HomeMy WebLinkAboutNCC230879_Site Plan or Location Map_20230329. ' o L 1 - I - 1V MAG (S) L-iv I i\niv'-,L_
ELEV
LJ R/�/�/ DENUDED = 858.00' STD. 30.11A
IAREA (NAVD 1988)
#4b (F)
LOT 30
tb (F)
/ CALL \
NC ONE —CALL
BEFORE YOU DIG
STO P
1-800-632-4949
AVOID UTILITY DAMAGE
\ IT'S THE LAW! /
F.E.M.A.- F.I.R.M. INFORMATION
COMMUNITY NUMBER: 370539 MAP NUMBER:3710551200K
EFFECTIVE DATE:02/19/2014 ZONE: X (OUT)
LEGEND
(F)
(S)
#4b
#5b
MAG
CM
R/W
—S-
-SD—
Em
DI
fiffi
CB
GENERAL NOTES & REFERENCES
SUBJECT PARCEL
TAX PARCEL #13904236
N/F
RUVIM SNKINDER
LOT 33
MAP BOOK 70 PAGE 838
DEED BOOK 37522-794
TOTAL AREA m 87,418 SF / 2.007 AC
PROPERTY CORNER
FOUND
SET
No. 4 REBAR
No. 5 REBAR
SURVEY NAIL
CONCRETE MONUMENT
RIGHT OF WAY
PROPOSED SEPTIC SUPPLY
STORM DRAIN
DROP INLET
CATCH BASIN
TOPOGRAPHIC SURVEY BY LUCAS-FORMAN, INC. DATED 01/30/2023.
EROSION CONTROL NOTES
Denuded area is 39,883 sq. ft. / 0.916 acres
Soil type is CeB2 & MeB
Subject Property is located in the Clear Watershed.
• All "Std." numbers refer to the Mecklenburg County Land Development Standards
Manual.
• On -site burial pits require an on -site demolition landfill permit from the Zoning
Administrator.
• Any grading beyond the denuded limits shown on the plan is a violation of the County
Erosion Control Ordinance and is subject to a fine.
• Grading more than one acre without an approved Erosion Control Plan is a violation of
the County Erosion Control Ordinance and is subject to a fine.
• Soil stabilization shall be required on any area of a site where land -disturbing activities
have temporarily or permanently ceased according to the following schedule:
•• All perimeter dikes, swales, ditches, perimeter slopes and all slopes steeper than 3
horizontal to 1 vertical (3:1) shall be provided temporary or permanent
stabilization with ground cover as soon as practicable but in any event within 7
calendar days from the last land -disturbing activity.
•• All other disturbed areas shall be provided temporary or permanent stabilization
with ground cover as soon as practicable but in any event within 14 calendar days
from the last land -disturbing activity.
• Additional measures to control erosion and sediment may be required by a
representative of the County.
• Slopes shall be graded no steeper than 2:1. Fill slopes greater than 10' require adequate
terracing [MCLDS #30.16]. Soils engineer to verify stability of slopes greater than 2:1.
• A grading plan must be submitted for any lot grading exceeding one acre that was not
previously approved.
• Temporary driveway permit for construction entrances in NCDOT right of way must be
presented at pre -construction meeting.
• All embankments must be constructed per Section 4.0.6 Embankment Requirements in
the BMP Design Manual.
CONSTRUCTION SEQUENCE
1. Obtain Grading/Erosion Control plan approval from the Mecklenburg County
LUESA.
2. Set up an on -site pre -construction conference with the following departments:
LUESA Erosion Control Inspector, Land Development Inspector and Zoning
Inspector. Failure to schedule such conference 48 hours prior to any land
disturbing activity is subject to fine.
3. Install silt fence, inlet protection, sediment traps, diversion ditches, tree
protection, and other measures as shown on plans, clearing only as necessary to
install these devices.
4. Call for on -site inspection by Inspector. When approved, Inspector issues the
Grading Permit and demolition, clearing and grubbing may begin.
5. The contractor shall diligently and continuously maintain all erosion control
devices and structures.
6. For phased erosion control plans, contractor shall meet with Erosion Control
Inspector prior to commencing with each phase of erosion control measures.
7. The land development inspector should be called to conduct inspections on
storm drainage, sidewalks, driveway on storm drainage, sidewalks, drive way
improvements, and all aspects of road construction
8. Stabilize site as areas are brought to finished grade.
9. Coordinate with Erosion Control Inspector prior to removal of erosion control
measures in each phase.
10. All erosion control measures shall be constructed in accordance with the N. C.
Erosion and Sediment Control Planning and Design Manual, U. S. Dept. of
Agriculture, Mecklenburg County Erosion Control Ordinance, and the
Charlotte -Mecklenburg Land Development Standards.
