HomeMy WebLinkAbout20150009 Ver 1_Approval Letter_20150129Pat McCrory
Governor
���
�+��
NCDENR
North Carolina Department of Environment and Natural Resources
Donald van der Vaart
Secretary
January 29, 2015
Avery County
NCDWR Project No. 20150009
SR 1515 Sampson Road
Project No. 11 C.006010
APPROVAL of 401 WATER QUALITY CERTIFICATION, with ADDITIOIVAL CONDITIONS
Mr. Heath Slaughter (electronic copy)
NCDOT, Division 11 Environmental Officer
P.O. Box 250
North Wilkesboro, NC 28659
Dear Mr. Slaughter:
You have our approval, in accordance with the conditions listed below, for the following impacts to grade, drain,
base and pave three previously gapped sections of SR 1515 (Pilot Ridge Road) in Avery County:
Stream Im
Temporary Fill in
Site Perennial Stream
Dewatering
(linear ft)
4+12 � -
128+25 40
in the Catawba River Basin
Permanent Fill in
Perennial Stream
(linear ft)
Totals � 40 �
Total Stream Impact for Project: 125 linear feet.
20
65
85
Stream
Total Stream Impacts
Impact Requiring
(linear ft) Mitigation
(linear ftl
20
105
125
The project shall be constructed in accordance with your application dated January 2, 2015. After reviewing your
application, we have decided that these impacts are covered by General Water Quality Certification Number 3886.
This certification corresponds to the Nationwide Permit 14 issued by the Corps of Engineers. In addition, you
should acquire any other federal, state o'r local permits before you proceed with your.project including (but not
limited to) Sediment and Erosion Control, Non-Discharge and Water Supply Watershed regulations. This approval
will expire with the accompanying 404 permit.
This approval is valid solely for the purpose and design described in your application (unless modified below).
Should your project change, you must notify the NCDWR and submit a new application. If the property is sold, the
new owner must be given a copy of this Certification and approval letter, and is thereby responsible for complying
with all the conditions. If total wetland fills for this project (now or in the future) exceed one acre, or of total
impacts to streams (now or in the future) exceed 150 linear feet, compensatory mitigation may be required as
described in 15A NCAC 2H .0506 (h) (6) and (7). For this approval to remain valid, you must adhere to the
conditions listed in the attached certification(s) and any additional conditions listed below.
1617 Mail Service Center, Raleigh, North Carolina 27699-1617
Phone: 919-807-63001 Internet: www.ncdenr.gov
An Equal Opportunity 1 Affirmalive Action Employer
Condition(s) of Certification:
Project Specific Conditions
Due to the conditions at Sites 4+12 and 128+25, which would require the placement of the pipes on
steep grades, NCDWQ will not require the burial of the culverts in the streambed in these locations.
However, design and placement of the culvert and other structures shall be installed in such a manner
that the original stream profiles are not altered (i.e., the depth of the channel must not be reduced by a
widening of the streambed). Existing stream dimensions (including pattern and profile) are to be
maintained above and below locations of each culvert. The structures shall be designed and installed to
allow for fish and other wildlife movement to the maximum extent practicable, as well as prevent
headcutting and scour of the stream. The applicant may be required to provide evidence that the
equilibrium has been maintained if requested in writing by the NCDWR. [15A NCAC 02H.0506(b)(2)]
2. For the 40 linear feet of streams being impacted due to site dewatering activities, the site shall be graded
to its preconstruction contours and revegetated with appropriate native species. [ 15A NCAC
02H.0506(b)(2)]
3. The stream channel shall be excavated no deeper than the natural bed material of the stream, to the
maximum extent practicable. Efforts must be made to minimize impacts to the stream banks, as well as
to vegetation responsible for maintaining the stream bank stability. Any applicable riparian buffer
impact for access to stream channel shall be temporary and be revegetated with native riparian species.
[15A NCAC 02H.0506(b)(2)]
4. This project has the potential to impact trout waters or other aquatic species of concern. No construction
activities shall begin until the NCWRC makes a determination regarding moratoria. Should the NCWRC
determine that a moratorium is applicable then the requirements of any moratorium(s) shall be a
condition of this 401 Certification. If the NCDOT does not wish to honor the moratorium, then a written
modification shall be submitted. (15A NCAC 02H.0506(b)(2) and I SA NCAC 04B. 0125)
5. Stormwater shall be directed to vegetated buffer areas, grass-lined ditches or other means appropriate to
the site for the purpose of pre-treating storm water runoff prior to discharging directly into streams.
Mowing of existing vegetated buffers is strongly discouraged.
6. Design Standards in Sensitive Watersheds (15A NCAC 4B.0124[a]-[e]) shall be used on this project.
However, due to the size of the project, the NCDOT shall not be required to meet 15A NCAC 4B
.0124(a) regarding the maximum amount of uncovered acres. Temporary cover (wheat, millet, or similar
annual grain) or permanent herbaceous cover shall be planted on all bare soil within 15 business days of
ground disturbing activities to provide erosion controL
7. NCDOT shall be in compliance with the NCS00250 issued to the NCDOT, including the applicable
requirements of the NCGO1000. Please note the extra protections for the sensitive watersheds.
