February 11, 2014
Lincoln County
NCDWR Project No. 20150170v.I
Bridge 124 on SR 1113
Project No. BD- 5112V(540124)
APPROVAL of 401 WATER QUALITY CERTIFICATION with ADDITIONAL CONDITIONS
Ms. Trish Beam, Environmental Supervisor
NCDOT. Division 12
P.O. Box 47
1710 E. Marion Street
Shelby, NC 28151
Dear Ms. Beam:
You have our approval, in accordance with the conditions listed below, for the following impacts for the purpose of
replacing Bridge No. 124 on SR 1113 (Reepsville Road) over Howards Creek in Lincoln County:
Stream Impacts in the Catawba River Basin
Total Stream Impact for Project: 110 linear feet.
The project shall be constructed in accordance with your application dated received February 10, 2015. After
reviewing your application, we have decided that these impacts are covered by General Water Quality Certification
Number 3883. This certification corresponds to the Nationwide Permit 3 issued by the Corps of Engineers. In
addition, you should acquire any other federal, state or local permits before you proceed with your project including
(but not limited to) Sediment and Erosion Control, Non - Discharge and Water Supply Watershed regulations. This
approval will expire with the accompanying 404 permit.
This approval is valid solely for the purpose and design described in your application (unless modified below).
Should your project change, you must notify the NCDWR and submit a new application. If the property is sold, the
new owner must be given a copy of this Certification and approval letter, and is thereby responsible for complying
with all the conditions. If total wetland fills for this project (now or in the future) exceed one acre, or of total
impacts to streams (now or in the future) exceed 150 linear feet, compensatory mitigation may be required as
described in 15A NCAC 2H .0506 (h) (6) and (7). For this approval to remain valid, you must adhere to the
conditions listed in the attached certification(s) and any additional conditions listed below.
1617 Mail Service Center, Raleigh, North Carolina 27699 -1617
Phone: 919- 807- 63001Internet: www.ncdenf.gov
An Equal Opportunity \ Affirmative Action Employer
Permanent Fill
Temporary Fill
Permanent Fill
Temporary Fill
Total Stream
Stream Impacts
in Intermittent
in Intermittent
in Perennial
in Perennial
Requiring
Site
Stream (linear
Stream (linear
Stream
Stream
Impact
Mitigation
ft)
ft)
(linear ft)
(linear ft)
(linear ft)
(linear ft)
1
8
8
0
2
45
47
92
0
3
l0
10
0
TOTAL
0
1 0
1 63
47
1 110
1 0
Total Stream Impact for Project: 110 linear feet.
The project shall be constructed in accordance with your application dated received February 10, 2015. After
reviewing your application, we have decided that these impacts are covered by General Water Quality Certification
Number 3883. This certification corresponds to the Nationwide Permit 3 issued by the Corps of Engineers. In
addition, you should acquire any other federal, state or local permits before you proceed with your project including
(but not limited to) Sediment and Erosion Control, Non - Discharge and Water Supply Watershed regulations. This
approval will expire with the accompanying 404 permit.
This approval is valid solely for the purpose and design described in your application (unless modified below).
Should your project change, you must notify the NCDWR and submit a new application. If the property is sold, the
new owner must be given a copy of this Certification and approval letter, and is thereby responsible for complying
with all the conditions. If total wetland fills for this project (now or in the future) exceed one acre, or of total
impacts to streams (now or in the future) exceed 150 linear feet, compensatory mitigation may be required as
described in 15A NCAC 2H .0506 (h) (6) and (7). For this approval to remain valid, you must adhere to the
conditions listed in the attached certification(s) and any additional conditions listed below.
1617 Mail Service Center, Raleigh, North Carolina 27699 -1617
Phone: 919- 807- 63001Internet: www.ncdenf.gov
An Equal Opportunity \ Affirmative Action Employer
Conditions of Certification:
Project Specific Conditions
I. Any rock material used during construction (such as in temporary work pads, causeways, temporary access
roads or detours, etc.) that comes in contact with stream water shall be pre - washed. Sound judgment shall be
used in determining suitable size of rock such that it will remain in place and not become dislodged during
precipitation events. Unauthorized rock in jurisdictional areas is considered fill and may require additional
mitigation. [15A NCAC 02H.0506(b)(3) and (c)(3)]
2. To aid in the removal of rock used for the temporary work pad, geotextile fabric shall be used under the rock
fill of the temporary work pad. [ 15A NCAC 02H.0506(b)(3) and (c)(3)]
3. All temporarily impacted or disturbed areas shall be restored as close to natural and pre- existing conditions as
possible upon project completion. [15A NCAC 02H.0506(b)(3) and (c)(3)]
4. As a condition of this 401 Water Quality Certification, the bridge demolition and construction must be
accomplished in strict compliance with the most recent version of NCDOT's Best Management Practices
for Construction and Maintenance Activities. [ 15A NCAC 02H .0507(d)(2) and 15A NCAC 02H
.0506(b)(5)]
5. All bridge construction shall be performed from the existing bridge, temporary work bridges, temporary
causeways, or floating or sunken barges. [15A NCAC 02H .0506(b)(3)]
General Conditions
6. If concrete is used during construction, a dry work area shall be maintained to prevent direct contact
between curing concrete and stream water. Water that inadvertently contacts uncured concrete shall not be
discharged to surface waters due to the potential for elevated pH and possible aquatic life and fish kills.