11. omitted: no BMPs proposed.
VICINITY MAP
n. t. s.
0 15 30 80
1 inch = 30 ft.
DRAWING ISSUE & REVISION STATUS
ISSUE DATE I BY I DESCRIPTION
r
Lucas -Forman
Incorporated
Land Surveying
Planning & Engineering
NC COA C-1215
4000 Stuart Andrew Boulevard
Charlotte, North Carolina 282f7
P.O. Box I f386 28220-f386
(704) 527-6626
email. postmaster@lucasrfonman.com
SEAL
- SEAL
02593T
CLIENT
OWNER: RUVIM SNKINDER
2102 CAPRICORN AV
INDIAN TRAIL, NC 28079
704-989-7404
PROJECT NAME
9225 ARLINGTON HILLS DRIVE
MINT HILL, NC
SHEET NAME
EROSION CONTROL &
GRADING PLAN
DRAWN BY DWG FILE NAME I DATE
JTE 02/23/2023
SURVEYED BY I DESIGNED BY SHEET NUMBER
MMA JTE
JOB NUMBER I FILE NUMBER C 1 .0
23011
PART III
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION A: SELF -INSPECTION
Self -inspections are required during normal business hours in accordance with the table
below. When adverse weather or site conditions would cause the safety of the inspection
personnel to be in jeopardy, the inspection may be delayed until the next business day on
which it is safe to perform the inspection. In addition, when a storm event of equal to or
greater than 1.0 inch occurs outside of normal business hours, the self -inspection shall be
performed upon the commencement of the next business day. Anytime when inspections
were delayed shall be noted in the Inspection Record.
Frequency
Inspect
(during normal
Inspection records must include:
business hours)
(1) Rain gauge
Daily
Daily rainfall amounts.
maintained in
If no daily rain gauge observations are made during weekend or
good working
holiday periods, and no individual -day rainfall information is
order
available, record the cumulative rain measurement for those un-
attended days (and this will determine if a site inspection is
needed). Days on which no rainfall occurred shall be recorded as
"zero." The permittee may use another rain -monitoring device
approved by the Division.
(2) E&SC
At least once per
1. Identification of the measures inspected,
Measures
7 calendar days
2. Date and time of the inspection,
and within 24
3. Name ofthe person performingthe inspection,
hours of a rain
4. Indication of whether the measures were operating
event > 1.0 inch in
properly,
24 hours
5. Description of maintenance needs forthe measure,
6. Description, evidence, and date of corrective actions taken.
(3) Stormwater
At least once per
1. Identification of the discharge outfalls inspected,
discharge
7 calendar days
2. Date and time of the inspection,
outfalls (SDOs)
and within 24
3. Name ofthe person performingthe inspection,
hours of a rain
4. Evidence of indicators of stormwater pollution such as oil
event > 1.0 inch in
sheen, floating or suspended solids or discoloration,
24 hours
5. Indication of visible sediment leaving the site,
6. Description, evidence, and date of corrective actions taken.
(4) Perimeter of
At least once per
If visible sedimentation is found outside site limits, then a record
site
7 calendar days
of the following shall be made:
and within 24
1. Actions taken to clean up or stabilize the sediment that has left
hours of a rain
the site limits,
event > 1.0 inch in
2. Description, evidence, and date of corrective actions taken, and
24 hours
3. An explanation as to the actions taken to control future
releases.
(5) Streams or
At least once per
If the stream or wetland has increased visible sedimentation or a
wetlands onsite
7 calendar days
stream has visible increased turbidity from the construction
or offsite
and within 24
activity, then a record ofthe following shall be made:
(where
hours of a rain
1. Description, evidence and date of corrective actions taken, and
accessible)
event > 1.0 inch in
2. Records of the required reports to the appropriate Division
24 hours
Regional Office per Part III, Section C, Item (2)(a) of this permit.
(6) Ground
After each phase
1. The phase of grading (installation of perimeter E&SC
stabilization
of grading
measures, clearing and grubbing, installation of storm
measures
drainage facilities, completion of all land -disturbing
activity, construction or redevelopment, Permanent
ground cover).
2. Documentation that the required ground stabilization
measures have been provided within the required
timeframe or an assurance that they will be provided as
soon as possible.
NOTE: The rain inspection resets the required 7 calendar day inspection requirement.
PART III
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION B: RECORDKEEPING
1. E&SC Plan Documentation
The approved E&SC plan as well as any approved deviation shall be kept on the site. The
approved E&SC plan must be kept up-to-date throughout the coverage under this permit.
The following items pertaining to the E&SC plan shall be kept on site and available for
inspection at all times during normal business hours.
