HomeMy WebLinkAboutNCC230549_Site Plan or Location Map_20230302M '
CUF
LEGEND
FLOW DIRECTION
SILT FENCE
SILT FENCE OUTLET
CONSTRUCTION ENTRANCE
CURB INLET
\NC -En vironmen to1.jpeg
CONSTRUCTION SCHEDULE
1. Obtain all necessary permits and plan approvals. Erosion and Sediment Control
(E&SC) permit and a Certificate of Coverage (COC) must be obtained before any land disturbing activities
occur. A copy of the E&SC permit, the COC and a hard copy of the plan must be kept on site, preferably in a
permits box, and accessible during inspection.
2. Install gravel construction entrances first, then silt fences, reinforced silt fence outlets and wattles.
3. Finish clearing and grubbing any necessary areas on the lots as they are started.
4. Begin lot grading and excavation activities
5. Begin or continue with house construction activities.
6. Finish all rough grading and house construction.
7. Install driveways, walks and patios.
8. Begin fine grading of lot areas
9. Final grassing, mulching and stabilizing of lot. In most cases this will involve the installation of sod on the lot.
The silt fence will remain in place until the lot is sodded or grassing is stabilized and takes hold.
10. The contractor shall conduct self -inspections of the erosion and sedimentation control measures and complete
the following combined self -inspection form found on the DEMLR website
https:Hfiles.ne.gov/nedeg/Energy%2oMineral%20and%2OLand%2OResourees/Stormwater/NPDES%20
General%20Permits/DEMLR-CSW-Monitoring-Forms-Rev-August-8-2019.pdf. Twelve months of complete
inspection forms shall be kept on site and available for inspection at all times. It is recommended a copy be
kept in a permits box. (GS 113A-54.1 (e), 15A NCAC 0413.0131, NCGOI Part III Sections A and B)
11. Self -inspections for erosion and sedimentation control measures are to be performed at least once every seven
calendar days and within 24 hours of every rain event of greater than 1 inch. Any needed repairs shall be
made immediately to maintain measures as designed. All ESC measures shall be maintained as specified in
the construction details on this plan. A rain gauge shall be installed at the project site for monitoring.
12. Inspection and final acceptance letters. When the project is complete, the permittees shall contact DEMLR to
close out the E&SC Plan. After DEMLR informs the permittee of the project close out, via inspection report,
the permittee shall visit "deq.nc.gov/NCGO1" to submit an electronic Notice of termination (e-NOT). A $100
annual general permit fee will be charged until the e-NOT has been filled out.
I. II Ileeueu, I lee riuuu Ouuil Ie Twily DIIUUIu uu IIIDIGIIeu diully llle uullel LUlle, Weudllu
boundary and/or around protected trees, providing a radius of at least 1.25 feet for each
inch of trunk diameter.
2. Install Silt Fence on the low elevation sides of each lot. Install Silt Fence outlets shown on
schematic/diagram and field adjusted, if necessary, for placement at low points. If lots are
contiguous and have different land owners or builders, each lot should have individual Silt
Fences.
3. Install required Silt Fence within 10 feet of property line to ensure there is no conflict with
septic system. It is the responsibility of the builder to ensure the installation of sediment
control measures does not impact the septic system and repair area(s).
4. At least one Construction Entrance/Exit is to be installed per lot.
5. Waste bins and other areas dedicated for managing building material waste shall be at
least 50 feet away from storm drain inlets or drainage ditches unless it can be shown that
no other alternative exists. If this separation cannot be achieved, these areas must be
contained behind Silt Fence.
6. Inlets downstream of disturbances should be protected; streets should be swept when
sediment from the construction activity is present.
7. Details for Silt Fence, Silt Fence Outlets, Construction Entrances and other measures are
provided on additional sheets. Erosion and sediment control details are not drawn to scale.
TYPICAL LOT LAYOUT WITH CURB AND GUTTER
PAGE:
DATE: PAGE:
Wire Fence Filter Fabric
Steel Post
8' Max. Standard Strength fabric with wire fence
6' Max. Extra strength fabric without wire fence
Wire ties
1
Wire Fence
- Steel Post
L 24„
8" down & 4" forward along the IT
nch
Backfill trench
and Compact
thoroughly
1 Upslope
In
8" 8" Min.
