HomeMy WebLinkAboutSW5140801_Stormwater Narrative_20220923September 21, 2022 NARRATIVE / CALCULATIONS / MAPS / SUPPORTING INFORMATION FOR STORMWATER REVIEW for project North Carolina National Guard Camp Butner Training Center ACFT SCO# 20-22776-01 Site Address: North Carolina National Guard Camp Butner Stem, NC 27509 Engineer Timmons Group Attn: Frank Slinsky III, PE 5410 Trinity Road, Ste. 102 Raleigh, NC 27607 T: 919.866.4505 E: frank.slinsky(a timmons.com Owner / Developer North Carolina National Guard Attn: LTC Rodney Newton 1636 Gold Star Dr., Suite 2600 Raleigh, NC 27607 T:984.345.6137 E: rod ney.d.newton. mil(a mail.mil TABLE OF CONTENTS Stormwater Narrative Stormwater Major Modification Application (copy) Stormwater Permit SW5140801 Environmental Maps: ■ USGS Quad Map ■ NRCS Soil Map ■ FEMA Flood Map Property Deed Stormwater Management Mapping Permitted Pre -Development Plan Permitted Post Development Plan Updated Post Development Plan Stormwater Calculations Pre -Post Development Hydraulic Routing Wet Pond A Design SNAP Tool (for Nutrient Accounting) (Refer to Full size plan set for additional information) Stormwater Narrative Narrative General Information a. New Project Name: NCNG Camp Butner Training Center ACFT Old Project Name: Camp Butner Range 4 Road Extension b. Address: Nort ' al Guard Camp Butner Stem, NC 27509 c. Total Site Are . 16.40 Acres d. Disturbed Area: r e. Wetland Area: 0 Acres (there are no wetlands onsite). f. Ownership: North Carolina National Guard g. Proposed Development: This project will be site improvements for the North Carolina National Guard (NCNG) Camp Butner Training Center in Stem, NC. The existing site contains two permitted stormwater ponds located at the southwestern (Pond A) and southeastern (Pond B) corners of the site. These were permitted to capture and treat permitted for 18,530 sf of BUA and Pond B was permitted for 10,670 sf of BUA. The improvements in this project include an exercise track with equipment pads, two concrete/artificial turf training fields located inside the boundary of the track, a large pavilion covering both fields and a small restroom building. Pond A will be increased in size to handle 79,306 sf of BUA. The post development drainage area to Pond B will contain 10,348 sf of BUA and will not be touched during construction. The site is located within the Neuse River/Falls Lake Watershed. As part of the modification to the stormwater permit, we are providing nutrient accounting to bring the site into compliance with 15A NCAC 02B .0281. Approximately 8 acres of protected forest has been added to the site area. This forest is a safety buffer between Range Road and Range 4 Road (within Camp Butner). Phasing: This project will be completed in two phases. Phase I will be the construction of the track, ACFT Field 1 and modifications to pond A. Phase II will be the installation of ACFT field, a pavilion covering both fields and a small restroom building. Phase two is expected to begin immediately after phase one is complete. r P"ermit:_'es. Nfaior Modification to Permit No NCDEQ Compliance Issues: None. k. Water & Sewer Service: No improvements to the existing water and sewer service. I. Historic Sites: N/A This is not a historic site and there are no historic features on this site. m. Public Funding This project is being funded with public monies. n. FEMA FIRM # 3720084800L, dated October 19t", 2018 indicates that the site is outside the limits the 100-year flood plain. o. Soils on the site consist of predominately VaB (Vance sandy loam) and HeB (Helena sandy loam). p. Pre -development BUA (On -Site): 0.49-ac q. Post -development BUA (On -Site): 2.55-ac r. BUA to be treated: 2.06-ac Stormwater Major Modification Application (copy) DEMLR USE ONLY Date Received Fee Paid Permit Number Applicable Rules: ❑ Coastal SW -1995 ❑ Coastal SW - 2008 ❑ Ph II - Post Construction (select all that apply) ❑ Non -Coastal SW- HQW/ORW Waters ❑ Universal Stormwater Management Plan ❑ Other WQ Mgmt Plan: State of North Carolina Department of Environment and Natural Resources Division of Energy, Mineral and Land Resources STORMWATER MANAGEMENT PERMIT APPLICATION FORM This form may be photocopied for use as an original I. GENERAL INFORMATION 1. Project Name (subdivision, facility, or establishment name - should be consistent with project name on plans, specifications, letters, operation and maintenance agreements, etc.): NCNG Camp Butner Training Center ACFT 2. Location of Project (street address): North Carolina National Guard Camp Butner City:Stem County:Durham Zip:27509 3. Directions to project (from nearest major intersection): From the intersection of Range Rd (SR 1126) and Roberts Chapel Rd (SR 1123), travel north on Roberts Chapel approximately 0.1 miles. Turn left into Camp Butner Training Center (CBTC) onto Division Rd. In .05 miles turn left onto an unnamed gravel road. In 0.15 miles turn left onto CBTC Range 4 Rd and the site is on the left. 4. Latitude:36010' 44" N Longitude:770 47' 59" W of the main entrance to the project. II. PERMIT INFORMATION: 1. a. Specify whether project is (check one): ❑New ®Modification ❑ Renewal w/ Modificationt tRenewals with modifications also requires SWU-102 - Renewal Application Form b.If this application is being submitted as the result of a modification to an existing permit, list the existing permit numberSW5140801 , its issue date (if known)4/28/2022 , and the status of construction: El Not Started ❑Partially Completed* ® Completed* *provide a designer's certification 2. Specify the type of project (check one): ❑Low Density ®High Density ❑Drains to an Offsite Stormwater System ❑Other 3. If this application is being submitted as the result of a previously returned application or a letter from DEMLR requesting a state stormwater management permit application, list the stormwater project number, if assigned, SW5140801 and the previous name of the project, if different than currently proposed, Camp Butner Range 4 Road Extension 4. a. Additional Project Requirements (check applicable blanks; information on required state permits can be obtained by contacting the Customer Service Center at 1-877-623-6748): ❑CAMA Major ®Sedimentation/Erosion Control: 5 ac of Disturbed Area ❑NPDES Industrial Stormwater 0404/401 Permit: Proposed Impacts b.If any of these permits have already been acquired please provide the Project Name, Project/Permit Number, issue date and the type of each permit: 5. Is the project located within 5 miles of a public airport? ®No ❑Yes If yes, see S.L. 2012-200, Part VI: httl2://portal.ncdenr.org/web/Ir/rules-and-regulations Form SWU-101 Version Oct. 31, 2013 Page 1 of 6 III. CONTACT INFORMATION 1. a. Print Applicant / Signing Official's name and title (specifically the developer, property owner, lessee, designated government official, individual, etc. who owns the project): Applicant/Organization: North Carolina National Guard Signing Official & Title:COL Rodney D. Newton b. Contact information for person listed in item 1a above: Street Address:1636 Gold Star Drive, Suite 2600 City:Raleigh State:NC Zip:27607 Mailing Address (if applicable):1636 Gold Star Drive City:Raleigh State:NC Zip:27607 Phone: (984 ) 664-6062 Fax: Email:rodney.d.newton.mil@mail.mil c. Please check the appropriate box. The applicant listed above is: ® The property owner (Skip to Contact Information, item 3a) ❑ Lessee* (Attach a copy of the lease agreement and complete Contact Information, item 2a and 2b below) ❑ Purchaser* (Attach a copy of the pending sales agreement and complete Contact Information, item 2a and 2b below) ❑ Developer* (Complete Contact Information, item 2a and 2b below.) 2. a. Print Property Owners name and title below, if you are the lessee, purchaser or developer. (This is the person who owns the property that the project is located on): Property Owner/ Signing Official & Title:, b. Contact information for person listed in item 2a above: Street Address: City: State: Zip: Mailing Address (if applicable): City: State: Zip: Phone: Email: Fax: 3. a. (Optional) Print the name and title of another contact such as the project's construction supervisor or other person who can answer questions about the project: Other Contact Person/Organization: Signing Official & Title: b. Contact information for person listed in item 3a above: Mailing Address: City: Phone: ( ) Email: 4. Local jurisdiction for building permits: Granville County State: Zip: Fax: ( ) Point of Contact: Phone #: Form SWU-101 Version Oct. 31, 2013 Page 2 of 6 IV. PROJECT INFORMATION 1. In the space provided below, briefly summarize how the stormwater runoff will be treated. Stormwater will be treated and attenuated in two existing, permitted wet pond SCMs (Pond A & Pond B). Pond B will not be modified. Pond A will be resized for additional impervious for this major modification. 2. a. If claiming vested rights, identify the supporting documents provided and the date they were approved: ❑ Approval of a Site Specific Development Plan or PUD Approval Date: ❑ Valid Building Permit Issued Date: ❑ Other: Date: b.If claiming vested rights, identify the regulation(s) the project has been designed in accordance with: ❑ Coastal SW -1995 ❑ Ph II - Post Construction 3. Stormwater runoff from this project drains to the Neuse River basin. 4. Total Property Area: 16.40 acres 5. Total Coastal Wetlands Area: 0 acres 6. Total Surface Water Area: 0.19 acres 7. Total Property Area (4) - Total Coastal Wetlands Area (5) - Total Surface Water Area (6) = Total Project Area+:16.21 acres + Total project area shall be calculated to exclude the following: the normal pool of im ounded structures, the area between the banks of streams and rivers, the area below the Normal High Water (Nline or Mean High Water (MHW) line, and coastal wetlands landward from the NHW (or MHM line. The resultant project area is used to calculate overall percent built upon area (BUA). Non -coastal wetlands landward of the NHW (or MHM line may be included in the total project area. 8. Project percent of impervious area: (Total Impervious Area / Total Project Area) X 100 =15.7 9. How many drainage areas does the project have?2 (For high density, count 1 for each proposed engineered stormwater BMP. For low density and other projects, use 1 for the whole property area) 10. Complete the following information for each drainage area identified in Project Information item 9. If there are more than four drainage areas in the project, attach an additional sheet with the information for each area provided in the same format as below. Basin Information Drainage Area A Drainage Area B Drainage Area _ Drainage Area Receiving Stream Name Rocky Creek Rocky Creek Stream Class * WS-III;NSW WS-III;NSW Stream Index Number * 27-3-7.5-(1) 27-3-7.5-(1) Total Drainage Area (sf) 144,024 56,318 On -site Drainage Area (sf) 144,024 56,318 Off -site Drainage Area (sf) 0 0 Proposed Impervious Area** (sf) 79,306 10,348 Impervious Area** (total) 55% 18% Impervious- Surface Area Drainage Area A Drainage Area B Drainage Area _ Drainage Area _ On -site Buildings/Lots (sf) 51,436 0 On -site Streets (sf) 0 4,215 On -site Parking (sf) 6,735 0 On -site Sidewalks (sf) 13,584 6,133 Other on -site (sf) 0 0 Future (sf) 0 0 Off -site (sf) 0 0 Existing BUA*** (sf) 7551 0 Total (sf): 1 61,705 1 10,348 * Stream Class and Index Number can be determined at: http://portal.ncdenr.org web/wq,42s/csu/classifications Impervious area is defined as the built upon area including, but not limited to, buildings, roads, parking areas, sidewalks, gravel areas, etc. Form SWU-101 Version Oct. 31, 2013 Page 3 of 6 'Report only that amount of existing BUA that will remain after development. Do not report any existing BUA that is to be removed and which will be replaced by new BUA. 11. How was the off -site impervious area listed above determined? Provide documentation. N/A Proiects in Union County: Contact DEMLR Central Office staff to check if the project is located within a Threatened & Endangered Species watershed that maybe subject to more stringent stormwater requirements as per 1 SA NCAC 02B .0600. V. SUPPLEMENT AND O&M FORMS The applicable state stormwater management permit supplement and operation and maintenance (O&M) forms must be submitted for each BMP specified for this project. The latest versions of the forms can be downloaded fromhttr)://r)orLal.ncdenr.orLy/web/wa/ws/su/bmn-manual. VI. SUBMITTAL REQUIREMENTS Only complete application packages will be accepted and reviewed by the Division of Energy, Mineral and Land Resources (DEMLR). A complete package includes all of the items listed below. A detailed application instruction sheet and BMP checklists are available from http://12ortal.ncdenr.org/web/wq/ws/su/statesw/forms docs. The complete application package should be submitted to the appropriate DEMLR Office. (The appropriate office may be found by locating project on the interactive online map at http://portal.ncdenr.org/web/wq/ws/su/maps.) Please indicate that the following required information have been provided by initialing in the space provided for each item. All original documents MUST be signed and initialed in blue ink. Download the latest versions for each submitted application package fromhII12://portal.ncdenr.org/web/wq/ws/su/statesw/forms docs. Initials 1. Original and one copy of the Stormwater Management Permit Application Form. 2. Original and one copy of the signed and notarized Deed Restrictions & Protective Covenants Form. (if required as per Part VII below) 3. Original of the applicable Supplement Form(s) (sealed, signed and dated) and O&M agreement(s) for each BMP. 4. Permit application processing fee of $505 payable to NCDENR. (For an Express review, refer to http://www.envhelp.org/pages/onestopexpress.html for information on the Express program and the associated fees. Contact the appropriate regional office Express Permit Coordinator for additional information and to schedule the required application meeting.) 5. A detailed narrative (one to two pages) describing the stormwater treatment/management for _ 6. A USGS map identifying the site location. If the receiving stream is reported as class SA or the receiving stream drains to class SA waters within 1/2 mile of the site boundary, include the 1/2 mile radius on the map. 7. Sealed, signed and dated calculations (one copy). 8. Two sets of plans folded to 8.5" x 14" (sealed, signed, & dated), including: a. Development/Project name. b. Engineer and firm. c. Location map with named streets and NCSR numbers. d. Legend. e. North arrow. f. Scale. g. Revision number and dates. h. Identify all surface waters on the plans by delineating the normal pool elevation of impounded structures, the banks of streams and rivers, the MHW or NHW line of tidal waters, and any coastal wetlands landward of the MHW or NHW lines. • Delineate the vegetated buffer landward from the normal pool elevation of impounded structures, the banks of streams or rivers, and the MHW (or NHW) of tidal waters. i. Dimensioned property/project boundary with bearings & distances. j. Site Layout with all BUA identified and dimensioned. k. Existing contours, proposed contours, spot elevations, finished floor elevations. 1. Details of roads, drainage features, collection systems, and stormwater control measures. m. Wetlands delineated, or a note on the plans that none exist. (Must be delineated by a qualified person. Provide documentation of qualifications and identify the person who made the determination on the plans. n. Existing drainage (including off -site), drainage easements, pipe sizes, runoff calculations. o. Drainage areas delineated (included in the main set of plans, not as a separate document). Form SWU-101 Version Oct. 31, 2013 Page 4 of 6 p. Vegetated buffers (where required). 9. Copy of any applicable soils report with the associated SHWT elevations (Please identify elevations in addition to depths) as well as a map of the boring locations with the existing elevations and boring logs. Include an 8.5"x11" copy of the NRCS County Soils map with the project area clearly delineated. For projects with infiltration BMPs, the report should also include the soil type, expected infiltration rate, and the method of determining the infiltration rate. (Infiltration Devices submitted to WiRO: Schedule a site visit for DEMLR to verify the SHWT prior to submittal, (910) 796-7378.) 