Loading...
HomeMy WebLinkAboutSW1220701_Plansheet - Misc. Detail_20220805 (6)TemDOrary Stabilization Temporary Stabilization is defined as a condition where exposed soils or disturbed areas are provided a temporary vegetative and/or non -vegetative protective cover to prevent erosion and sediment loss. Temporary stabilization may include temporary seeding, geotextiles, mulches, and other techniques to reduce or eliminate erosion until either final stabilization can be achieved or until further construction activities take place to re -disturb this area. Initiatina Temporary Stabilization Initiate temporary stabilization by mulch or temporary stabilization by seeding within 7 calendar days where land disturbing activities have temporarily ceased on the Project and will not resume for a period exceeding 14 calendar days. Where land disturbing activities on a portion of the Project are temporarily ceased, and the land disturbing activities are resumed within 14 days, temporary stabilization measures are not required to be initiated on that portion of the Project. Temporary stabilization by seeding is required if the Project will not be worked for a period longer than 60 days. Initiate temporary stabilization measures as soon as practicable for areas where initiating temporary stabilization measures within 7 days is infeasible (e.g., where snow cover, frozen ground, or drought conditions preclude stabilization). Temporary Stabilization Acceptance of Temporary Stabilization Before acceptance of temporary stabilization by the regulatory agency and the Design Engineer or Landscape Architect, temporary stabilization is required that is sufficient to control erosion for a given area and length of time before the next phase of construction or the establishment of permanent seeding is to commence. A satisfactory stand of temporary stabilization meeting the requirements of this Specification is required regardless of the time of the year the work is performed. Temporary Cover by Mulch Use temporary cover by mulch where it is not feasible or practicable to bring an area to final slope and grade. Finish the surface so that permanent seeding can be performed without subsequent disturbance by additional grading. Temporary Cover by Seedina Following the preparation of the seedbed, sow seed per the seeding Tables and apply an appropriate Mulch prior to a rainfall event that compacts the seedbed. The CONTRACTOR may add granular lime and fertilizer as necessary to enhance growth. Final Stabilization Final Stabilization is defined that all land -disturbing activities at the construction site have been completed and that on all areas not covered by permanent structures, either (1) A uniform (e.g., evenly distributed, without large bare areas) permanent vegetative cover with a density of 70 percent has been established, or (2) Equivalent permanent stabilization measures (such as the use of landscaping mulch, riprap, pavement, and gravel) have been implemented to provide effective cover for exposed portions of the construction site not stabilized with permanent vegetation. Final stabilization by vegetation must be achieved with permanent perennial vegetation prior to issuing the Notice of Termination (NOT). Permanent Seedin Initiate permanent seeding within 7 calendar days where land disturbing activities have permanently ceased on the Project. Where land disturbing activities are resumed within 14 days, stabilization measures are not required to be initiated on that portion of the Project. Initiate permanent seeding measures as soon as practicable for areas where initiating permanent seeding measures within 7 days is infeasible (e.g., where snow cover, frozen ground, or drought conditions preclude stabilization). When performing permanent seeding for permanent detention ponds, ensure that the detention pond is cleaned of any deposited sediment and graded to the required