The demolition of the CPI Southport Wastewater Treatment System is complete. Attached are pictures
taken during the demolition process and after completion of demolition. The only remaining work in the
area of the treatment system is final grading.
These photographs are presented in support of the request to rescind NPDES Permit NC0065099.
Beginning of demolition of the South Basin and the center dividing wall between the North and South
basins.
Jackhammer punching holes through the basin bottoms
Dividing wall demolished, outer wall demo nearing completion, basin bottom breaching in progress
Demo of Wastewater Treatment System Equipment Building in progress
All basin walls demolished including basin influent and effluent structures and Equipment Building
Holes in the basin bottoms
Plugged Outfall 003 Pipe