1
• Filter Fabric 0
Construction: CROSS SECTION VIEW
1. Construct the sediment barrier of standard strength or extra strength synthetic filter fabrics.
2. Ensure that the height of the sediment fence does not exceed 24 inches above the ground. (Higher fences may impound volumes of water
sufficient to cause failure of the structure) Maintenance:
3. Construct the filter fabric from a continuous roll cut to the length of the barrier to avoid joints. When joints are necessary, securely fasten the 1 Inspect sediment fences at least once a week and after each 1 inch or greater
filter cloth only at a support post with 4 feet minimum overiap to the next post. 4. Support standard strength filter fabric by wire mesh fastened securely to the upslope side of the posts. Extend the wire mesh support to the rainfall. Make any required repairs immediately.
2 Should the fabric of a sediment fence collapse, tear, decompose, or become
bottom of the trench. Fasten the wire reinforcement, then fabric on the upslope side of the fence post. Wire or plastic zip ties should have a ineffective, replace it promptly.
minimum pound tensile strength. 3Remove sediment deposits as necessary to provide adequate storage volume
5. When a wire mesh support fence is used, space posts a maximum of 8 feet apart. Supports should be driven securely into the ground a .
minimum of for the next rain and reduce pressure on the fence. Take care to avoid
undermining the fence during cleanouts.
6. Extra strengtthh filter inches. fabric with 6 foot post spacing does not require a wire mesh support fence. Securely fasten the filter fabric directly to posts. 4 Remove all fencing materials and unstable sediment deposits and bring the
Wire plastic zip ties should have a minimum of pound tensile strength. area to grade and stabilize it after the contributing drainage area has been
t 7. Excavate
anthe trench approximately 4 inches wide and inches deep along the proposed line of the posts and upslope from the barrier. properly stabilized.
8. Place 12 inches of fabric along the bottom and side of the trench.
9. Backfill the trench with soil placed over the filter fabric and compact. Thorough compaction of the backfill is critical to silt fence performance.
10. Do not attach filter fabric to existing trees.
\N C- En vi ron m en to I. jp eg
TOP OF SILT FENCE
MUST BE AT LEAST
ABOVE THE TOP OF
THE WASHED STOti
STEEL FENCE P WIRE FEN
HARDWARECLQ�ST
FILTER OF MrK
WASHED STO
BURY WIRE FENCE AND
..\NC-Environmenta1.jpeg
CLOTH
SILT FENCE
4' MIN.
SILT FENCE
FRONT VIEW
BURY WIRE FENCE,
FILTER FABRIC,
AND HARDWARE
STEEL FENCE POPT CLOTH IN TRENCH
SET MAX 2' APARjI
MIN. 18" INTO SOLID
T FILTER FABRIC GROUND
ON GROUND NOTES:
1. Hardware cloth and gravel should overlay the sift fence at least 12 inches.
2. Stone outlets should be placed on low elevation areas of silt fence and
based on field conditions.
MAINTENANCE:
1. Per NCG-01, inspect outlet at lest once a week and after each 1 inch
or greater rainfall event. Complete any required repairs immediately.
BURY 6" OF UPPER EDGE 05 Freshen stone when sediment accumulation exceeds 6 inches.
FILTER FABRIC IN TRENCH 3. Keep mesh free of debris to provide adequate flow.
4. Remove sediment when haft of stone outlet is covered.
5. Replace stone as needed to facilitate de -watering.
SILT FENCE OUTLET
A "SELF -INSPECTION REPORT FOR LAND DISTURBING ACTIVITY AS REQUIRED BY
NCGS 113A-54.1"IS AVAILABLE FOR USE. IT CAN BE COMPLETED BY HAND OR
COMPLETED AS AN EXCEL SPREADSHEET.
AN ALTERNATIVE IS TO MAKE NOTATIONS ON THE COPY OF THE APPROVED
EROSION AND
SEDIMENTATION CONTROL PLAN THAT IS KEPT ON THE PROJECT SITE. RULE 15A
NCAC 04B. 0131 STATES THAT "...DOCUMENTATION SHALL BE ACCOMPLISHED BY
INITIALING AND DATING EACH MEASURE OR PRACTICE SHOWN ON A COPY OF THE
APPROVED EROSION AND SEDIMENTATION CONTROL PLAN OR BY COMPLETING,
DATING AND SIGNING AN INSPECTION REPORT THAT LISTS EACH MEASURE,
PRACTICE OR DEVICE SHOWN ON THE APPROVED EROSION AND SEDIMENTATION
CONTROL PLAN."