10. A copy of the most current property deed. Deed book: Page No: 11. For corporations and limited liability corporations (LLC): Provide documentation from the NC Secretary of State or other official documentation, which supports the titles and positions held by the persons listed in Contact Information, item 1a, 2a, and/or 3a per 15A NCAC 21-1.1003(e). The corporation or LLC must be listed as an active corporation in good standing with the NC Secretary of State, otherwise the application will be returned. http://www.secretory.state.nc.us/Corporations/CSearch.aspx VII. DEED RESTRICTIONS AND PROTECTIVE COVENANTS For all subdivisions, outparcels, and future development, the appropriate property restrictions and protective covenants are required to be recorded prior to the sale of any lot. If lot sizes vary significantly or the proposed BUA allocations vary, a table listing each lot number, lot size, and the allowable built -upon area must be provided as an attachment to the completed and notarized deed restriction form. The appropriate deed restrictions and protective covenants forms can be downloaded from http://portal.ncdenr.org/web/Ir/state- stormwater-forms docs. Download the latest versions for each submittal. In the instances where the applicant is different than the property owner, it is the responsibility of the property owner to sign the deed restrictions and protective covenants form while the applicant is responsible for ensuring that the deed restrictions are recorded. By the notarized signature(s) below, the permit holder(s) certify that the recorded property restrictions and protective covenants for this project, if required, shall include all the items required in the permit and listed on the forms available on the website, that the covenants will be binding on all parties and persons claiming under them, that they will run with the land, that the required covenants cannot be changed or deleted without concurrence from the NC DEMLR, and that they will be recorded prior to the sale of any lot. VIII. CONSULTANT INFORMATION AND AUTHORIZATION Applicant: Complete this section if you wish to designate authority to another individual and/or firm (such as a consulting engineer and/or firm) so that they may provide information on your behalf for this project (such as addressing requests for additional information). Consulting Engineer:Francis Slinky, PE Consulting Firm: Timmons Group Mailing Address:5410 Trinity Road, Suite 102 City:Raleigh Phone: (919 ) 866-4505 Email:frank.slinsky@timmons.com State:NC Zip:27607 Fax: (919 ) 859-5663 IX. PROPERTY OWNER AUTHORIZATION (if Contact Information, item 2 has been filled out, complete this section) I, (print or type name of person listed in Contact Information, item 2a) , certify that I own the property identified in this permit application, and thus give permission to (print or type name of person listed in Contact Information, item 1a) with (print or type name of organization listed in Contact Information, item 1a) to develop the project as currently proposed. A copy of the lease agreement or pending property sales contract has been provided with the submittal, which indicates the party responsible for the operation and maintenance of the stormwater system. Form SWU-101 Version Oct. 31, 2013 Page 5 of 6 As the legal property owner I acknowledge, understand, and agree by my signature below, that if my designated agent (entity listed in Contact Information, item 1) dissolves their company and/or cancels or defaults on their lease agreement, or pending sale, responsibility for compliance with the DEMLR Stormwater permit reverts back to me, the property owner. As the property owner, it is my responsibility to notify DEMLR immediately and submit a completed Name/Ownership Change Form within 30 days; otherwise I will be operating a stormwater treatment facility without a valid permit. I understand that the operation of a stormwater treatment facility without a valid permit is a violation of NC General Statue 143-215.1 and may result in appropriate enforcement action including the assessment of civil penalties of up to $25,000 per day, pursuant to NCGS 143-215.6. Signature: D a Notary Public for the State of, . County of do hereby certify that before me this _ day of personally appeared and acknowledge the due execution of the application for a stormwater permit. Witness my hand and official seal, SEAL My commission expires X. APPLICANT'S CERTIFICATION I, (print or type name of person listed in Contact Information, item 1a) Rodney Newton certify that the information included on this permit application form is, to the best of my knowledge, correct and that the project will be constructed in conformance with the approved plans, that the required deed restrictions and protective covenants will be recorded, and that the proposed project complies with the requirements of the applicable stormwater rules under 15A NCAC 2H .1000 and any other applicable state stormwater requirements. Signature: YL.�_ � Date: `'1'i_MA-A 7-2 I, W nn d� f1J a Notary Public for the State of Mg [_ Ylh .[d.lr Q[JY .County of IIIIa.y—T do hereby Certify that (7 W 7)• _�3� personally appeared before me this _ nay of &Aa to , and acknowledge the due execution of the application for a stormwater permit. Witness my hand and official seal,�.L[ on c�° NOTARY = PUBLIC 24 couNC'� il=d $116il00, SEAL My commission expires 2N ,10LLQ L1 20 -2t., Form SWU-101 Version Oct. 31, 2013 Page 6 of 6 Stormwater Permit SW5140801 ROY COOPER Governor ELIZABETH S. BISER Secretary BRIAN WRENN Director April 28, 2022 NORTH CAROLINA Environmental Quality North Carolina National Guard Attn: LTC Rodney Newton, Facility Maintenance Officer 1636 Gold Star Drive Raleigh, NC 27607 Subject: Post -Construction Stormwater Management Permit No. SW5140801 Camp Butner Range 4 Road Extension High Density Project Durham County Dear Colonel Newton: The Division of Energy, Mineral and Land Resources received a complete 8-year Permit Renewal Application for the subject permit on April 27, 2022. The Division is hereby notifying you that permit SW5140801 has been renewed, updated, and re -issued on April 28, 2022, as attached. As requested, a copy of the current operation and maintenance agreement is also enclosed. Please be aware that the renewal and re -issuance of this stormwater permit does not imply that the site is currently in compliance. This permit shall be effective until April 28, 2030 and does not supersede any other agency permit that may be required. The project shall be subject to the conditions and limitations as specified therein. This permit does not impose new or increased stormwater control requirements; it clarifies the rules and requirements of this program to provide you with a better understanding of your obligations under this permit. Failure to comply with these requirements will result in future compliance problems. Please note that this permit is not transferable except after notice to and approval by the Division. If any parts, requirements, or limitations contained in this permit are unacceptable, you have the right to request an adjudicatory hearing by filing a written petition with the Office of Administrative Hearings (OAH). The written petition must conform to Chapter 150B of the North Carolina General Statutes and must be filed with the OAH within thirty (30) days of receipt of this permit. You should contact the OAH with all questions regarding the filing fee (if a filing fee is required) and/or the details of the filing process at 6714 Mail Service Center, Raleigh, NC 27699-6714, or via telephone at 919-431-3000, or visit their website at www.NCOAH.com. Unless such demands are made this permit shall be final and binding. This project will be kept on file at the Raleigh Regional Office. If you have any questions concerning this permit, please contact Jim Farkas in the Central Office, at (919) 707-3646 or jim.farkas@ncdenr.gov Sincerely, Ougco42 ¢ Iwd 4 Almw 57 Brian Wrenn, Director Division of Energy, Mineral and Land Resources Enclosures: Attachment A — Designer's Certification Form Application Documents DES/jf. \\WaterResources\DEMLR - Stormwater\SW Permits\SW5140801\SW5140801_Renewal_20220428 cc: Frank Slinsky, PE; Timmons Group Raleigh Regional Office Stormwater File North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources 512 North Salisbury Street 11612 Mail Service Center I Raleigh, North Carolina 27699-1612 NORhI CAROLINA DepamMmmenim me,t,l r� / 919.707.9200 Post -Construction Stormwater Management Permit No. SW5140801 STATE OF NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY DIVISION OF ENERGY, MINERAL AND LAND RESOURCES POST -CONSTRUCTION STORMWATER MANAGEMENT PERMIT HIGH DENSITY DEVELOPMENT In compliance with the provisions of Article 21 of Chapter 143, General Statutes of North Carolina as amended, and other applicable Laws, Rules, and Regulations promulgated and adopted by the North Carolina Environmental Management Commission, including 15A NCAC 02H.1000 amended on January 1, 2017 (2017 Rules) (the "stormwater rules"), PERMISSION IS HEREBY GRANTED TO North Carolina National Guard Camp Butner Range 4 Road Extension 539 Roberts Chapel Road, Stern, Durham County FOR THE construction, management, operation and maintenance of built -upon area (BUA) draining to two (2) wet ponds ("stormwater control measures" or "SCMs") as outlined in the application, approved stormwater management plans, supplement, calculations, operation and maintenance agreement, recorded documents, specifications, and other supporting data (the "approved plans and specifications") as attached and/or on file with and approved by the Division of Energy, Mineral and Land Resources (the "Division" or "DEMLR"). The project shall be constructed, operated and maintained in accordance with these approved plans and specifications. The approved plans and specifications are incorporated by reference and are enforceable part of this permit. This permit shall be effective from the date of issuance until April 28, 2030 and shall be subject to the following specified conditions and limitations. The permit issued shall continue in force and effect until the permittee files a request with the Division for a permit modification, transfer, renewal, or rescission; however, these actions do not stay any condition. The issuance of this permit does not prohibit the Director from reopening and modifying the permit, revoking and reissuing the permit, or terminating the permit for cause as allowed by the laws, rules, and regulations contained in Title 15A NCAC 2H.1000 and NCGS 143-215.1 et.al. BUA REQUIREMENTS. The maximum amount of BUA allowed for the entire project is 29,200 square feet (including 2,500 square feet of existing BUA). The runoff from all BUA within the permitted high density drainage areas of this project must be directed into the permitted SCMs. The BUA requirements and allocations for this project are as follows: a. SCM BUA LIMITS. The SCMs labeled "A" & "B" have been designed to handle the runoff from 18,530 & 10,670 square feet of BUA, respectively, within the delineated drainage areas. The BUA for future development within the drainage areas to the SCMs labeled "A" & "B" is limited to 8,205 & 7,594 square feet, respectively. 2. PERVIOUS AREA IMPROVEMENTS. At this time, none of the pervious area improvements listed in G.S. 143-214.7(b2) or the Stormwater Design Manual have been proposed for this project. Pervious area improvements will be allowed in this project if documentation is provided demonstrating those improvements meet the requirements of the stormwater rule. Page 1 of 5 Post -Construction Stormwater Management Permit No. SW5140801 3. SCM REQUIREMENTS. The SCM requirements for this project are as follows: a. SCM DESIGN. The SCMs are permitted based on the design criteria presented in the sealed, signed and dated supplement and as shown in the approved plans and specifications. These SCMs must be provided and maintained at the design condition. b. PLANTING PLAN. The SCM landscape planting plan shown in the approved plans shall be followed in its entirety during construction. After the plants are established, the operation and maintenance agreement must be followed. c. FOUNTAINS. At this time, a decorative spray fountain has not been proposed within the wet pond. Decorative spray fountains will be allowed in the wet pond if documentation is provided demonstrating that the proposed fountain will not cause resuspension of sediment within the pond or cause erosion of the pond side slopes. d. IRRIGATION. If the wet pond is to be used for irrigation, it is recommended that some water be maintained in the permanent pool, the vegetated shelf is planted with appropriate species that can handle fluctuating conditions, and human health issues are addressed. 4. STORMWATER OUTLETS. The peak flow from the 10-year storm event shall not cause erosion downslope of the discharge point. 5. VEGETATED SETBACKS. A 30-foot wide vegetative setback must be provided and maintained in grass or other vegetation adjacent to all surface waters as shown on the approved plans. The setback is measured horizontally from the normal pool elevation of impounded structures, from the top of bank of each side of streams or rivers, and from the mean high waterline of tidal waters, perpendicular to the shoreline. a. BUA IN THE VEGETATED SETBACK. BUA may not be added to the vegetated setback except as shown on the approved plans. b. RELEASE OF STORMWATER NOT TREATED IN AN SCM. Stormwater that is not treated in an SCM must be released at the edge of the vegetated setback and allowed to flow through the setback as dispersed flow. 6. CONSTRUCTION. During construction, erosion shall be kept to a minimum and any eroded areas of the on -site stormwater system will be repaired immediately. a. PROJECT CONSTRUCTION, OPERATION AND MAINTENANCE. During construction, all operation and maintenance for the project shall follow the Erosion Control Plan requirements until the Sediment -Erosion Control devices are converted to SCMs or no longer needed. Once the device is converted to a SCM, the permittee shall provide and perform the operation and maintenance as outlined in the applicable section below. b. SCM RESTORATION. If one or more of the SCMs are used as an Erosion Control device and/or removed or destroyed during construction, it must be restored to the approved design condition prior to close-out of the erosion control plan and/or project completion and/or transfer of the permit. Upon restoration, a new or updated certification will be required for the SCM(s) and a copy must be submitted to the appropriate DEQ regional office. Page 2of5 Post -Construction Stormwater Management Permit No. SW5140801 7. MODIFICATIONS. No person or entity, including the permittee, shall alter any component shown in the approved plans and specifications. Prior to the construction of any modification to the approved plans, the permittee shall submit to the Director, and shall have received approval for modified plans, specifications, and calculations including, but not limited to, those listed below. For changes to the project or SCM that impact the certifications, a new or updated certification(s), as applicable, will be required and a copy must be submitted to the appropriate DEQ regional office upon completion of the modification. a. Any modification to the approved plans and specifications, regardless of size including the SCM(s), BUA, details, etc. b. Redesign or addition to the approved amount of BUA or to the drainage area. c. Further development, subdivision, acquisition, lease or sale of any, all or part of the project and/or property area as reported in the approved plans and specifications. d. Altering, modifying, removing, relocating, redirecting, regrading, or resizing of any component of the approved SCM(s), stormwater collection system and/or vegetative conveyance shown on the approved plan. e. The construction of any allocated future BUA. f. The construction of any infiltrating permeable pavement, #57 stone area, public trails, or landscaping material to be considered a pervious surface that were not included in the approved plans and specifications. g. Other modifications as determined by the Director. 8. DESIGNER'S CERTIFICATION. Upon completion of the project, the permittee shall determine if the project is in compliance with the approved plans and take the necessary following actions: a. If the permittee determines that the project is in compliance with the approved plans, then within 45 days of completion, the permittee shall submit to the Division one hard copy and one electronic copy of the following: i. The completed and signed Designer's Certification provided in Attachment A noting any deviations from the approved plans and specifications. Deviations may require approval from the Division; ii. A copy of the recorded operation and maintenance agreement; iii. Unless already provided, a copy of the recorded deed restrictions and protective covenants; and iv. A copy of the recorded plat delineating the public rights -of -way, dedicated common areas and/or permanent recorded easements, when applicable. b. If the permittee determines that the project is not in compliance with the approved plans, the permittee shall submit an application to modify the permit within 30 days of completion of the project or provide a plan of action, with a timeline, to bring the site into compliance. 