[15A NCAC 026.02001
7. During the construction of the project, no staging of equipment of any kind is permitted in waters of the
U.S., or protected riparian buffers. [ 15A NCAC 02H.0506(b)(2)]
8. The dimension, pattern and profile of the stream above and below the crossing shall not be modified.
Disturbed floodplains and streams shall be restored to natural geomorphic conditions. [15A NCAC
02H.0506(b)(2)]
9. The use of rip -rap above the Normal High Water Mark shall be minimized. Any rip -rap placed for stream
stabilization shall be placed in stream channels in such a manner that it does not impede aquatic life
passage. [15A NCAC 02H.0506(b)(2)]
10. The Permittee shall ensure that the final design drawings adhere to the permit and to the permit drawings
submitted for approval. [ 15A NCAC 02H .0507(c) and 15A NCAC 02H .0506 (b)(2) and (c)(2)]
11. All work in or adjacent to stream waters shall be conducted in a dry work area. Approved BMP measures
from the most current version of NCDOT Construction and Maintenance Activities manual such as
sandbags, rock berms, cofferdams and other diversion structures shall be used to prevent excavation in
flowing water. [15A NCAC 02H.0506(b)(3) and (c)(3)]
12. Heavy equipment shall be operated from the banks rather than in the stream channel in order to minimize
sedimentation and reduce the introduction of other pollutants into the stream. [ 15A NCAC 02H.0506(b)(3)]
13. All mechanized equipment operated near surface waters must be regularly inspected and maintained to
prevent contamination of stream waters from fuels, lubricants, hydraulic fluids, or other toxic materials. [I 5A
NCAC 02H.0506(b)(3)]
14. No rock, sand or other materials shall be dredged from the stream channel except where authorized by this
certification. [15A NCAC 02H.0506(b)(3)]
15. Discharging hydroseed mixtures and washing out hydroseeders and other equipment in or adjacent to surface
waters is prohibited. [15A NCAC 02H.0506(b)(3)]
16. The permittee and its authorized agents shall conduct its activities in a manner consistent with State water
quality standards (including any requirements resulting from compliance with §303(d) of the Clean Water
Act) and any other appropriate requirements of State and Federal law. If the NCDWR determines that such
standards or laws are not being met (including the failure to sustain a designated or achieved use) or that State
or federal law is being violated, or that further conditions are necessary to assure compliance, the NCDWR
may reevaluate and modify this certification. [15A NCAC 02B.0200]
17. The outside buffer, wetland or water boundary located within the construction corridor approved by this
authorization shall be clearly marked by highly visible fencing prior to any land disturbing activities. Impacts
to areas within the fencing are prohibited unless otherwise authorized by this certification. [15A NCAC
02H.0501 and .05021
18. The issuance of this certification does not exempt the Permittee from complying with any and all statutes,
rules, regulations, or ordinances that may be imposed by other government agencies (i.e. local, state, and
federal) having jurisdiction, including but not limited to applicable buffer rules, stormwater management
rules, soil erosion and sedimentation control requirements, etc.
19. Native riparian vegetation must be reestablished in the riparian areas within the construction limits of the
project by the end of the growing season following completion of construction. [ 15A NCAC 02B.0506(c)(3)]
20. There shall be no excavation from, or waste disposal into, jurisdictional wetlands or waters associated with
this permit without appropriate modification. Should waste or borrow sites, or access roads to waste or
borrow sites, be located in wetlands or streams, compensatory mitigation will be required since that is a direct
impact from road construction activities.[15A NCAC 02H.0506(b)(3) and (c)(3)]
21. Erosion and sediment control practices must be in full compliance with all specifications governing the
proper design, installation and operation and maintenance of such Best Management Practices in order to
protect surface waters standards [15A NCAC 02H.0506(b)(3) and (c)(3]):
a. The erosion and sediment control measures for the project must be designed, installed, operated,
and maintained in accordance with the most recent version of the North Carolina Sediment and
Erosion Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion control measures
must be such that they equal, or exceed, the requirements specified in the most recent version of
the North Carolina Sediment and Erosion Control Manual. The devices shall be maintained on all
construction sites, borrow sites, and waste pile (spoil) projects, including contractor -owned or
leased borrow pits associated with the project.