permanent detention basin configuration. Ensure the seedbed for the permanent seeding is established in accordance with this Specification. Acceptance of Permanent Seedina Before acceptance, a uniform perennial vegetative cover with a density of 70% of each square yard of the seeded area is required. A well developed root system must be established to sufficiently survive dry periods and winter weather and be capable of reestablishment in the spring. Permanent Seedina Installation Following the preparation of the seedbed, perform permanent seeding per the seeding Tables and apply an appropriate Mulch within 5 working days and/or prior to a rainfall event that compacts the prepared seedbed. If a rain event occurs that compacts or erodes the seedbed prior to performing permanent seeding, the seedbed must be re -prepared prior to conducting permanent seeding. Add fertilizer and lime as required by a soil test. Sod Initiate Sod applications within 7 calendar days where land disturbing activities have permanently ceased on the Project. Initiate Sod applications measures as soon as practicable for areas where initiating Sod applications within 7 days is infeasible (e.g., where snow cover, frozen ground, or drought conditions preclude stabilization). Use Sod on slopes less than 2HAV. Acceptance of Sod Acceptance is contingent on establishing a satisfactory stand of perennial grass. Sod application areas are acceptable when all requirements including maintenance are met and a healthy, evenly colored, viable stand of grass is established. A satisfactory stand of grass must have a root system that is sufficient to survive dry periods and winter weather and is capable of re-establishing in the spring. Sod Do not use sodding on slopes steeper than 2HA V, and if sodding is mowed, do not place on slopes greater than 3HAV. Install Warm Season Sod between March 1st and September 1st. Install Cool Season Sod anytime during the year as long as the soil is not frozen. Do not place Sod on: Soil that is frozen and/or when the 10-day forecasted low temperature remains below 35 degrees Fahrenheit; Soil that is excessively wet; Soil that is excessively dry (periods of heat or drought) unless watering is specified; Soil that is composed of compacted clay; and Soil than has been treated with pesticides. Sod Bed Preparation Ensure the Sod bed is uniform and conforms to the finished grade of the Project. Loosen the Sod Bed to a minimum depth of 3 inches before placing Sod. Furnish and place topsoil or compost in the Sod Bed in areas where the existing Sod Bed has little or no topsoil, Lay Sod when Sod Bed is moist. Moisten dry Sod Beds before sod is laid. Sod Material Provide Sod with living, well -established growth, with a dense root mat of predominant grass Specified. Provide vigorous, well rooted, healthy turf, free from disease, insect pests, weeds, other grasses, stones, and any other harmful or detrimental materials. Sod Installations Ensure Sod is not installed until the end of the project or when final stabilization is achieved on adjacent areas of the project that drain or discharge to the Sod application. Lime Agricultural Granular Lime Use agricultural grade, standard ground limestone for all permanent seeding applications and Sodding applications. Applying Granular Lime A soil analysis is recommended prior to application. Apply at a rate within ±10% of weight recommendation of soil analysis. Do not apply more than 2,500 Ibs/acre of in a single application. Fast Acting Lime Use fast acting liquid and/or dry forms of lime for all temporary seeding and permanent seeding applications. Fertilizer Granular Fertilizer Use for all permanent seeding applications and all Sodding applications. Proper mixture is dependent on the existing soil conditions and it is recommended that a soil analysis be performed if the soil conditions are uncertain in the area of fertilizer application. Use