General Conditions
Unless otherwise approved in this certification, placement of culverts and other structures in open waters
and streams shall be placed below the elevation of the streambed by one foot for all culverts with a
diameter greater than 48 inches, and 20 percent of the culvert diameter for culverts having a diameter less
than 48 inches, to allow low flow passage of water and aquatic life. Design and placement of culverts and
other structures including temporary erosion control measures shall not be conducted in a manner that
may result in dis-equilibrium of wetlands or streambeds or banks, adjacent to or upstream and
downstream of the above structures. The applicant is required to provide evidence that the equilibrium is
being maintained if requested in writing by NCDWR. If this condition is unable to be met due to bedrock
or other limiting features encountered during construction, please contact NCDWR for guidance on how
to proceed and to determine whether or not a permit modification will be required. [15A NCAC
02H.0506(b)(2)]
2. If concrete is used during construction, a dry work area shall be maintained to prevent direct contact
between curing concrete and stream water. Water that inadvertently contacts uncured concrete shall not
be discharged to surface waters due to the potential for elevated pH and possible aquatic life and fish
kills. [15A NCAC 02B.0200]
3. During the construction of the project, no staging of equipment of any kind is permitted in waters of the
U.S., or protected riparian buffers. [15A NCAC 02H.0506(b)(2)]
4. The dimension, pattern and profile of the stream above and below the crossing shall not be modified.
Disturbed floodplains and streams shall be restored to natural geomorphic conditions. [15A NCAC
02H.0506(b)(2)]
5. . The use of rip-rap above the Normal High Water Mark, shall be minimized. Any rip-rap placed for
stream stabilization shall be placed in stream channels in such a manner that it does not impede aquatic
life passage. [15A NCAC 02H.0506(b)(2)]
6. The Permittee shall ensure that the final design drawings adhere to the permit and to the permit
drawings submitted for approval. [15A NCAC 02H .0507(c) and 15A NCAC 02H .0506 (b)(2) and
(�)(2)l
7. All work in or adjacent to stream waters shall be conducted in a dry work area. Approved BMP
measures from the most current version ofNCDOT Construction and Maintenance Activities manual
such as sandbags, rock berms, coffer.dams and other diversion structures shall be used to prevent
excavation in flowing water. [ 15A NCAC 02H.0506(b)(3) and (c)(3)]
8. Heavy equipment shall be operated from the banks rather than in the stream channel in order to
minimize sedimentation and reduce the introduction of other pollutants into the stream. [15A NCAC
02H.0506(b)(3)]
9. All mechanized equipment operated near surface waters must be regularly inspected and maintained to
prevent contamination of stream waters from fuels, lubricants, hydraulic fluids, or other toxic materials.
[15A NCAC 02H.0506(b)(3)]
10. No rock, sand or other materials shall be dredged from the stream channel except where authorized by
this certification. [15A NCAC 02H.0506(b)(3)]
11. Discharging hydroseed mixtures and washing out hydroseeders and other equipment in or adjacent to
surface waters is prohibited. [15A NCAC 02H.0506(b)(3)]
12. The permittee and its authorized agents shall conduct its activities in a manner consistent with State water
quality standards (including any requirements resulting from compliance with §303(d) of the Clean Water
Act) and any other appropriate requirements of State and Federal law. If the NCDWR determines that
such standards or laws are not being met (including the failure to sustain a designated or achieved use) or
that State or federal law is being violated, or that further conditions are necessary to assure compliance,
the NCDWR may reevaluate and modify this certification. [15A NCAC 02B.0200]
13. All fill slopes located in jurisdictional wetlands shall be placed at slopes no flatter than 3:1, unless
otherwise authorized by this certification. [ 15A NCAC 02H.0506(b)(2)]
l4. A copy of this Water Quality Certification shall be maintained on the construction site at all times. In
addition, the Water Quality Certification and all subsequent modifications, if any, shall be maintained
with the Division Engineer and the on-site project manager. [ISA NCAC 02H .0507(c) and 15A NCAC
02H .0506 (b)(2) and (c)(2)]
I5. The outside buffer, wetland or water boundary-located within the construction corridor approved by this
authorization shall be clearly marked by highly visible fencing prior to any land disturbing
activities. Impacts to areas within the fencing are prohibited unless otherwise authorized by this
certification. [ 1 SA NCAC 02H.0501 and .0502]
16. The issuance of this certification does not exempt the Permittee from complying with any and all statutes,
rules, regulations, or ordinances that may be imposed by other government agencies (i:e. local, state, and
federal) having jurisdiction, including but not limited to applicable buffer rules, stormwater management
rules, soil erosion and sedimentation control requirements, etc.
