Dear Mr. Snider and Mrs. Graznak,
GREAT PLACE 7o VE
A -
COUNCIL MEMBERS
Larry Coble
Mayor ProTem
Tyson Nixon
Tern Caviness
JR Beard
Don Herndon
I am reporting on the SOC for the Town of Liberty for the Quarter from July - September, 2021
in accordance to the SOC EMC SOC WQ S19-011 guidelines.
Section 2(a)(2) and Section 2(a)5 of the SOC discusses the GoldenLeaf Funds. All of the 3,231
linear feet of sewer main line has been rehabilitated as of April 28, 2021. There was an
additional portion of sewer found at a manhole on Fayetteville Street that needed some extra
attention that was not on the initial 3,231 linear feet. We have reached out to GoldenLeaf and
received funds to fix the lateral that is coming into that particular manhole. This work will be
completed as soon as we get the permit back from Northfolk Southern. The application has been
submitted and we have finally received confirmation. We have asked for a Golden Leaf
extension to October 31, 2021 so that the engineering firm can provide Norfolk Southern some
engineered data that they have requested. We have completed this section of the SOC and are
doing more than initially planned. We will continue to give updates until the final section is
replaced with GL funds.
Section 2(a)(3) and Section 2(a)(6) of the SOC discusses the CDBG funded project. This project
is well underway. The construction update meetings are being held monthly, spot repairs are well
underway, and the project is progressing ahead of schedule. All construction will be completed
on time. The original scheduled completion date is December, 2021. Section 2(a)(3) is complete
and we will give an update on the construction progress on the next quarterly report and Section
2(a)(6) will be completed on time.
Section 2(a)(4) and Section 2(a)(7) of the SOC discusses the ASADRA project. The engineering
reports have been submitted and we have passed a resolution to accept the funds. We have had
our kickoff meeting and will be moving forward with next steps.
Town of Liberty • P. 0. Box 1006 • 239 South Fayetteville Street • Liberty, North Carolina
27298
Phone (336) 622-4276 • Fax (336) 622-2665 • www.Liberty-NC.com
The completion of section 2(a)(3) will be completed by Aug, 2022. We will continue to give
updates on this section as we move forward. Section 2(a)(7) is the completion date for this
project on or before Sept 30, 2023. This should be attainable.
If you have any further questions or need any clarification, please let us know and we will
answer them. Thanks again for your help and guidance on all of this. Our next report will be for
the 4th quarter, October -December 2021.
Sincerely,
ScottKidd
Town Manager
Town of Liberty NC
336-215-2339