HomeMy WebLinkAboutSW6220903_Plansheet - Grading/Drainage Plan_20221102VICINITY MAP
NOT TO SCALE
LEGEND:
EGIZ ECM -EXISTING CONCRETE MONUMENT
EIP 00 EIP-EXISTING IRON PIPE
EIR 00 EIR-EXISTING IRON ROD
EIS O EIS -EXISTING IRON STAKE
ERB0 ERB-EXISTING REBAR
SIR 00 SIR -SET IRON ROD
SPKO SPK-SET PK NAIL
SRB0 SRB-SET REBAR
o COMPUTED POINT _
N/F - NOW OR FORMERLY
R/W - RIGHT OF WAY
RCP - REINFORCED CONCRETE PIPE
PROPERTY LINE
ADJACENT PROPERTY LINE '
TIE LINE
RIGHT-OF-WAY
OVERHEAD UTILITY
- - - - CREEK
- - WETLANDS
TREE LINE
210MAJOR CONTOUR
207 MINOR CONTOUR
----------EDGE OF WATER
too r> 100 YEAR FLOOD ZONE
BENCHMARK
SIGN SIGN
PPS UTILITY POLE
C GUY WIRE
❑T TELEPHONE PEDESTAL
ASPHALT
UNSUITABLE SOILS
WETLANDS
LOC LIMITS OF CONSTRUCTION
SF SILT FENCE LINE
OINLET PROTECTION
GROUND STABILIZATION CHART
EROSION CONTROL NOTES
/
CHANNEL. IF REMAINING FOR MORE THAN SEVEN DAYS,
ACTIVITIES.
NOTIFICATION OF COMBINED SELF -MONITORING AND
GRADING NOTES
AND BELOW GROUND, SHOWN OR NOT SHOWN ON THESE
STABILIZE THE STOCKPILES BY VEGETATIVE COVER, TARPS,
12. THE PERMITTEE SHALL BE HELD RESPONSIBLE FOR THE
SELF -INSPECTION FORM:
PLANS. THEY WILL BE HELD RESPONSIBLE FOR ALL DAMAGE
1. ALL INLET/OUTLET PROTECTION WILL BE CHECKED FOR
OR OTHER MEANS. CONTROL EROSION FROM ALL
ACTIONS AND PERFORMANCE OF ANY OTHER PARTIES
1.
ALL ELEVATIONS SHOWN ARE IN REFERENCE TO THE
TO ANY UTILITIES OR STRUCTURES CAUSED BY HIS
MAINTENANCE AND FAILURE EACH ACTIVE DAY ON SITE.
STOCKPILES BY PLACING SILT BARRIERS AROUND THE PILES.
PERFORMING WORK ON THIS PROJECT.
THE SEDIMENTATION POLLUTION CONTROL ACT WAS AMENDED IN
BENCHMARK AND MUST BE VERIFIED BY THE GENERAL
OPERATION.
SEDIMENT WILL BE REMOVED FROM THE SEDIMENT TRAP
TEMPORARY STOCKPILES LOCATED ON PAVED SURFACES
13. ALL EROSION AND SEDIMENT CONTROL PRACTICES WILL BE
2006 TO REQUIRE THAT PERSONS RESPONSIBLE FOR
CONTRACTOR.ALL SPOT ELEVATIONS ARE TO THE FINISHED
7. ALL CUT AND FILL SLOPES SHOULD BE INVESTIGATED BOTH
AND INLET PROTECTION DEVICES WHEN THE STORAGE
MUST BE NO LESS THAN FIVE FEET FROM THE
CHECKED FOR STABILITY AND OPERATION FOLLOWING EVERY
LAND -DISTURBING ACTIVITIES INSPECT A PROJECT AFTER EACH
GRADE OF THE CURB, UNLESS OTHERWISE NOTED.
DURING AND AFTER GRADING BY THE CONTRACTOR TO
CAPACITY HAS BEEN APPROXIMATELY 50% FILLED. GRAVEL
DRAINAGE/GUTTER LINE AND SHALL BE COVERED IF LEFT
RUNOFF -PRODUCING RAINFALL BUT IN NO CASE LESS THAN
PHASE OF THE PROJECT TO MAKE SURE THAT THE APPROVED
2.
