HomeMy WebLinkAbout20140379 Ver 1_Corps of Engineer Correspondence_20140506Homewood, Sue
From:
Bailey, David E SAW <David.E.Bailey2 @usace.army.mil>
Sent:
Tuesday, May 06, 2014 8:33 AM
To:
George Junkin
Cc:
Ashley Sylvester; Homewood, Sue
Subject:
Cardinal Pipeline, Red Slide Park bank stabilization, Alamance Co., NC;
SAW - 2014 -00824 (UNCLASSIFIED)
Classification: UNCLASSIFIED
Caveats: NONE
Mr. Junkin,
Thanks for your PCN and attached plans dated 4/8/2013, received 4/15/2014, for the above referenced project. I have
reviewed the information and need clarification before proceeding with verifying the use of Nationwide Permit 13
http: / /www.saw.usace. army. mil / Portals /59/ docs / regulatory /regdocs /NWP2012 /NWP13 3- 23.pdf:
1) Regional Condition 3.5.1 of NWP 13 requires that filter cloth be placed underneath riprap as an additional
requirement of its use in North Carolina waters. Please confirm that filter cloth will be placed under Armor Stone, or
explain how the proposed project otherwise meets the NWP terms and conditions.
2) Regional Condition 3.9.1 of NWP 13 requires that the PCN /plans show sediment and erosion control measures.
Specifically, what S and EC measures will be employed during project installation? Given that excavation will occur in
order to place base stone below existing grade at the toe of slope for Area A, and other minor grading may occur in Area
B, turbidity in the adjacent Waters is a concern.
Please submit the above information (via e -mail is fine) within 30 days of receipt of this Notification, otherwise the
proposed project may not fit the terms and conditions of the Nationwide Permit. If you have any questions please let me
know.
Sincerely,
Dave Bailey
David E. Bailey
Project Manager
US Army Corps of Engineers
CE- SAW -RG -R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Phone: (919) 554 -4884, Ext. 30.
Fax: (919) 562 -0421
Email: David. E. Bailey2 @usace.army.mil
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we
continue to do so, please complete the Customer Satisfaction Survey located at http : / /regulatory.usacesurvey.com /.