HomeMy WebLinkAboutNCC213836_NOT Closeout Documents_20230621 Sedimentation/Construction Stormwater Inspection Report
North Carolina Department of Environmental Quality
Land Resources: 127 Cardinal Drive Extension,Wilmington,NC 28405 (910) 796-7215
County: Duplin Project: Lee Sub-Wallace 115kV Replace Cap River basin: Cape Fear
Person financially responsible:Duke Energy Progress,LLC-Randy Veltri, Project#: DUPLI-2021-011
Director of Transmission Permitting
Address: 550 S.Tryon St.,Suite 4500,Charlotte,NC
1. Project Location: Fonvielle Road,Wolfscrape
Pictures: No
2. Weather and soil conditions: 90 clear dry Initial inspection: Yes
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A.and rules? Yes If no,check violations below:
5. Violations:
6. Is the site in compliance with NPDES Permit NCG010000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes,where? (check all that apply)
Degree of damage:
8. Contact made with(name): Title:
Inspection report: Sent Report Date given/sent: August 23,2022
9. Corrective action needed:
10. Comments: Permanent ground cover sufficient to restrain erosion has been established.No additional
self-monitoring or self-inspections are required.Project is in compliance and released under
the SPCA.Termination of coverage under the NPDES General Stormwater Permit for
Construction Activities(NCG01)must be requested by the permittee via a Notice of
Termination(NOT).The NOT is available at:
https://edocs.deq.nc.gov/Forms/NCG01-Termination.Please note that this correspondence
must be uploaded as part of completing the NOT process.
Reported by: Brian Lambe Others present:
Date of inspection: August 11,2022 Time arriving on site: 12:00 PM Time leaving site: 12:30 PM