ALL SIDEWALKS AND PEDESTRIAN WALKING SURFACES
DETERMINE IF ANY SLOPE STABILITY PROBLEMS EXIST. IF IT
WILL BE CLEANED OR REPLACED WHEN THE SEDIMENT POOL
MORE THAN 24 HOURS.
ONCE EVERY WEEK. ANY NEEDED REPAIRS WILL BE MADE
EROSION AND SEDIMENTATION CONTROL PLAN IS BEING
SHALL HAVE A CROSS SLOPE NO STEEPER THAN 2% AND
IS DETERMINED THAT THERE IS A SLOPE STABILITY
NO LONGER DRAINS PROPERLY. SEDIMENT WILL BE
7. MAINTAIN ALL TEMPORARY EROSION AND SEDIMENT
IMMEDIATELY TO MAINTAIN ALL PRACTICES AS DESIGNED.
FOLLOWED. RULES DETAILING THE DOCUMENTATION OF THESE
LONGITUDINAL SLOPE NO STEEPER THAN 5%.
PROBLEM THE ENGINEER OF RECORD SHOULD BE NOTIFIED.
REMOVED FROM BEHIND THE SEDIMENT FENCE WHEN IT
CONTROL DEVICES IN PLACE UNTIL THE CONTRIBUTING
14. PURSUANT TO G.S. 113A-57(2), THE ANGLE FOR GRADED
INSPECTIONS TOOK EFFECT OCTOBER 1, 2010.
3.
THE CONTRACTOR SHALL ASSUME RESPONSIBILITY FOR ALL
8. STOCKPILE AREAS THAT WILL EXCEED 10' IN HEIGHT
BECOMES ABOUT 0.5' DEEP AT THE FENCE. THE SEDIMENT
DRAINAGE AREA HAS BEEN STABILIZED. INSPECT
SLOPES AND FILLS SHALL BE NO GREATER THAN THE
LAND DISTURBING ACTIVITIES AND ENSURE COMPLIANCE
SHOULD BE GRADED WITH 3:1 SLOPES AND SURROUNDED
FENCE WILL BE REPAIRED AS NEEDED TO MAINTAIN A
TEMPORARY EROSION AND SEDIMENT CONTROL DEVICES ON
ANGLE THAT CAN BE RETAINED BY VEGETATIVE COVER OR
TO SIMPLIFY DOCUMENTATION OF SELF -INSPECTION REPORTS
WITH THE APPROVED EROSION AND SEDIMENTATION
BY SILT FENCE.
PROPER BARRIER.
A DAILY BASIS AND REPLACE DETERIORATED, DAMAGED, OR
OTHER ADEQUATE EROSION CONTROL DEVICES OR
AND NPDES SELF -MONITORING REPORTS, DWQ AND DEMLR
CONTROL PLAN. THE CONTRACTOR SHALL INSPECT AND
9. APPROVED COPIES OF THE GRADING AND EROSION CONTROL
2. TEMPORARY EROSION CONTROL FACILITIES AND/OR
ROTTED EROSION CONTROL DEVICES IMMEDIATELY.
STRUCTURES. IN ANY EVENT, SLOPES LEFT EXPOSED WILL,
DEVELOPED A COMBINED FORM. THE SELF -INSPECTION
MAINTAIN ALL EROSION CONTROL DEVICES AND CLEAR ANY
PLANS SHALL BE ON THE PERMITTED SITE WHILE WORK IS
PERMANENT FACILITIES INTENDED TO CONTROL EROSION OF
8. TEMPORARILY OR PERMANENTLY STABILIZE ALL DENUDED
WITHIN 7 OR 14 CALENDAR DAYS OF COMPLETION OF ANY
PROGRAM IS SEPARATE FROM THE WEEKLY SELF -MONITORING
DEBRIS LEAVING THE SITE ON NEIGHBORING ROADS.
IN PROGRESS.
AND EARTH DISTURBANCE OPERATION SHALL BE INSTALLED
AREAS WHICH HAVE BEEN FINISH GRADED, AND ALL
PHASE OF GRADING, BE PLANTED OR OTHERWISE PROVIDED
PROGRAM OF THE NPDES STORMWATER PERMIT FOR
4.