Item to Document
Documentation Requirements
(a) Each E&SC measure has been installed
Initial and date each E&SC measure on a copy
and does not significantly deviate from the
of the approved E&SC plan or complete, date
locations, dimensions and relative elevations
and sign an inspection report that lists each
shown on the approved E&SC plan.
E&SC measure shown on the approved E&SC
plan. This documentation is required upon the
initial installation ofthe E&SC measures or if
the E&SC measures are modified after initial
installation.
(b) A phase of grading has been completed.
Initial and date a copy ofthe approved E&SC
plan or complete, date and sign an inspection
report to indicate completion of the
construction phase.
(c) Ground cover is located and installed
Initial and date a copy of the approved E&SC
in accordance with the approved E&SC
plan or complete, date and sign an inspection
plan.
report to indicate compliance with approved
ground cover specifications.
(d) The maintenance and repair
Complete, date and sign an inspection report.
requirements for all E&SC measures
have been performed.
(e) Corrective actions have been taken
Initial and date a copy ofthe approved E&SC
to E&SC measures.
plan or complete, date and sign an inspection
report to indicate the completion of the
corrective action.
2. Additional Documentation to be Kept on Site
In addition to the E&SC plan documents above, the following items shall be kept on the
site and available for inspectors at all times during normal business hours, unless the
Division provides a site -specific exemption based on unique site conditions that make
this requirement not practical:
(a) This General Permit as well as the Certificate of Coverage, after it is received.
(b) Records of inspections made during the previous twelve months. The permittee shall
record the required observations on the Inspection Record Form provided by the
Division or a similar inspection form that includes all the required elements. Use of
P q
electronically -available records in lieu of the required paper copies will be allowed if
shown to provide equal access and utility as the hard -copy records.
3. Documentation to be Retained for Three Years
All data used to complete the a-NOI and all inspection records shall be maintained for a period
of three years after project completion and made available upon request. [40 CFR 122.41]
PART II, SECTION G, ITEM (4)
DRAW DOWN OF SEDIMENT BASINS FOR MAINTENANCE OR CLOSE OUT
Sediment basins and traps that receive runoff from drainage areas of one acre or more shall use outlet structures that withdraw water from the surface when these devices need to be drawn down
for maintenance or close out unless this is infeasible. The circumstances in which it is not feasible to withdraw water from the surface shall be rare (for example, times with extended cold weather).
Non -surface withdrawals from sediment basins shall be allowed only when all of the following criteria have been met:
(a) The ESSC plan authority has been provided with documentation ofthe non -surface withdrawal and the specific time periods or conditions in which it will occur. The non -surface withdrawal
shall not commence until the E&SC plan authority has approved these items,
(b) The non -surface withdrawal has been reported as an anticipated bypass in accordance with Part III, Section C, Item (2)(c) and (d) of this permit,
(c) Dewatering discharges are treated with controls to minimize discharges of pollutants from stormwater that is removed from the sediment basin. Examples of appropriate controls include
properly sited, designed and maintained dewatering tanks, weir tanks, and filtration systems,
(d) Vegetated, upland areas of the sites or a properly designed stone pad is used to the extent feasible at the outlet ofthe dewatering treatment devices described in Item (c) above,
(e) Velocity dissipation devices such as check dams, sediment traps, and riprap are provided at the discharge points of all dewatering devices, and
(f) Sediment removed from the dewatering treatment devices described in Item (c) above is disposed of in a manner that does not cause deposition of sediment into waters of the United States.
PART III
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION C: REPORTING
1. Occurrences that Must be Reported
Permittees shall report the following occurrences:
(a) Visible sediment deposition in a stream or wetland.
(b) Oil spills if:
• They are 25 gallons or more,
• They are less than 25 gallons but cannot be cleaned up within 24 hours,
• They cause sheen on surface waters (regardless of volume), or
• They are within 100 feet of surface waters (regardless of volume).
(c) Releases of hazardous substances in excess of reportable quantities under Section 311
of the Clean Water Act (Ref: 40 CFR 110.3 and 40 CFR 117.3) or Section 102 of CERCLA
(Ref: 40 CFR 302.4) or G.S. 143-215.85.
(d) Anticipated bypasses and unanticipated bypasses.
(e) Noncompliance with the conditions of this permit that may endanger health or the
environment.
2. Reporting Timeframes and Other Requirements
After a permittee becomes aware of an occurrence that must be reported, he shall contact
the appropriate Division regional office within the timeframes and in accordance with the
other requirements listed below. Occurrences outside normal business hours may also be
reported to the Department's Environmental Emergency Center personnel at (800)
858-0368.