fertilizer that incorporates a minimum of 50% water insoluble (slow release) nitrogen . Animal by-product or municipal waste fertilizers are not acceptable under this Specification. Unless a soil analysis is performed to determine otherwise, a good rule of thumb granular fertilizer to apply in the Upstate of South Carolina is 10-10-10. In no case should a 20-20-20 fertilizer be used due to the potential burning of the seedbed. Compost Soil Amendment For seedbeds that have little or no topsoil, are highly acidic, or are lacking sufficient nutrients to sustain a health stand of grass place, and mix certified weed free compost into the seedbed to ensure a good stand of grass. Biological Growth Stimulant Use for all permanent seeding, Sodding, and temporary seeding applications. Animal by-products or municipal waste products are not acceptable. Liquid fertilizers are not acceptable, and can cause burning of the seedbed if applied as such. Seeding Dates and Rates of Application Perform seeding during the periods and at the rates specified in the seeding tables. Do not use temporary cover by seeding or permanent seeding for projects when: The ground is frozen and/or when the 10-day forecasted low temperature remains below 35 degrees Fahrenheit; The ground is excessively wet; or The ground is excessively dry (periods of drought) unless watering is specified. During periods of adverse conditions, use temporary cover by mulch. Seedbed Preparation Ensure that the areas receiving permanent seeding are uniform and conform to the finished grade of the Project. Perform minor shaping and evening of uneven and rough areas outside of the graded area in order to provide for more effective erosion control and for ease of subsequent mowing operations. Loosen the seedbed (including cut slopes) to a minimum depth of three (3) inches before initiating permanent seeding and temporary seeding. An acceptable method of preparing the seedbed on slopes is vertically tracking the seedbed up and seedbed up and down the slope with proper equipment. Remove stones larger than two and one-half (21/2) inches in any dimension, large dirt clods, roots, or other debris brought to the surface. Use compost if good seedbed material is not located on site or results of the soil test show the seedbed is excessively nutrient deficient to the extent of requiring costly fertilizer additions and or have excessively low pH values (lower than 5.0). Consider the use of mechanical seed drills to perform permanent seeding on areas where temporary seeding or temporary cover by mulch was previously utilized. Mulch Required for all permanent seeding, temporary seeding, and temporary cover applications. Do not use Mulch in areas where concentrated flow is expected. Use HECP Mulch for temporary seeding and temporary cover applications when the application area will require additional grading prior to permanent seeding. Do not use Erosion Control Blankets (ECB) or Turf Reinforcement Matting (TRM) in this situation. Wood Chip Mulch Wood chip mulch is not acceptable for seeding applications. If wood chip mulch is used for temporary cover by mulch, it must be removed prior to performing permanent seeding Straw or Hay Mulch with Tackifier Use material that is certified weed. Do not use on slopes steeper than 4HA V. Anchor using one of the following tacking agents: Organic or Chemical Tackifier Hydraulic Straw Tackifiers Emulsified Asphalt Applying Straw or Hay Mulch Uniformly apply material at the rate of 2,000 pounds per acre. Compost Mulch Only use from producer that participates in the USCC STA program. Do not use materials that have been treated with chemical preservatives as a compost mulch. Do not use mixed municipal solid waste compost. Hydraulic Erosion Control Products (HECPs) Use as an allowable mulch for temporary cover by mulch, temporary cover by seeding or permanent cover by seeding applications. Do