9. OPERATION AND MAINTENANCE. The permittee shall provide and perform the operation and maintenance necessary, as listed in the signed operation and maintenance agreement, to assure that all components of the permitted on -site stormwater system are maintained at the approved design condition. The approved operation and maintenance agreement must be followed in its entirety and maintenance must occur at the scheduled intervals. a. CORRECTIVE ACTIONS REQUIRED. If the facilities fail to perform satisfactorily, the permittee shall take immediate corrective actions. This includes actions required by the Division and the stormwater rules such as the construction of additional or replacement on - site stormwater systems. These additional or replacement measures shall receive a permit from the Division prior to construction. b. MAINTENANCE RECORDS. Records of maintenance activities must be kept and made available upon request to authorized personnel of the Division. The records will indicate the date, activity, name of person performing the work and what actions were taken. Page 3of5 Post -Construction Stormwater Management Permit No. SW5140801 10. PERMIT RENEWAL. A permit renewal request must be submitted at least 180 days prior to the expiration date of this permit. The renewal request must include the appropriate application, documentation and the processing fee as outlined in 15A NCAC 02H.1045(3). 11. CHANGES TO THE PROJECT NAME, PERMITTEE NAME OR CONTACT INFORMATION. The permittee shall submit a completed Permit Information Update Application Form to the Division within 30 days to making any one of these changes. 12. TRANSFER. This permit is not transferable to any person or entity except after notice to and approval by the Director. Neither the sale of the project and/or property, in whole or in part, nor the conveyance of common area to a third party constitutes an approved transfer of the permit. a. TRANSFER REQUEST. The transfer request must include the appropriate application, documentation and the processing fee as outlined in 15A NCAC 02H.1045(2). This request must be submitted within 90 days of the permit holder meeting one or more of the following: i. A natural person who is deceased; ii. A partnership, limited liability corporation, corporation, or any other business association that has been dissolved; iii. A person or entity who has been lawfully and finally divested of title to the property on which the permitted activity is occurring or will occur through foreclosure, bankruptcy, or other legal proceeding. iv. A person or entity who has sold the property, in whole or in part, on which the permitted activity is occurring or will occur; V. The assignment of declarant rights to another individual or entity; vi. The sale or conveyance of the common areas to a Homeowner's or Property Owner's Association, subject to the requirements of NCGS 143-214.7(c2); b. TRANSFER INSPECTION. Prior to transfer of the permit, a file review and site inspection will be conducted by Division personnel to ensure the permit conditions have been met and that the project and the on -site stormwater system complies with the permit conditions. Records of maintenance activities performed to date may be requested. Projects not in compliance with the permit will not be transferred until all permit and/or general statute conditions are met. 13. COMPLIANCE. The permittee is responsible for complying with the terms and conditions of this permit and the approved plans and specifications until the Division approves the transfer request. a. REVIEWING AND MONITORING FOR COMPLIANCE. The permittee is responsible for verifying that the proposed BUA within each drainage area and for the entire project does not exceed the maximum amount allowed by this permit. The permittee shall review and routinely monitor the project to ensure continued compliance with the conditions of the permit, the approved plans and specifications. b. APPROVED PLANS AND SPECIFICATIONS. A copy of this permit, approved plans, application, supplement, operation and maintenance agreement, all applicable recorded documents, and specifications shall be maintained on file by the permittee at all times. c. MAINTENANCE ACCESS. SCMs, stormwater collection systems, and vegetated conveyances must be accessible for inspection, operation, maintenance and repair as shown on the approved plans. d. DIVISION ACCESS. The permittee grants Division Staff permission to enter the property during normal business hours to inspect all components of the permitted project. e. ENFORCEMENT. Any individual or entity found to be in noncompliance with the provisions of a stormwater management permit or the requirements of the stormwater rules is subject to enforcement procedures as set forth in NCGS 143 Article 21. f. ANNUAL CERTIFICATION. The permittee shall electronically submit to the Division an annual certification completed by either the permittee or their designee confirming the projects conformance with permit conditions. Page 4of5 Post -Construction Stormwater Management Permit No. SW5140801 g. OBTAINING COMPLIANCE. The Director may notify the permittee when the permitted site does not meet one or more of the minimum requirements of the permit. Within the time frame specified in the notice, the permittee shall submit a written time schedule to the Director for modifying the site to meet minimum requirements. The permittee shall provide copies of modified plans and certification in writing to the Director that the changes have been made. OTHER PERMITS. The issuance of this permit does not preclude the permittee from obtaining and complying with any and all other permits or approvals that are required for this development to take place, as required by any statutes, rules, regulations, or ordinances, which are imposed by any other Local, State or Federal government agency having jurisdiction. Any activities undertaken at this site that cause a water quality violation or undertaken prior to receipt of the necessary permits or approvals to do so are considered violations of NCGS 143-215.1, and subject to enforcement procedures pursuant to NCGS 143-215.6. Permit modified, updated, and reissued this the 281" day of April 2022. NORTH CAROLINA ENVIRONMENTAL MANAGEMENT COMMISSION Brian Wrenn, Director Division of Energy, Mineral and Land Resources By Authority of the Environmental Management Commission Permit Number SW5140801 Page 5of5 Post -Construction Stormwater Management Permit No. SW5140801 Attachment A Certification Forms The following blank Designer Certification forms are included and specific for this project: • As -Built Permittee Certification • As -Built Designer's Certification General MDC • As -Built Designer's Certification for Wet Detention Pond Project A separate certification is required for each SCM. These blank certification forms may be copied and used, as needed, for each SCM and/or as a partial certification to address a section or phase of the project. Page 1 of 1 Post -Construction Stormwater Management Permit No. SW5140801 AS -BUILT PERMITTEE CERTIFICATION I hereby state that I am the current permittee for the project named above, and I certify by my signature below, that the project meets the below listed Final Submittal Requirements found in NCAC 02H.1042(4) and the terms, conditions and provisions listed in the permit documents, plans and specifications on file with or provided to the Division. Check here if this is a partial certification. Section/phase/SCM #? Check here if this is part of a Fast Track As -built Package Submittal. Printed Name County of personally appeared before me this Signature a Notary Public in the State of do hereby certify that day of and acknowledge the due execution of this as -built certification. (SEAL) Witness my hand and official seal My commission expires 20 Permittee's Certification NCAC .1042(4) Completed / Provided N/A A. DEED RESTRICTIONS / BUA RECORDS 1. The deed restrictions and protective covenants have been recorded Y or N and contain the necessary language to ensure that the project is maintained consistent with the stormwater regulations and with the permit conditions. 2. A copy of the recorded deed restrictions and protective covenants Y or N has been provided to the Division. 3. Records which track the BUA on each lot are being kept. (See Note Y or N 1 B. MAINTENANCE ACCESS 1. The SCMs are accessible for inspection, maintenance and repair. Y or N 2. The access is a minimum of 10 feet wide. Y or N 3. The access extends to the nearest public right-of-way. Y or N C. EASEMENTS 1. The SCMs and the components of the runoff collection / conveyance Y N system are located in recorded drainage easements. or 2. A copy of the recorded plat(s) is provided. Y or N D. SINGLE FAMILY RESIDENTIAL LOTS - Plats for residential lots that Y N have an SCM include the following: or 1. The specific location of the SCM on the lot. Y or N 2. A typical detail for the SCM. Y or N 3. A note that the SCM is required to meet stormwater regulations and that the lot owner is subject to enforcement action as set forth in Y N NCGS 143 Article 21 if the SCM is removed, relocated or altered or without prior approval. E. OPERATION AND MAINTENANCE AGREEMENT Y or N 1. The O&M Agreement is referenced on the final recorded plat. Y or N 2. The O&M Agreement is recorded with the Register of Deeds and Y N appears in the chain of title. or F. OPERATION AND MAINTENANCE PLAN — maintenance records are being kept in a known set location for each SCM and are available for Y or N review. Page 1 of 6 Post -Construction Stormwater Management Permit No. SW5140801 G. DESIGNER'S CERTIFICATION FORM — has been provided to the Y or N Division. Note 1- Acceptable records include ARC approvals, as -built surveys, and county tax records. Provide an explanation for every requirement that was not met, and for every "N/A" below. Attach additional sheets as needed. Page 2of6 Post -Construction Stormwater Management Permit No. SW5140801 AS -BUILT DESIGNER'S CERTIFICATION GENERAL MDC I hereby state that I am a licensed professional and I certify by my signature and seal below, that I have observed the construction of the project named above to the best of my abilities with all due care and diligence, and that the project meets the below listed General MDC found in NCAC 02H.1050 in accordance with the permit documents, plans and specifications on file with or provided to the Division, except as noted on the "AS -BUILT" drawings, such that the intent of the stormwater rules and statutes has been preserved. Check here if this is a partial certification. Section/phase/SCM #? Check here if this is a part of a Fast -Track As -Built Package Submittal per .1044(3). Check here if the designer did not observe the construction, but is certifying the project. Check here if pictures of the SCM are provided. Printed Name NC Registration Number Date SEAL: Signature Consultant's Mailing Address: City/State/ZIP Phone Number Consultant's Email address: O Circle N if the as -built value differs from the Plan. If N is circled, provide an explanation on Page 2. OO N/E = not evaluated (provide explanation on page 2) OO N/A = not applicable to this SCM or project. Consultant's Certification NCAC .1003((3) & General MDC OAs-built OO N/E OO N/A .1050 A. TREATMENT REQUIREMENTS 1. The SCM achieves runoff treatment. Y or N 2. The SCM achieves runoff volume match. Y or N 3. Runoff from offsite areas and/or existing BUA is Y or N bypassed. 4. Runoff from offsite areas and/or existing BUA is directed Y or N into the permitted SCM and is accounted for at the full build -out potential. 5. The project controls runoff through an offsite permitted Y or N SCM that meets the requirements of the MDC. 6. The net area of new BUA increase for an existing project Y or N has been accounted for at the appropriate design storm level. 7. The SCM(s) meets all the specific minimum design Y or N criteria. B. VEGETATED SETBACKS / BUA 1. The width of the vegetated setback has been measured Y or N from the normal pool of impounded waters, the MHW line of tidal waters, or the top of bank of each side of rivers or streams. 2. The vegetated setback is maintained in grass or other Y or N vegetation. 3. BUA that meets the requirements of NCGS 143-214.7 Y or N b2 2 is located in the setback. Page 3of6 Post -Construction Stormwater Management Permit No. SW5140801 4. BUA that does not meet the requirements of NCGS 143- Y or N 214.7 (b2)(2) is located within the setback and is limited to: a. Publicly funded linear projects (road, greenway sidewalk) b. Water -dependent structures c. Minimal footprint uses (utility poles, signs, security lighting and appurtenances) 5. Stormwater that is not treated in an SCM is released at Y or N the edge of the setback and allowed to flow through the setback as dispersed flow. OAs-built OO N/E OO N/A C. STORMWATER OUTLETS — the outlet handles the peak Y N flow from the 10 year storm with no downslo e erosion. or D. VARIATIONS 1. A variation (alternative) from the stormwater rule Y N provisions has been implemented. or 2. The variation provides equal or better stormwater control Y N and equal or better protection of surface waters. or E. COMPLIANCE WITH OTHER REGULATORY PROGRAMS Y N has been met. or F. SIZING -the volume of the SCM takes the runoff from all surfaces into account and is sufficient to handle the required Y or N storm depth. G. CONTAMINATED SOILS — infiltrating SCM's are not Y or N located in or on areas with contaminated soils. H. SIDE SLOPES 1. Vegetated side slopes are no steeper than 3H:1 V. Y or N 2. Side slopes include retaining walls, gabion walls, or Y or N other surfaces that are steeper than 3H:1 V. 3. Vegetated side slopes are steeper than 3H:1 V (provide Y or N supporting documents for soils and vegetation). I. EROSION PROTECTION 1. The inlets do not cause erosion in the SCM. Y or N 2. The outlet does not cause erosion downslope of the Y or N discharge point during the peak flow from the 10 year storm. J. EXCESS FLOWS — An overflow / bypass has been Y N provided. or K. DEWATERING — A method to drawdown standing water has Y or N been provided to facilitate maintenance and inspection. L. CLEANOUT AFTER CONSTRUCTION — the SCM has been Y or N cleaned out and converted to its approved design state. M. MAINTENANCE ACCESS 1. The SCM is accessible for maintenance and repair. Y or N 2. The access does not include lateral or incline slopes Y or N >3:1. N. DESIGNER QUALIFICATIONS (FAST -TRACK PERMIT) — The designer is licensed under Chapters 89A, 89C, 89E, or Y or N 89F of the General Statutes. Provide an explanation for every MDC that was not met, and for every item marked "N/A" or "WE", below. Attach additional pages as needed: Page 4of6 Post -Construction Stormwater Management Permit No. SW5140801 AS -BUILT DESIGNER'S CERTIFICATION FOR WET DETENTION POND PROJECT I hereby state that I am a licensed professional and I certify by my signature and seal below, that I have observed the construction of the project named above to the best of my abilities with all due care and diligence, and that the project meets all of the MDC found in NCAC 02H.1053, in accordance with the permit documents, plans and specifications on file with or provided to the Division, except as noted on the "AS -BUILT" drawings, such that the intent of the stormwater rules and the general statutes has been preserved. Check here if this is a partial certification. Section/phase/SCM #? Check here if this is part of a Fast -Track As -Built Package Submittal per .1044(3). Check here if the Designer did not observe the construction, but is certifying the project. Check here if pictures of the SCM are provided. Printed Name NC Registration Number SEAL: Signature Date Consultant's Mailing Address City/State/ZIP Phone Number Consultant's Email address O Circle N if the as -built value differs from the Plan/permit. If N is circled, provide an explanation on page 2 OO N/E = not evaluated (provide explanation on page 2) OO N/A = not applicable to this project or SCM. This Certification must be completed in conjunction with the General MDC certification under NCAC 02H.1050 Consultant's Certification (MDC .1053) OAs-built OO N/E OO N/A A. Forebay / Depths / Fountain 1. The available Sediment storage is consistent with the Y N approved plan and is a minimum of 6 in. or 2. Water flow over the forebay berm into the main pond Y N occurs at a non -erosive velocity. or 3. The provided Forebay Volume is 15%-20% of the main Y N pool volume. or 4. The Forebay entrance elevation is deeper than the exit Y N elevation into the pond. or 5. The Average Design Depth of the main pond below the permanent pool elevation is consistent with the permitted Y or N value? 