Occurrence
Reporting Timeframes (After Discovery) and Other Requirements
(a) Visible sediment
• Within 24 hours, an oral or electronic notification.
deposition in a
• Within 7 calendar days, a report that contains a description of the
stream or wetland
sediment and actions taken to address the cause of the deposition.
Division staff may waive the requirement for a written report on a
case -by -case basis.
• If the stream is named on the INC 303(d) list as impaired for sediment -
related causes, the permittee may be required to perform additional
monitoring, inspections or apply more stringent practices if staff
determine that additional requirements are needed to assure compliance
with the federal or state impaired -waters conditions.
b Oils ills and
I) P
• Within 24 hours an oral or electronic notification. The notification
,
release of
shall include information about the date, time, nature, volume and
hazardous
location of the spill or release.
substances per Item
1(b)-(c) above
(c) Anticipated
• A report at least ten days before the date ofthe bypass, if possible.
bypasses [40 CFR
The report shall include an evaluation of the anticipated quality and
122.41(m)(3)]
effect of the bypass.
(d) Unanticipated
• Within 24 hours, an oral or electronic notification.
bypasses [40 CFR
• Within 7 calendar days, a report that includes an evaluation ofthe
122.41(m)(3)]
quality and effect of the bypass.
(e) Noncompliance
• Within 24 hours, an oral or electronic notification.
with the conditions
• Within 7 calendar days, a report that contains a description of the
of this permit that
noncompliance, and its causes; the period of noncompliance,
may endanger
including exact dates and times, and if the noncompliance has not
health or the
been corrected, the anticipated time noncompliance is expected to
environment[40
continue; and steps taken or planned to reduce, eliminate, and
CFR 122.41(I)(7)]
prevent reoccurrence of the noncompliance. [40 CFR 122.41(I)(6).
• Division staff may waive the requirement for a written report on a
case -by -case basis.
NCGO1 SELF -INSPECTION, RECORDKEEPING AND REPORTING EFFECTIVE: 04/01/19 1
GROUND STABILIZATION AND MATERIALS HANDLING PRACTICES FOR COMPLIANCE WITH
THE NCGO1 CONSTRUCTION GENERAL PERMIT
Implementing the details and specifications on this plan sheet will result in the construction
activity being considered compliant with the Ground Stabilization and Materials Handling
sections of the NCGO1 Construction General Permit Sections E and F respectively). ( P Y). The
permittee shall comply with the Erosion and Sediment Control plan approved by the
delegated authority having jurisdiction. All details and specifications shown on this sheet
may not apply depending on site conditions and the delegated authority having jurisdiction.
SECTION E: GROUND STABILIZATION
Required Ground Stabilization Timeframes
Stabilize within this
Site Area Description
many calendar
Timeframe variations
days after ceasing
land disturbance
(a) Perimeter dikes,
swales, ditches, and
7
None
perimeter slopes
(b) High Quality Water
7
None
(HQW) Zones
(c) Slopes steeper than
If slopes are 10' or less in length and are
3:1
7
not steeper than 2:1, 14 days are
allowed
-7 days for slopes greater than 50' in
length and with slopes steeper than 4:1
-7 days for perimeter dikes, swales,
(d) Slopes 3:1 to 4:1
14
ditches, perimeter slopes and HQW
Zones
-10 days for Falls Lake Watershed
-7 days for perimeter dikes, swales,
(e) Areas with slopes
ditches, perimeter slopes and HQW Zones
flatter than 4:1
14
-10 days for Falls Lake Watershed unless
there is zero slope
Note: After the permanent cessation of construction activities, any areas with temporary
ground stabilization shall be converted to permanent ground stabilization as soon as
practicable but in no case longer than 90 calendar days after the last land disturbing
activity. Temporary ground stabilization shall be maintained in a manner to render the
surface stable against accelerated erosion until permanent ground stabilization is achieved.
GROUND STABILIZATION SPECIFICATION
Stabilize the ground sufficiently so that rain will not dislodge the soil. Use one of the
techniques in the table below:
Temporary Stabilization
Permanent Stabilization
• Temporary grass seed covered with straw or
• Permanent grass seed covered with straw or
other mulches and tackifiers
other mulches and tackifiers
• Hydroseeding
• Geotextile fabrics such as permanent soil
• Rolled erosion control products with or
reinforcement matting
without temporary grass seed
• Hydroseeding
• Appropriately applied straw or other mulch
• Shrubs or other permanent plantings covered
• Plastic sheeting
with mulch
• Uniform and evenly distributed ground cover
sufficientto restrain erosion
• Structural methods such as concrete, asphalt or
retainingwalls
• Rolled erosion control products with grass seed
POLYACRYLAMIDES (PAMS) AND FLOCCULANTS
1. Select flocculants that are appropriate for the soils being exposed during
construction, selecting from the NC DWR List of Approved PAMS/Flocculants.