Pursuant to G.S.113A(3), provisions for permanent ground cover sufficient to
restrain erosion must be accomplished for all disturbed areas within 14
working days or 60 calendar days (whichever is shorter) following completion
of construction.
General Erosion Control Notes
1. Only the areas shown shall be disturbed.
2. Temporary ground stabilization is required within 7 days on all
areas.
I
OPEN SPXCE
THIS PROJECT IS IN A
HIGH -QUALITY WATER ZONE
AND ALL REQUIREMENTS
REGARDING SENSITIVE AREA
WATERSHEDS SHOULD
BE FOLLOWED
THIS PROJECT IS IN A
HIGH -QUALITY WATER ZONE
AND ALL REQUIREMENTS
REGARDING SENSITIVE AREA
WATERSHEDS SHOULD
BE FOLLOWED
`P\
1 THIS PROJEGT�IS IN A
HIGH -QUALITY WATEkR ZONE
I AND ALL REQUIREMr=NTS
1 REGARDING SENSITIVE AR-kA
1 WATERSHEDS SHOULD
BE FOLLOWED
i 11P
70 1
I
GROUND STABILIZATION
SITE AREA
STABILIZATION
EXCEPTIONS
DESCRIPTION
TIME FRAME
PERIMETER DIKES,
7 DAYS
NONE
SWALES, DITCHES
& SLOPES
HIGH QUALITY
7 DAYS
NONE
WATER ZONES
(HQW)
SLOPES STEEPER
7 DAYS
IF SLOPES ARE
THAN 3:1
10' OR LESS IN
LENGTH AND ARE
NOT STEEPER
THAN 2:1, 14
DAYS ARE
ALLOWED
SLOPES 3:1 OR
14 DAYS
7 DAYS FOR
FLATTER
SLOPES GREATER
THAN 50' IN
LENGTH
ALL OTHER AREAS
14 DAYS
NONE (EXCEPT
WITH SLOPES
FOR PERIMETERS
FLATTER THAN 4:1
AND HQW ZONES)
SODDING
w..ww.w.wrw. r..w.wwwwwrw
LAY SOD IN A STAGGERED
4�✓N�
ry, ,
PATTERN. BUTT THE STRIPS
�
TIGHTLY AGAINST EACH OTHER.
pot
DO NOT LEAVE SPACES AND DO
NOT OVERLAP. A SHARPENED
MASON'S TROWEL IS A HANDY
TOOL FOR TUCKING DOWN THE
ENDS AND TRIMMING PIECES.
con �
CAUSED BY THE AUTO -
wcORRECT
MATIC SOD CUTTER MUST BE
M=
MATCHED CORRECTLY.
CORRECT
)LL SOD IMMEDIATELY TO WATER TO A DEPTH OF 4" MOW WHEN THE SOD IS
THIEVE FIRM CONTACT AS NEEDED. WATER WELL ESTABLISHED - IN 2-3
ITH THE SOIL AS SOON AS THE SOD IS WEEKS. SET THE MOWER
LAID. HIGH (2"-3").
APPEARANCE OF GOOD SOD
SHOOTS -OR GRASSBLABES_
GRASS SHOULD BE GREEN AND
HEALTHY, MOWED AT A2"-3"
CUTTING HEIGHT_
THATCH - GRASS CLIPPINGSAND DEAD
LEAVES_ UPTO 112"THICK_
ROOT ZON E - SOIL AND ROOTS SHOULD BE
1 /7 - 3W TH ICK, WITH DEN BE ROOT MAT
FOR STRENGTH_
/ MAINTENANCE OF EROSION AND SEDIMENTATION CONTROL MEASURES FOR LOT CONSTRUCTION
raj / Gravel Construction Entrance - The gravel pad should remain in a condition to prevent mud or sediment from leaving the construction site.