6. Fountain documentation is provided. Y or N B. Side slopes / Banks / Vegetated Shelf 1. The width of the Vegetated Shelf is consistent with the Y N approved plans and is a minimum of 6 feet. or 2. The slope of the Vegetated Shelf is consistent with the Y N approved plans and is no steeper than 6:1. or C. As -built Main Pool / Areas / Volumes / Elevations 1. The permanent pool surface area provided is consistent Y N with the permitted value. or 2. The Temporary Pool Volume provided is consistent with Y N the permitted value. or Page 5of6 Post -Construction Stormwater Management Permit No. SW5140801 3. The permanent pool elevation is consistent with the Y N permitted value. or 4. The temporary pool elevation is consistent with the Y N permitted value. or OAs-built OO N/E OO N/A D. Inlets / Outlet / Drawdown 1. The design volume draws down in 2-5 days. Y or N 2. The size of the Orifice is consistent with the permitted Y N value. or 3. A trash rack is provided on the outlet structure. Y or N 4. Hydrologic impacts to the receiving channel are minimized Y N from the 1 yr 24 hr storm discharge? or 5. The inlets and the outlet location are situated per the Y N approved plan and avoid short-circuiting. or E. Vegetation 1. The vegetated shelf has been planted with a minimum of 3 Y N diverse species. or 2. The vegetated shelf plant density is consistent with the approved plans and is no less than 50 plants per 200 sf or Y or N no less than 24 inches on center. Provide an explanation for every MDC that was not met, and for every item marked "N/A" or "N/E" below. Attach additional pages as needed: Page 6of6 Environmental Maps USGS Quad Map NRCS Soil Map FEMA Flood Map National Flood Hazard Layer FI RMette *FEMA Legend 78o48'15'W 36o10'56"N SEE FIS REPORT FOR DETAILED LEGEND AND INDEX MAP FOR FIRM PANEL LAYOUT I.V,VVV 0 250 500 1,000 1,500 2,000 Basemap: USGS National Map: Orthoimagery: Data refreshed October, 2020 Without Base Flood Elevation (BFE) Zone A, V, A99 SPECIAL FLOOD Wit hBFE orDepthZoneAE,AD,AH,Ve,Aa HAZARD AREAS Regulatory Floodway OTHER AREAS OF FLOOD HAZARD 0.2% Annual Chance Flood Hazard, Areas of 1% annual chance flood with average depth less than one foot or with drainage areas of less than one square mile Zonex Future Conditions 1% Annual 4 '- Chance Flood Hazard Zonex "Area with Reduced Flood Risk due to Levee. See Notes. Zonex " Area with Flood Risk due to Leveezone D NOSCREEN Area of Minimal Flood Hazard Q Effective LOMRs OTHER AREAS Area of Undetermined Flood Hazard GENERAL - — - - Channel, Culvert, or Storm Sewer STRUCTURES IIIIIII Levee, Dike, or Floodwall e zo.z Cross Sections with 1% Annual Chance 17.5 Water Surface Elevation a - - - Coastal Transect —sfa— Base Flood Elevation Line (BFE) Limit of Study Jurisdiction Boundary — --- Coastal Transect Baseline OTHER _ Profile Baseline FEATURES Hydrographic Feature Digital Data Available AN El No Digital Data Available MAP PANELS El Unmapped QThe pin displayed on the map is an approximate point selected by the user and does not represent an authoritative property location. This map complies with FEMA's standards for the use of digital flood maps if it is not void as described below. The basemap shown complies with FEMA's basemap accuracy standards The flood hazard information is derived directly from the authoritative NFHL web services provided by FEMA. This map was exported on 5/11/2022 at 12:51 PM and does not reflect changes or amendments subsequent to this date and time. The NFHL and effective information may change or become superseded by new data overtime. This map image is void if the one or more of the following map elements do not appear: basemap imagery, flood zone labels, legend, scale bar, map creation date, community identifiers, FIRM panel number, and FIRM effective date. Map images for unmapped and unmodernized areas cannot be used for regulatory purposes. Property Deed to st+ka Ho. 151 thanoo H 7. 031 55a 3 5102 to IFS Stake N. 14; thanan 11 6' 56, 04n W 328, to Stake r• _ 1106 131-thcnoe H 19D 201.02" W 57V to stake No. 12; thence N 19'- 281 02■ W 251 to stake 11c. 1lj thence H 26' 081 31n W Wl to strsko No. 10; thence U 115' 281 f>0t1 W 8420 to Stake fro. 91 theme 11 1t4° 27t 29% W 2681 to Stake Ho. 81 thetro H 31' 28+ 28n if 405t to Stake No. 7; thence Joking said fight-Of-utty, H 88' 19c 5?" W 4091 to Honuennt No. 6.2 on the oaat side of a county roadl thenoe slang scat sins of county road, tr 1' i)hi IA& E 1>.1.41; thanes H 4' 06t F 146+j thenno 11 3' 23t E 10241; thence H 1' 201 1OW E 5W.7t; thence 11 4' 44, 50 F 25211 thenoa N 12. 281 20}o E 17331 thence 1; 5' 26r 40,1 E 198tj.thonce H 1, 05, W 196, j then o ;1 4' 57 t 1ps+ 8 174' ; thono e W 3' 11t 20R W, Lit; themo H 23. 35t 20" if 146t thence 1[ 56. 02� WH W� 1511 j thenca 0 32' 3 t 1C" W 1321; thmcs H 30. 03t gin W 3431; thema 11 26' 1111t W4 W 146t j thence H 33' 171 3M W 26311 thoace H 30* ,161 40" W 61911'thenoa N 28■ N' 20" W 258tj thence H 26. 13t 50" W 301ti tkEmo H 37. 52t 20N W 31411 thence H-59' obt 30" W 119! 1 thence N- 41' Or ?.0a W 367, 1 thence ls&" East eido of CounW Road, H•0' 57, 401, E 79711 thence N 2. 19' 30" E 6011 to a 531-6— in the cantnr of anothor Con ty' Roadh hpn4o slang the oetster lino ok avid Counts ;toad, H 43' 161 30■ E 4021 to the intcraeotien of the _9iknttai-line Of he1i? Ystoit-Romdjrthn�sce_�{ $9".E��� 3521, tnoe H`89. 30) E 868;jfthance 11 85. 45t 8 10101 j theme H 21 451 E 1511 thon66 S. 07• 151 E 1398t; thence H 2' 145t g 2831; thence S 87' 151 E 4921.1 to a point which is the center line of Woods Road and Oranville-Durham County Uney also the Southeast corner of Treat No. E-80-Dj thence along Counttiy Line and center lies of 110odn Road, south 231, to the NorThwart oorner Of Tracts No. F-1-0; thence along the northern hcwudwry of said taact= s 86. 30t E 2699, to a point on the awter line of Knap O; Heeds Creek; thence along tha omttar line of $Ad Creek, S 1' W 550, to the intersection of the center line of : Knap of Reeds Creek with the center line of Hetpton Road; thence in a Hortherlr direction along the Sceiheost Wmdary Of Trust No, F-3-G H 59' E 1941; thatnee H 22, E 3621; thence N 47' 10t E 1451; thano a if 46' H Wei j there e W 48' - 451 E 3721 to a point which is the East cornsr of Tract No, F-3-0; thence along the Southern boundary of Traot Ho. F-52--G a.jprovlmatoly 1973 feet to a point on the north line of Tract Ire. C-{:7-0p the Southeast wrncr of Tract 110. F-52-0 and the gouthwrsnt'oore75rsgC'?rAot'Ho. F-116-01 theme thsrcugh Tract 110..F-47-G South' appro ximatol y 4 ahaim (264 feet) to the center of a road] thence eeytrrly along the center of said road upproxLasatek7 9 chains (594. feet) to P- w CaRLW {1320 feet) alonK Sold :xtmedud ennterly line and the aaaterly line of Tract no. F-5-G to a point on the north line, 0f TTrac No. F �'-(l j thonr,e throe a Tract F.6 q S 20. b apprext— ]+ately 111 chaian (924 feet) to the moat waetesly Corner of Tract No. P-8-4; thence along the EAatdr re bowtdary oP Treat No. F-6-G and the Waetran botun�- dario5 Of Tracts no. F-$--ot F"IL-G and r-9-0� 8 12• g 634t; thonce 3 12• E 587T1 thence 3 12• E 6117t to a point uhich is the Southoast mrr" of Tract No. F-6-0; thence alcnK the Southern bavndary of Tract No. F-'b-G end the NorthoM boundary Or Tract No- F-ID-a 8 01,0 W 462a to a point whILh is the Westerrmoat cmnor of Treat lto. F--10.42; thence along the Heaton boundary of Treat 1104 F-10-Q and +he Euatorn boundary of Tract Yio. D`�Ge s 201' E 759, to a p01at which 119 lb Southernwat corner of tract NO. F..10..p; thmee along the 8antern bcantivy of Tract No. 10_M_G and the yjestr:rn beunnary of Tract No. D 66b G a M"ndrring Southeaatorn dir"1410n 36Wf tc a point which is the Eaoternmont corner or Tract 110. D-65-0) thence N 800 9 loot to a Crank eevorm ing Treat No* 11d43KG; thence in a masndaring Southwestern direction along said Creek, 990t to • Er mh on the NostperTmoilt boundary of TI-act No■ D-1 2-GJ tie rnoe alertg the Branch, which is the Hear thsarrtern boundary of Tract No. D-1}2r6 and the SOLMmostarn boundary of Tract +10. D--�3.0e in a meandering Southesatern direction 1650t to a paint ire a road ass the Wmatrrn boundary or Tract No. D-411-0; thence along the Road S 13• W 378e to a point which ie the Sauth"atorn ccrmr of Tract f10. D-42—G and the SMhlleateln corner of Tract No. 1}44•0j thence leaving said mad s 651- g 330, along the Southern boundary of Tract No. D-114.0 arA the Northern bou nd=7 or Tract No, i-3L-G to ■ point which Ia thu Hortheastrsn corner, of Tract No. D+364; thoroe along tha Easttrn Gong.-. dar7 of Tract No. 'R-3 -0 cad the Wostern boundary of Tract Ile. t}-?3-.a S 241* W 11197 to a point which is the Nerthweatrrn corner of Tract ro. -3C 6; thence along the West"n bcundarr of Traat No. D-318-fi and the Pastern boundaries of Tracts No. N34-0 and D-28+-G s 24j' W 86ot to a point which is the Horthwestarn aernar oX Tract Notj iy-25-Gj th*noe along tits Wa'tern boendary of Tract NO, D-25-0 sad the 'Eastern toundarieu of Tracts No. I1-2d-.O, D-35-0 and r.-27-.G 8 24j* W 460ti thenoo S 77• E IWO; thanee S 530 w I$o0e tv a point in Ste Road end being the moat F10sterly corner or Tract No. D-25.91 thence along Sham Road„Which_.ftL.tho-Morth6rn„bucudarg off — Tra.at No- f3-15-0 and the SoutJntn bounaariea of - -- Txacta No. D-27-0 and D-35-G, in a meandering 4 ,fi' 73 V os' �x rrAnt f1�35-Cr wig .. " "na 9 No. Llarthar cu ern Y Sraot Ha, f?-13'4i 11 80• w 1p3of to n bn,zn. r ctaq . V.., whi�1 iz the ttoc-thfregtern ocra ant Trani No, ytl3-Pj' thence lvavinc 3t[m ftvnel 3 2a3111• FI 99C' and the a Fastnrn bounaary of Traractct If }� +lvstarrf bo,,d,, 3-C tr to rs pn l"tr, ' r�Rcti tl 81' W 16,37, a1and the #Ck"g thorn baunaa NO. l}. 7 a1' Trnet .No. T}�1.' 35-n +u1d the Southern bolln. Umtheaaturn ¢crn� oY ' to a Point xfalch In the � H 22-26+ ttO. T�12-C; thine❑ N tra. V-3 +1anF � Southom bovadary, of Tract 12-11 5 [' and the Nartharn bound 11,7 ai' Tract tfo. "C► to a Faint xhich is the tdortheaatern �rnar o!' Tract C-c'5-0; thence S ap W 16 }+ along the Sou+}1e-n t+oundari, of Tract No. C-78.rjG and the Northern boundary oi• Tract C+af.n Lo n point uttheh is the Flartheastern a�np nx Tract go. C..67..p: thence along the mOpthern b01 C�67an tf e7. i1 5C+e1= thucaa N�5d,3%14't7'1'A�'tic• arthpa Barn to a point in a road uh#Ch p thanoc ,tam bcunc?arq ae Tract is as thu along 5ai4 road sower It". Cr67:p3 thennce rae�dcring Nart7xraotrr g Tract tlo. C-68.p in a at a read int eraec n 4Lrectien 16pr to a paint corner op t4on which is tho 3onthenet,rn Tract ro. C-tr9..g1 thence along sale road In a 9cner1UY Wastrrn direction which is the Southern boundary of Tract tie. Cw69-D and tde !Earth,,,, their d at a act tic■ C.m.n 158oi to a poi. In d oak uhieh .is thu So:thxuatom of Tract tfo. C»69.D; thcusca corner along sai�! Cravk in a o"eanl$�'� Horthwr y direstial which ie the p:in arlt f Tract No. C+6Of t No. Ct toD a,1d the 1jestnlYs be undt+ry tlortbvoeta 9 D 7Cpr to a point which 1, the xd earlof Tract tta. CM5],D; thonCcs leaning said Cree-t H 25• ''d 33or; thence N 88• F] 2l�6pr al"g tho Honk',,,, bourtdyy Of Tract t1n, to C 7a—D and W1v Hcutharn boundary or Tract flo■ C-7a�-D SgtRa d; 2i on the Mast ridit-*i:,uay of U1v 'rlvct RanKa °;g; 177ii.n is the point Of bog:bu,Ing, r+nd callt-r]AnA» i 9 acres, I,ra, or laze,, F pThevabc'rn deccri6od prrc+tZs bang the samO rro� National utilized by the St, Guard as te of HOrth Carolina a general zYring r ago. BRCEPPIHG, N,7,m9F8, from this oanreyarCe and rnserving to the party of the z'irst part, in accordance with precutLra Ordr.+r 9908, epgroyed on TDdcomber 5, 1947, S12 r. n. 3223), all uranium, thoriwn, and all Other matim-:LaLs datrcrr,L{Red pt'duant to section 5 (b) {1) o£ the Atoffou Fher97 Act of 1946 (60 Stet. 76t), to be PCOU112rly eustntial to the production of fisaionahle material, contained, in Nllatevox 5 ,P�!> newe Dy reserved for the us's'of the , United Statee- together with the right of the United States throudi its authorized agents or representatives at anytime to' enter upon the land and prospect fo one, and remove tha same, making just compensation r, for any �� or injury occasioned thare br, 'R'Over ruts other ° such iand map be used, and any wise squired by this be a �poeition mapr �ceroisad, as if no reservation of such materiale had been madel except that, when such use results in the extraction of any such material pi,os he land in quantities which may not be tran5femed or delivered without a License unticz the Atomic F]rergy Act of 19g6 8e it saw 40, be amen exists or may hereafter tled, such material shall be the property oP the United States Atomic gnar� Commission, and the Co�aoisdioti may require delivery of �O such material to it by any pcesessor thereof after such material has been separated a such from the ores in which it was contaiRed, lY the Colwldeeion re quires the delivery of sech material to it, it shall Pay the Prrson mining ar extracting the as the Cosame, or to such other Person Commission detwalnea to be entitled -thereto, such aums, inc profits, as the Commission deems fair e, Lyle discoluding and reasonable for Ong, devalopmnaL, I?overy, duotion,-traotioni and other services per formed vith respect to ;Auclh material Pa9ment shall not include ea prior to such delivery, but such y amount on account of the value of such naterial before removal from its place of deposit in nature, If tha Comniesioth dose not require u bdelivery of such material to it, the resehti vatioa hereby made e}1de of no further force or effect. ADd further excepting from this eo nve9ance and reserving to the Party of the Pi1•sL Cgngressi all-rmLnerpa`t' ae required under said Public Law 927 . 83rd r ai rights,—ina.tusir�g-�s...ad-oil,'in the ]Ann Fsrsia. above described. 1'C PAVE AND xo RCLD the said promisee vith appm'+nanoee there- 6 .unto conditions c to the the said pa eat forth in BY the rty of the-..aond pert forever, this iaetri�ra�nt` accept...° party of the secondcf this dead or rights hereunder, the Bald part agrees that the instrument is accepted, subject to Property transferred in aub-para the follow by this graphB (l) fl+�d (2j oP t rag restrictions Bet forth the land and which are his paragraph, which shall imposed•.s run with A:blic meat,drof Bald (1) That the 7 - 8gid Congress, approved i►pr 2 d virtue a 1954: faailitiea'in uhiah this • lend, buildingaa structure improvements and used for ry pur•poses�strument transfer' ark. interest shall milita for such ate' and In the event be p6poseB, title thereto B it shall not be used States, and, in addltto hall i�edlately revert to the United of the .... n, title to all impro"'-"te made � �� dur'ine its coon by the Party Without payment of a Pency shall vest in th omp°asatioa therefor. a United states, (2) That whenever the Congress �B9s of the 3 a state of war or other fates shall nstlo declares a state of emergency marg � usl emergency or the President � the S ° cy to axlst a y ecrstary of Defense that the upon the determination by or nece Property herein Bsary £or military, oonveyed is useful ' air or naval of national defense p�PoBas the United States or the Merest r charge, exoept as shall have . use t �isated below, to ra_° right' without f cede he same or aRY Part thereof, including enter upon the Property and f b9 the pa uding any end all ! Party' of the "'Ond improvements lunation of Pert for a period net 1 such state to exceed the ad u .f war or national e upon ..cacti. �rgBnay, plus s n of auah use, such months, arty of the second part Property shall rl3vartto Party together the with•a� and all -improvements i °pPur''tenaneea appertain J ice thereto thereon i aer'vations, restri'a ' subject t JJJ tions and a o �• axoeptions, r at the" United S otlt�ne of this aonvayanoe 1 States shall be responsible dun f PRCVIDM), RCG1EM :bIg the period of such use for 7 0 -- '—'Perrly BO Used, .mod --" r:",�`;`N'..',';' - Wr.X. rental fOl the us and �BhQll, which have been I e of any a _n Added thereto vith..", truc�tu"x or Other improvements IN WiTHESs t Federal aid. Vmmp, the United stiktaa Or America ha these Presents to be 8--c"Ied in its nfte by the 8,or.ta,, , the! I *'D'Partlunt. of the and the as&I of the dAJV of Ar'V to be ber,,nt, 1!�A. cad# thin SF" or 'm LXpL"mDC Tm 4mmOF . ............... . . . 04ft .S ........... . . STATE OF rtRCU.0 COtW= OF ARZnrM-0M for the state Of Virgir4 Notary ftil" in and that T. a d cot" Of Arlington, do hereby wtjr ooaye,ry Secretary of the JDapa of the a I Al"Y' Personally 4PP4w,d rItment, the due w6clutIon of the tb*70 andbefore me this day and a0kr1owl8deed ,1".Ip:L.g W'MM" 17 hand and official I foie I 2-2/67' Of � ?, "11"Z lop COMM1-13JDjj - 4 vi VICINTY MAP 1 xalc Ell WEARING 11119rA1II7g 5 52°36'11'w 359-75 _ N 69°14'S5'W 359.43 N 88'16'17'W 295.05 5 B9°45.44'W 5... N 61°00'14'W 479.76 0 N fi0°59'21'N 440.70 N 16°4B'93'X 177.66 N 096180270E 97.39 N 14.34'59'N 26B.7B N 156510650E 339.79 N SO°2B'33•W Ill92 S B5°35'98•N 500.13 N 11615139.11 260.52 N 00.24.58•E = f92.DB W OB•20'091E 190. 12 N 06°30'08'E 54.BB N 07-00'44 •E 462.18 N 07°06'23'W 301.02 N 19620639'X 81.03 N 25'02'59'W 414.59 N 45°23'49'W 65.313 N 44°24'10'W 29W.04 IN 9f°%'0B'N 405.01 N 6B°1B'16'M 401 N 01°09'32'E 40.186 N 03.58'19'E 145.68 N 21.22'23'E 600.80 N 04.450360E 252.00 N 12.31060.E 172.57 N OG'm'1W1•E 11W1. SW N 01•04.!0'W 1B$.15 N 04.57'49'E 11S.O3 N 03•S1'64'l 136.37 N 23.35'OB'W 145.93 N 56.03.13•x 1 16s.31 N &-%%'24'M 1 19l If 3C 03.48-M 342.90 N 28°46'44'N 147.22 N 33°i6'53'N 262.92 N 30°17'011•N 618.61 N 26'31.0B'N 257.71 N 25-14.13•W 901.13 N 376520f6'W 314.14 N 5B'54'2B•W S1B.40 N 81°47'54'W 365.79 N 02°20'11•E 601.26 N 43•17'32'E 226.44 S B7.22'fiB•E 362.47 S 84°33'30'E 310.83 6 21.WI1571E 213.59 5 07°01'23'E 23D.49 9 04.95'21'E 649-81 N 576060030E I 239.96 N 166480250E 362.20 N 41.40'21'f 143.55 W 49.530140E 442.2E N 43630'08'E 371_69 N 39522021.E 969.99 N 54°11'42'E 520.17 S B3°64.95-E 279.96 S 636690610E 207.87 S 74°57'12'E 392.04 5 51°29.34'E 226.20 S 226460196E 74,V S 67-17.21-W 461.94 5 57'39'26'N 395.61 S 21@48.1BRE 335.94 9 32°59'02'E 455.09 5 31°32'S1•E 357.61 6 300500148E 350.51 8 /i•Z2L49•r 127.13 S 0A 49'43'W 672.90 S 68•05'49eW .01.90 S 211°52.22•N 544.45 S S4°13'44'E 133.51 6 66°21'11'X 620.36 N 77656113'N 384.00 8 646030900E 543.00 N 676540350E Sol 8 676070540E i59.57 5 19646.008E 374.50 6 04°52050'E 299.96 6 40°31'14•E 292.14 0024•x S65 626• 9.fio 4.BB _ S 22626'fi7'N 187.08 f ON„p L 5n CONTROL 1Rou wF 9g N.R. CARRINSTOIL TINIOTQ ECN 2 O9. i64 PI1. f6f CM X/F N��c A6 09. 