not use as a channel liner or for areas receiving concentrated flow. Temporary Erosion Control Blankets (ECB) and Turf Reinforcement Mattina (TRM) Consider for permanent seeding application areas with steep slopes or areas where there is a significant erosion problem or potential for erosion. Use in areas where concentrated flow is expected. Do not use for temporary seeding applications when the application areas will require additional grading or modifications prior to permanent seeding. Protection of Structures Cover any parts of bridges, culverts, guardrails, signs, sidewalks, curb and gutters, catch basins, pipe ends, and other structures as necessary to prevent discoloration before spraying HECPs, organic or chemical tackifiers. Slope Interruption Devices The maximum allowable continuous slope length for straw or hay mulch, HECPs, compost and ECB applications is 50 feet. Slope interruption devices (such as sediment tubes) or TRMs are required for continuous slope length longer than 50 feet. Inspection Ensure that all seed, Sod, fast acting lime, biological growth stimulants, agricultural granular lime, granular fertilizer, straw and hay mulch, HECPs, compost mulch, and ECBs are applied as Specified. The Design Engineer or Landscape Architect, or member of the Design Engineer or Landscape Architect staff must document on -site that these materials are applied correctly by completing and signing proper forms. Perform all maintenance necessary to keep Stabilization areas in a satisfactory condition until the work is finally accepted. This includes mowing, repairing areas of erosion and washes, and applying additional seed, fertilizer, and mulch to areas where a satisfactory stand of grass has not been achieved. Mowing Mow road shoulders and medians when vegetation reaches a height of approximately 18 to 24 inches. Do not perform excessive mowing of Slopes resulting in ruts, furrows or grooves. Do not perform excessive mowing of Slopes that inhibits the establishment of the slope vegetation. Do not perform mowing when soil and weather conditions are such that rutting or other damage to the Project may occur. Ensure mowing results in a uniform vegetation height of 4 to 6 inches, unless otherwise directed. When utilizing a nurse crop for permanent seeding, mow Millet (no lower than 3 inches) once it reaches a height of 18 inches to reduce competitiveness with the permanent vegetation. Mow Wheat and Rye Grain (no lower than 3 inches) once they reach a height of 6-8 inches to reduce competitiveness with permanent vegetation. MULCH APPLICATION TABLE Mulch Applicable Slopes (H: ' Minimum Application Rate Ibs/acre -d 2 Wood Chips <_ 4:1 500 CY/acre Straw or Hay with Tackifier <_ 4:1 2,000 HECP Type 1 <_ 4:1 2,000 HECP Type 2 4:1 < S <_ 3:1 2,500 HECP Type 3 3:1 < S <_ 2:1 3,000 HECP Tvpe 4 2:1 < S 5 1:1 3,500 >1:1 4,000 (temp cover only)3 Compost Mulch <- 2:1 200 CY/acre 1 The maximum allowable continuous slope length for all mulch applications is 50 feet. Slope interruption devices or TRMs are required for continuous slope length longer than 50 feet. 2 Strictly comply with the manufacturer's mixing recommendations for the actual slope steepness and the actual continuous slope length of the application. 3 HECP Type 4 may be used for permanent cover applications on slopes 1:1 or greater at a minimum rate of 4,500 pounds per acre. ECB and TRM APPLICATION TABLE ECB/TRM Type' Slope (H:V) 2 Minimum Slope Length (ft) Temporary ECB or Type 1 TRM <_ 2:1 5 Type 2 TRM <_ 1.5:1 5 Type 3 TRM <_ 1:1 5 1 Strictly comply with the manufacturer's specifications. 2 The maximum allowable continuous slope length for ECBs is 50 feet. Slope interruption devices or TRMs are required for continuous slope length longer than 50 feet. GRASSING NOTES: 1. ON ANY PORTION OF THE SITE WHERE CONSTRUCTION HAS TEMPORARILY OR PERMANENTLY CEASED, ALL DISTURBED AREAS SHALL BE STABILIZED WITH GRASS AS SOON AS PRACTICAL, BUT NOT EXCEEDING FOURTEEN (14) DAYS AFTER WORK HAS CEASED. TEMPORARY GRASS SHALL BE APPLIED IN AREAS WHERE FUTURE CONSTRUCTION WILL RE -DISTURB THIS AREA, OTHERWISE, PERMANENT GRASS SHALL BE APPLIED. 