Grassed Swale Operation and Maintenance Agreement
1 will keep a maintenance record on this BMP. This maintenance record will be kept in a
log in a known set location. Any deficient BNiP elements noted in the inspection will be
corrected, repaired or replaced immediately. These deficiencies can affect the integrity
of structures, safety of the public, and the removal efficiency of the BMP.
Important maintenance procedures:
— The drainage area of the grassed swale will be carefully managed to reduce the
sediment load to the grassed swale.
— After the first-time fertilization to establish the grass in the swale, fertilizer will
not be applied to the grassed swale.
The grassed swale will be inspected once a quarter. Records of operation and
maintenance will be kept in a known set location and will be available upon request.
Inspection activities shall be performed as follows. Any problems that are found shall
be repaired immediately. FEB 1 0 2015
BMP element:
Potentialproblem:
How I will remediate theproblem:
The entire length of the
'trash/debris is present.
Remove the trash/debris.
swale
Areas of bare soil and/or
Regrade the soil if necessary to
erosive gullies have formed.
remove the gully, and then re -sod
(or plant with other appropriate
species) and water until established.
Provide time and a one-time
fertilizer application.
Sediment covers the grass at
Remove sediment and dispose in an
the bottom of the swale.
area that will not impact streams or
BMPs. Re -sod if necessary.
Vegetation is too short or too
Maintain vegetation at a height of
long.
approximately. six inches.
The receiving water
Erosion or other signs of
Contact the NC Division of Water
damage have occurred at the
Quality 401 Oversight Unit at 919-
outlet.
733-1786.
Form SW401-Grassed Swale O&M-Rev3 Page I of 2
Permit Number:
(to be provided by DWQ)
I acknowledge and agree by my signature below that I am responsible for the
performance of the maintenance procedures listed above. I agree to notify DWQ of any
problems with the system or prior to any changes to the system or responsible party.
Project name:RTI Motor Pool Expansion at Fort Bragg
BMP drainage area number:
Print name:LTC TOM L. COATS
T1tle:CONSTRUCTION FACILITY MANAGEMENT OFFICER
Address:1636 Gold Star Drive, Raleigh, NC, 27607-6410
Date: ii 2 lw �a
Note: The legally responsible party should not be a homeowners association unless more than 50% of
the lots have been sold and a resident of the subdivision has been named the president.
I, a Notary Public for the State of
County of , do hereby certify that
personally appeared before me this
day of , and acknowledge the due execution of the
forgoing grassed swale maintenance requirements. Witness my hand and official seal,
SEAL
My commission
Form SW401-Grassed Swale O&M-Rev.3 Page 2 of 2
t
Permit Number:
(to be provided by DWQ)
Drainage Area Numher:
Dry Extended Detention Basin
Operation and Maintenance Agreement
I will keep a maintenance record on this BMP. 'Phis maintenance record will be kept in a
log in a known set location. Any deficient BMP elements noted in the inspection will be
corrected, repaired or replaced immediately. These deficiencies can affect the integrity
of structures, safety of the public, and the removal efficiency of the BMP.
The dry extended detention basin system is defined as the dry detention basin, outlet
structure, pretreatment including forebays and the vegetated filter if one is provided.
This system (check one):
❑ does ® does not incorporate a vegetated filter at the outlet.
This system (check one):
® does ❑ does not incorporate pretreatment other than a forebay.
Important maintenance procedures:
— The drainage area will be managed to reduce the sediment load to the dry
extended detention basin.
— Immediately after the dry extended detention basin is established, the vegetation
will be watered twice weekly if needed until the plants become established
(commonly six weeks).
— No portion of the dry extended detention pond will be fertilized after the first
initial fertilization that is required to establish the vegetation.
— I will maintain the vegetation in and around the basin at a height of
approximately six inches.
Once a year, a dam safety expert will inspect the embankment. F EB 1 0 2015
After the dry extended detention basin is established, it will be inspected once a quarter
and within 24 hours after every storm event greater than 1.0 inches (or 1.5 inches if in
a Coastal County). Records of operation and maintenance will be kept in a known set
location and will be available upon request.
Inspection activities shall be performed as follows. Any problems that are found shall
be repaired immediately.
BMP element:
Potentialproblem:
How I will remediate theproblem:
The entire BMP
Trash debris is present.
Remove the trash debris.
The perimeter of the dry
Areas of bare soil and/or
Regrade the soil if necessary to
extended detention
erosive gullies have formed.
remove the gully, and then plant a
basin
ground cover and water until it is
established. Provide lime and a
one-time fertilizer application.