694 PG. f49 yF' N/F CHAMPION INTERNATIONAL MAN ����p� � N/F NANCY P. WAN9uM �' 1113?XAIFL J. ELLI6 N EL11 BOBBL. AND B. WRIM PB. 9B P6. S60 NO OEEO Rff R E tip! [n �'0•••' L LSBrnp�(SOtAYF n 0[ a°cc . ILi Ma" M ���� .ya i OPS B20p_B�! P/LL BBYBMEN 222' i16B9139.1q E41 CR x EY ] 00N f•208189G.69 9 ,MF °�W9 Jn1L'016 UPS 4 E [CN n ,AIW .UC093 A 9H q, r SP5 a i EUN Ui E '9 b [ .7p� �� a 9�fP5 A0NfR0t2I7 9 � WE ILEYR.7NE • y E � RAF HENRY1,1101131 3Bl P0T TRACT 1 ECN �9 wF R.T. GAWK D S NS NO [EEO NEPE m Elm V, G7P AREAS ErA E ECH 1 TRACT 1 = 4480.2437 ACRES 195159413 S _ F _ 1n e0" TRACT 1 A = 75.9453 ACRES Eck 3308175 S . F "b" ENCIMACNKHT IDOP EY NOTE: SS DAiv[ FINAL AREAS SUBJECT TO ROAD R/W'S IA1 IPS @k . y1 Z• N/F KEY=-988-02 E W LiaL T LGY * JNGS N. N9Nlm -� E Ff5 ' N/F NIF - RaFipRq C. CTf}ll TOWN OF BUTNE 09. 2f40 n. FS /F EG TO g ACA[5 OWill FROM NELN5 J4AH O. RO L.& TO BTATE OF XORTW CARN.INA O9. i149 Ps:. 1N f7e. 160 1b. 19 69 b. OA P4. 2� N/F 46bs 0 GUTNER >P< GRae. GAS -P . WE, /7 LAKE sP6 -.1a. FENCE ,p 1F6 1pV E I �J y x Ell TRACT 1 A N0L xEll pieP w. 66 n. 91 E l C.1 16A lop) = 9 CWdinEx IRON WF STATE OF NORTH CAROLINA WAKE COUNTY yp' 9A z g I�6! r0Bu0. a.LBLeie A9$ WAv� OR1YIxLT I. SEORGE SCOTT WILSON, 00 HEREBY CERTIFY CC IPA 14waAVA.Ni THAT UNDER MY SUPERVISION NAP WAS DRAWN ON FROM AN ACTUAL SURVEY BPW COMEIREL IRON MAC UNDER MY SUPERVISION, FROM y/yXIF-y !6, Oi y0, pA JA199 9. MILLRT6. JR. DE O aESCBE RdD�,� RETORTED IH GOOK NI 13AI1IiE AVJw•r PAGE Ned LTHATATE THE FFrWOR •S �=' Ip. Q1fa 1r:. TL9 OF CLOSURE ANDAS CALCULATES BY LAKE MIEN ESTATES LATITUDES BOUNDARY DEPARTURES IS 711 °.Mo �� $.$ pS, fe PG. fii THAT THE BOUNDARY LINES NOT FROM NFO A �J CLEARLY INDICATED REFERENC AS CITED; FROM INFORMATION FOUND IN REFERENCE CITED; THAT THIS NAP ASSANPRE ARENDEOEO IN ACCORDANCE WITH G.S. 47-9D I ecn WIT74ESS MY ORIGINAL 9IOMAIVRE.` REOISYRAT]DN loll SEAL TWIG DAY OF 2000. SIGNED:!` 'l L-2601 IPS i 3 .�P 0 ROBERTS CHAPEL, ROAD - SR 1123 P 4tr�Ro� Fmr 5 auA4 60' R/W d3 KExxE1x R. TRACT 4 BERM% M1 ` SEAL N/F [ 1 1f�l AN r4a k.C.9.0.T, iN0.41CT a.7Te15t ELTI 426M STATE OF MONTH CAROLINA 0 EGI GAS CONrROL IRON 0 A fE49.94 ^ S° o@., L.Tn.1m p V •6A'M 61 IF7M.Wf N, O Mil N/F 4, LTAIE OF NONTN CAROLINA [ A'10 EAST COBtIT. 1104_ CtlWiER S. DOSS IP3 W. f96 M. 299 I, SCOTT WILSON. PROFESSIONAL LAND SURVEYOR NO. L-2601 B EC11 GtI1 CERTIFY THAT THIS PLAT IS OF A SU VlOF AN EXISTING PARCEL fi 1 rP3 E])1 OR PARCELS OF LAND; �i LEGEND I En EIP = EXISTING IRON PIPE IPS ^ ' y STAN OF WORTH CAROLINA CPS CONT� IROfI ECM =EXISTING CONCRETE MONUMENT COT ILSDN, P.L.S. L-2801 jG 1. �Q S qas r1�L 1R(M €LA IPS = IRON PIPE SET NCM = NEW CONCRETE MONUMENT erATE GF CAROLINA Ev • Bi i MH PP - POWERLPDLE X ;GG 9 Stormwater Management Mapping Permitted Pre -Development Plan Permitted Post Development Plan Updated Post Development Plan 7 �I RANGE 4 SIGN/ YIELD N 7F I / 4 9 \ METAL POSTS O0 17 / \ SPRAYED CONCRETE BUILDINGS / Iv i 1 J SPRAYED CONCRETE BUILDINGS 1\` Ll 10 I � PRE —DEVELOPMENT ANALYSIS BASIN FLOW FLOWRATE POINT DRAINAGE TYPE NOTES 01 Q2 AREA (CFS) (CFS) (AC) A SUB -BASIN 'A' 3.80 TOTAL 4.48 6.71 ANALYSIS POINT 'A' Q POST < Q PRE B SUB -BASIN 'B' 1•24 TOTAL 1.14 1.83 ANALYSIS POINT 'B' Q POST < Q PRE SPRAYED CONCRETE BUILDINGS NOW OR F MERLY STATE OF ORTH CAROUNA 41* ' 4V*4P* �- v` 4V*4P* ` STORM WA TER SUMMARY (REFER TO CALCULATION BOOKLET FOR ADDITIONAL INFORMATION) i / ♦ ♦ �! \� y DRAINAGE AkE.\A TO ANALYSIS \ vv DRAWA-GE_ AREA TO ANALYSIS �� POINT 'B' = 1. 4—AC ICE of ♦�!�• \ ��� \ �� ��'\ \ \-_ POINT 'A' = 3.80 AC Q SPA4 10 �� A ��V �A*�1 10 IBOULDERS\� i -483-_ \ \\\V 7 \ \ \- 489 \ > \ \\ \ \\ J BI \ FIRING Y� \ RANGE 480— i \ \ \ \� _--STREET_SIGN �� A�� � 9 vv \V459 v _ — -- T� —--F`OHUTI—\\ ��---------OHP/OHUT --- — ---- _----------- -476- \ _—�-477 4�g� �� �_ A ��-- ___ — --- --- - — - ------ - -------------- ------ — ---- ------------- -- �118' --- — —--- y�--- — ------ _---------- ---- ----- — �� ---- ---- ----- -- — —� _ -- _ ---------' — '----------------- -- - INV_ 73.73--- -- ------ —� ----- ---- —_-- —_---- ------ ------ — — — - - ------------ - ------------------- -- - ----- -------------------------------_� -- - -- - -- - --- -----------------------------_--------------_�--- - II RANGE ROAD S.R. 1610 II 60' RIGHT OF WAY --------------- ----------------------------- 18" RCP II INV=472.2011 ANALYSIS POINT 'A' ANALYSIS POINT 'B' r---wh pmmmmmp 40 TOTAL SITE AREA = 714,000 SF (16.40 AC) PROJECT AREA = SITE AREA - SURFACE WATER AREA 705,913 SF (16.21 AC) _ _ _ _ DRAINAGE AREAS TO ANALYSIS POINTS PRE -DEVELOPMENT BUILT UPON AREA (BUA) _ 21, 356-SF (0.49 AC / 3% OF SITE) THIS DRAWING IS FOR NCDENR REVIEW. DO NOT USE FOR CONSTRUCTION GRAPHIC SCALE 0 20 40 80 160 ( IN FEET ) 1 inch = 40 ft. CLH DESIGN CLH Design, PA 400 Regency Forest Dr. Suite 120 Cary, NC 27518 Phone: 919.319.6716 Fax: 919.319.7516 LA: C-106, PE: C-159 MCA RO�i '. ?� ESS/ y'9 L 033612 ,S S; �NS���`• LLJ w U (D z z Q Q o O LLJ CIOm z Q U w O CL ::D U z O LLJJ Q Z z O UU O J O m H O z w Q z Q z J O Q z O z w LU Q U 0 z O z O U w Q ci z J U 2 O LU U J ° U Q LLJ O z w 0 _ Oz z o U) CL Ld z 0 N z o N O j c�a DRAWN BY. FJS CHECKED BY: KAL DATE: 8-21-2014 CLH PROD. NO: 14-121 S.C.O. ID#: 14-10860-01 A PRE -DEVELOPMENT STORMWATER MANAGEMENT MAP BID SET C�3m T 919 7818582 F 919 7813979 4600 Lake Boone Trail Suite 205 Raleigh, NC 27607 info@smithsinnett.com a� N O 2 a LO - N OD , U O +� x W 'w o co a co o zw Y"a0�� � U O a Z 7 .� 0 fO W 2co c"-0a) z U0_cUrnLO • o Z c E Z °O W ��•L��rn > z U oH tma) J E•• O '� C o U N M= m F-> .9 Z�QLnWaLL LU Z Z = J= C/) - V 0 mcoco\ C9 ^ tJ M co W -E O 0 Lu C O to 4J O N C, W n s O O c �.!E-U � - ¢ ('7 CD Zo � ¢ mo o D m � `� 0 X N C w 4- C O N •L--. VJ� -EP O Cn Q o (D Q "' ¢ 00 o� cn Q �_ Q o c t LU o .`n c o o c CO o i� (D � Q LU o_ Z -o .-- o m � Q O_ !EO Q O U ."' E � d D_ d Q O N E OU UJ 2 W m W `Z I` ■ QM W O 00 Q U _/ N C7 C) J Q Z Q p� E Z I Q co Z W QLU v Q c�a Z c Z W Z z - — J o 0 1,,— Q W V N � V Q O = N m Z O 0 LLJ m Z F-- cn Lo 2 9/23/22 NCDEQ STORM #2 ID DATE DESCRIPTION DRAWN BY: J L CHECKED BY: FS POST -DEVELOPMENT STORMWATER MANAGEMENT MAP 2021009 8 J U L 2022 I / / I / / / / / / / / / / / / / / co 00 a Z SCALE 1 "=100' 0 100, 200' I 1 I\V 1 —.Lr-, IW.-- 00 W.11 »ma \ / )r . � , •:-�. �i�:���•c w-air-�+•a��%c'�c;� � � • T!--- �I�••p�C••�!i•V-I��1i� wi . �: • � � 'tom JS''� = �I T 919 7818582 F 919 7813979 4600 Lake Boone Trail Suite 205 Raleigh, NC 27607 info@smithsinnett.com a� 0 N O 2 u LO L N OD i U O x W +� o m a o co > ( '� •� > w Z M n� ��(0 O a Z �.__ o�(0 W 2inw" 00ai ♦ z U�:,Ua)LO • o T Z c E Z °O W �.L-ern > z U o H tm J E•• O '2 C H > ZLnWaLL %%% Z = LU � �Q � co\ZMCQ— J= C/) _ - V C9 M M y CD C O to _� 4J N- N L--' �-- W LU LU CDN N -� (6 CV 4 2 U) to s O O c Q n- � 0- f- I'D `O Of >G o O N •L--. VJ� "' ¢ CDo� cn Q �_ Q o c t M o .`n c o o c co o i) Q LU o' Z -o a`) .-- a`) a) m Q D' L O Q O U �--' E F- d d Q O N E cS UJ 2 W F- m W Z H LL H Q m Q 00 Q (, LA N C7 U J Q Z Q p� E Z I Q co Z W QLU U Q c�a Z � Z W Z z - — o Q W V N � U Q O = N m Z O O Q W U M Z 0 F-- cn LA 2 9/23/22 NCDEQ STORM #2 ID DATE DESCRIPTION DRAWN BY: J L CHECKED BY: FS POST -DEVELOPMENT STORMWATER MANAGEMENT MAP 2021U L 2022 C3.3� Design Calculations Pre -Post Development Hydraulic Routing Wet Pond A Design SNAP Tool (for Nutrient Accounting) I Watershed Model Schematic HydraflowHydrographsExtension for Autodesk® Civil 3D®2019byAutodesk,Inc. v2019.2 1 2 8 9 10 Legend Hvd. Origin Description 1 SCS Runoff Post-Dev to BMP'A' 2 SCS Runoff Post-Dev to BMP'B' 3 Reservoir BMP'A' 4 Reservoir BMP'B' 5 SCS Runoff Post-Dev By -Pass to Analysis Point'A' 6 SCS Runoff Post-Dev By -Pass to Analysis Point'B' 7 SCS Runoff Pre-Dev to Analysis Point'A' 8 SCS Runoff Pre-Dev to Analysis Point'B' 9 Combine Post Development A Combined 10 Combine Post Development B Combined Project: 14-121-hyd Wetpond.gpw Wednesday, 09 / 21 / 2022 Hydraflow Table of Contents 14-121-hyd Wetpond.gpw Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Watershed Model Schematic...................................................................................... 1 Hydrograph Return Period Recap............................................................................. 2 - Year SummaryReport......................................................................................................................... 3 HydrographReports................................................................................................................... 4 Hydrograph No. 1, SCS Runoff, Post-Dev to BMP'A............................................................... 4 Hydrograph No. 2, SCS Runoff, Post-Dev to BMP'B'.............................................................. 5 Hydrograph No. 3, Reservoir, BMP'A'..................................................................................... 6 PondReport - BMP'A'......................................................................................................... 7 Hydrograph No. 4, Reservoir, BMP'B'..................................................................................... 8 PondReport - BMP'B'......................................................................................................... 9 Hydrograph No. 5, SCS Runoff, Post-Dev By -Pass to Analysis Point'A................................ 10 Hydrograph No. 6, SCS Runoff, Post-Dev By -Pass to Analysis Point'B................................ 11 Hydrograph No. 7, SCS Runoff, Pre-Dev to Analysis Point 'A' ............................................... 12 Hydrograph No. 8, SCS Runoff, Pre-Dev to Analysis Point 'B' ............................................... 13 Hydrograph No. 9, Combine, Post Development A Combined ............................................... 14 Hydrograph No. 10, Combine, Post Development B Combined ............................................ 15 2 - Year SummaryReport....................................................................................................................... 16 HydrographReports................................................................................................................. 17 Hydrograph No. 1, SCS Runoff, Post-Dev to BMP'A............................................................. 17 Hydrograph No. 2, SCS Runoff, Post-Dev to BMP'B'............................................................ 18 Hydrograph No. 3, Reservoir, BMP'A'................................................................................... 19 Hydrograph No. 4, Reservoir, BMP'B'................................................................................... 20 Hydrograph No. 5, SCS Runoff, Post-Dev By -Pass to Analysis Point'A................................ 21 Hydrograph No. 6, SCS Runoff, Post-Dev By -Pass to Analysis Point'B................................ 22 Hydrograph No. 7, SCS Runoff, Pre-Dev to Analysis Point 'A' ............................................... 23 Hydrograph No. 8, SCS Runoff, Pre-Dev to Analysis Point 'B' ............................................... 24 Hydrograph No. 9, Combine, Post Development A Combined ............................................... 25 Hydrograph No. 10, Combine, Post Development B Combined ............................................ 26 10 -Year SummaryReport....................................................................................................................... 27 HydrographReports................................................................................................................. 28 Hydrograph No. 1, SCS Runoff, Post-Dev to BMP'A............................................................. 28 Hydrograph No. 2, SCS Runoff, Post-Dev to BMP'B'............................................................ 29 Hydrograph No. 3, Reservoir, BMP'A'................................................................................... 30 Hydrograph No. 4, Reservoir, BMP'B'................................................................................... 31 Hydrograph No. 5, SCS Runoff, Post-Dev By -Pass to Analysis Point'A................................ 32 Hydrograph No. 6, SCS Runoff, Post-Dev By -Pass to Analysis Point'B................................ 33 Hydrograph No. 7, SCS Runoff, Pre-Dev to Analysis Point 'A' ............................................... 34 Hydrograph No. 8, SCS Runoff, Pre-Dev to Analysis Point 'B' ............................................... 35 Hydrograph No. 9, Combine, Post Development A Combined ............................................... 36 Hydrograph No. 10, Combine, Post Development B Combined ............................................ 37 100 -Year Contents continued... 14-121-hyd Wetpond.gpw SummaryReport....................................................................................................................... 38 HydrographReports................................................................................................................. 39 Hydrograph No. 1, SCS Runoff, Post-Dev to BMP'A............................................................. 39 Hydrograph No. 2, SCS Runoff, Post-Dev to BMP'B'............................................................ 40 Hydrograph No. 3, Reservoir, BMP'A'................................................................................... 41 Hydrograph No. 4, Reservoir, BMP'B'................................................................................... 42 Hydrograph No. 5, SCS Runoff, Post-Dev By -Pass to Analysis Point'A................................ 43 Hydrograph No. 6, SCS Runoff, Post-Dev By -Pass to Analysis Point'B................................ 44 Hydrograph No. 7, SCS Runoff, Pre-Dev to Analysis Point 'A' ............................................... 45 Hydrograph No. 8, SCS Runoff, Pre-Dev to Analysis Point'B................................................ 46 Hydrograph No. 9, Combine, Post Development A Combined ............................................... 47 Hydrograph No. 10, Combine, Post Development B Combined ............................................ 48 OFReport.................................................................................................................. 49 Hydrograph Return Period Recan 'F Hydra of-Hydrographs Extension for Autodesk@ Civil 3D@ 2019 by Autodesk, Inc. v2019.2 Hyd. Hydrograph Inflow Peak Outflow (cfs) Hydrograph No. type hyd(s) Description (origin) I -yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr 1 SCS Runoff ------ 8.341 10.99 ------- ------- 17.87 ------- ------- 28.47 Post-Dev to BMP'A' 2 SCS Runoff ------ 2.680 3.666 ------- ------- 6.299 ------- ------- 10.44 Post-Dev to BMP'B' 3 Reservoir 1 2.673 6.292 ------- ------- 11.77 ------- ------- 22.36 BMP'A' 4 Reservoir 2 0.039 0.236 ------- ------- 3.066 ------- ------- 8.784 BMP'B' 5 SCS Runoff ------ 2.779 3.888 ------- ------- 6.987 ------- ------- 11.97 Post-Dev By -Pass to Analysis Point' 6 SCS Runoff ------ 0.998 1.396 ------- ------- 2.508 ------- ------- 4.295 Post-Dev By -Pass to Analysis Point' 7 SCS Runoff ------ 4.484 6.710 ------- ------- 13.11 ------- ------- 23.95 Pre-Dev to Analysis Point'A' 8 SCS Runoff ------ 1.135 1.835 ------- ------- 3.902 ------- ------- 7.545 Pre-Dev to Analysis Point'B' 9 Combine 3, 5, 3.877 8.928 ------- ------- 18.67 ------- ------- 32.47 Post Development A Combined 10 Combine 4,6, 1.023 1.427 ------- ------- 4.567 ------- ------- 12.42 Post Development B Combined Proj. file: 14-121-hyd Wetpond.gpw Wednesday, 09 / 21 / 2022 Hydrograph Summary Report draflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cult) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 1 SCS Runoff 8.341 2 718 19,123 ------ ------ ------ Post-Dev to BMP'A' 2 SCS Runoff 2.680 2 718 6,139 ------ ------ ------ Post-Dev to BMP'B' 3 Reservoir 2.673 2 728 18,629 1 485.36 8,824 BMP'A' 4 Reservoir 0.039 2 1188 6,058 2 489.96 4,520 BMP'B' 5 SCS Runoff 2.779 2 720 6,365 ------ ------ ------ Post-Dev By -Pass to Analysis Point' 6 SCS Runoff 0.998 2 720 2,285 ------ ------ ------ Post-Dev By -Pass to Analysis Point' 7 SCS Runoff 4.484 2 722 12,112 ------ ------ ------ Pre-Dev to Analysis Point 'A' 8 SCS Runoff 1.135 2 720 2,799 ------ ------ ------ Pre-Dev to Analysis Point 'B' 9 Combine 3.877 2 726 24,994 3, 5, ------ ------ Post Development A Combined 10 Combine 1.023 2 720 8,343 4, 6, ------ ------ Post Development B Combined 14-121-hyd Wetpond.gpw Return Period: 1 Year Wednesday, 09 / 21 / 2022 4 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 1 Post-Dev to BMP 'A' Hydrograph type = SCS Runoff Peak discharge = 8.341 cfs Storm frequency = 1 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 19,123 cuft Drainage area = 3.310 ac Curve number = 87* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 2.