the fast track permitting
process. In this case, the permittee shall obtain a permit through the standard permitting
process to complete the project. Full or partial designer certifications must be completed
and submitted with the standard permit application for any SCMs that were already
completed under the ATC.
4. DOCUMENTATION AND INSPECTION. The ATC application and required items and technical
design documents shall be available upon request by the Division throughout the life of this
permit. A copy of the ATC application and permit shall be maintained on file by the Permittee at
all times. In addition, the permittee grants Division staff permission to enter the property during
normal business hours to inspect the project and all components of the stormwater management
facility.
5. COMMENCEMENT OF CONSTRUCTION. DEMLR shall be notified at least 48 hours in
advance of constructing the approved project by submitting the completed Construction
Commencement Form found in Attachment A.
6. FINAL FAST-TRACK PERMIT APPLICATION. Within 45 days of completion of the project, a
Final Fast Track Stormwater Permit Application and all required items shall be submitted to
DEMLR in accordance with Rule 15A NCAC 02H .1044(3). Approval of the as-built stormwater
plans shall be required before the Erosion and Sedimentation Control Plan for the project may
be closed out.
Page 3of4
Post-Construction Stormwater Management
ATC Permit No. SWA000182
7. ENFORCEMENT. Any individual or entity found to be in noncompliance with the provisions of a
stormwater management permit or the requirements of the stormwater rules is subject to
enforcement action as set forth in NCGS 143, Article 21. Any of the following actions shall be
considered a violation of the stormwater rules and are grounds for enforcement action in
accordance with NCGS 143-215.6A:
a. Failure to abide by the conditions contained in this permit.
b. Knowingly making false statement, representation, or certification regarding this project.
c. Failure to maintain a licensed professional of record for the duration of the project.
8. DIRECTOR'S AUTHORITY. The Director may modify, revoke, reissue or terminate this permit
for cause as allowed by 15A NCAC 02H.1000 and NCGS 143-215.1.
9. OTHER REQUIREMENTS AND/OR PERMITS. The issuance of this permit does not preclude
the permittee from obtaining and complying with any and all other permits or approvals that are
required in order for this development to take place, as required by any statutes, rules,
regulations, or ordinances, which are imposed by any other Local, State or Federal government
agency having jurisdiction.
Permit issued this the 22Id day of February 2023.
NORTH CAROLINA ENVIRONMENTAL MANAGEMENT COMMISSION
O"afae aqmd4a� 5
Douglas R. Ansel, Interim Director
Division of Energy, Mineral and Land Resources
By Authority of the Environmental Management Commission
ATC Permit Number SWA000181
Page 4of4
Post-Construction Stormwater Management
ATC Permit No. SWA000182
Attachment A
Fast Track Construction Commencement Form
ATC Permit No. SWA000181
Steelpoint
Union County
Complete and submit this form (NO SUBSTITUTES) to the Mooresville Regional Office
The undersigned hereby notifies the agency below that the construction of this project is expected to
commence on (mm/dd/yyyy) and is expected to be completed by
(mm/dd/yyyy). I understand that this protect shall not be considered complete until
the Division has received the final Fast-Track Stormwater Permit Application Form and all
required supporting documentation.
Signature of Permit Holder Title (if any) Date
Designer's Certification
I, , as a duly re istered Licensed Professional in the State of
North Carolina, having been authorized to observe ((] periodically, ❑ weekly, ❑ full time) the
construction of the subject project on behalf of the Permittee. I hereby state that, to the best of my
abilities, due care and diligence will be used such that the project and all stormwater control measures
(SCMs) shall be constructed to meet all applicable requirements of 15A NCAC 02H Section .1000-
.1062, including the Minimum Design Criteria (MDC).
.......................................................................
North Carolina Licensed Professional Seal, signature,
and date:
......................................................................:
It is highly recommended that this notification be sent in a manner that provides proof of receipt by the
Division. The Division does not acknowledge receipt of Fast Track Construction Commencement Notification
Forms.
Submit this form to the following Office:
Division of Energy, Mineral and Land Resources c%Jerry Eplin
Post-Construction Stormwater Management Program
Mooresville Regional Office
610 East Center Avenue, Suite 301
Mooresville, NC 28115
Page 1 of 1