EXISTING GROUND UPON WHICH FILL OR BASE IS TO BE
10. ALL EXISTING DRAINAGE COURSES THROUGH THIS SITE
BEFORE ANY EARTH DISTURBANCE OPERATIONS TAKE PLACE
DENUDED AREAS IN WHICH GRADING OR SITE BUILDING
WITH TEMPORARY OR PERMANENT GROUND COVER, DEVICES
CONSTRUCTION ACTIVITIES. THE FOCUS OF THE
PLACED SHALL BE CLEARED OF WEEDS, DEBRIS, TOPSOIL,
SHALL REMAIN IN A CONDITION SUCH THAT THEY CAN
OR AT THE EARLIEST POSSIBLE POINT DURING
CONSTRUCTION OPERATIONS ARE NOT ACTIVELY UNDERWAY
OR STRUCTURES SUFFICIENT TO RESTRAIN EROSION.
SELF -INSPECTION REPORT IS THE INSTALLATION AND
AND ALL OTHER DELETERIOUS MATERIALS; NO FILL SHALL
TRANSPORT THE NATURAL DRAINAGE UNTIL FACILITIES TO
CONSTRUCTION.
AGAINST EROSION DUE TO RAIN, WIND AND RUNNING WATER
PURSUANT TO G.S. 113A-57(3), PROVISIONS FOR
MAINTENANCE OF EROSION AND SEDIMENTATION CONTROL
BE PLACED UNTIL PREPARATION OF THE EXISTING GROUND
HANDLE THE STORM WATER ARE CONSTRUCTED. THE
3. TEMPORARY & PERMANENT EROSION CONTROL MEASURES
WITHIN 14 DAYS. USE SEEDING AND MULCHING, EROSION
PERMANENT GROUND COVER SUFFICIENT TO RETAIN EROSION
MEASURES ACCORDING TO THE APPROVED PLAN. THE
HAS BEEN COMPLETED
CONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE
SHALL BE CONSTRUCTED PER THE DETAILS HEREIN, OR
CONTROL MATTING, AND/OR SODDING AND STAKING IN
MUST BE ACCOMPLISHED FOR ALL DISTURBED AREAS WITHIN
INSPECTIONS SHOULD BE CONDUCTED AFTER EACH PHASE OF
5.
PROTECTIVE MEASURES SHALL BE TAKEN BY THE
DUE TO OBSTRUCTING NATURAL DRAINAGE PATTERNS.
SHALL BE CONSTRUCTED IN ACCORDANCE WITH THE NORTH
GREEN SPACE AREAS AND OTHERWISE APPROPRIATE
90 CALENDAR DAYS FOLLOWING COMPLETION OF
THE PROJECT, AND CONTINUED UNTIL PERMANENT GROUND
CONTRACTOR AND THE OWNER TO PROTECT ADJACENT
11. ANY DEVIATION FROM THE APPROVED GRADING PLAN
CAROLINA EROSION AND SEDIMENT CONTROL PLANNING AND
MEASURES. USE EARLY APPLICATION OF GRAVEL BASE ON
CONSTRUCTION OR DEVELOPMENT.
COVER IS ESTABLISHED. THE FORM CAN BE ACCESSED AT:
PROPERTY, THE PUBLIC AND UTILITIES DURING GRADING
SHOULD BE REPORTED TO THE ENGINEER OF RECORD PRIOR
DESIGN MANUAL.
AREAS TO BE PAVED.
15. CONTRACTOR IS RESPONSIBLE FOR INSTALLING ALL EROSION
HTTP: //PORTAL.NCID ENR.ORG/WEB/LR/EROSION
OPERATIONS. THE CONTRACTOR ASSUMES ALL LIABILITY FOR
TO IMPLEMENTATION OF THE CHANGE.
4. THE CONTRACTOR MUST NOTIFY THE APPROPRIATE NCDEQ
9. DO NOT REMOVE ANY EROSION AND SEDIMENT CONTROL
CONTROL MEASURES SHOWN AND ANY ADDITIONAL
THE UNDERGROUND UTILITY PIPES, CONDUITS, OR
12. ALL SLOPES 3:1 OR STEEPER THAT EXTEND TEN FEET OR
OFFICE A MINIMUM OF 48 HOURS PRIOR TO BEGINNING ANY
DEVICES AFTER THE PROTECTED AREA HAS UNDERGONE
MEASURES REQUIRED TO CONTROL THE SEDIMENT DURING
IF YOU HAVE QUESTIONS OR CANNOT ACCESS THE FORM,
STRUCTURES, WHETHER SHOWN OR NOT ON THE PLAN
MORE SHALL BE LINED WITH NORTH AMERICAN GREEN S75
LAND DISTURBING ACTIVITIES. 910-433-3300
FINAL STABILIZATION AND PERMANENT VEGETATION HAS
THE COURSE OF CONSTRUCTION.