17. The Permittee shall report any violations of this certification to the Division of Water Resource's within
24 hours of discovery. [15A NCAC 02B.0506(b)(2)]
18. Upon completion of the project (including any impacts at associated borrow or waste sites), the NCDOT
Division Engineer shall complete and return the enclosed "Certification of Completion Form" to notify
the NCDWR when all work included in the 401 Certification has been completed. [15A NCAC
02H.0502( fl]
19. Native riparian vegetation must be reestablished in the riparian areas within the construction limits of the
project by the end of the growing �season following completion of construction.[ 15A NCAC 02B.0225]
20. There shall be no excavation from, or waste disposal into, jurisdictional wetlands or waters associated
with this permit without appropriate modification. Should waste or borrow sites, or access roads to waste
or borrow sites, be located in wetlands or streams, compensatory mitigation will be required since that is a
direct impact from road construction activities.[15A NCAC 02H.0506(b)(3) and (c)(3)]
21. Erosion and sediment control practices must be in full compliance with all specifications governing the
proper design, installation and operation and maintenance of such Best Management Practices in order to
protect surface waters standards [15A NCAC 02H.0506(b)(3) and (c)(3]):
a. The erosion and sediment control measures for the project must be designed, installed, operated,
and maintained in accordance with the most recent version of the North Carolina Sediment and
Erosion Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion control measures
must be such that they equal, or exceed, the requirements specified in the most recent version of
the North Carolina Sediment anct Erosion Control Manual. The devices shall be maintained on all
construction sites, borrow sites, and waste pile (spoil) projects, including contractor-owned or
leased borrow pits associated with the project.
c. For borrow pit sites, the erosion and sediment control measures must be designed, installed,
operated, and maintained in accordance with the most recent version of the North Carolina
Surface Mining Manual.
d. The reclamation measures and implementation must comply with the reclamation in accordance
with the requirements of the Sedimentation Pollution Control Act.
22. Sediment and erosion control measures shall not be placed in wetlands or waters unless otherwise
approved by this Certification. [15A NCAC 02H.0506(b)(3) and (c)(3)]
If you wish to contest any statement in the attached Certification you must file a petition for ari administrative
hearing. You may obtain the petition form from the office of Administrative hearings. You must file the petition
with the office of Administrative Hearings within sixty (60) days of receipt of this notice. A petition is considered
filed when it is received in the office of Administrative Hearings during normal office hours. The Office of
Administrative Hearings accepts filings Monday through Friday between the hours of 8:OOam and S:OOpm,. except
for official state holidays. The original and one (1) copy of the petition must be filed with the Office of
Administrative Hearings.
The petition may be faxed-provided the original and one copy of the document is received by the Office of
Administrative Hearings within five (5) business days following the faxed transmission.
The mailing address for the Office of Administrative Hearings is:
Office of Administrative Hearings
6714 Mail Service Center
Raleigh, NC 27699-6714
Telephone: (919)-431-3000, Facsimile: (919)-431-3100
A copy of the petition must also be served on DENR as follows:
Mr. John Evans, General Counsel ,
Department of Environment and Natural Resources
1601 Mail Service Center
This letter completes the review of the Division of Water Resources under Section 401 of the Clean Water Act. If you
have any questions, please contact Dave Wanucha at (336)-776-9703 or dave.wanucha@ncdenr.gov.
Sincerely;
�po-^' -
S. Jay Zimmerman, Acting Director
Division of Water Resources
Electronic copy only distribution:
James Latinger, US Army Corps of Engineers, Raleigh Field Office
Marella Buncick, US Fish and Wildlife Service �
Marla Chambers, NC Wildlife Resources Commission
NC Division of Water Resources Raleigh Central Office
Dave Wanucha, NC Division of Water Resources Winston Salem Regional Office
File Copy
���
����
NCDENR
North Carolina Department of Environment and Natural Resources
Pat McCrory
Governor
NCDWR Project No.:
Applicant: �
Project Name:
Date of Issuance of 40l Water Quality Certification:
County:
Donald van der Vaart
Secretary
Certificate of Completion '
Upon completion of all work approved within the 401 Water Quality Certification or applicable Buffer Rules, and
any subsequent modifications, the applicant is required to return this certificate to the 401 Transportation Permitting
Unit, North Carolina Division of Water Resources, 1617 Mail Service Center, Raleigh, NC, 27699-1617. This form
may be returned to NCDWR by the applicant, the applicant's authorized agent, or the project engineer. It is not
necessary to send certificates from all of these.
Applicant's Certification
I, , hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved plans and
specifications, and other supporting materials.
Signature: Date:
Agent's Certification
I, ; hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules,.the approved plans and
specifications, and other supporting materials.
Signature:
Engineer's Certification
Partial Final
Date:
I, , as a duly registered Professional Engineer in the State of North
Carolina, having been authorized to observe (periodically, weekly, full time) the construction of the project for the
Permittee hereby state that, to the best of my abilities, due care and diligence was used in the observation of the
construction such that the construction was observed to be built within substantial compliance and intent of the 401
Water Quality Certification and Buffer Rules, the approved plans and specifications, and other supporting materials.
Signature
Date
Registration No.