HomeMy WebLinkAbout20151065 Ver 1_Correspondence_20220427Strickland, Bev
From: Wright, Matt <Matt.Wrightl @jacobs.com>
Sent: Wednesday, April 27, 2022 10:15 AM
To: Homewood, Sue; Alex Rosser
Cc: Brad Luckey; Turney, Kimberly; Kight, Stephanie/GVL
Subject: RE: [External] PTI - Airport - Northwest Development - Phase 3
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Sue,
Yes, upon receipt of the permit for the channel from ESB-2 to the stream (which we have designated "Swale 7") we
issued a plan revision to the Contractor and asked for pricing from them to do the work. This was a frustrating process as
the Contractor kept delaying a proposal for the work, until finally, around the close of the year they stated they would
not perform the work at all as they deemed it "too risky". We inquired and pushed into their concerns and even offered
them a dialogue with your office since the request originated with DEQ. We were unable to make much progress and so
we were going to include this work in the next grading design package that is currently underway.
About 6-8 weeks ago however there was a change in the Contractor's management and so we brought back up the issue
of Swale 7. Thankfully the new project manager did not share the same concerns and did provide a price to undertake
this work in accordance with the permit revision.
That work was included in a very large Change Order which included, the dewatering of the pond and backfill, along with
grading revisions to what will become the Boom site. That Change Order was agreed to in principle at the Airports
Authority Board Meeting yesterday, and the goal is to get it executed by the end of this week and commence
construction as early as Monday, May 2na
We will prioritize the installation of Swale 7 as soon as this work begins and let you know when it is completed.
Thank you!
Matt
Matt Wright, P.E.*
Jacobs
Project Manager 1 Aviation
+1.919.859.5793 direct
+1.540.808.8535 mobile
Matt.Wright1@jacobs.com
www.jacobs.com
*Registered in AR, NC, OK, SC, VA, WV
From: Homewood, Sue <sue.homewood@ncdenr.gov>
Sent: Wednesday, April 27, 2022 10:01 AM
To: Wright, Matt <Matt.Wrightl@jacobs.com>; Alex Rosser <RosserA@gsoair.org>
Cc: Brad Luckey <bluckey@pilotenviro.com>; Turney, Kimberly <kimberly.turney@ncdenr.gov>; Kight, Stephanie/GVL
<Stephanie.Kight@jacobs.com>
Subject: RE: [External] PTI - Airport - Northwest Development - Phase 3
1
Hello Matt,
I visited the site with Pilot and Jacobs staff to assess the sediment loss recently. During that site visit I requested an
update on the project that was proposed in June 2021 to reconstruct the channel from ESB-2 to the stream in order to
address concerns of erosion and degradation within the channel which posed a risk to downstream waters. I realize that
I had been under the assumption that the airport would commence this work upon receipt of all applicable permits,
however I discovered that the work has yet to commence. The outlet channel continues to erode and threaten
downstream water quality. Please provide an updated of the proposed schedule for this work to commence and
expected completion date.
Thank you.
Sue Homewood
Division of Water Resources, Winston Salem Regional Office
Department of Environmental Quality
336 776 9693 office
336 813 1863 mobile
Sue.Homewood@ncdenr.gov
450 W. Hanes Mill Rd, Suite 300
Winston Salem NC 27105
From: Wright, Matt <Matt.Wrightl@jacobs.com>
Sent: Monday, March 28, 2022 4:02 PM
To: Homewood, Sue <sue.homewood@ncdenr.gov>
Subject: FW: [External] PTI - Airport - Northwest Development - Phase 3
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Sue
See email below. Initially this one bounced back to me as undeliverable. Hopefully it goes through this time.
Thank you!
Matt
Matt Wright, P.E.*
Jacobs
Project Manager 1 Aviation
+1.919.859.5793 direct
+1.540.808.8535 mobile
Matt.Wright1@jacobs.com
www.jacobs.com
*Registered in AR, NC, OK, SC, VA, \NV
2
From: Wright, Matt
Sent: Monday, March 28, 2022 3:57 PM
To: sue.homewood@ncdenr.com
Cc: Turney, Kimberly <kimberly.turney@ncdenr.gov>; Lorin Akins <AkinsL@gsoair.org>; Lisa Elmore
<ElmoreL@gsoair.org>; akkoushs <akkoushs@gsoair.org>; Alex Rosser <rossera@gsoair.org>; Kight, Stephanie/GVL
<Stephanie.Kight@jacobs.com>; Stephen Arenson (sarenson@pilotenviro.com) <sarenson@pilotenviro.com>; Matt
Carter <mcarter@pilotenviro.com>
Subject: FW: [External] PTI - Airport - Northwest Development - Phase 3
Good Afternoon Sue,
I apologize for not copying you on the initial correspondence but please see the exchange below. We wanted to let DEQ
know that due to some recent storms and the culmination of the size of the site and coming out of the winter months,
we did have some sediment leave the Northwest Development Site at the PTI airport in two locations. One is the small
wetland that existed within the old golf course, and the other is the stream head in the area.
As Kimberly noted, she will be inspecting the site this Wednesday, and the Contactor has already begun removing
sediment with non -mechanical means. Additionally, and most importantly, we believe we were able to isolate the issues
that allowed the discharge of sediment which seems to be from the following areas:
1. Sediment got through the silt fence around the wetland just due to an accumulation and inability to be able to
get the disturbed area stabilized over the winter. The Contractor has already manually removed the sediment in
this wetland area, installed a diversion dike to protect it, and is moving forward quickly on stabilizing the area
above the wetland.
