HomeMy WebLinkAbout20221775 Ver 1_DCM Permit_20230324Permit Class
NEW
Permit Number
38-23
STATE OF NORTH CAROLINA
Department of Environmental Quality
and
Coastal Resources Commission
r r t nit
for
X Major Development in an Area of Environmental Concern
pursuant to NCGS 113A-118
X Excavation and/or filling pursuant to NCGS 113-229
Issued to Bald Eagle Lane, LLC, 8748 Bald Eagle Lane, Wilmington, NC 28411
Authorizing development in
New Hanover
County at adj. to AIWW at 8748 Bald Eagle Lane, in
Wilmington , as requested in the permittee's application dated 4/14/22 (MP-1, MP-4), including work plan
drawings (2) Sheets 1-2 of 2 dated "received Sep 08 2022, DCM Wilmington, NC".
This permit, issued on March 24, 2023 , is subject to compliance with the application (where
consistent with the permit), all applicable regulations, special conditions and notes set forth below. Any violation
of these terms may be subject to fines, imprisonment or civil action; or may cause the permit to be null and void.
Bulkhead Replacement
1) The bulkhead shall extend a maximum of one (1) foot waterward from the waterward edge of the
existing bulkhead at any point along its alignment at the time of construction.
2) No vegetated wetlands or open water shall be excavated or filled, even temporarily, outside of the
approved bulkhead alignment.
3) The bulkhead shall be solid and constructed of treated wood, concrete slabs, metal or vinyl sheet
piles, or other suitable materials approved by Division personnel.
(See attached sheets for Additional Conditions)
This permit action may be appealed by the permittee or other
qualified persons within twenty (20) days of the issuing date.
This permit must be accessible on -site to Department
personnel when the project is inspected for compliance.
Any maintenance work or project modification not covered
hereunder requires further Division approval.
All work must cease when the permit expires on
March 24, 2028
In issuing this permit, the State of North Carolina agrees that
your project is consistent with the North Carolina Coastal
Management Program.
Signed by the authority of the Secretary of DEQ and the Chair
of the Coastal Resources Commission.
For Braxton C. Davis, Director
Division of Coastal Management
This permit and its conditions are hereby accepted.
Signature of Permittee
Bald Eagle Lane, LLC Permit No. 38-23
Page 2 of 3
ADDITIONAL CONDITIONS
4) The bulkhead shall be constructed prior to any backfilling activities.
5) The bulkhead shall be structurally tight so as to prevent seepage of backfill materials through the
structure.
6) This permit does not authorize any excavation waterward of the approved alignment.
7) The fill material shall be clean and free of any pollutants except in trace quantities.
8) Unless altered herein, all backfill material shall be obtained from a high ground source and confined
behind the permitted bulkhead.
9) No backfill material is to be placed within 30 feet of the normal high-water level, except that which will
be used to backfill the area behind the permitted bulkhead.
Sedimentation and Erosion Control
10) In order to protect water quality, runoff from construction shall not visibly increase the amount of
suspended sediments in adjacent waters.
11) Appropriate sedimentation and erosion control devices, measures or structures shall be implemented to
ensure that eroded materials do not enter adjacent wetlands, watercourses or properties.
12) A ground cover sufficient to restrain erosion shall be provided within 30 calendar days of any phase of
grading on cut or filled slopes. At a minimum, a silt fence shall be properly installed immediately
landward of the bulkhead cap immediately following completion of backfilling activities.
General
13) This permit shall not be assigned, transferred, sold, or otherwise disposed of to a third party without the
written approval of the Division of Coastal Management.
14) All construction debris associated with the removal or construction of the permitted development shall
be contained within the authorized project area and disposed of in an approved upland location.
15) The permittee and/or his or her contractor shall meet with a representative of the Division prior to
project initiation.
NOTE: This permit does not eliminate the need to obtain any additional state, federal or local permits,
approvals or authorizations that may be required.
NOTE: The U.S. Army Corps of Engineers authorized the project by way of Nationwide Permit 3
(Action ID SAW-2022-02715).