c. For borrow pit sites, the erosion and sediment control measures must be designed, installed,
operated, and maintained in accordance with the most recent version of the North Carolina
Surface Mining Manual.
d. The reclamation measures and implementation must comply with the reclamation in accordance
with the requirements of the Sedimentation Pollution Control Act,
22. Sediment and erosion control measures shall not be placed in wetlands or waters unless otherwise approved
by this Certification. [15A NCAC 02H.0506(b)(3) and (c)(3)]
23. A copy of this Water Quality Certification shall be maintained on the construction site at all times. In
addition, the Water Quality Certification and all subsequent modifications, if any, shall be maintained with
the Division Engineer and the on -site project manager. [ 15A NCAC 02H .0507(c) and 15A NCAC 02H .0506
(b)(2) and (c)(2)]
24. The Permittee shall report any violations of this certification to the Division of Water Resources within 24
hours of discovery. [ 15A NCAC 02B.0506(b)(2)]
25. Upon completion of the project (including any impacts at associated borrow or waste sites), the NCDOT
Division Engineer shall complete and return the enclosed "Certification of Completion Form" to notify the
NCDWR when all work included in the 401 Certification has been completed. [15A NCAC 02H.0502(t)]
If you wish to contest any statement in the attached Certification you must file a petition for an administrative
hearing. You may obtain the petition form from the office of Administrative hearings. You must file the petition
with the office of Administrative Hearings within sixty (60) days of receipt of this notice. A petition is considered
filed when it is received in the office of Administrative Hearings during normal office hours. The Office of
Administrative Hearings accepts filings Monday through Friday between the hours of 8:OOam and 5:OOpm, except
for official state holidays. The original and one (1) copy of the petition must be filed with the Office of
Administrative Hearings.
The petition may be faxed - provided the original and one copy of the document is received by the Office of
Administrative Hearings within five (5) business days following the faxed transmission.
The mailing address for the Office of Administrative Hearings is:
Office of Administrative Hearings
6714 Mail Service Center
Raleigh, NC 27699 -6714
Telephone: (919) -431 -3000, Facsimile: (919) -431 -3100
A copy of the petition must also be served on DENR as follows:
Mr. John Evans, General Counsel
Department of Environment and Natural Resources
1601 Mail Service Center
This letter completes the review of the Division of Water Resources under Section 401 of the Clean Water Act. If you
have any questions, please contact David Wainwright at (919)707 -8787 or David.Wainwright @ncdenr.gov.
Sincerely,
�� ���
.Jay Zimme man, Acting D� ector
Division of Water Resources
Electronic copy only distribution:
Steve Kichefski, US Army Corps of Engineers, Asheville Field Office
Marella Buncick, US Fish and Wildlife Service
Marla Chambers, NC Wildlife Resources Commission
File Copy
e
NCDENR
North Carolina Department of Environment and Natural Resources
Pat McCrory
Governor
NCDWR Project No.:
Applicant:
Project Name:
Date of Issuance of 401 Water Quality Certification:
County:
Donald van der Vaarl
Secretary
Certificate of Completion
Upon completion of all work approved within the 401 Water Quality Certification or applicable Buffer Rules, and
any subsequent modifications, the applicant is required to return this certificate to the 401 Transportation Permitting
Unit, North Carolina Division of Water Resources, 1617 Mail Service Center, Raleigh, NC, 27699 -1617. This form
may be returned to NCDWR by the applicant, the applicant's authorized agent, or the project engineer. It is not
necessary to send certificates from all of these.
Applicant's Certification
I, , hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved plans and
specifications, and other supporting materials.
Signature:
Agent's Certification
Date:
1, , hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved plans and
specifications, and other supporting materials.
Signature:
Engineer's Certification
Partial Final
1, , as a duly registered Professional Engineer in the State of North
Carolina, having been authorized to observe (periodically, weekly, full time) the construction of the project for the
Permittee hereby state that, to the best of my abilities, due care and diligence was used in the observation of the
construction such that the construction was observed to be built within substantial compliance and intent of the 401
Water Quality Certification and Buffer Rules, the approved plans and specifications, and other supporting materials.
Signature
Date
Registration No.
1617 Mail Service Center, Raleigh, North Carolina 27699 -1617
Phone: 919- 807 -63001 Internet: www.nodenr.gov
An Equal Opportunity 1 ARrmaOve Action Employer