This may require periodic topdressing with 2-inch stone. After each rainfall, inspect any structure used to trap sediment and clean it out as necessary.
Immediately remove all objectionable materials spilled, washed, or tracked onto public roadways.
Silt Fence - Sediment fences should be inspected at least once a week and after each rainfall event. Any repairs should be made immediately.
Damaged or decomposed fabric should be replaced promptly. Any sediment deposits that build up against the fence should be removed and disposed
of properly to insure that the removed sediment does not wash back against the fence. Adequate storage volume should be provided for behind the fence
at tall times. Take care to not undermine the fence during cleanout operations.
/ Sodding - The sod should be properly maintained to insure that the grass take holds in the areas being secured. The sod should be watered as necessary
to maintain adequate moisture in the root zone and prevent dormancy of the sod. The sod should not be mowed to close, since this could inhibit adequate
growth and stabilization of the root bed. The sod should be limed and fertilized as per soil type recommendations and type of grass recommendations when
and if possible.
Grassing and Mulching - The area to receive grassing and mulching should be properly fertilized and limed as necessary as an initial step in soil preparation.
` Once the grassing has been placed, the area should be maintained as needed to insure that all areas are germinating properly. Any bare areas should be repaired,
and reseeded as soon as possible. If the time of year does not permit the establishment of a permanent grass, then a temporary grassing should be used until the
/ growing season permits the use of a permanent grass.
Diversion Berms - Diversion berms shall be inspected weekly or after each runoff producing rainfall to insure that they are operating as designed and that there
/ have been no breaches in the berm. Berms shall not exceed 18" in height, and shall be placed in locations that will not interfere with home construction activities.
/ Once the house construction is completed and the lot is ready to receive sod, then the berm shall be removed and the material incorporated into the graded lot area
and covered immediately with sod. All proper care shall be taken to insure that the berms are installed according to the applicable detail with the berm material
compacted sufficiently to insure that the berm remains in place during the course of the construction activities.
' General - All measures will be inspected and corrections made after runoff producing rainfalls, or at least once per week minimum. The builder will insure that the
construction activities on any particular lot do not adversely affect any of the installed erosion control measures. If lot construction dictates, measures will be relocated
1 on the lot to insure that the potential for sedimentation runoff is eliminated as much as possible. Silt fences and gravel construction entrances will be maintained as suggested
` in the erosion control manual. Sodding, seeding and mulching will be maintained to insure proper ground stabilizing cover.
Wattles - Wattles shall be inspected after significant rainfall events. Rills or gullies upslope of the wattle and any undercutting is to be repaired. Sediment deposits
that impair the filtration capability of the wattle shall be removed when the sediment reaches one-third of the wattles functional freeboard height. Removed
sediment shall be deposited within the project in such a way that the sediment is not subject to erosion by wind or water.
Reinforced Sitt Fence Outlet - Remove sediment deposits as necessary to provide adequate storage volume for the next rain to reduce
pressure on the fence/outlet. Take care to avoid undermining the fence during cleanout. Remove and replace stone as necessary
as it becomes clogged with sediment. Remove all fencing materials and unstable sediment deposits and bring the area to grade
and stabilize it after the contributing drainage area has been properly stabilized.
PAGE 1 of 2
LOT EROSION CONTROL PLAN
TOTAL DISTURBED ACREAGE: 0.23 ACRES
OF
LOTS 15 & 20
STATION
FAR
DREAM FINDERS HOMES, LLC
IN THE CITY OF VASS
McNEILL
TOWNSHIP
MOORE COUNTY, N.C.
SCALE: 1
"= 100'
FEBRUARY 2023
GRAPHIC
SCALE IN FEET
ENGINEERS
o D
-100
0
100 200 300 400
PLANNERS
SURVEYORS
MOORMAN, KIZER
& REITZEL, INC.
115 BROADFOOT AVE. FAYETTEVILLE, N.C.
M O O R M A N, K I Z E R 8c R E I TZ E L-, I N C.
PHONE
(910) 484-5191
FAX (910) 484-0388 License #: F-0106
UPPFNT J^R';A P -Fr P ''^,NSTP.I I''T^R`;AFF-1 1 7 q5 WINF'FR ' T^ I^N-F-', PI INs\ A/INF'FR ' Tn EXPRESS-