HomeMy WebLinkAbout20141078 Ver 1_DCM Permit_20141201Permit Class
NEW
STATE OF NORTH CAROLINA
Department of Environment and Natural Resources
and
Coastal Resources Commission
Permit
for
Permit Number
103 -14
RECEIVED
CEC 01 814
DENR -LAND QUALITY
STORMWATER PERMITTING
X Major Development in an Area of Environmental Concern
pursuant to NCGS 113A -118
X Excavation and/or filling pursuant to NCGS 113 -229
Issued to Clarence and Gloria Richards, 211 Poplar Drive, Elizabeth City, NC 27909
Authorizing development in Pasquotank County adi. to the Little River at 211 Poplar Drive, in
Elizabeth City , as requested in the permittee's application dated 9/3/14 including the
attached workplan drawings (2). 1 dated 9/16/14 and 1 dated 9/30/14.
This permit, issued on November 25. 2014 , is subject to compliance with the application (where consistent
with the permit), all applicable regulations, special conditions and notes set forth below. Any violation of these terms may
be subject to fines, imprisonment or civil action; or may cause the permit to be null and void.
Shoreline Stabilization
1) The authorized bulkhead and associated wingwalls shall adhere to the alignment depicted on the
attached workplan drawings.
2) The alignment of the authorized bulkhead shall be staked by the permittee and approved by a
representative of the Division of Coastal Management within a maximum of 30 days prior to the start
of any construction.
3) The bulkhead shall be structurally tight so as to prevent seepage of backfill materials through the
structure.
(See attached sheet for Additional Conditions)
This permit action may be appealed by the pertnittee or Signed by the authority of the Secretary of DENR and the
other qualified persons within twenty (20) days of the issuing Chairman of the Coastal Resources Commission
date.
This permit must be accessible on -site to Department
personnel when the project is inspected for compliance.
Any maintenance work or project modification not covered
hereunder requires further Division approval
All work must cease when the permit expires on
December 31, 2017
In issuing this permit, the State of North Carolina agrees
that your project is consistent with the North Carolina Coastal
Management Program
2 Braxton C. Davis, Director
Division of Coastal Management
This permit and its conditions are hereby accepted.
Signature of Permittee
Clarence and Gloria Richards
ADDITIONAL CONDITIONS
Permit # 103 -14
Page 2 of 2
4) The bulkhead shall be solid and constructed of treated wood, concrete slabs, metal sheet piles or other
suitable materials approved by department personnel. No excavation landward of the authorized
alignment is permitted except for that which may be required for the construction of the bulkhead wall
and deadmen cables, etc.
5) The bulkhead shall be constructed prior to any backfilling activities.
6) All backfill material shall be clean and free of any pollutants except in trace quantities.
7) All backfill material shall be obtained from a high ground source and confined behind the permitted
bulkhead.
Sedimentation and Erosion Control
8) In order to protect water quality, runoff from construction shall not visibly increase the amount of
suspended sediments in adjacent waters.
9) Appropriate sedimentation and erosion control devices, measures or structures shall be implemented to
ensure that eroded materials do not enter adjacent wetlands, watercourses and property (e.g. silt fence,
diversion swales or berms, etc.). At a minimum, a silt fence shall be properly installed immediately
landward of the bulkhead cap immediately following completion of backfilling activities.
10) All disturbed areas shall be properly graded and provided a ground cover sufficient to restrain erosion
within thirty days of project completion.
General
11) The permittee and/or his contractor shall meet with a representative of the Division prior to project
initiation in order to discuss the conditions set forth in this permit.
12) This permit shall not be assigned, transferred, sold, or otherwise disposed of to a third party without the
written approval of the Division of Coastal Management.
NOTE: This permit does not eliminate the need to obtain any additional state, federal or local permits,
approvals or authorizations that may be required.
NOTE: Future development of the permittee's property may require a modification of this permit.
Contact a representative of the Division at (252) 946 -6481 prior to the commencement of any
such activity for this determination. The permittee is further advised that many non -water
dependent activities are not authorized within 30 feet of the normal water level.
NOTE: The U.S. Army Corps of Engineers has assigned the proposed project COE Action Id. No SAW -
2014- 02155.