HomeMy WebLinkAboutFW_ Request for Additional Information Bridge 247 on SR 1410 Little Creek Yancey
Carpenter,Kristi
From:Mitchell, Robert K
Sent:Tuesday, December 13, 2022 9:33 AM
To:Carpenter,Kristi
Subject:FW: Request for Additional Information Bridge 247 on SR 1410 Little Creek Yancey
From: Bryan, Roger D <rdbryan@ncdot.gov>
Sent: Tuesday, December 13, 2022 8:34 AM
To: Mitchell, Robert K <kevin.mitchell@ncdenr.gov>
Cc: Beckwith, Loretta A CIV USARMY CESAW (USA) <Loretta.A.Beckwith@usace.army.mil>; Chapman, Amy
<amy.chapman@ncdenr.gov>
Subject: RE: Request for Additional Information Bridge 247 on SR 1410 Little Creek Yancey
Kevin,
DOT wishes to withdraw the application for Bridge 274 and reapply at a later date.
Thanks
Roger D. Bryan
Division Environmental Officer
Division 13
Department of Transportation
828 250 3005 office
828 337 5234 mobile
rdbryan@ncdot.gov
55 Orange Street
Asheville, NC 28801
From: Mitchell, Robert K <kevin.mitchell@ncdenr.gov>
Sent: Tuesday, December 13, 2022 7:43 AM
To: Bryan, Roger D <rdbryan@ncdot.gov>
Cc: Beckwith, Loretta A CIV USARMY CESAW (USA) <Loretta.A.Beckwith@usace.army.mil>; Chapman, Amy
<amy.chapman@ncdenr.gov>
Subject: FW: Request for Additional Information Bridge 247 on SR 1410 Little Creek Yancey
Roger,
I know we spoke on the phone about this last month, but I wanted to check in with you again to see how things are
progressing with this project. Can you provide me with an update on when you expect to have the additional
information/new design submitted? We are approaching 60 days from the day of the initial request for additional
information. Thanks.
Kevin Mitchell
Environmental Specialist II
1
Division of Water Resources
401 & Buffer Transportation Permitting
NC Department of Environmental Quality
828-296-4650 Office
828-231-1580 Mobile
Email Kevin.mitchell@ncdenr.gov
NC DEQ Asheville Regional Office
2090 U.S. Hwy. 70
Swannanoa, N.C. 28778
From: Mitchell, Robert K
Sent: Tuesday, October 18, 2022 3:18 PM
To: Bryan, Roger D <rdbryan@ncdot.gov>
Cc: Beckwith, Loretta A CIV USARMY CESAW (USA) <Loretta.A.Beckwith@usace.army.mil>; McHenry, David G
<david.mchenry@ncwildlife.org>
Subject: Request for Additional Information Bridge 247 on SR 1410 Little Creek Yancey
Roger,
I have a few questions that I did not see explained in the application. The questions are related to aquatic life passage
since Little Creek supports trout.
On October 7, 2022, the Division of Water Resources (Division) received your application dated October 7, 2022,
requesting a 401 Water Quality Certification from the Division for the subject project. The Division has determined that
your application is incomplete and cannot be processed. The application is on-hold until the following information is
received:
1. The slope of the double barrel RCBC is 3.9%. Per NCDOT guidance (Guidelines for Drainage Studies and Hydraulic
Design, 2016), if the culvert slope is greater than 2%, then sills and baffles are required to help retain native
material within the culvert. The Division has concerns that the proposed design with sills at the inlet/outlet will not
retain bed load and may need additional baffles. Please redesign or provide justification for not having additional
sills or baffles inside the culvert. \[15A NCAC 02H .0506(b)\]
2. Condition 11 of GC 4135 states “ Placement of culverts and other structures in streams shall be below the elevation
of the streambed by one foot for all culverts greater than 48 inches”. The cross section and profile for the 87”x 63”
CMPA indicates that the structure will be installed at grade and will not meet Condition 11. Slope is 4.8%. Please
redesign or provide justification for the design. Also, can baffles or sills be utilized to retain material in the culvert?
\[15A NCAC 02H .0506(b)\]
2
Pursuant to Title 15A NCAC 02H .0502 (c), the applicant shall furnish all of the above requested information for the
proper consideration of the application. If all of the requested information is not received within 30 calendar days, of
receipt of this email, the Division will be unable to approve the application and it will be returned. The return of this
project will necessitate reapplication to the Division for approval, including a complete application package and the
appropriate fee.
You may provide your response via email or mail to the address noted below.
Should you have any questions regarding these matters, please contact Kevin Mitchell at (828) 231-1580 or
kevin.mitchell@ncdenr.gov.
Kevin Mitchell
Environmental Specialist II
Division of Water Resources
401 & Buffer Transportation Permitting
NC Department of Environmental Quality
828-296-4650 Office
828-231-1580 Mobile
Email Kevin.mitchell@ncdenr.gov
NC DEQ Asheville Regional Office
2090 U.S. Hwy. 70
Swannanoa, N.C. 28778
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.