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(1.820 x 98) + (1.490 x 74)] / 3.310 Post-Dev to BMP 'A' Q (cfs) Hyd. No. 1 -- 1 Year Q (cfs) 10.00 10.00 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 0.00 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Hyd No. 1 Time (hrs) Hydrograph Report 5 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 2 Post-Dev to BMP 'B' Hydrograph type = SCS Runoff Peak discharge = 2.680 cfs Storm frequency = 1 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 6,139 cuft Drainage area = 1.290 ac Curve number = 83* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 2.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(0.240 x 98) + (1.050 x 80)] / 1.290 Post-Dev to BMP 'B' Q (cfs) Hyd. No. 2 -- 1 Year Q (cfs) 3.00 3.00 2.00 2.00 1.00 1.00 0.00 0 2 4 6 8 10 — Hyd No. 2 12 14 16 18 20 0.00 22 24 26 Time (hrs) I Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 3 BMP 'A' Hydrograph type = Reservoir Peak discharge = 2.673 cfs Storm frequency = 1 yrs Time to peak = 12.13 hrs Time interval = 2 min Hyd. volume = 18,629 cuft Inflow hyd. No. = 1 - Post-Dev to BMP'A' Max. Elevation = 485.36 ft Reservoir name = BMP 'A' Max. Storage = 8,824 cuft Storage Indication method used Q (cfs) 10.00 . 11 4.00 2.00 BMP 'A' Hyd. No. 3 -- 1 Year 6 12 18 24 30 36 42 48 54 Hyd No. 3 Hyd No. 1 Total storage used = 8,824 cuft Q (cfs) 10.00 NIM 4.00 2.00 0.00 60 Time (hrs) Pop d°N o. 1 - B M P 'A' Hydraflow Hydrographs Extension for Autodesk® Civil 3D@ 2019 by Autodesk, Inc. v2019.2 Top of pond Elev. 487.00 3.00 2.00 1.00 L 0.00 Stage (ft) 2-yr 1-yr Inflow hydrograph = 1. SCS Runoff - Post-Dev to BMP 'A' Project: 14-121-hyd Wetpond.gpw I Tuesday, 09 / 13 / 2022 1 Pond Report 7 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Pond No. 1 - BMP'A' Pond Data Contours -User-defined contour areas. Conic method used for volume calculation. Begining Elevation = 484.00 ft Stage / Storage Table Stage (ft) Elevation (ft) Contour area (sgft) Incr. Storage (cult) Total storage (cult) 0.00 484.00 5,523 0 0 0.50 484.50 6,358 2,968 2,968 1.00 485.00 6,767 3,280 6,248 2.00 486.00 7,717 7,236 13,484 3.00 487.00 8,694 8,200 21,684 Culvert / Orifice Structures Weir Structures [A] [B] [C] [PrfRsr] [A] [B] [C] [D] Rise (in) = 15.00 1.25 Inactive Inactive Crest Len (ft) = 6.00 Inactive 10.00 Inactive Span (in) = 15.00 1.25 0.00 0.00 Crest El. (ft) = 485.10 483.50 486.00 0.00 No. Barrels = 1 1 0 0 Weir Coeff. = 3.33 3.33 2.60 3.33 Invert El. (ft) = 480.00 484.00 0.00 0.00 Weir Type = 1 Rect Broad --- Length (ft) = 118.00 0.67 0.00 0.00 Multi -Stage = Yes Yes No No Slope (%) = 2.50 0.00 0.00 n/a N-Value = .013 .013 .013 n/a Orifice Coeff. = 0.60 0.60 0.60 0.60 Exfil.(in/hr) = 0.000 (by Contour) Multi -Stage = n/a Yes No No TW Elev. (ft) = 0.00 Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s). Stage / Storage / Discharge Table Stage Storage Elevation Clv A Clv B Clv C PrfRsr Wr A Wr B Wr C Wr D Exfil User Total ft cuft ft cfs cfs cfs cfs cfs cfs cfs cfs cfs cfs cfs 0.00 0 484.00 0.00 0.00 --- --- 0.00 0.00 0.00 --- --- --- 0.000 0.50 2,968 484.50 10.85 is 0.03 is --- --- 0.00 0.00 0.00 --- --- --- 0.027 1.00 6,248 485.00 10.85 is 0.04 is --- --- 0.00 0.00 0.00 --- --- --- 0.040 2.00 13,484 486.00 11.71 is 0.05 is --- --- 11.48 is 0.00 0.00 --- --- --- 11.53 3.00 21,684 487.00 14.11 oc 0.01 is --- --- 14.10 s 0.00 26.00 --- --- --- 40.11 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Hyd. No. 4 BMP 'B' Hydrograph type = Reservoir Peak discharge Storm frequency = 1 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyd. No. = 2 - Post-Dev to BMP'B' Max. Elevation Reservoir name = BMP 'B' Max. Storage Storage Indication method used. Q (cfs) 3.00 2.00 1.00 BMP 'B' Hyd. No. 4 -- 1 Year Wednesday, 09 / 21 / 2022 = 0.039 cfs = 19.80 hrs = 6,058 cuft = 489.96 ft = 4,520 cuft 10 20 30 40 50 60 70 80 90 Hyd No. 4 Hyd No. 2 Total storage used = 4,520 cuft Q (cfs) 3.00 2.00 1.00 1 0.00 100 Time (hrs) POF d"N o. 3 - B M P , B, Hydraflow Hydrographs Extension for Autodesk® Civil 3D@ 2019 by Autodesk, Inc. v2019.2 Top of pond EIev.492.00 3.00 ►41I11 1.00 L 0.00 Stage (ft) 2-yr 1-yr Inflow hydrograph = 2. SCS Runoff - Post-Dev to BMP 'B' Project: 14-121-hyd Wetpond.gpw I Tuesday, 09 / 13 / 2022 1 Pond Report 0 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Pond No. 3 - BMP'B' Pond Data Contours -User-defined contour areas. Conic method used for volume calculation. Begining Elevation = 489.00 ft Stage / Storage Table Stage (ft) Elevation (ft) Contour area (sgft) Incr. Storage (cult) Total storage (cult) 0.00 489.00 3,874 0 0 1.00 490.00 5,554 4,688 4,688 2.00 491.00 6,418 5,980 10,669 3.00 492.00 7,340 6,873 17,542 Culvert / Orifice Structures Weir Structures [A] [B] [C] [PrfRsr] [A] [B] [C] [D] Rise (in) = 15.00 1.25 Inactive Inactive Crest Len (ft) = 6.00 Inactive 10.00 Inactive Span (in) = 15.00 1.25 0.00 0.00 Crest El. (ft) = 490.00 490.50 490.50 0.00 No. Barrels = 1 1 0 0 Weir Coeff. = 3.33 3.33 2.60 3.33 Invert El. (ft) = 486.00 489.00 0.00 0.00 Weir Type = 1 Rect Broad --- Length (ft) = 102.00 0.67 0.00 0.00 Multi -Stage = Yes Yes No No Slope (%) = 5.30 0.00 0.00 n/a N-Value = .013 .013 .013 n/a Orifice Coeff. = 0.60 0.60 0.60 0.60 Exfil.(in/hr) = 0.000 (by Contour) Multi -Stage = n/a Yes No No TW Elev. (ft) = 0.00 Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s). Stage / Storage / Discharge Table Stage Storage Elevation Clv A Clv B Clv C PrfRsr Wr A Wr B Wr C Wr D Exfil User Total ft cuft ft cfs cfs cfs cfs cfs cfs cfs cfs cfs cfs cfs 0.00 0 489.00 0.00 0.00 --- --- 0.00 0.00 0.00 --- --- --- 0.000 1.00 4,688 490.00 9.11 is 0.04 is --- --- 0.00 0.00 0.00 --- --- --- 0.040 2.00 10,669 491.00 12.09 is 0.02 is --- --- 12.07 s 0.00 9.19 --- --- --- 21.28 3.00 17,542 492.00 13.65 is 0.01 is --- --- 13.64 s 0.00 47.77 --- --- --- 61.41 Hydrograph Report 10 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 5 Post-Dev By -Pass to Analysis Point'A' Hydrograph type = SCS Runoff Peak discharge = 2.779 cfs Storm frequency = 1 yrs Time to peak = 12.00 hrs Time interval = 2 min Hyd. volume = 6,365 cuft Drainage area = 1.560 ac Curve number = 80 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 9.00 min Total precip. = 2.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) Post-Dev By -Pass to Analysis Point 'A' Hyd. No. 5 -- 1 Year Q (cfs) 3.00 3.00 2.00 2.00 1.00 1.00 0.00 0 2 4 6 8 10 12 14 16 18 20 — Hyd No. 5 0.00 22 24 26 Time (hrs) Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 6 Post-Dev By -Pass to Analysis Point'B' Hydrograph type = SCS Runoff Peak discharge = 0.998 cfs Storm frequency = 1 yrs Time to peak = 12.00 hrs Time interval = 2 min Hyd. volume = 2,285 cuft Drainage area = 0.560 ac Curve number = 80 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 2.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) 1.00 0.90 0.80 0.70 0.60 0.50 0.40 0.30 0.20 0.10 0 00 Post-Dev By -Pass to Analysis Point 'B' Hyd. No. 6 -- 1 Year Q (cfs) 1.00 0.90 0.80 0.70 0.60 0.50 0.40 0.30 0.20 0.10 0 00 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Hyd No. 6 Time (hrs) 12 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 7 Pre-Dev to Analysis Point'A' Hydrograph type = SCS Runoff Peak discharge = 4.484 cfs Storm frequency = 1 yrs Time to peak = 12.03 hrs Time interval = 2 min Hyd. volume = 12,112 cuft Drainage area = 3.800 ac Curve number = 75 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 11.00 min Total precip. = 2.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) 5.00 4.00 3.00 2.00 1.00 0.00 0 2 4 — Hyd No. 7 6 8 Pre-Dev to Analysis Point 'A' Hyd. No. 7 -- 1 Year Q (cfs) 5.00 4.00 3.00 2.00 1.00 0.00 10 12 14 16 18 20 22 24 26 Time (hrs) Hydrograph Report 13 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Hyd. No. 8 Pre-Dev to Analysis Point'B' Hydrograph type = SCS Runoff Peak discharge Storm frequency = 1 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 1.240 ac Curve number Basin Slope = 0.0 % Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 2.83 in Distribution Storm duration = 24 hrs Shape factor Q (cfs) 2.00 1.00 2 4 Hyd No. 8 Pre-Dev to Analysis Point 'B' Hyd. No. 8 -- 1 Year Wednesday, 09 / 21 / 2022 = 1.135 cfs = 12.00 hrs = 2,799 cuft = 70 = 0 ft = 7.00 min = Type II = 484 6 8 10 12 14 16 18 20 22 24 Q (cfs) 2.00 1.00 -1-- 0.00 26 Time (hrs) Hydrograph Report 14 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 9 Post Development A Combined Hydrograph type = Combine Peak discharge = 3.877 cfs Storm frequency = 1 yrs Time to peak = 12.10 hrs Time interval = 2 min Hyd. volume = 24,994 cuft Inflow hyds. = 3, 5 Contrib. drain. area = 1.560 ac Q (cfs) 4.00 3.00 2.00 1.00 Post Development A Combined Hyd. No. 9 -- 1 Year 0.00 ' T 0 4 8 12 16 20 — Hyd No. 9 Hyd No. 3 Hyd No. 5 24 28 Q (cfs) 4.00 3.00 2.00 1.00 =;;- 0.00 32 Time (hrs) Hydrograph Report 1s Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 10 Post Development B Combined Hydrograph type = Combine Peak discharge = 1.023 cfs Storm frequency = 1 yrs Time to peak = 12.00 hrs Time interval = 2 min Hyd. volume = 8,343 cuft Inflow hyds. = 4, 6 Contrib. drain. area = 0.560 ac Q (Cfs) 2.00 1.00 WOTAN 0 6 12 Hyd No. 10 Post Development B Combined Hyd. No. 10 -- 1 Year 18 24 30 Hyd No. 4 36 42 48 Hyd No. 6 Q (Cfs) 2.00 1.00 0.00 54 60 66 72 Time (hrs) 16 Hydrograph Summary Report draflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cult) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 1 SCS Runoff 10.99 2 718 25,360 ------ ------ ------ Post-Dev to BMP'A' 2 SCS Runoff 3.666 2 718 8,389 ------ ------ ------ Post-Dev to BMP'B' 3 Reservoir 6.292 2 724 24,864 1 485.57 10,293 BMP'A' 4 Reservoir 0.236 2 778 8,299 2 490.03 4,873 BMP'B' 5 SCS Runoff 3.888 2 720 8,908 ------ ------ ------ Post-Dev By -Pass to Analysis Point' 6 SCS Runoff 1.396 2 720 3,198 ------ ------ ------ Post-Dev By -Pass to Analysis Point' 7 SCS Runoff 6.710 2 722 17,717 ------ ------ ------ Pre-Dev to Analysis Point 'A' 8 SCS Runoff 1.835 2 720 4,317 ------ ------ ------ Pre-Dev to Analysis Point 'B' 9 Combine 8.928 2 724 33,772 3, 5, ------ ------ Post Development A Combined 10 Combine 1.427 2 720 11,497 4, 6, ------ ------ Post Development B Combined 14-121-hyd Wetpond.gpw Return Period: 2 Year Wednesday, 09 / 21 / 2022 17 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 1 Post-Dev to BMP 'A' Hydrograph type = SCS Runoff Peak discharge = 10.99 cfs Storm frequency = 2 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 25,360 cuft Drainage area = 3.310 ac Curve number = 87* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 3.42 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(1.820 x 98) + (1.490 x 74)] / 3.310 Post-Dev to BMP 'A' Q (cfs) Hyd. No. 1 -- 2 Year Q (cfs) 12.00 12.00 10.00 10.00 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 0.00 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Hyd No. 1 Time (hrs) 18 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 2 Post-Dev to BMP 'B' Hydrograph type = SCS Runoff Peak discharge = 3.666 cfs Storm frequency = 2 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 8,389 cuft Drainage area = 1.290 ac Curve number = 83* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 3.42 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) = [(0.240 x 98) + (1.050 x 80)] / 1.290 Q (cfs) 4.00 3.00 2.00 1.00 0.00 0 2 4 — Hyd No. 2 Post-Dev to BMP 'B' Hyd. No. 2 -- 2 Year 6 8 10 12 14 16 Q (cfs) 4.00 3.00 2.00 1.00 0.00 18 20 22 24 26 Time (hrs) 19 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 3 BMP 'A' Hydrograph type = Reservoir Peak discharge = 6.292 cfs Storm frequency = 2 yrs Time to peak = 12.07 hrs Time interval = 2 min Hyd. volume = 24,864 cuft Inflow hyd. No. = 1 - Post-Dev to BMP'A' Max. Elevation = 485.57 ft Reservoir name = BMP 'A' Max. Storage = 10,293 cuft Storage Indication method used BMP 'A' Q (cfs) Hyd. No. 3 -- 2 Year Q (cfs) 12.00 12.00 10.00 10.00 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 0.00 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Time (hrs) Hyd No. 3 — Hyd No. 1 Total storage used = 10,293 cult Hydrograph Report 20 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Hyd. No. 4 BMP 'B' Hydrograph type = Reservoir Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyd. No. = 2 - Post-Dev to BMP'B' Max. Elevation Reservoir name = BMP 'B' Max. Storage Storage Indication method used. Q (cfs) 4.00 3.00 2.00 1.00 0.00 0 10 — Hyd No. 4 BMP 'B' Hyd. No. 4 -- 2 Year Wednesday, 09 / 21 / 2022 = 0.236 cfs = 12.97 hrs = 8,299 cuft = 490.03 ft = 4,873 cuft 20 30 40 50 60 70 80 90 Hyd No. 2 Total storage used = 4,873 cuft Q (cfs) 4.00 3.00 2.00 1.00 1 0.00 100 Time (hrs) 21 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 5 Post-Dev By -Pass to Analysis Point'A' Hydrograph type = SCS Runoff Peak discharge = 3.888 cfs Storm frequency = 2 yrs Time to peak = 12.00 hrs Time interval = 2 min Hyd. volume = 8,908 cuft Drainage area = 1.560 ac Curve number = 80 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 9.00 min Total precip. = 3.42 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) 4.00 3.00 2.00 1.00 0.00 0 2 4 — Hyd No. 5 Post-Dev By -Pass to Analysis Point 'A' Hyd. No. 5 -- 2 Year 6 8 10 12 14 16 Q (cfs) 4.00 3.00 2.00 1.00 0.00 18 20 22 24 26 Time (hrs) Hydrograph Report 22 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Hyd. No. 6 Post-Dev By -Pass to Analysis Point'B' Hydrograph type = SCS Runoff Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 0.560 ac Curve number Basin Slope = 0.0 % Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 3.42 in Distribution Storm duration = 24 hrs Shape factor Q (cfs) 2.00 1.00 2 4 Hyd No. 6 Post-Dev By -Pass to Analysis Point 'B' Hyd. No. 6 -- 2 Year Wednesday, 09 / 21 / 2022 = 1.396 cfs = 12.00 hrs = 3,198 cuft = 80 = 0 ft = 8.00 min = Type II = 484 6 8 10 12 14 16 18 20 22 24 Q (cfs) 2.00 1.00 -1-- 0.00 26 Time (hrs) 23 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 7 Pre-Dev to Analysis Point'A' Hydrograph type = SCS Runoff Peak discharge = 6.710 cfs Storm frequency = 2 yrs Time to peak = 12.03 hrs Time interval = 2 min Hyd. volume = 17,717 cuft Drainage area = 3.800 ac Curve number = 75 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 11.00 min Total precip. = 3.42 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) 7.00 5.00 i 3.00 2.00 1.00 0.00 0 2 4 — Hyd No. 7 Pre-Dev to Analysis Point 'A' Hyd. No. 7 -- 2 Year Q (cfs) 7.00 5.00 4.00 3.00 2.00 1.00 0.00 8 10 12 14 16 18 20 22 24 26 Time (hrs) Hydrograph Report 24 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Hyd. No. 8 Pre-Dev to Analysis Point'B' Hydrograph type = SCS Runoff Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 1.240 ac Curve number Basin Slope = 0.0 % Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 3.42 in Distribution Storm duration = 24 hrs Shape factor Q (cfs) 2.00 1.00 2 4 Hyd No. 8 Pre-Dev to Analysis Point 'B' Hyd. No. 8 -- 2 Year Wednesday, 09 / 21 / 2022 = 1.835 cfs = 12.00 hrs = 4,317 cuft = 70 = 0 ft = 7.00 min = Type II = 484 6 8 10 12 14 16 18 20 22 24 Q (cfs) 2.00 1.00 -1-- 0.00 26 Time (hrs) Hydrograph Report 25 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 9 Post Development A Combined Hydrograph type = Combine Peak discharge = 8.928 cfs Storm frequency = 2 yrs Time to peak = 12.07 hrs Time interval = 2 min Hyd. volume = 33,772 cuft Inflow hyds. = 3, 5 Contrib. drain. area = 1.560 ac Post Development A Combined Q (cfs) Hyd. No. 9 -- 2 Year Q (cfs) 10.00 10.00 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 0.00 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Time (hrs) Hyd No. 9 — Hyd No. 3 Hyd No. 5 Hydrograph Report 26 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 10 Post Development B Combined Hydrograph type = Combine Peak discharge = 1.427 cfs Storm frequency = 2 yrs Time to peak = 12.00 hrs Time interval = 2 min Hyd. volume = 11,497 cuft Inflow hyds. = 4, 6 Contrib. drain. area = 0.560 ac Q (Cfs) 2.00 1.00 Post Development B Combined Hyd. No. 10 -- 2 Year 6 12 18 24 30 36 42 48 54 60 Hyd No. 10 Hyd No. 4 Hyd No. 6 Q (Cfs) 2.00 1.00 0.00 66 Time (hrs) 27 Hydrograph Summary Report draflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cult) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 1 SCS Runoff 17.87 2 718 42,071 ------ ------ ------ Post-Dev to BMP'A' 2 SCS Runoff 6.299 2 718 14,567 ------ ------ ------ Post-Dev to BMP'B' 3 Reservoir 11.77 2 724 41,571 1 486.02 13,623 BMP'A' 4 Reservoir 3.066 2 726 14,476 2 490.28 6,377 BMP'B' 5 SCS Runoff 6.987 2 718 16,036 ------ ------ ------ Post-Dev By -Pass to Analysis Point' 6 SCS Runoff 2.508 2 718 5,757 ------ ------ ------ Post-Dev By -Pass to Analysis Point' 7 SCS Runoff 13.11 2 720 34,035 ------ ------ ------ Pre-Dev to Analysis Point 'A' 8 SCS Runoff 3.902 2 720 8,933 ------ ------ ------ Pre-Dev to Analysis Point 'B' 9 Combine 18.67 2 718 57,607 3, 5, ------ ------ Post Development A Combined 10 Combine 4.567 2 724 20,233 4, 6, ------ ------ Post Development B Combined 14-121-hyd Wetpond.gpw Return Period: 10 Year Wednesday, 09 / 21 / 2022 28 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 1 Post-Dev to BMP 'A' Hydrograph type = SCS Runoff Peak discharge = 17.87 cfs Storm frequency = 10 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 42,071 cuft Drainage area = 3.310 ac Curve number = 87* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 4.93 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(1.820 x 98) + (1.490 x 74)] / 3.310 Post-Dev to BMP 'A' Q (cfs) Hyd. No. 1 -- 10 Year Q (cfs) 18.00 18.00 15.00 15.00 12.00 12.00 9.00 9.00 6.00 6.00 3.00 3.00 0.00 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 Hyd No. 1 Time (hrs) 29 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 2 Post-Dev to BMP 'B' Hydrograph type = SCS Runoff Peak discharge = 6.299 cfs Storm frequency = 10 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 14,567 cuft Drainage area = 1.290 ac Curve number = 83* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 4.93 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) = [(0.240 x 98) + (1.050 x 80)] / 1.290 Q (cfs) 7.00 5.00 i 3.00 2.00 1.00 0.00 0 2 4 — Hyd No. 2 Post-Dev to BMP 'B' Hyd. No. 2 -- 10 Year Q (cfs) 7.00 5.00 4.00 3.00 2.00 1.00 ♦� 0.00 8 10 12 14 16 18 20 22 24 26 Time (hrs) 30 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 3 BMP 'A' Hydrograph type = Reservoir Peak discharge = 11.77 cfs Storm frequency = 10 yrs Time to peak = 12.07 hrs Time interval = 2 min Hyd. volume = 41,571 cuft Inflow hyd. No. = 1 - Post-Dev to BMP'A' Max. Elevation = 486.02 ft Reservoir name = BMP 'A' Max. Storage = 13,623 cuft Storage Indication method used Q (cfs) 18.00 15.00 12.00 9.00 6.00 3.00 0.00 - 0 2 4 6 Hyd No. 3 BMP 'A' Hyd. No. 3 -- 10 Year Q (cfs) 18.00 15.00 12.00 3.00 T- T 0.00 8 10 12 14 16 18 20 22 24 26 Time (hrs) Hyd No. 1 Total storage used = 13,623 cult 31 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 4 BMP 'B' Hydrograph type = Reservoir Peak discharge = 3.066 cfs Storm frequency = 10 yrs Time to peak = 12.10 hrs Time interval = 2 min Hyd. volume = 14,476 cuft Inflow hyd. No. = 2 - Post-Dev to BMP'B' Max. Elevation = 490.28 ft Reservoir name = BMP 'B' Max. Storage = 6,377 cuft Storage Indication method used Q (cfs) 7.00 5.00 i 3.00 2.00 1.00 0.00 0 4 — Hyd No. 4 8 BMP 'B' Hyd. No. 4 -- 10 Year Q (cfs) 7.00 5.00 4.00 3.00 2.00 1.00 0.00 12 16 20 24 28 32 36 40 Time (hrs) Hyd No. 2 Total storage used = 6,377 cuft 32 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 5 Post-Dev By -Pass to Analysis Point'A' Hydrograph type = SCS Runoff Peak discharge = 6.987 cfs Storm frequency = 10 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 16,036 cuft Drainage area = 1.560 ac Curve number = 80 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 9.00 min Total precip. = 4.93 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) 7.00 5.00 i 3.00 2.00 1.00 0.00 0 2 4 — Hyd No. 5 Post-Dev By -Pass to Analysis Point 'A' Hyd. No. 5 -- 10 Year Q (cfs) 7.00 5.00 4.00 3.00 2.00 1.00 0.00 8 10 12 14 16 18 20 22 24 26 Time (hrs) Hydrograph Report 33 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 6 Post-Dev By -Pass to Analysis Point'B' Hydrograph type = SCS Runoff Peak discharge = 2.508 cfs Storm frequency = 10 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 5,757 cuft Drainage area = 0.560 ac Curve number = 80 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 4.93 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) Post-Dev By -Pass to Analysis Point 'B' Hyd. No. 6 -- 10 Year Q (cfs) 3.00 3.00 2.00 2.00 1.00 1.00 0.00 0 2 4 6 8 10 12 14 16 18 20 — Hyd No. 6 0.00 22 24 26 Time (hrs) 34 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 7 Pre-Dev to Analysis Point'A' Hydrograph type = SCS Runoff Peak discharge = 13.11 cfs Storm frequency = 10 yrs Time to peak = 12.00 hrs Time interval = 2 min Hyd. volume = 34,035 cuft Drainage area = 3.800 ac Curve number = 75 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 11.00 min Total precip. = 4.93 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Pre-Dev to Analysis Point 'A' Q (cfs) Hyd. No. 7 -- 10 Year Q (cfs) 14.00 14.00 12.00 12.00 10.00 10.00 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 0.00 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Hyd No. 7 Time (hrs) 35 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 8 Pre-Dev to Analysis Point'B' Hydrograph type = SCS Runoff Peak discharge = 3.902 cfs Storm frequency = 10 yrs Time to peak = 12.00 hrs Time interval = 2 min Hyd. volume = 8,933 cuft Drainage area = 1.240 ac Curve number = 70 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 7.00 min Total precip. = 4.93 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) 4.00 3.00 2.00 1.00 0.00 0 2 4 — Hyd No. 8 Pre-Dev to Analysis Point 'B' Hyd. No. 8 -- 10 Year 6 8 10 12 14 16 Q (cfs) 4.00 3.00 2.00 1.00 0.00 18 20 22 24 26 Time (hrs) Hydrograph Report 36 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 9 Post Development A Combined Hydrograph type = Combine Peak discharge = 18.67 cfs Storm frequency = 10 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 57,607 cuft Inflow hyds. = 3, 5 Contrib. drain. area = 1.560 ac Q (cfs) 21.00 18.00 15.00 12.00 . II 3.00 0.00 0 2 4 — Hyd No. 9 Post Development A Combined Hyd. No. 9 -- 10 Year Q (cfs) 21.00 18.00 15.00 12.00 3.00 0.00 6 8 10 12 14 16 18 20 22 24 26 Time (hrs) Hyd No. 3 Hyd No. 5 Hydrograph Report 37 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 10 Post Development B Combined Hydrograph type = Combine Peak discharge = 4.567 cfs Storm frequency = 10 yrs Time to peak = 12.07 hrs Time interval = 2 min Hyd. volume = 20,233 cuft Inflow hyds. = 4, 6 Contrib. drain. area = 0.560 ac Post Development B Combined Q (cfs) Hyd. No. 10 -- 10 Year Q (cfs) 5.00 5.00 4.00 4.00 3.00 3.00 2.00 2.00 1.00 1.00 0.00 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Time (hrs) — Hyd No. 10 Hyd No. 4 Hyd No. 6 38 Hydrograph Summary Report draflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cult) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 1 SCS Runoff 28.47 2 718 68,859 ------ ------ ------ Post-Dev to BMP'A' 2 SCS Runoff 10.44 2 718 24,695 ------ ------ ------ Post-Dev to BMP'B' 3 Reservoir 22.36 2 722 68,356 1 486.49 17,437 BMP'A' 4 Reservoir 8.784 2 722 24,603 2 490.56 8,007 BMP'B' 5 SCS Runoff 11.97 2 718 27,946 ------ ------ ------ Post-Dev By -Pass to Analysis Point' 6 SCS Runoff 4.295 2 718 10,032 ------ ------ ------ Post-Dev By -Pass to Analysis Point' 7 SCS Runoff 23.95 2 720 62,296 ------ ------ ------ Pre-Dev to Analysis Point 'A' 8 SCS Runoff 7.545 2 718 17,265 ------ ------ ------ Pre-Dev to Analysis Point 'B' 9 Combine 32.47 2 720 96,302 3, 5, ------ ------ Post Development A Combined 10 Combine 12.42 2 720 34,635 4, 6, ------ ------ Post Development B Combined 14-121-hyd Wetpond.gpw Return Period: 100 Year Wednesday, 09 / 21 / 2022 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 1 Post-Dev to BMP 'A' Hydrograph type = SCS Runoff Peak discharge = 28.47 cfs Storm frequency = 100 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 68,859 cuft Drainage area = 3.310 ac Curve number = 87* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 7.26 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) = [(1.820 x 98) + (1.490 x 74)] / 3.310 Q (cfs) 30.00 25.00 15.00 10.00 5.00 0.00 0.0 2.0 4.0 - Hyd No. 1 6.0 8.0 Post-Dev to BMP 'A' Hyd. No. 1 -- 100 Year Q (cfs) 30.00 25.00 20.00 15.00 10.00 5.00 0.00 10.0 12.0 14.0 16.0 18.0 20.0 22.0 Time (hrs) 40 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 2 Post-Dev to BMP 'B' Hydrograph type = SCS Runoff Peak discharge = 10.44 cfs Storm frequency = 100 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 24,695 cuft Drainage area = 1.290 ac Curve number = 83* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 7.26 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) = [(0.240 x 98) + (1.050 x 80)] / 1.290 Q (cfs) 12.00 10.00 i 2.00 2 4 Hyd No. 2 6 8 Post-Dev to BMP 'B' Hyd. No. 2 -- 100 Year Q (cfs) 12.00 10.00 4.00 2.00 0.00 10 12 14 16 18 20 22 24 Time (hrs) 41 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 3 BMP 'A' Hydrograph type = Reservoir Peak discharge = 22.36 cfs Storm frequency = 100 yrs Time to peak = 12.03 hrs Time interval = 2 min Hyd. volume = 68,356 cuft Inflow hyd. No. = 1 - Post-Dev to BMP'A' Max. Elevation = 486.49 ft Reservoir name = BMP 'A' Max. Storage = 17,437 cuft Storage Indication method used Q (cfs) 30.00 25.00 15.00 10.00 5.00 0.00 0 2 4 — Hyd No. 3 BMP 'A' Hyd. No. 3 -- 100 Year 6 8 10 Hyd No. 1 12 Q (cfs) 30.00 25.00 20.00 15.00 10.00 5.00 0.00 14 16 18 20 22 24 26 Time (hrs) Total storage used = 17,437 cult 42 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 4 BMP 'B' Hydrograph type = Reservoir Peak discharge = 8.784 cfs Storm frequency = 100 yrs Time to peak = 12.03 hrs Time interval = 2 min Hyd. volume = 24,603 cuft Inflow hyd. No. = 2 - Post-Dev to BMP'B' Max. Elevation = 490.56 ft Reservoir name = BMP 'B' Max. Storage = 8,007 cuft Storage Indication method used BMP 'B' Q (cfs) Hyd. No. 4 -- 100 Year Q (cfs) 12.00 12.00 10.00 10.00 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 0.00 - -- - - 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Time (hrs) Hyd No. 4 Hyd No. 2 Total storage used = 8,007 cuft 43 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 5 Post-Dev By -Pass to Analysis Point'A' Hydrograph type = SCS Runoff Peak discharge = 11.97 cfs Storm frequency = 100 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 27,946 cuft Drainage area = 1.560 ac Curve number = 80 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 9.00 min Total precip. = 7.26 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Post-Dev By -Pass to Analysis Point 'A' Q (cfs) Hyd. No. 5 -- 100 Year Q (cfs) 12.00 12.00 10.00 10.00 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 0.00 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 Hyd No. 5 Time (hrs) 44 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 6 Post-Dev By -Pass to Analysis Point'B' Hydrograph type = SCS Runoff Peak discharge = 4.295 cfs Storm frequency = 100 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 10,032 cuft Drainage area = 0.560 ac Curve number = 80 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 8.00 min Total precip. = 7.26 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Post-Dev By -Pass to Analysis Point 'B' Q (cfs) Hyd. No. 6 -- 100 Year Q (cfs) 5.00 5.00 4.00 4.00 3.00 3.00 2.00 2.00 1.00 1.00 0.00 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 — Hyd No. 6 Time (hrs) Hydrograph Report 45 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 7 Pre-Dev to Analysis Point'A' Hydrograph type = SCS Runoff Peak discharge = 23.95 cfs Storm frequency = 100 yrs Time to peak = 12.00 hrs Time interval = 2 min Hyd. volume = 62,296 cuft Drainage area = 3.800 ac Curve number = 75 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 11.00 min Total precip. = 7.26 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) Pre-Dev to Hyd. No. Analysis Point 'A' 7 -- 100 Year Q (cfs) 24.00 24.00 20.00 20.00 16.00 16.00 12.00 12.00 8.00 8.00 4.00 4.00 0.00 0 2 4 6 8 10 12 — Hyd No. 7 14 16 18 20 0.00 22 24 26 Time (hrs) 46 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 8 Pre-Dev to Analysis Point'B' Hydrograph type = SCS Runoff Peak discharge = 7.545 cfs Storm frequency = 100 yrs Time to peak = 11.97 hrs Time interval = 2 min Hyd. volume = 17,265 cuft Drainage area = 1.240 ac Curve number = 70 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 7.00 min Total precip. = 7.26 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) 8.00 i 2.00 0.00 1 0 2 4 — Hyd No. 8 Pre-Dev to Analysis Point 'B' Hyd. No. 8 -- 100 Year 6 8 10 12 14 16 Q (cfs) 8.00 4.00 2.00 0.00 18 20 22 24 26 Time (hrs) Hydrograph Report 47 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 9 Post Development A Combined Hydrograph type = Combine Peak discharge = 32.47 cfs Storm frequency = 100 yrs Time to peak = 12.00 hrs Time interval = 2 min Hyd. volume = 96,302 cuft Inflow hyds. = 3, 5 Contrib. drain. area = 1.560 ac Q (cfs) 35.00 25.00 20.00 15.00 10.00 5.00 0.00 0 2 4 — Hyd No. 9 Post Development A Combined Hyd. No. 9 -- 100 Year Q (cfs) 35.00 30.00 25.00 20.00 15.00 10.00 5.00 0.00 6 8 10 12 14 16 18 20 22 24 26 Time (hrs) Hyd No. 3 Hyd No. 5 Hydrograph Report 48 Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Hyd. No. 10 Post Development B Combined Hydrograph type = Combine Peak discharge = 12.42 cfs Storm frequency = 100 yrs Time to peak = 12.00 hrs Time interval = 2 min Hyd. volume = 34,635 cuft Inflow hyds. = 4, 6 Contrib. drain. area = 0.560 ac Post Development B Combined Q (cfs) Hyd. No. 10 -- 100 Year Q (cfs) 14.00 14.00 12.00 12.00 10.00 10.00 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 0.00 L 0.00 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Time (hrs) Hyd No. 10 Hyd No. 4 Hyd No. 6 49 Hydraflow Rainfall Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 09 / 21 / 2022 Return Period Intensity -Duration -Frequency Equation Coefficients (FHA) (Yrs) B D E (N/A) 1 44.0806 13.2000 0.8773 -------- 2 74.0559 13.3000 0.8788 -------- 3 0.0000 0.0000 0.0000 -------- 5 70.2293 12.5000 0.8172 -------- 10 105.7041 16.8000 0.8710 -------- 25 118.9252 17.6000 0.8582 -------- 50 137.0265 18.6000 0.8630 -------- 100 157.1769 19.6000 0.8692 -------- File name: Franklin Co..IDF Intensity = B / (Tc + D)^E Return Period Intensity Values (in/hr) (Yrs) 5 min 10 15 20 25 30 35 40 45 50 55 60 1 3.46 2.79 2.36 2.04 1.80 1.62 1.47 1.35 1.25 1.16 1.09 1.02 2 5.76 4.65 3.92 3.40 3.01 2.70 2.45 2.25 2.08 1.93 1.81 1.70 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5 6.77 5.52 4.68 4.08 3.63 3.28 3.00 2.76 2.56 2.39 2.25 2.12 10 7.22 6.03 5.19 4.57 4.09 3.71 3.40 3.13 2.91 2.72 2.56 2.41 25 8.19 6.90 5.98 5.29 4.75 4.32 3.97 3.67 3.41 3.20 3.01 2.84 50 8.95 7.59 6.60 5.86 5.27 4.80 4.41 4.08 3.81 3.57 3.36 3.17 100 9.71 8.27 7.22 6.42 5.79 5.28 4.86 4.50 4.20 3.93 3.70 3.50 Tc = time in minutes. Values may exceed 60. Precip. file name: Sample.pcp Storm Rainfall Precipitation Table (in) Distribution 1-yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr SCS 24-hour 2.83 3.42 0.00 4.27 4.93 6.41 6.80 7.26 SCS 6-Hr 2.00 2.39 0.00 2.95 3.44 4.06 4.57 5.09 Huff -1st 0.00 1.55 0.00 2.75 4.00 5.38 6.50 8.00 Huff-2nd 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-3rd 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-4th 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-Indy 0.00 1.55 0.00 2.75 4.00 5.38 6.50 8.00 Custom 2.79 3.38 0.00 2.80 4.82 6.41 6.00 7.15 9/21/2022 .•• •% 'OJECT NAME PROJECT NO TIMMONS GROUP CNG CBTC ACFT 149652 1 ECATION tem, NC BY jJake Lewis Drainage Area, (DA) = 3.31 ac 11 Pre= 7.22 in/hr Impervious Area c= 0.95 1.82 ac CcPre= 0.52 Pervious Area c= 0.30 1.49 ac Q1 Pre= 12.41 cfs Cc = 0.66 11 Post= 7.22 in/hr CN= Q1 Post= 15.71 cfs Permanent Water Quality Pool % Impervious = 55.1 % Permanent Pool Design Depth = 3.00 ft SA / DA Ratio = 1.94 (from Tbl. 1.1) Required Surface Area = 2,797 sf Permanent Pool Volume Req.= 8,391 cf Temporary Water Quality Pool Design Storm Rainfall 1.00 in (Typically 1-in) Runoff Coeff. (Rv = 0.05 + 0.009 (% Imperv.)) = 0.55 in/in Required Volume (design rainfall)(Rv)(DA) = 6,548.05 cf Surface Area Provided: Permanent Pool Max. Depth = 6.00 ft Area of Pond Bottom (Above PSS) = 1,225 sf (EL= 479.5) Area Bottom of Shelf= 3,715 sf (EL= 484.0) Area of Permanent Pool= 4,213 sf (EL= 484.5) Area Top of Shelf= 5,159 sf (EL=485.0) Perm. Pool Volume Provided= 13,460 cf > 8,391 OK Avg. Perm. Pool Depth Provided (Eq. 3)= 3.19 ft > 3.00 OK Surface Area at 1" Storage Volume= 6,889 sf (EL= 1203.1) 1" Storage Volume Provided= 6,944 cf > 6,548 OK Temp. Storage Depth above Dewatering Hole = 1.10 ft Diameter of Dewatering Hole = 1.25 in Detention (Draw -Down) Time = 3.1 days (2-5 days Required) T days=(Temp. Storage Vol Req / (0.6 " A " (2"g"(h))11/2) " 86400 (where h = one third temp. storage depth measured to centroid of orifice) Max Drawdow Rate= 0.04 cfs Permanent Pool Volume= 13,460 cf > 8,391 OK Forebay Volume Required = 2,019 cf Forebay Volume Provided = 2,389 cf 17.8 % OK TahlP 1 1 SA / DA Ratios 85 % TSS efficiency Permanent Pool Depth (ft) Impervious 3.0 4.0 5.0 6.0 10 0.51 0.43 0.37 0.30 20 0.84 0.69 0.61 0.51 30 1.17 0.94 0.84 0.72 40 1.51 1.24 1.09 0.91 50 1.79 1.51 1.31 1.13 60 2.09 1.77 1.49 1.31 70 2.51 2.09 1.80 1.56 80 2.92 2.41 2.07 1.82 90 1 3.25 2.64 2.31 2.04 s'.\1319\0001\caIcs\PondSize-Wet Pond-piedmont-90 tss printed. 91211202210. 