2. Apply flocculants at or before the inlets to Erosion and Sediment Control Measures.
3. Apply flocculants at the concentrations specified in the NC DWR List of Approved
PAMS/Flocculants and in accordance with the manufacturer's instructions.
4. Provide ponding area for containment of treated Stormwater before discharging
offsite.
5. Store flocculants in leak -proof containers that are kept under storm -resistant cover
or surrounded by secondary containment structures.
EQUIPMENT AND VEHICLE MAINTENANCE
1. Maintain vehicles and equipmentto prevent discharge of fluids.
2. Provide drip pans under any stored equipment.
3. Identify leaks and repair as soon as feasible, or remove leaking equipment from the
project.
4. Collect all spent fluids, store in separate containers and properly dispose as
hazardous waste (recycle when possible).
5. Remove leaking vehicles and construction equipment from service until the problem
has been corrected.
6. Bring used fuels, lubricants, coolants, hydraulic fluids and other petroleum products
to a recycling or disposal center that handles these materials.
LITTER, BUILDING MATERIAL AND LAND CLEARING WASTE
1. Never bury or burn waste. Place litter and debris in approved waste containers.
2. Provide a sufficient number and size of waste containers (e.g dumpster, trash
receptacle) on site to contain construction and domestic wastes.
3. Locate waste containers at least 50 feet away from storm drain inlets and surface
waters unless no other alternatives are reasonably available.
4. Locate waste containers on areas that do not receive substantial amounts of runoff
from upland areas and does not drain directly to a storm drain, stream or wetland.
5. Cover waste containers at the end of each workday and before storm events or
provide secondary containment. Repair or replace damaged waste containers.
6. Anchor all lightweight items in waste containers during times of high winds.
7. Empty waste containers as needed to prevent overflow. Clean up immediately if
containers overflow.
8. Dispose waste off -site at an approved disposal facility.
9. On business days, clean up and dispose of waste in designated waste containers.
PAINT AND OTHER LIQUID WASTE
1. Do not dump paint and other liquid waste into storm drains, streams or wetlands.
2. Locate paint washouts at least 50 feet away from storm drain inlets and surface
waters unless no other alternatives are reasonably available.
3. Contain liquid wastes in a controlled area.
4. Containment must be labeled, sized and placed appropriately for the needs of site.
5. Prevent the discharge of soaps, solvents, detergents and other liquid wastes from
construction sites.
PORTABLE TOILETS
1. Install portable toilets on level ground, at least 50 feet away from storm drains,
streams or wetlands unless there is no alternative reasonably available. If 50 foot
offset is not attainable, provide relocation of portable toilet behind silt fence or place
on a gravel pad and surround with sand bags.
2. Provide staking or anchoring of portable toilets during periods of high winds or in high
foot traffic areas.
3. Monitor portable toilets for leaking and properly dispose of any leaked material.
Utilize a licensed sanitary waste hauler to remove leaking portable toilets and replace
with properly operating unit.
EARTHEN STOCKPILE MANAGEMENT
1. Show stockpile locations on plans. Locate earthen -material stockpile areas at least
P P p
50 feet away from storm drain inlets, sediment basins, perimeter sediment controls
and surface waters unless it can be shown no other alternatives are reasonably
available.
2. Protect stockpile with silt fence installed along toe of slope with a minimum offset of
five feet from the toe of stockpile.
3. Provide stable stone access point when feasible.
4. Stabilize stockpile within the timeframes provided on this sheet and in accordance
with the approved plan and any additional requirements. Soil stabilization is defined
as vegetative, physical or chemical coverage techniques that will restrain accelerated
erosion on disturbed soils for temporary or permanent control needs.
ONSITE CONCRETE WASHOUT
STRUCTURE WITH LINER
a
0 m m 0 T �ma' I�'"`�.-
0 00 0 - 1
0 0
00
B
oer.url. .a. sccnox - ,•r��r�ws.,,., ,�,rm, oEra.-o,.
TTs ..ate
even even �."
BELOW GRADE WASHDOT STROCTORE ABOVE GRADE VASHOOTS STROCTORE
CONCRETE WASHOUTS
1. Do not discharge concrete or cement slurry from the site.
2. Disposeor recycle of settled hardened concrete residue in accordance with local
and state solid waste regulations and at an approved facility.
3. Manage washout from mortar mixers in accordance with the above item and in
addition place the mixer and associated materials on impervious barrier and within
lot perimeter silt fence.
4. Install temporary concrete washouts per local requirements, where applicable. If an
alternate method or product is to be used, contact your approval authority for
review and approval. If local standard details are not available, use one ofthe two
types of temporary concrete washouts provided on this detail.
