Dear Mr. Snider and Mrs. Graznak,
I am reporting on the SOC for the Town of Liberty for the Quarter from October 1, 2022 - January 1,
2023 in accordance with the SOC EMC SOC WQ S19-011 guidelines.
Section 2(a)(2) and Section 2(a)5 of the SOC discuss the GoldenLeaf Funds. All of the 3,231 linear feet of
the sewer main line have been rehabilitated as of April 28, 2021. The additional portion of sewer
Fayetteville Street that needed some extra attention has been repaired. All GoldenLeaf projects in the
SOC have been completed and project is complete.
Section 2(a)(3) and Section 2(a)(6) of the SOC discuss the CDBG funded project. This project
is in the final stages. We have completed all construction work. The Towns audit for FY 20/21 has not
been completed due to an auditor change. The only remaining items on this project are final grant
closeout which can not happen until the audit is complete — all other aspects of this grant have been
completed in the time lines set forth in the SOC.
Section 2(a)(4) and Section 2(a)(7) of the SOC discuss the ASADRA project. The engineering
reports have been submitted and we have passed a resolution to accept the funds. The ASADRA project
has had many delays. It was initially awarded during COVID as well as a town manager changing during
the beginning stages of the grant. Engineering drawings were submitted to the State for review with
some delays. WithersRavnel also requested a project separation request to work best for the grant and
it was approved February 2023. WithersRavnel also helped us right a supplement grant that would add
$12.5 million additional dollars to the $3 million original grant. Final decision on this grant will be
decided 2/21/2023. If these funds are awarded, it will be added to the project that has the collection
system rehabilitation components in it. The Town will not meet the deadline in Section 2(a)(7) which is
September 30, 2023. At this point, with being confident in the additional funds, this project will need to
be extended to finish all the work. Please see the attached timeline for the current $3 million ASADRA
project but also know that this project timeline will change if/when the additional funds are acquired.
If you have any further questions or need any clarification, please let us know and we will answer them.
Thanks again for your help and guidance on all of this. Our next report will be for the 1st quarter report
for 2023, January 1- March 30, 2023 which will be due by April 30, 2023.
Sincerely,
Scott Kidd
Town Manager Town of Liberty