2. IN ANY AREA IN WHICH TEMPORARY GRASS HAS BEEN APPLIED, THE GRASS SHALL BE MOWED AND THE SEED BED RE -SCARIFIED BEFORE PERMANENT GRASS APPLICATION. 3. BEFORE PERMANENT GRASS SEEDING IS PERFORMED, THE ENGINEER/ OWNER SHALL BE NOTIFIED FOR AN ON SITE INSPECTION OF THE PREPARED SEED BED AND FOR AN INSPECTION OF THE QUANTITIES OF MATERIAL TO BE APPLIED. CALL (864) 582-0585 TO SCHEDULE AN INSPECTION. ANY PROPOSED MODIFICATIONS TO THE GRASSING SPECIFICATIONS AND/OR METHODOLOGY SHOULD BE SUBMITTED TO THE ENGINEER WELL IN ADVANCE OF GRASSING ACTIVITIES. MODIFICATIONS MAY OR MAY NOT BE APPROVED. 4. THE CONTRACTOR SHALL PROVIDE A CERTIFIED LETTER INDICATING THE QUANTITIES OF MATERIAL APPLIED PER ACRE. 5. BEFORE ACCEPTANCE OF THE SEEDING PERFORMED FOR THE ESTABLISHMENT OF PERMANENT VEGETATION, THE CONTRACTOR WILL BE REQUIRED TO PRODUCE A UNIFORM VEGETATIVE COVER WITH A DENSITY OF 80% OF THE SEEDED AREA. 6. PERMANENT GRASS SHALL BE PROVIDED FOR ALL DISTURBED AREAS WITH THE FOLLOWING CRITERIA: A. LIME SHALL BE AGRICULTURAL GRADE GROUND LIMESTONE CONTAINING LEAST 34% MAGNESIUM CARBONATE. B. SEED SHALL BE A MINIMUM 90 % PURITY AND 80 % GERMINATION. C. AREAS TO HAVE GRASS APPLIED SHALL BE SCARIFIED CULTIVATED TO A DEPTH OF 3 INCHES, WITH ALL CLODS OR CLUMPS GREATER THAN 3" BROKEN UP AND FOREIGN MATERIAL INCLUDING ROCK, ROOTS, AND MISC. DEBRIS REMOVED. D. FERTILIZER AND LIME SHALL BE THOROUGHLY WORKED INTO THE SOIL, AND THE SURFACE RAKED SMOOTH BEFORE APPLYING SEED. E. SEED SHALL BE APPLIED EVENLY AT THE MINIMUM RATE AND RAKED IN LIGHTLY WITH APPROXIMATELY 1 /4" TOPSOIL COVER. SEEDED AREAS SHALL BE DRESSED SMOOTH, THEN MULCH (STRAW) SHALL BE APPLIED MECHANICALLY- F. AREAS SHALL BE SPRAYED IMMEDIATELY WITH AN EMULSION TO BIND SEED AND MULCH. 7. THE CONTRACTOR SHALL BE REQUIRED TO PROVIDE ALL MAINTENANCE NECESSARY TO KEEP SEEDED AREAS IN SATISFACTORY CONDITION UNTIL THE WORK IS ACCEPTED. THIS INCLUDES MOWING, IRRIGATING, REPAIRING OF EROSION WASHES, AND ADDITIONAL SEED, FERTILIZER AND MULCH APPLIED TO AREAS WHERE A SATISFACTORY STAND OF GRASS HAS NOT BEEN ACHIEVED. ALL COSTS INCLUDING IRRIGATING AND MOWING TO BE INCLUDED IN BASE BID PRICE. 8. PAYMENT TO THE CONTRACTOR SHALL NOT EXCEED 75 % OF THE CONTRACT PRICE FOR GRASS UNTIL A SATISFACTORY STAND OF PERMANENT GRASS HAS BEEN OBTAINED. 9. CONTRACTOR IS RESPONSIBLE FOR PROVIDING A STAND OF GRASS WITH A ROOT SYSTEM THAT HAS DEVELOPED SUFFICIENTLY TO SURVIVE DRY PERIODS AND WINTER WEATHER AND BE CAPABLE OF RE-ESTABLISHMENT IN THE SPRING- THE CONTRACTOR SHALL WARRANTY ALL GRASS FOR A PERIOD OF 1 YEAR BEGINNING FROM THE DATE OF ACCEPTANCE BY THE OWNER/ENGINEER. 10. ALL COSTS FOR PROVIDING AN ACCEPTABLE STAND OF GRASS (PERMANENT & TEMPORARY SEEDINGS) SHALL BE INCLUDED IN BASE BID (INCLUDING TEMPORARY IRRIGATION IF REQUIRED). NO ADDITIONAL CHARGES WILL BE HONORED FOR REPAIRS DUE TO WEATHER OR OTHER REASONS. THE CONTRACTOR SHALL ACCEPT RESPONSIBILITY AND COSTS FOR PROVIDING AN ACCEPTABLE STAND OF GRASS. 11. UPON PROVIDING A STAND OR GRASS (PERMANENT) THE CONTRACTOR SHALL MECHANICALLY MOW (A MINIMUM OF 2 TIMES) AT THE GRASS TYPE RECOMMENDED HEIGHT. FLEXTERRA APPLICATION RATES SLOPE GRADIENT/ CONDITION APPLICATION RATE <= 4H TO IV 2,500 LB/AC > 4H TO IV AND <= 3H TO IV 3,000 LB/AC > 3H TO IV AND <= 2H TO IV 3,500 LB/AC > 2H TO IV AND <= 1 H TO IV 4,000 LB/AC > 1H TO 1V 4,500 LB/AC BELOW ECB OR TRM 1,500 LB/AC AS INFILL FOR TRM 3,500 LB/AC • ALL UNSURFACED AREAS DISTURBED BY GRADING OPERATIONS SHALL RECEIVE 4 INCHES OF TOPSOIL AND PERMANENT GRASSING. U.N.O. CONTRACTOR SHALL APPLY EROSION CONTROL BLANKETS (NORTH AMERICAN GREEN SC150 OR APPROVED EQUAL) TO ALL SLOPES 3H:1V OR STEEPER AND PERMANENT SYNTHETIC