2. Sediment appears to have entered the stream through an old sediment basin that was being removed as part of
this job. The replacement basin(s) have been installed and are functioning correctly, however the Contractor has
failed to fully divert all runoff away from the basin being removed as they slowly fill in said basin. We are
pushing the contractor to prioritize this area to match the plans ASAP and feel that will eliminate any future loss
of sediment in this area.
3. Lastly, our downstream swale connecting to the stream buffer has just accumulated sediment through the
winter and is being cleaned to ensure it does not contribute and sediment loss moving forward.
Please let us know if you have any additional concerns, or want to visit the site or weigh in on the cleanup methods
currently being instilled. With the weather coming into our favor we should be able to start getting large portions of the
site stabilized as we complete grading operations in certain areas.
Thank you!
Matt
Matt Wright, P.E.*
Jacobs
Project Manager I Aviation
+1.919.859.5793 direct
+1.540.808.8535 mobile
Matt.Wright1@jacobs.com
www.jacobs.com
*Registered in AR, NC, OK, SC, VA, WV
From: Turney, Kimberly <kimberly.turney@ncdenr.gov>
Sent: Thursday, March 24, 2022 2:29 PM
To: Wright, Matt <Matt.Wrightl@jacobs.com>; Lentz, Zachary <zac.lentz@ncdenr.gov>
3
Cc: Paul Rogers <progers@kprcompany.com>; Michael Havrilla <mhavrilla@gloverconstruction.com>; Kight,
Stephanie/GVL <Stephanie.Kight@jacobs.com>; Myers, Phil/DEN <Phil.Myers@jacobs.com>; Stephen Arenson
(sarenson@pilotenviro.com) <sarenson@pilotenviro.com>; Matt Carter <mcarter@pilotenviro.com>; Lorin Akins
<AkinsL@gsoair.org>; Alex Rosser <rossera@gsoair.org>; Lisa Elmore <ElmoreL@gsoair.org>;
pking@gloverconstruction.com; emartin@gloverconstruction.com; mglover@gloverconstruction.com
Subject: RE: [External] PTI - Airport - Northwest Development - Phase 3
Good afternoon, everyone,
Thank you for notifying us of the loss. If you haven't already, please notify your 401-permit holder, Sue Homewood,
since the impacts also fall within her regulatory area as well. If the sediment is easily retrieved using non -mechanical
means with minimal disturbance, then yes, please go ahead and begin removing it. I would also like to schedule an
inspection of these areas; would Wednesday, March 30, at 9:00 am work?
Sincerely,
Kim
Kimberly Turney
Environmental Specialist II
Division of Energy, Mineral, and Land Resources
Department of Environmental Quality
336-776-9657 office
919-302-4740 mobile
kimberly.turney@ncdenr.govl
450 W. Hanes Mill Rd, Suite 300
Winston Salem NC 27105
E
: A
L�pp.p drum.' of Enrrironmpnisl {kohl")
From: Wright, Matt <Matt.Wrightl@jacobs.com>
Sent: Tuesday, March 22, 2022 11:59 AM
To: Lentz, Zachary <zac.lentz@ncdenr.gov>; Turney, Kimberly <kimberly.turney@ncdenr.gov>
Cc: Paul Rogers <progers@kprcompany.com>; Michael Havrilla <mhavrilla@gloverconstruction.com>; Kight,
Stephanie/GVL <Stephanie.Kight@jacobs.com>; Myers, Phil/DEN <Phil.Myers@jacobs.com>; Stephen Arenson
(sarenson@pilotenviro.com) <sarenson@pilotenviro.com>; Matt Carter <mcarter@pilotenviro.com>; Lorin Akins
<AkinsL@gsoair.org>; Alex Rosser <rossera@gsoair.org>; Lisa Elmore <ElmoreL@gsoair.org>
Subject: [External] PTI - Airport - Northwest Development - Phase 3
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Good afternoon Kimberly and Zac,
We wanted to make you aware that unfortunately after our most recent site inspection we have noticed some
sedimentation getting past our erosion control perimeter features in two locations.
4
This is for the Northwest Development — Phase 3 Site (Permit No. GUILF-2021-025).
The two locations are the small interior wetland and the stream down from Swale 3.
We were wondering if you would like to come out to the site and take a look or if we should immediately begin
removing the sedimentation with non -mechanical means?
Most importantly we believe we understand why this has occurred and the contractor is already in the process of
making improvements to the site features to keep this from re -occurring. Also coming out of winter, we are going to be
able to start permanently stabilizing areas soon as well to further improve the situation.
Please let us know how best we should proceed.
Thank you!
Matt
Matt Wright, P.E.*, C.M., LEED AP BD+C
Jacobs
Project Manager I Aviation
+1.919.859.5793 direct
+1.540.808.8535 mobile
Matt.Wright1@jacobs.com
111 Corning Road., Suite 200
Cary, NC 27518
USA
www.jacobs.com
*Registered in AR, NC, OK, SC, VA, WV
NOTICE - This communication may contain confidential and privileged information that is for the sole use of the intended recipient. Any
viewing, copying or distribution of, or reliance on this message by unintended recipients is strictly prohibited. If you have received this
message in error, please notify us immediately by replying to the message and deleting it from your computer.
NOTICE - This communication may contain confidential and privileged information that is for the sole use of the intended recipient. Any
viewing, copying or distribution of, or reliance on this message by unintended recipients is strictly prohibited. If you have received this
message in error, please notify us immediately by replying to the message and deleting it from your computer.
NOTICE - This communication may contain confidential and privileged information that is for the sole use of the intended recipient. Any
viewing, copying or distribution of, or reliance on this message by unintended recipients is strictly prohibited. If you have received this
message in error, please notify us immediately by replying to the message and deleting it from your computer.
5