5. Do not use concrete washouts for dewatering or storing defective curb or sidewalk
sections. Stormwater accumulated within the washout may not be pumped into or
discharged to the storm drain system or receiving surface waters. Liquid waste must
be pumped out and removed from project.
6. Locate washouts at least 50 feet from storm drain inlets and surface waters unless it
can be shown that no other alternatives are reasonably available. At a minimum,
install protection of storm drain inlet(s) closest to the washout which could receive
spills or overflow.
7. Locate washouts in an easily accessible area, on level ground and install a stone
entrance pad in front of the washout. Additional controls may be required by the
approving authority.
8. Install at [east one sign directing concrete trucks to the washout within the project
limits. Post signage on the washout itself to identify this location.
9. Remove leavings from the washout when at approximately 75% capacity to limit
overflow events. Replace the tarp, sand bags or other temporary structural
components when no longer functional. When utilizing alternative or proprietary
products, follow manufacturer's instructions.
10. At the completion of the concrete work, remove remaining leavings and dispose of
in an approved disposal facility. Fill pit, if applicable, and stabilize any disturbance
caused by removal of washout.
1. Store and apply herbicides, pesticides and rodenticides in accordance with label
restrictions.
2. Store herbicides pesticides and rodenticides in their original containers with the
.P
label, which lists directions for use, ingredients and first aid steps in case of
accidental poisoning.
3. Do not store herbicides, pesticides and rodenticides in areas where flooding is
possible or where they may spill or leak into wells, stormwater drains, ground water
or surface water. If a spill occurs, clean area immediately.
4. Do not stockpile these materials onsite.
HAZARDOUS AND TOXIC WASTE
1. Create designated hazardous waste collection areas on -site.
2. Place hazardous waste containers under cover or in secondary containment.
3. Do not store hazardous chemicals, drums or bagged materials directly on the ground.
NCGO1 GROUND STABILIZATION AND MATERIALS HANDLING EFFECTIVE: 04/01/19I
6' MAX.
WOVEN FILTER FABRIC
i
GENERAL NOTES:
1. FILTER FABRIC FENCE SHALL BE A MINIMUM of 32" IN WIDTH AND SHALL HAVE A
MINIMUM OF 6 LINE WIRES WITH 12" STAY SPACING.
2. WOVEN FILTER FABRIC BE USED WHERE SILT FENCE IS TO REMAIN FOR A PERIOD OF
MORE THAN 30 DAYS.
3. STEEL POSTS SHALL BE 5'-0" IN HEIGHT AND BE OF THE SELF -FASTENER ANGLE STEEL
TYPE.
4. TURN SILT FENCE UP SLOPE AT ENDS.
5. ORANGE SAFETY FENCE IS REQUIRED AT BACK OF SILT FENCE WHEN GRADING IS
ADJACENT TO SWIM BUFFERS, STREAMS OR WETLANDS (REFER TO SWIM BUFFER
GUIDELINES). THE COLOR ORANGE IS RESERVED FOR VISUAL IDENTIFICATION OF
ENVIRONMENTALLY SENSITIVE AREAS.
6. DRAINAGE AREA CAN NOT BE GREATER THAN 1/4 ACRE PER 100 FT OF FENCE.
7. SLOPE LENGTHS CAN NOT EXCEED CRITERIA SHOWN IN TABLE 6.62A NORTH CAROLINA
EROSION AND SEDIMENT CONTROL PLANNING AND DESIGN MANUAL.
8. DO NOT INSTALL SEDIMENT FENCE ACROSS STREAMS, DITCHES, WATERWAYS OR OTHER
AREAS OF CONCENTRATED FLOW.
MECKLENBURG COUNTY re spa
z
LAND DEVELOPMENT
f
y11
z o z
STANDARDS
4' MAX
WIRE FENCING
(IF APPLICABL
WOVEN FILTER FABRIC
GENERAL NOTES:
1. SEDIMENT FILTER OUTLET AND HARDWARE CLOTH SHALL BE 16 INCHES HIGH BUT NO
TALLER THAN 18 INCHES.
2. HARDWARE CLOTH SHALL BE ANCHORED TO THE STEEL POSTS SECURELY USING
APPROPRIATE ANCHORS. HARDWARE CLOTH SHALL BE KEYED IN A MINIMUM OF 12 INCHES
IN LENGTH AND BACKFILLED PROPERLY AS SHOWN IN ABOVE DETAIL. HARDWARE CLOTH TO
BE SAME AS STD. 30.09 19 GAUGE 1 4' SPACING).
// ( / )
3. POSTS SHALL BE NO MORE THAN 4 FEET APART.
4. SITE OUTLETS AT ANY POINT SMALL CONCENTRATED FLOWS ARE ANTICIPATED AND AT THE
DIRECTION OF THE INSPECTOR.