TURF REINFORCEMENT MATTING (NORTH AMERICAN GREEN P300 OR APPROVED EQUAL) TO ALL SLOPES 2H:1V OR STEEPER UNTIL A HEALTHY STAND OF GRASS IS OBTAINED. INSTALL BLANKETS WITH BIODEGRADABLE STAPLES PER MANUFACTURER'S SPECIFICATIONS AND RECOMMENDATIONS. IF SOD GRASSING IS INSTALLED, IT SHALL BE PROPERLY SECURED AND STAPLED • CONTRACTOR SHALL REFER TO GRASSING NOTES AND DETAILS FOR FURTHER INFORMATION. CONTRACTOR SHALL ALSO COORDINATE WITH LANDSCAPE PLANS FOR AREAS TO RECEIVE SOD. AREAS TO RECEIVE SOD MAY REQUIRE TEMPORARY GRASSING. PERMANENT GRASSING (NON SOD AREAS) AREAS SHALL RECEIVE HYDRAULICALLY APPLIED FLEXTERRA FGM IMMEDIATELY AFTER FINISHING GRADING AND PRIOR TO FIRST RAINFALL EVENT. APPLICATION AND INSTALLATION OF FLEXTERRA SHALL STRICTLY COMPLY WITH MANUFACTURERS RECOMMENDATIONS. Non Slope Areas Spring/ Summer Non Slope Areas (durin establishment, mow when Millet reaches 18-Inches In height) Common Name' Botanical Name Planning Rate (lbslacre) Planting Rate (lbsH000so Planting Dates y- . Q �, f _ i Q y O= a Common Bermudagrass' (hulled = hull absent) Cynodon dactylon 50 1.15 • • • • White Clover Trifolium repens 5 0.11 • • • Browntop Millet Panicum remosum 10 0.23 • • • • • Fall I Winter Non Slone Areas rdurinn establishment. mow when Rue reaches B to R-inches in heiohtl Common Name' Botanical Name Planting Rate (IbNacre) Planting Rate (lba/IGDOA Planting Dates n o f _ Tall Fesoue (KY-31) Festuca arundinacea 50 1.15 • • • • • • • - Common Bermudagrass' (unhulled = hull present) Cynodon dactylon 15 0.34 • • • • • • • • White Clover Tdfolium repens 5 0.11 • • • • • • Crirmon Cloven Tdolium incamafum 20 0.46 • • • • • • • Rye Grain' LRe.-,=• secale cereale 15 0.34 • • • • • • • • Common Bermudagrase Do not use Giant BermudagrasSNK-37). 2 Only use pre -inoculated legurnes or use an appropriate inoculam With the seed at planting. ' Mow Rye Crain (no 1-than 3 inches) once it reaches a height of 6-8 inches to reduce conpelifiveness with perrmnent vegetation. " If the Common Name of the seed listed in the Tables is not available, use seed With the listed Botanical Name. Road Medians & Shoulders Spring I Summer Road Median I4 Shoulders (during establishment, mow when Millet reaches 18-inches in height) Planting Planting Planting Dates Common Name° Botanical Name Rate Rate (Ibalacre) pbsn000aq I a 2< f -, a y o Common Bermudagrasa, Cynodon dactylon 25 0.57 • • • • (hulled = hull absent) Browntop Millet Panic- remosum 10 0.23 • • • • • rail / winter Rosa median a snoulaers (during establishment, mow when Nye reaches a to a -inches in nerg Common Name Botanical Name Planting Rate (Ibslacre) Planting Rate (Ibs/1000s0 Panting Dates _ Tall Fescue (KY-31) Festuca amninaoea 50 1.15 • • • • • • • • IldCommon Bermudagrass' (unhulled = hull present) cynodon dectylon 15 0.34 • • • • • • • Crimson Cloven TAolium incamafum 20 0.46 • • • • • • • • Rye Grains seca/e cereals 15 0.34 • • • • • • • • ' Common Bermudegress: Do not use Cant BermudagraseNK-37). ' ony use pre -inoculated legumes or use an appropriate inoculant with the seed at planting. 'Mow Rye Crain (no borer than 3 inches) once it reaches a height of 6-8 inches to reduce competitiveness with permanent vegetation. ° If the Common Name of the seed listed in the Tables is not available, use seed with the listed Botanical Name. Slopes & Buffers Spring / Summer Slopes (during establishment, mow when Millet reaches 18-inches in height. Common Name' Botanical Name Planting Rate (Ibslacre) Planting Rate (lb./1000.0 Planting Dates -•j Ii 1 Q s i _ Q g rn O 2 S Tall Fescue (KY-31) Festuca aruninacea 50 1.15 • • u 6 Bahiagrass Paspalum notafum 30 0.69 • • • • • Common Bermudagrass' (hulled = hull absent) Cynodon dactylon 15 0.34 • • • • White Clover Tdfolium repens 5 0.11 • • • Weeping Lovegrass Erograsds cum/a 5 0.11 • • • • • • Hairy Vetch' Viola villosa 10 0.23 • Browntop Millet Panicum ramosum 10 0.23 • • • • • Fall / Winter Slopes (during establishment, mow when Rye reaches 6 to 8-inches in height. After establishment, only mow at end of winter season) Common Name' Botanical Name Planting Rate (Ibs/acre) Planting Rate (lbs/1000s0 Planting Dates �- Q°' -�, i < �, XX z a fM Tall Fescue (KY-31) Festuca arumnisma 50 1.15 • • • • • • • Common Bermudagrass' (unhulled = hull present) Cynodon decylon 15 0.34 • • • • • • • White Clover' Trifolium repens 5 0.11 • • • • • Weeping Lovegrass Emgrestis curvula 5 0.11 • • • • • • • U Crimson Clover2 Trlolium incamatum 20 0.46 • • • • • • • Hairy Vetch' Vicia villosa 10 0.23 • • • • • • • Rye Grains '.cal. cereal. 15 0.34 • • • • • • • 'Common Bermudagrass: Do not use Cant BerrrudagraseNK-37). ' Only use pre -inoculated legumes or use an appropriate inoculard With the seed at planting. ' Mow Rye Grain (no lower than 3 inches) once it reaches a height of 6-8 inches to reduce competitiveness with permanent vegetation. ° If the Common Nam of the seed listed in the Tables is not available, use seed with the listed Botanical Name. m SLOPE INSTALLATION NCGO1 NOTES: SELF -INSPECTIONS ARE REQUIRED BY S.S. 15A NCAC 04B .0131 SELF -INSPECTIONS SHALL BE DONE FOR THE FOLLOWING PHASES: a. INITIAL INSTALLATION OF EROSION AND SEDIMENT CONTROL MEASURES; b. CLEARING AND GRUBBING OF EXISTING GROUND COVER; C. COMPLETION OF ANY GRADING THAT REQUIRES GROUND COVER; cl. COMPLETION OF ALL LAND -DISTURBING ACTIVITY, CONSTRUCTION, OR DEVELOPMENT, INCLUDING PERMANENT GROUND COVER ESTABLISHMENT AND REMOVAL OF ALL TEMPORARY MEASURES; AND e. TRANSFER OF OWNERSHIP OR CONTROL OF THE TRACT OF LAND WHERE THE EROSION AND SEDIMENTATION CONTROL PLAN HAS BEEN APPROVED AND WORK HAS BEGUN IN ADDITION, WEEKLY AND RAIN -EVENT SELF -INSPECTIONS ARE REQUIRED BY FEDERAL REGULATIONS, THAT ARE IMPLEMENTED THROUGH THE NPDES CONSTRUCTION GENERAL PERMIT NO. NCG 010000. DOZER TRI CLEAT IMP TO THE SLl SHOULD BE SEEDED AND STABILIZED IMMEDIATELY. SLOPE TRACKING DETAIL NOT TO SCALE TEMPORARY STOCKPILE AREA 10" TYR) SILT FENCE (SEE DETAIL) ZLESOIL/SEDIMENT 0. STOCKPI AREA ORIGINAL GROUND SURFACE NOTES: 1. SILT FENCE TO EXTEND AROUND ENTIRE PERIMETER OF STOCKPILE, OR IF STOCKPILE AREA IS LOCATED ON/NEAR A SLOP THE SILT FENCE IS TO EXTEND ALONG CONTOURS OF THE DOWN -GRADIENT AREA. 2. IF STOCKPILE IS TO REMAIN FOR MORE THAN 14 DAYS, TEMPORARY STABILIZATION MEASURES MUST BE IMPLEMENTED. 3. SILT FENCE SHALL BE MAINTAINED UNTIL STOCKPILE AREA HAS EITHER BEEN REMOVED OR PERMANENTLY STABILIZED. 4. THE KEY TO FUNCTIONAL TEMPORARY STOCKPILE AREAS IS WEEKLY INSPECTIONS, ROUTINE MAINTENANCE, AND REGULAR SEDIMENT REMOVAL. SOIL STOCKPILE DETAIL NOT TO SCALEI 1. PREPARE SOIL BEFORE INSTALLING BLANKETS, INCLUDING ANY NECESSARY APPLICATION OF LIME, FERTILIZER, AND SEED. NOTE: WHEN USING CELL-O-SEED DO NOT SEED PREPARED AREA. CELL-O-SEED MUST BE INSTALLED WITH PAPER SIDE DOWN. 2. BEGIN AT THE TOP OF THE SLOPE BY ANCHORING THE BLANKET IN A 6" (15 CM) DEEP X 6" (15 CM) WIDE TRENCH WITH APPROXIMATELY 12" (30cm) OF BLANKET EXTENDED BEYOND THE UP -SLOPE PORTION OF THE TRENCH. ANCHOR THE BLANKET WITH A ROW OF STAPLES/STAKES APPROXIMATELY 12" (30 CM) APART IN THE BOTTOM OF THE TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING. APPLY SEED TO COMPACTED SOIL AND FOLD REMAINING 12" (30 CM) PORTION OF BLANKET BACK OVER SEED AND COMPACTED SOIL. SECURE BLANKET OVER COMPACTED SOIL WITH A ROW OF STAPLES/STAKES SPACED APPROXIMATELY 12" (30 CM) APART ACROSS THE WIDTH OF THE BLANKET. 3. ROLL THE BLANKETS (A.) DOWN OR (B.) HORIZONTALLY ACROSS THE SLOPE. BLANKETS WILL UNROLL WITH APPROPRIATE SIDE AGAINST THE SOIL SURFACE. ALL BLANKETS MUST BE SECURELY FASTENED TO SOIL SURFACE BY PLACING STAPLES/STAKES IN APPROPRIATE LOCATIONS AS SHOWN IN THE STAPLE PATTERN GUIDE. WHEN USING THE DOT SYSTEM STAPLES/STAKES SHOULD BE PLACED THROUGH EACH OF THE COLORED DOTS CORRESPONDING TO THE APPROPRIATE STAPLE PATTERN. 