23-0274 Approval for Minor Erosion and Sediment Control
SITE ADDRESS: 175 EAGLE POINT LN ISSUED: 03/02/2023
PROJECT NAME: 175 Eagle Point Lane EXPIRES: 08/29/2023
PARCEL: 857200427602 LAT:35.185292 LONG:-79.419333
APPLICANT: OWNER: FINANCIALLY RESPONSIBLE PARTY:
LATITUDE BUILDERS LLC LANZA, ETTORE M. LATITUDE BUILDERS LLC
PO Box 1301 2355 NE OCEAN BLVD UNIT B37 PO Box 1301
SOUTHERN PINES, NC 28388 STUART, FL 34996 SOUTHERN PINES, NC 28388
CITY: SOUTHERN PINES COUNTY: DISTURBED AREA(ACRES): 0.20 HOW: NO
RECEIVING WATER: Unnamed tributary RIVER BASIN: Lumber STREAM CLASSIFICATION: C
DATE RECEIVED BY TOSP: 2023-02-15 00:00:00.000 PLAN TYPE:
The review of the above referenced erosion control plan has been completed and the plan submitted has been found acceptable.
Amendments to the plan should be submitted to this office under the same procedure as followed for the original plan.
Title 15A NCAC 4B.0118(a)and the NCG01 permit require that the following documentation be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC,once it is received.
3. Records of inspections made during the previous 30 days.
This project is subject to the National Pollutant Discharge Elimination System(NPDES). As of April 1,2019,all new construction activities are required
to complete and submit an electronic Notice of Intent(NOI)from requesting a Certificate of Coverage(COC)under the NCG010000 Construction
Sormwater General Permit. This form MUST be submitted prior to the commencement of any land disturbing activity on the above named project. The
NOI form may be accessed at deq.nc.gov/NCG01. After you submit a complete and correct NOI Form,a COC will be emailed to you within three
business days. DEMLR will charge a fee for coverage under the NCGO1 permit. This fee is to be sent to the DEMLR Stormwater Central Office staff in
Raleigh. Please see North Carolina Department of Environmental Quality(NCDEQ)documentation regarding procedures for obtaining permit
NCG010000. Refer to the NCDEQNCGO1 Ground Stabilization and Materials Handling Sheet for additional details on compliance with these
requirements. Should you have questions contact the Division of Energy,Mineral and Land Resources,919-707-3639.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water quality laws,regulations,and rules. In addition,
local city or county ordinances or rules may also apply to this land-disturbing activity. This approval does not supersede any other permit or approval.
This Approval Shall Expire:
1. There is no substantial construction,erection,alteration,excavation,demolition or similar work authorized by such permits within one(1)year after
issuance.
2. Work has commenced,but there is no substantial progress on the project for a period of one(1)year.
3. The project has not been completed within two(2)years of issuance of the permit.
Authorized Signature: 9411142---
Date: 03/03/2023