5. ONE ACRE MAXIMUM DRAINAGE AREA PER OUTLET.
MECKLENBURG COUNTY
LAND DEVELOPMENT
f
y11
z o z
STANDARDS
GENTLE SLOPES
STEEL POST
z
FILTER FABRIC
o
-o
�m
4
FLOW
T I
- IIIIII iW„i I I i. --
F4 ANCHOR SKIRT;
EXCAVATE TRENCH
AND COMPACT
BACKFILL
MAINTENANCE NOTES:
1. FILTER BARRIERS SHALL BE INSPECTED BY THE FINANCIALLY RESPONSIBLE PARTY
OR HIS AGENT IMMEDIATELY AFTER EACH RAINFALL AND AT LEAST DAILY DURING
PROLONGED RAINFALL. ANY REPAIRS NEEDED SHALL BE MADE IMMEDIATELY.
2. SHOULD THE FABRIC DECOMPOSE OR BECOME INEFFECTIVE PRIOR TO THE END
OF THE EXPECTED USABLE LIFE AND THE BARRIER STILL IS NECESSARY, THE
FABRIC SHALL BE REPLACED PROMPTLY.
3. SEDIMENT DEPOSITS SHOULD BE REMOVED WHEN DEPOSITS REACH APPROX. HALF
THE HEIGHT OF THE BARRIER. ANY SEDIMENT DEPOSITS REMAINING IN PLACE
AFTER THE SILT FENCE IS REMOVED SHALL BE DRESSED TO CONFORM TO THE
EXISTING GRADE, PREPARED AND SEEDED.
Ira•I1�1:�:�yaa��l�re�z�T;a��m: ►�����n�iK�z��y�Y��
EARLY SUMMER SEASON
STEEP SLOPES
SEEDING
MIXTURE
40 Ibs/acre of German millet
80 Ibs/acre of tall fesue
120 Ibs/acre Rye (grain)
80 Ibs/acre tall fesue
May 1 - August 15
October 25 - December 30
SEEDING
Refertilize if growth is not fully adequate.
Between December 30 - February 15,
DATES
add 50 Ibs/acre of annual Kobe lespedeza.
Apply 4000 Ibs/acre straw or equivalent
Apply 4000 Ibs/acre straw or equivalent
hydroseeding.
hydroseeding.
SEEDING
Apply lime and fertilizer per soil tests, or 2000
Apply lime and fertilizer per soil tests, or 2000
AMENDMENTS
Ibs/acre limestone and 750 Ibs/acre 10-10-10
Ibs/acre limestone and 750 Ibs/acre 10-10-10
fertilizer.
fertilizer.
APPROVED DATE: 0212007
NOT TO SCALE
MECKLENBURG COUNTY re spa°
LAND DEVELOPMENT
x
.,I
STD. N0. REV. y11
TEMPORARY SIFT FENCE _rd e z
z o
30.06A STANDARDS
POST
ARE CLOTH
- WASHED STONE
(NCOOT 05 OR #57)
FLOW
4-
ANCHOR SKIRT;
EXCAVATE TRENCH
AND COMPACT
BACKFILL
MAINTENANCE NOTES:
1. FILTER OUTLETS SHALL BE INSPECTED BY THE FINANCIALLY RESPONSIBLE PARTY OR
HIS AGENT IMMEDIATELY AFTER EACH RAINFALL AND AT LEAST DAILY DURING
PROLONGED RAINFALL. ANY REPAIRS NEEDED SHALL BE MADE IMMEDIATELY.
2. THE STONE SHALL BE REPLACED PROMPTLY AFTER ANY EVENT THAT HAS CLOGGED
OR REMOVED IT.
3. SEDIMENT DEPOSITS SHOULD BE REMOVED WHEN DEPOSITS REACH HALF THE HEIGHT
OF THE BARRIER. ANY SEDIMENT DEPOSITS REMAINING IN PLACE AFTER THE SILT
FENCE OUTLET IS REMOVED SHALL BE DRESSED TO CONFORM TO THE EXISTING
GRADE, PREPARED AND SEEDED.
SILT FENCE
OUTLET OPTION 2
STEEP SLOPES
SEEDING SCHEDULE
(SEASONAL)
NOTES:
1. A STABILIZED ENTRANCE PAD OF 2"-3" WASHED STONE SHALL BE LOCATED WHERE TRAFFIC WILL ENTER OR LEAVE
THE CONSTRUCTION SITE ONTO A PUBLIC STREET.