4. THE EDGES OF PARALLEL BLANKETS MUST BE STAPLED WITH APPROXIMATELY 2" - 5" (5 CM - 12.5 CM) OVERLAP DEPENDING ON BLANKET TYPE. 5. CONSECUTNE BLANKETS SPLICED DOWN THE SLOPE MUST BE PLACED END OVER END (SHINGLE STYLE) WITH AN APPROXIMATE 3" (7.5 CM) OVERLAP. STAPLE THROUGH OVERLAPPED AREA, APPROXIMATELY 12" (30 CM) APART ACROSS ENTIRE BLANKET WIDTH. NOTE: *IN LOOSE SOIL CONDITIONS, THE USE OF STAPLE OR STAKE LENGTHS GREATER THAN 6" (15 CM) MAY BE NECESSARY TO PROPERLY SECURE THE BLANKETS. EROSION CONTROL BLANKET INSTALLATION CRITICAL POINTS NOTES: A. Overlaps and Seams *Horizontal staple spacing should be B. Projected Water Line C. Channel Bottom/Side Slope Vertices altered if necessary to allow staples to secure the critical points along the channel A H A B�lnC surface. of s loose soil conditions, the use of staple or stake lengths greater than 6Use or s may be necessary to property secure the Drawing Not To Scale RECP's. NORTH Disclaimer: AMERICAN GREEN The information presented herein is general design information only. For specific applications, consult an independent professional for further design guidance. 5401 St. Wendel - Cynthiana Rd. PH: 800-722-2040 Poseyville, IN 47633 nagreen.com Drawn on: 5 17 NOT TO SCALE CHANNEL INSTALLATION DETAIL 1. Prepare soil before installing rolled erosion control products (RECPs), including any necessary application of lime, fertilizer, and seed. 2. Begin al the lop of the channel by anchoring the RECPs in a 6"(15cm) deep X 6"(15cm) wide trench with approximately 12"(30cm) of RECPs extendetl beyond the up -slope portion of the trench. Use ShoreMax mat at the channel/culvert outlet as supplemental our protection as needed. Anchor the RECPs with a row of staples/stakes approximately 12"(30cm) apart in the bottom of the trench. Backfill and compact the trench after stapling. Apply seed to the compacted soil and fold the remaining 12"(30m) portion of RECPs back over the seed and compacted soil. Secure RECPs over compacted soil with a w of staples/stakes spaced approximately 12" apart across the width of the RECPs. 3. Roll center RECPs in direction of water flow In bottom of channel. RECPs will unroll with appropriate side against the soil surface. All RECPs must be urely fastened to soil surface by placing staples/stakes in appropriate locations as shown in the staple pattern guide. 4. Place consecutive RECPs entl-over-end (Shingle style) with a 4".6" overlap. Use S double row of staples staggered 4" aPart and 4" on center to secure RECPs. 5. Full length edge of RECPs at top of side slopes must be anchored with a row of staplewstakes approximately 12"(30cm) apart in a 6"(15cm) deep X 6"(15cm) wide trench. Backfill and compact the trench after stapling. 6. Adjacent RECPs must be overlapped approximately 2"-5" (5-12.5cm) (Depending on RECPs type) and stapled. 7.In high Flow channel applications a staple check slot is recommended at 30 to 40 foot (9 -12m) intervals. Use a double row of staples staggered 4"(10an) apart and 4"(10cm) on center over entire width of the channel. 8. The terminal end of the RECPs must be anchored with a row of staples/stakes approximately 12"(30an) apart in 6"(15cm) deep X 6"(15cm) wide trench. Backfill and compact the bench after stapling. p CO 0 W W W H v>>O vOZp 0� O� � 0- p Q p ~ zQ O Z W (~j W W �OOOZpwtYp�lY::D IY } m W p LL1CO LU C) p J LU tY =LLJ �ZQtY0~LU a'W 1­­ 0 Z LLU 3: O lY] 0- W O ADEPTUS ARCHITECTURE, INC. 121 MANLY STREET GREENVILLE, SC 29601 864-242-2514 U CO o 04 V U O U N r/ 00 � Ln Q - co 3 sT � 00 o c L LL C rn LO Lc, W O LLO C �t •c 00 rn c t § L d co C.� G of;r 0-zZ z O _O o z co C)C COto CU Z z O J � Q ZD m _ 1) f, 0 CD Z I wCO z m _0 o 0 ^ C J z z 0 _o N Ln Ln W m Q 0 J J QV � 41 U 4- O N L N D_ 1- Engineer JDM Drawn By CWJ Date APRIL 2022 Revisions A ISSUE FOR PERMIT REVIEW 05.25.22 Project Number 2273.001 EROSION CONTROL NOTES DRAINAGE DITCH STABILIZATION NOT TO SCALE Sheet C501