44 AM Page 1 of 2 Vega •• .. Main Pool Permanent Pool Volume Stage (ft) Elevation Area (sf) Storage (cf) -6.00 478.00 822 Top of Sed. Stor. in Main Pond -5.00 479.00 1,225 1,024 4.00 480.00 1,672 2,472 -3.00 481.00 2,156 4,386 -2.00 482.00 2,673 6,801 -1.00 483.00 3,216 9,745 -0.50 483.50 3,715 11,478 Inside of Shelf Elev. 0.00 484.00 4,213 13,460 Normal Pool Elev. 0.50 484.50 5,159 15,803 Outside of Shelf Elev. Forebay Volume Stage (ft) Elevation Area (sf) Storage (cf) -6.00 478.00 21 0 Top of Sed. Stor. in Forebay -5.00 479.00 99 60 -4.00 480.00 223 221 -3.00 481.00 357 511 -2.00 482.00 522 951 -1.00 483.00 713 1,568 0.00 484.00 929 2,389 Normal Pool Elev. Total Pond Stage / Storage Detail 0.00 484.0 5,523 0 Normal Pool Elev. 0.50 484.5 6,358 2970.25 1.00 485 6,797 6259 1.10 485.10 6,889 - 2.00 486 7717 10117.5 Water Quality Elevation 3.00 487 8694 18323 s:\1319\0001\ca1cs\PondSize-Wet Pond-piedmont-90 tss printed: 9/21/2022 10:44 AM Page 2 of 2 SUPPLEMENT-EZ COVER PAGE LOAD SUPPLEMENT FORMS PROJECT INFORMATION 1 Project Name ACFT 2 Project Area ac 16.21 3 Coastal Wetland Area ac 0 4 Surface Water Area ac 0.19 5 Is this proiect Hi h or Low Density? High 6 Does this project use an off -site SCM? No COMP[JANCEVATH 02H AD0.3(4) 7 Width of vegetated setbacks provided feet N/A 8 Will the vegetated setback remain ve etated? Yes 9 Is BUA other that as listed in .1 0034 c-d out of the setback? Yes 10 Is streambank stabilization proposed on this project? No NUMBER AND TYPE OF SCMs; 11 Infiltration System 0 12 Sioretention Cell 0 13 Wet Pond 2 14 Stormwater Wetland 0 15 Permeable Pavement 0 16 Sand Filter 0 17 Rainwater Harvesting RWH 0 18 Green Roof 0 19 Level.S reader-FRerStri LS-FS 0 20 Disconnected Impervious Surface (DIS) 0 21 Treatment Swale 0 22 Dry Pond 0 23 StormFilter 0 24 Silva Cell 0 25 §21jilter 0 26 Filterra 0 LOAD SUPPLEMENT FORMS DESIGNER CERTIFICATION 27 Name and Title: Frank Sfinsk P.E Senior Project Mana er 28 Organization: Timmons Group 29 Street address: _ City, State Zip: Phone numbers : Email: 5410 Trinity Road, Suite 102 30 Raleigh, NC, 27607 31 919 866-4505 32 frank.slinsky@timmons.com Certification Stafement I certify, under penalty of law that this Supplement-EZ form and all supporting information were prepared under my direction or supervision; that the information provided in the form is, to the best of my knowledge and belief, true, accurate, and complete; and that the engineering plans, specifications, operation and maintenance agreements and other supporting information are consistent with the information provided here. �`•�Z'� �CARIssa''•� (f ,ram _ :9L SEAL ter: 033612 Glox Signature of Designer Date q / -2—) I Zo 2 -t- DRAINAGE AREAS 1 Is this a high density project? Yes 2 If so, number of drainage areas/SCMs 2 3 Is all/part of this project subject to previous rule versions? No FORMS LOADED DRAINAGE AREA INFORMATION Entire Site 1 2 4 T pe of SCM Wet Pond A Wet Pond B 5 Total BUA in project (sq ft 110984 sf 79306 sf 10348 sf 6 New BUA on subdivided lots (subject to ermitting) (sq ft sf sf sf 7 New BUA outside of subdivided lots (subject to permitting) (sf) 89628 sf 71755 sf 10348 sf 8 Offsite - total area (sq ft) 9 Offsite BUA (sq ft 10 Breakdown of new BUA outside subdivided lots: - Parking (sq ft 6913 sf 6735 sf - Sidewalk (sq ft 19717 sf 13584 sf 6133 sf - Roof (sq ft 51436 sf 51436 sf - Roadway s ft 11562 sf sf 4215 sf - Future (sq ft - Other, please specify in the comment box below (sq ft) sf 11 New infiltrating permeable pavement on subdivided lots (sq ft sf sf 12 New infiltrating permeable pavement outside of subdivided lots (sq ft sf sf 13 Exisitng BUA that will remain no subject to ermitting) (sq ft 21356 sf 7551 sf 14 Existing BUA that is already ermitted (sq ft sf sf 15 Existing BUA that will be removed (sq ft sf sf 16 Percent BUA 55% 18% 17 Design storm inches 1 in 1 in 18 Design volume of SCM cu ft 6548 cf 1010 cf 19 Calculation method for design volume Simple Method Simple Method ADDITIONAL INFORMATION 20 Please use this space to provide any additional information about the drainage area(s): Wet pond B will not have an increase in impervious area or total drainage I' Wet pond B will not be modified as part of this project. WET POND 1 Drainage area number 1 (Pond A) 2 Design volume of SCM (cu ft) 6550 cf C.FNFRAI Mnr FROM n7H .1 n5n 31 Is the SCM sized to treat the SW from all surfaces at build -out? Is the SCM located away from contaminated soils? Yes 4 Yes 3:1 5 What are the side slopes of the SCM (H:V)? 6 Does the SCM have retaining walls, gabion walls or other engineered side slopes? No 7 Are the inlets, outlets, and receiving stream protected from erosion (10-year storm)? Yes 8 Is there an overflow or bypass for inflow volume in excess of the design volume? Yes 9 What is the method for dewatering the SCM for maintenance? Drawdown Orifice 10 If applicable, will the SCM be cleaned out after construction? Yes 11 Does the maintenance access comply with General MDC (8)? Yes 12 Does the drainage easement comply with General MDC (9)? No 13 If the SCM is on a single family lot, does (will?) the plat comply with General MDC (10)? 14 Is there an O&M Agreement that complies with General MDC (11)? Yes 15 Is there an O&M Plan that complies with General MDC (12)? Yes 16 Does the SCM follow the device specific MDC? Yes 17 Was the SCM designed by an NC licensed professional? Yes IWFT PANG MOG FRAM n9H 1nF3 181 Method used I SA/DA 19 Has a stage/storage table been provided in the calculations? Yes 20 Elevation of the excavated main pool depth (bottom of sediment removal) (fmsl) 477.00 21 Elevation of the main pool bottom -(top of sediment removal) (fmsl) 478.00 22 Elevation of the bottom of the vegetated shelf (fmsl) 483.50 23 Elevation of the permanent pool (fmsl) 484.00 24 Elevation of the top of the vegetated shelf (fmsl) 484.50 25 Elevation of the temporary pool (fmsl) 485.10 26 Surface area of the main permanent pool (square feet) 4213.00 27 Volume of the main permanent pool (cubic feet) 13460 cf 28 Average depth of the main pool (feet) 3.19 ft 29 Average depth equation used Equation 2 301 If using equation 3, main pool perimeter (feet) N/A 31 If using equation 3, width of submerged veg. shelf (feet) N/A 32 Volume of the forebay (cubic feet) 2389 cf 33 Is this 15-20% of the volume in the main pool? Yes 34 Clean -out depth for forebay (inches) 72 in 35 Design volume of SCM (cu ft) 6550 cf 36 Is the outlet an orifice or a weir'? Orifice 371 If orifice, orifice diameter (inches) 1.3 in 38 If weir, weir height (inches) N/A 39 If weir, weir length (inches) N/A 40 Drawdown time for the temporary pool (days) 3.1 41 Are the inlet(s) and outlet located in a manner that avoids short- circuiting? Yes 42 Are berms or baffles provided to improve the flow path? Yes 431 Depth of forebay at entrance (inches) 72 in 44 Depth of forebay at exit (inches) 60 in 45 Does water flow out of the forebay in a non -erosive manner? Yes 46 Width of the vegetated shelf (feet) 6 ft 47 Slope of vegetated shelf (H:V) 6:1 48 Does the orifice drawdown from below the top surface of the permanent pool? Yes 49 Does the pond minimize impacts to the receiving channel from the 1- yr, 24-hr storm? Yes 50 Are fountains proposed? (If Y, please provide documentation that MDC(9) is met.) No 51 Is a trash rack or other device provided to protect the outlet system? Yes 52 Are the dam and embankment planted in non -clumping turf grass? Yes 53 Species of turf that will be used on the dam and embankment Bermuda Has a planting plan been provided or the vegetate shelf.? Yes ADDITIONAL INFORMATION 55 Please use this space to provide any additional information about the wet pond(s): The property is a 5,000 acre, state-owned parcel. It is exempt from recording drainage easements. Wet pond B will not have an increase in impervious area or total drainage area. Wet pond B will not be modified as part of this project. Wet Pond 3 12:30 PM 9/13/2022 Project Information Project Name: NCNG CBTC ACFT Submission Date: 09/21/2022 Project Area (ft): 714,000 ft2 Disturbed Area (ft): 198,158 ft2 Development Land Use Type: Institutional Development Activity Type: Development - New Designated Downtown Area? no Project Location/Address: 539 Roberts Chapel Road County: Granville Local Jurisdiction: State/Federal Project Latitude Coordinates: 36.178278 N Project Longitude Coordinates: -78.799533 W Precipitation Station: Durham Physiographic Region: Piedmont Nutrient Management Watershed: Falls Lake Subwatershed: Falls - Upper Phosphorus Delivery Zone: Falls - Upper Nitrogen Delivery Zone: Falls - Upper Project Designer and Contact Phone Number / Email: Jacob Lewis 919-532-3236 Part of Common Development Plan? no Project Owner Type: State non-NCDOT Project Description: Asphalt, concrete, artificial turf fitness area R = 0.05 + (0.009 *1) where I = percent impervious (%) Average Annual Pollutant Load, L L= (Pj *RR *(P/12))*(C*A*2.72) where C = event mean concentration (mg/L) i A = 16.3912 P = 47.81 V = 196931 1 = 3% Rv = 0.08 Pj = 0.9 CTN = 1.16 CTP = 0.10 LTN = 14.25 LTP = 1.24 ac in. ft3 mg/L mg/L Ib/yr Ib/yr Project Area Land Cover Characteristics PROJECT AREA LAND COVERS Roof Roadway TN TP I Pre- ! Post - EMC EMC Project Project (rrI (mg/L) Area (ft) Area (ft) 1.18 0.11 51,436 1.64 0.34 Parking/Driveway/Sidewalk 1.42 0.18 21,356 59,548 Protected Forest 0.97 0.03 676,171 485,983 Other Pervious/Landscaping 2.48 1.07 16,473 108,946 CUSTOM LAND COVER 1 CUSTOM LAND COVER 2 CUSTOM LAND COVER 3 LAND TAKEN UP BY SCM 1.18 0.11 8,087 LAND COVER AREA CHECK Net Change of Land Covers (ft): 190,188 Total Project Area Entered (ft): 714,000 Total Pre -Project Calculated Area (ft): 714,000 Total Post -Project Calculated Area (ft): 714,000 Equations Used and Project Area Calculations SIMPLE METHOD Stormwater Runoff Volume Generated, V Runoff Coefficient R v V = Pi * Rv * (P/12) * A where A = drainage area (ft) Pj = fraction of rain events with runoff P = average annual rainfall depth (in) Project: A = 16.3912 P = 47.81 V = 513724 1 = 17% Rv = 0.20 Pj = 0.9 CTN = 1.29 CTP = 0.16 LTN = 41.34 LTP = 5.15 ac in. ft3 mg/L mg/L Ib/yr Ib/yr 3. SCM Characteristics SCM Characteristics Catchment ID SCM ID Type of SCM Predominant hydrologic soil group at SCM location SCM Description Design Storm Size (inches/24hrs) Percent of Full Size Hydrologic Value - Percent Annual Effluent Hydrologic Value - Percent Annual Overflow Hydrologic Value - Percent Annual ET/Infiltrated SCM Effluent TP EMC (mg/L) SCM Effluent TN EMC (mg/L) SCM Land Cover TP EMC (mg/L) SCM Land Cover TN EMC (mg/L) Drains to SCM ID 1 1 1 101 102 103 Wet Pond per MDC C 1.00 100 72% 16% 13% 0.15 1.22 0.11 1.18 0 Catchment Routing (Source Catchment) Catchment 1 Catchment 2 Catchment 3 Catchment 4 Catchment 5 Catchment 6 3. SCM Characteristics Catchments Draining to Catchments Draining to SCM 101 SCM 102 Catchments Draining to SCM 103 SCM ID: 101 102 103 Area Draining Directly to Area Draining Directly to Area Draining Directly to SCM Drainage Area Land Covers SCM 101 (ft2) SCM 102 (ft2) SCM 103 (ft2) Roof 51,436 Roadway Parking/Driveway/Sidewalk 27,870 Protected Forest Other Pervious/Landscaping 60,505 CUSTOM LAND COVER 1 CUSTOM LAND COVER 2 CUSTOM LAND COVER 3 LAND TAKEN UP BY SCM 4,213 TOTAL AREA DRAINING TO SCM (ft): 144,024 CATCHMENT AREA (ft):144,024 0 0 3. SCM Characteristics SCM Characteristics Catchment ID SCM ID Type of SCM Predominant hydrologic soil group at SCM location SCM Description Design Storm Size (inches/24hrs) Percent of Full Size Hydrologic Value - Percent Annual Effluent Hydrologic Value - Percent Annual Overflow Hydrologic Value - Percent Annual ET/Infiltrated SCM Effluent TP EMC (mg/L) SCM Effluent TN EMC (mg/L) SCM Land Cover TP EMC (mg/L) SCM Land Cover TN EMC (mg/L) Drains to SCM ID 2 2 2 201 202 203 Wet Pond per MDC C 1.00 100 72% 16% 13% 0.15 1.22 0.11 1.18 0 3. SCM Characteristics Catchment Routing (Source Catchment) Catchment 1 Catchment 2 Catchment 3 Catchment 4 Catchment 5 Catchment 6 Catchments Draining to SCM 201 Catchments Draining to SCM 202 Catchments Draining to SCM 203 J SCM ID: 201 202 203 Area Draining Directly to Area Draining Directly to Area Draining Directly to SCM Drainage Area Land Covers SCM 201 (ft2) I SCM 202 (ft2) SCM 203 (ft2) Roof Roadway Parking/Driveway/Sidewalk 10,348 Protected Forest Other Pervious/Landscaping 42,096 CUSTOM LAND COVER 1 CUSTOM LAND COVER 2 CUSTOM LAND COVER 3 LAND TAKEN UP BY SCM TOTAL AREA DRAINING TO SCM (ft): CATCHMENT AREA (ft): 3,874 56,318 56,318 0 3. SCM Characteristics SCM Characteristics Catchment ID SCM ID Type of SCM Predominant hydrologic soil group at SCM location SCM Description Design Storm Size (inches/24hrs) Percent of Full Size Hydrologic Value - Percent Annual Effluent Hydrologic Value - Percent Annual Overflow Hydrologic Value - Percent Annual ET/Infiltrated SCM Effluent TP EMC (mg/L) SCM Effluent TN EMC (mg/L) SCM Land Cover TP EMC (mg/L) SCM Land Cover TN EMC (mg/L) Drains to SCM ID 3. SCM Characteristics Catchment Routing (Source Catchment) Catchment 1 Catchment 2 Catchment 3 Catchment 4 Catchment 5 Catchment 6 SCM ID: SCM Drainage Area Land Covers Roof Roadway Parking/Driveway/Sidewalk Protected Forest Other Pervious/Landscaping CUSTOM LAND COVER 1 CUSTOM LAND COVER 2 CUSTOM LAND COVER 3 LAND TAKEN UP BY SCM TOTAL AREA DRAINING TO SCM (ft): CATCHMENT AREA (ft): Total Land Use Area Treated By All SCMs (ftZ) 51,436 0 Allowable Total Land Use Area to be Treated Based Z on Post -Project Areas ft 51,436 Post -Project Untreated Land Area (ftZ) _ 0 0 0 38,218 59,548 21,330 0 485,983 485,983 102,601 108,946 6,345 0 0 0 0 0 0 0 8,087 0 0 0 8,087 200,342 714,000 513,658 Project Summary Project Name: NCNG CBTC ACFT 714,000 ft 198,158 ft2 16.3912 acres Submission Date: 4.5491 acres September 21, 2022 Project Area (ft): Disturbed Area (ft): County: Granville Local Jurisdiction: State/Federal Development Land Use Type: Institutional Owner Type: State non-NCDOT Development Activity Type: Development - New Designated Downtown Area? no Nutrient Management Watershed: Falls Lake Subwatershed: Falls - Upper Phosphorus Delivery Zone: Falls - Upper Nitrogen Delivery Zone: Falls - Upper Phosphorus Delivery Factor (%): 100% Nitrogen Delivery Factor (%): 100% Phosphorus Loading Rate Target (Ib/ac/yr): 0.33 Nitrogen Loading Rate Target (Ib/ac/yr): 2.20 Phosphorus Load Target at Site (lb/yr): 5.41 Nitrogen Load Target at Site (lb/yr): 36.06 Phosphorus Load Leaving Site w/SCMs (lb/yr): 4.06 Nitrogen Load Leaving Site w/SCMs (lb/yr): 35.71 P Offsite Buy -Down Threshold Loading Rate (lb/ac/yr): 1.16 N Offsite Buy -Down Threshold Loading Rate 8.51 Total P Load Reduction Needed (lb/yr): -0.26 Total N Load Reduction Needed (lb/yr): 5.27 P Load Treatment Balance at Site (lb/yr): -1.35 N Load Treatment Balance at Site (lb/yr): -0.35 P Load Treatment Balance at Lake (lb/yr): -1.35 N Load Treatment Balance at Lake (lb/yr): -0.35 Nutrient Export Summary Percent Impervious (for runoff calculation) (%) Pre -Project Whole Site Conditions Post -Project Whole Site without SCMs Post -Project Post -Project Whole Site with SCM-Treated SCMs Area Post -Project Untreated Area 3.0% 16.7% 16.7% 48.8% 4.2% Percent Built -Upon Area (BUA) (%) 3.0% 15.5% 15.5% 44.8% 4.2% Annual Runoff Volume ft3/ r 196,931 513,724 469,050 308,121 160,928 Annual Runoff % Change (relative to pre-D) 0% 161% 138% Total Nitrogen EMC (mg/L) 1.16 1.29 1.22 1.25 1.18 Total Nitrogen Load Leaving Site (lb/yr) 14.25 41.34 35.71 23.82 11.89 Total Nitrogen Loading Rate (Ib/ac/yr) 0.87 2.52 2.18 5.18 1.01 Total Nitrogen % Change (relative to pre-D) 0% 190% 151% Total Phosphorus EMC (mg/L) 0.10 0.16 0.14 0.16 0.11 Total Phosphorus Load Leaving Site (lb/yr) 1.24 5.15 4.06 3.00 1.06 Total Phosphorus Loading Rate (Ib/ac/yr) 0.08 1 0.31 1 0.25 0.65 0.09 Total Phosphorus % Change (relative to pre-D) 0% 1 315% 1 227% SCM/Catchment Summary SCM ID and Type Volume Reduction (%) TN Out (mg/L) TIP Out (mg/L) TN Out I TP Out (Ibs/ac/yr) (Ibs/ac/yr) 1.24 0.15 6.02 0.75 TN Reduction TIP Reduction N N Catchment 1 12.66% 17.49% 20.37% 101: Wet Pond per MDC 12.66% 1.24 0.15 6.02 0.75 17.49% 20.37% 102: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 103: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% Catchment 2 12.66% 1.27 0.17 3.03 0.41 26.30% 46.27% 201: Wet Pond per MDC 12.66% 1.27 0.17 3.03 0.41 26.30% 46.27% 202: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 203: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% Catchment 3 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 301: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 302: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 303: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% Catchment 4 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 401: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 402: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 403: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% Catchment 5 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 501: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 502: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 503: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% Catchment 6 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 601: NA 0.00% 0.00 0.00 0.00 0.00 0.00% 0.00% 602: NA 0.00% 603: NA 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00 0.00 SCM rows in red have a data entry error for the SCM that makes an error in the calculation.