PLEASE CONTACT THE FAYETTEVILLE REGIONAL OFFICE AT (910)
6.
IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO VERIFY
TEMPORARY EROSION CONTROL BLANKET OR EQUAL
5. REMOVE ALL SOILS AND SEDIMENTS TRACKED OR
BEEN ESTABLISHED, IT IS RECOMMENDED THAT NCDEQ
16. ALL SEEDED AREAS WILL BE FERTILIZED, RESEEDED AS
433-3300.
THE LOCATION OF ALL UTILITIES OR STRUCTURES ABOVE
SUBSTITUTE.
OTHERWISE DEPOSITED ONTO PUBLIC AND PRIVATE
APPROVE THE ACTION PRIOR TO REMOVAL.
NECESSARY, AND MULCHED ACCORDING TO THE DETAILS
PAVEMENT AREAS. REMOVAL SHALL BE ON A DAILY BASIS
10. THE CONSTRUCTION ENTRANCE SHALL BE INSTALLED
HEREIN.
WHEN TRACKING OCCURS.
CONCURRENTLY WITH THE INITIATION OF CONSTRUCTION
17. THE CONTACT PERSON FOR EROSION CONTROL ISSUES THAT
6. LOCATE SOIL STOCKPILES NO LESS THAN FIFTY (50) FEET
ACTIVITY.
ARISE ON SITE IS BEN STOUT. CONTACT 910-779-0019.
FROM ANY PUBLIC OR PRIVATE ROADWAY OR DRAINAGE
11. THE INSTALLATION OF EROSION CONTROL MEASURES SHALL
TAKE PRECEDENCE OVER ALL OTHER CONSTRUCTION
/
/
0 0 \
1/2
ERB �
1/21,
EIP
NOD " 1 /2" \
/
ERB \
�$ ERB
�1/2„ \
ERB
1/2,
SITE AREA
STABILIZATION
STABILIZATION TIME
DESCRIPTION
TIME FRAME
FRAME EXCEPTIONS
PERIMETER DIKES,
SWALES, DITHCES
7 DAYS
NONE
AND SLOPES
HIGH QUALITY
WATER (HQW)
7 DAYS
NONE
ZONES
IF SLOPES ARE 10' OR
SLOPES STEEPER
7 DAYS
LESS IN LENGTH AND ARE
THAN 3:1
NOT STEEPER THAN 2: 1,
14 DAYS ARE ALLOWED
SLOPES 3:1 OR
7-DAYS FOR SLOPES
FLATTER
14 DAYS
GREATER THAN 50 FEET
IN LENGTH
NONE
ALL OTHER AREAS
(EXCEPT FOR
WITH SLOPES FLATTER
14 DAYS
PERIMETERS AND
THAN 4:1
HQW ZONES)
o
1 /2" J\ L I
EIP ` V
N 549,052.060
E 2,066,885.331 0 ` 1/2
NC GRID NAD 83 ERB
(20 /1) � 105 1 2 1/2 \ 2
EIS
1 1
ERB
\
c 1/2„
/ --r ERB
ERB
L
/ 1 ��
� � L
/ ERB
r
ERB SHEET KEY ✓ �� : �'
100 1F
1 /2„ 1 2" ADO ERB J I/" 100 YF
v \ EIR 1 /2„ 1 /2„ : f _
1 .
ERB ERB
EIR
-1 /2„ \ \ \ 1ERB 1 /2„ 1ERB r� °o �_ /__���r / i< 105 o e o
\ EIR ERB
17
�'p,1. x .
Y �Y
1. ,11�s>1►lIIG!♦ ♦!!♦
♦!!�� �
.