2. FILTER FABRIC OR COMPACTED CRUSHER RUN STONE SHALL BE USED AS A BASE FOR THE CONSTRUCTION ENTRANCE.
3. THE ENTRANCE SHALL BE MAINTAINED IN A CONDITION WHICH WILL PREVENT TRACKING OR FLOWING OF SEDIMENT
ONTO PUBLIC STREETS OR EXISTING PAVEMENT. THIS MAY REQUIRE PERIODIC TOP DRESSING WITH ADDITIONAL
STONE AS CONDITIONS WARRANT AND REPAIR OR CLEANOUT OF ANY MEASURES USED TO TRAP SEDIMENT.
4. ANY SEDIMENT SPILLED, DROPPED, WASHED, OR TRACKED ONTO PUBLIC STREETS MUST BE REMOVED IMMEDIATELY.
5. WHEN APPROPRIATE, WHEELS MUST BE CLEANED TO REMOVE SEDIMENT PRIOR TO ENTERING A PUBLIC STREET. WHEN
WASHING IS REQUIRED, IT SHALL BE DONE IN AN AREA STABILIZED WITH CRUSHED STONE WHICH DRAINS INTO AN
APPROVED SEDIMENT BASIN SEE STD. NO. 30.11B.
6. COUNTY MAY REQUIRE A STANDARD COMMERCIAL DRIVEWAY (STD. 10.24 & 10.25) TO
ACCESS THE CONSTRUCTION SITE IF THE DRIVEWAY IS ON A THOROUGHFARE.
EXISTING GROUND'
APPROVED DATE; 0212007
NOT TO SCALE
MECKLENBURG COUNTY r-`"".UR°
LAND DEVELOPMENT f »'
n. l r
STD. N0. REV. _i
«2
o i
1,30.06DI STANDARDS
SEEDING
MIXTURE
80 Ibs/acre of tall fesue
100 Ibs/acre tall fescue
30 Ibs/acre Sericea lespedeza
(unscorified after August 15)
10 Ibs/acre Kobe lespedeza
FALL: August 25 - October
FALL: August 25 - October 15
Late winter: February 15 - April 15
Late winter: February 15 - April 15
SEEDING
To extend spring seeding into June, add
To extend spring seeding into June, add
DATES
15 Ibs/acre hulled Bermudagrass
15 Ibs/acre hulled Bermudagrass
Overseeding of Kobe lespedeza over fall -seeded
Overseeding of Kobe lespedeza over fall -seeded
tall fescue is very effective.
tall fescue is very effective.
SEEDING
Apply lime and fertilizer per soil tests, or 4000
Apply lime and fertilizer per soil tests, or 4000
AMENDMENTS
Ibs/acre limestone and 1000 Ibs/acre 10-10-10
Ibs/acre limestone and 1000 Ibs/acre 10-10-10
fertilizer.
fertilizer.
NOTE 1
Ground Cover-- Protective cover must be established on all disturbed areas within 21 calendar days after
land disturbing activity is completed or has temporarily ceased.
NOTE 2
Graded slopes and fills --Protective cover must be established on all graded slopes and fills within 21 calendar days after
a phase of grading is completed or has temporarily ceased.
APPROVED DATE 0212007
MECKLENBURG COUNTY
LAND DEVELOPMENT fi z
STANDARDS
SEEDING SCHEDULE
30.1 7A
SOIL STABILIZATION FABRIC =
UNDER 2"-3" WASHED STONE
NOT TO SCALE
PUBLIC STREET
I-
LJ
w
of
Cn
U1
U
J
m
a-
30.17B
NOT TO SCALE
y"no] WAR0z410Myr:4 dKGPIE I r:�ry0
30.1 1A
VICINITY MAP
n. t. s.
0 15 30 60
1 inch = 30 ft.
DRAWING ISSUE & REVISION STATUS
ISSUE DATE BY DESCRIPTION
r
Lucas -Forman
Incorporated
Land Surveying
Planning & Engineering
NC COA C-12115
4000 Stuart Andrew Boulevard
Charlotte, North Carolina 282f7
P.O. Box 19386 28220-f386
(704) 527-6626
email: postmaster@lucasrforman.com
SEAL
SEAL
02593T ow
r��7►' ��� >4't`Aiq� ��6la�
Io 0_,
qA ' i
yv��"
CLIENT
OWNER: RUVIM SHKINDER
2102 CAPRICORN AV
INDIAN TRAIL, NC 28079
704-989-7404
PROJECT NAME
9225 ARLINGTON HILLS DRIVE
MINT HILL, NC
SHEET NAME
EROSION CONTROL
DETAILS &
SPECIFICATIONS
DRAWN BY
D1113 FILE NAME
DATE
JTE
02/23/2023
I
SURVEYED BY
DESIGNED BY
SHEET NUMBER
MMA
JTE
FILE NUMBER
C2.0
JOB NUMBER
23011