Form SW401-Dry Detention O&M-Rev.3
Page I of 4
1
BMP element
Potentialproblem:
Haw I will remediate theproblem:
The inlet device: pipe or
"I'he pipe is clogged (if
Unclog the pipe. Dispose of the
Swale
applicable).
sediment off -site.
The pipe is cracked or
Replace the pipe.
otherwise damaged (if
applicable).
Erosion is occurring in the
Regrade the swale if necessary to
Swale (if applicable).
smooth it over and provide erosion
control devices such as reinforced
turf matting or riprap to avoid
future problems with erosion.
The forebay
Sediment has accumulated
Search for the source of the
and reduced the depth to 75%
sediment and remedy the problem if
of the original design depth
possible. Remove the sediment and
(see diagram below).
dispose of it in a location where it
will not cause impacts to streams or
the BMP.
Erosion has occurred or
Provide additional erosion
riprap is displaced.
protection such as reinforced turf
matting or riprap if needed to
.prevent future erosionproblems.
Weeds are present.
Remove the weeds, preferably by
hand. If pesticides are used, wipe
them on the plants rather than
spraying.
The main treatment area
Sediment has accumulated
Search for the source of the
and reduced the depth to 757.
sediment and remedy the problem if
of the original design depth
possible. Remove the sediment and
(see diagrarn below).
dispose of it in a location where it
will not cause impacts to streams or
the BMP. Revegetate disturbed
areas immediately with sod
(preferred) or seed protected with
securely staked erosion mat.
Water is standing more than
Check outlet structure for clogging.
5 clays after a storm event.
If it is a design issue, consult an
appropriate rofessional.
Weeds and noxious plants are
Remove the plants by hand or by
growing in the main
wiping them with pesticide (do not
treatment area,
spray).
Form SW401-Dry Detention O&M-Rev.3 Page 2 of 4
r� s
BMP element
Potentialproblem:
How I will remediate theproblem:
The embankment
Shrubs or trees have started
Remove shrubs or trees
to grow on the embankment.
immediately.
Crass cover is unhealthy or
Restore the health of the grass cover
eroding.
- consult a professional if necessary.
Signs of seepage on the
Consult a professional.
downstream face.
Evidence of muskrat or
Use traps to remove muskrats and
beaver activity is present.
consult a professional to remove
beavers.
An annual inspection by an
Make all needed repairs.
appropriate professional
shows that the embankment
needs repair.
The outlet device
Clogging has occurred.
Clean out the outlet device. Dispose
of the sediment off -site.
The outlet device is damaged
Repair or replace the outlet device.
The receiving water
Erosion or other signs of
Contact the NC Division of Water
damage have occurred at the
Quality 401 Oversight Unit at 919-
outlet.
733-1786.
The measuring device used to determine the sediment elevation shall be such that it will
give an accurate deptli reading and not readily penetrate into accumulated sediments.
When the basin depth reads 227 feet in the main pond, the sediment shall be removed.
When the basin depth reads n a feet in the forebay, the sediment shall be removed.
BASIN DIAGRAM
ill in the blanks)
Temporary Pool Elevation 228.5
Sediment Removal E n/a b,�25%
rrar Peol 'Temp
-----------------olunte Sediment Removal Elevation 2=7 Vol
Bottom Elevatioi ))L ------------------227 Vol
Bottom Elevation 226 25%
Storage
FOREBAY MAIN POND
Form SW401-Dry Detention O&M-Rev.3
Page 3 of 4
Permit Number:
(to be provided by DWQ)
I acknowledge and agree by my signature below that I am responsible for the
performance of the maintenance procedures listed above. I agree to notify DWQ of any
problems with the system or prior to any changes to the system or responsible party.
Project name:RTI MOV PARKING EXPANSION
BMP drainage area number:
Print name:LTC TONI L. COATS
Title:CONSTRUCTION FACILITY MANAGEMENT OFFICER
Address:1636 GOLD STAR DRIVE RALEIGH, NC, 27607-6410
Signature: JT3Ak_ A , 1. I&D9t
Date:
Note: 'the legally responsible party should not be a homeowners association unless more than 50% of
the lots have been sold and a resident of the subdivision has been named the president.
I,
County of
a Notary Public for the State of
do hereby certify that
personally appeared before me this
day of 1 , and acknowledge the due execution of the
forgoing dry detention basin maintenance requirements. Witness my hand and official
seal,
SEAL
My commission
Form SW401-Dry Detention O&M-Rev.3 Page 4 of