0 o
113 00
ro
CONSTRUCTION SEQUENCE u `�� 9 O O O O D
� 12 � 11 10 O I �---. � z
1. OBTAIN ALL NECESSARY PERMITS AND APPROVALS AND 15 / 14 13 j
HOLD PRE CONSTRUCTION CONFERENCE. p 18 17 �� 16 �I L)
2. INSTALL STONE CONSTRUCTION ENTRANCES AND z
TEMPORARY SILT FENCE WHERE SPECIFIED.
3. CONSTRUCT TEMPORARY SKIMMER & SEDIMENT BASINS. 0 113' v I O
4. CLEAR AND GRUB THE SITE AS NEEDED.
5. ROUGH GRADE THE SITE AND APPLY TEMPORARY SEEDING t /�
TO AREAS REMAIN GRASSED.
6. INSTALL TEMPORARY CHECK DAMS IN SWALES AS SHOWN. _ S r�
7. INSTALL UTILITIES.
8. INSTALL INLET PROTECTION ON ALL NEW STORM WATER A�
INLETS.
9. PERFORM FINE GRADING. )
10. INSTALL AND PREPARE BASE COURSE.
11. PAVE ROADWAYS. ti _
12. FERTILIZE, SEED AND MULCH ALL REMAINING DISTURBED 125 ti
AREAS. �- V - L-
13. UPON SITE STABILIZATION, SEEK NCDEQ APPROVAL TO =
REMOVE ALL TEMPORARY MEASURES. > ^� ti 120
14. ALL EROSION CONTROL MEASURES SHALL BE MAINTAINED
AS OUTLINED IN THE DETAILS WITHIN THE PLANS AND c -�
ACCORDING TO THE NCDEQ EROSION CONTROL MANUAL.
15. TERMINATION OF COVERAGE UNDER THE NPDES GENERAL r
STORMWATER PERMIT FOR CONSTRUCTION ACTIVITIES MUST
BE REQUESTED BY THE PERMITTEE VIA A NOTICE OF C /N
TERMINATION (NOT). THE NOT IS AVAILABLE AT:
HTTPS://EDOCS.DEQ.NC.GOV/FORMS/NCG01-TERMINATION. - -
PLEASE NOTE THAT THE CLOSE OUT INSPECTION REPORT
MUST BE UPLOADED AS PART OF COMPLETING THE NOTICEOF TERMINATION PROCESS. )�� , _ - - - - > cry-_S�r4 . - 01
,
i I a -- --- -- - -- _- -- -- - JamI - _RANCH HOUSE
_ _ loon _ _ -ooP� _ - oo�- - - - - - -
-j I --SEAHAWK CT _ - - 00� 00l OOl 00� OOl -
-- ---� --�\. -00E�..L C--_----
j r--V
PP15 --- _�__� -- -- -_ ---
�
J n-_�-_�-_------�- 1/2„
_-- ---- --- _ - � - - - - _ iNv�------- -- -- ERB ERB GRAPHIC SCALE
NC 217 -LINDEN ROAD
----------
60' PUBLIC R W
_ _ 100 0 50 100 200 400
1 EIP
Know what's below. EIP
IN ET
Call before you dig. 1 c ch FE100)ft.
THE CONTRACTOR MUST CONTACT NORTH CAROLINA ONE CALL CENTER AT 1-800-632-4949 A MINIMUM OF 72 HOURS PRIOR TO DIGGING IN ORDER TO HAVE THE EXISTING UTILITIES LOCATED
4Dsite
solutions
civil engineering I land surveying
409 Chicago Drive, Suite 112, Fayetteville, INC 28306
office 1910-426-6777 fax 1910-426-5777 license number I C-2354
wwwAD site solutions.com
IN
SEA
0274
`�VG � •�.• Z ��
11111111N
0")-21`1)-22
REVISIONS
PROJECT NAME
LINDEN
LANDING
SUBDIVISION
OVERALL
GRADING AND
EROSION
CONTROL PLAN
CLIENT
AGS LAND LLC
1786 Metromedical Drive
Fayetteville, North Carolina 28304
Phone: (910) 779-0019
PROJECT INFORMATION
DESIGNED BY:
BRETT
DRAWN BY:
BRETT
CHECKED BY:
SCOTT
PROJECT NUMBER:
1878
DRAWING SCALE
HORIZONTAL: 1 "=100'
DATE RELEASED
SEPTEMBER 29, 2022
SHEET NUMBER
C-3mO