HomeMy WebLinkAboutNCC221044_ESC Approval Submitted_20220315ROY COOPER Governor DIONNE DELLFGATTI Secretary BRIAN WRENN Director NORTH CAROLINA Environmental Quality May 21, 2021 LETTER OF APPROVAL WITH MODIFICATIONS Duke Energy Carolinas, LLC Attn: Mr. Randy Veltri -Director, Transmission Permitting 550 S. Tryon St., Suite 4500 Charlotte, NC 28202 RE: Project Name: HANKINS 44KV LINE REBUILD PHASE 2 Acres Approved: 41.8 Project 1D: MCDOW-2021-012 County: McDowell City: Marion Address: U.S. Hwy. 70 River Basin: Catawba Stream Classification: Forsyth Creek & Catawba River - Class C Submitted By: Duke Energy Carolinas, LLC - Mr, Kevin Mason, P.E. Date Received by LQS: April 23, 2021 Plan Type: Utility Dear Mr. Veltri, This office has reviewed the subject erosion and sedimentation control plan and hereby issues this Letter of Approval with Modifications. A list of the modifications is attached. This plan approval shall expire three (3) years following the date of approval, if no land - disturbing activity has been undertaken, as is required by Title 15A NCAC 4B .0129. Should the plan not perform adequately, a revised plan will be required (G.S. 113A-54.1)(b). As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the NCGO10000 Construction General Permit, After the form is reviewed and found to be complete, you will receive a link with payment instructions for the $100 annual permit fee. After the fee is received, you will receive the COC via email. You MUST obtain the COC prior to commencement of any land disturbing activity. The eNOI form may be accessed at deq.nc.gov/NCGO1. Please direct questions about the eNOI form to Annette Lucas at Annette.lucas@ncdenr.gov or Paul Clark at Paul.clark@ncdenr.gov. If the owner/operator of this project changes in the future, the new responsible party is required to apply for his/her own COC. � North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources Asheville Regional Office 1 2090 U.S. Highway 70 1 Swannanoa, North Carolina 28778 roan-i cuzou�u. � Department of Enotrnnmemat Qeally 828.296.4500 Letter of Approval with Modifications Duke Energy Carolinas, LLC ATTN: Mr. Randy Veltri May 21, 2021 Page 2 of 4 Title 15A NCAC 413.0118(a) and the NCG01 permit require that the following documentation be kept on file at the job site: 1. The approved E&SC plan as well as any approved deviation. 2. The NCG01 permit and the COC, once it is received. 3. Records of inspections made during the previous 12 months. Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to insure compliance with the approved plan. North Carolina's Sedimentation Pollution Control Program is performance -oriented, requiring protection of existing natural resources and adjoining properties. If, following the commencement of this project, it is determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this office may require revisions to the plan and implementation of the revisions to ensure compliance with the Act. Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply to this land -disturbing activity. This approval does not supersede any other permit or approval. Please note that this approval is based in part on the accuracy of the information provided in the Financial Responsibility Form, which you provided. This permit allows for a land - disturbance, as called for on the application plan, not to exceed the approved acres. Exceeding the acreage will be a violation of this permit and would require a revised plan and additional application fee. You are requested to file an amended form if there is any change in the information included on the form. In addition, it would be helpful if you notify this office of the proposed starting date for this project. Please notify us if you plan to have a preconstruction conference. Your cooperation is appreciated. Sincere , Fred Walker, P.E. Express Engineer Land Quality Section Letter of Approval with Modifications Duke Energy Carolinas, LLC ATTN: Mr. Randy Veltri May 21, 2021 Page 3 of 4 Enclosures: Certificate of Approval NPDES NCGO1 Fact Sheet Modifications cc: Mr. Kevin Mason, RLA - Duke Energy Carolinas (kevin.mason@duke-ever rycom) Mr. Landon Davidson, P.G. - NCDEQ-DWR (landon.davidson@ncdenr.gov) Ms. Amy Annino. - NCDEQ-DWR (amy.annino@ncndeanz-OW) cc: Regional Office file Letter of Approval with Modifications Duke Energy Carolinas, LLC ATTN: Mr, Randy Veltri May 21, 2021 Page 4 of 4 MODIFICATIONS REQUIRED FOR APPROVAL Project Name: HANKINS 44KV LINE REBUILD PHASE 2 Project ID: MCDOW-2021-012 County: McDowell For final plan approval please provide to this office the requested documents listed below: I. Provide N.C. surface water classification for waterbodies shown on the plan sheets. {15A NCAC 04B .0106(a)(1)} 2. Remove S. lespedeza from the seeding list, since it is considered an invasive species. Also include seeding detail for native riparian seeding. {G.S. 113A-57.(3)} 3. Provide copies of approvals to the Asheville Regional Office - Land Quality Section from U.S. Army Corps of Engineers and N.C. Division of Water Resources to impact surface waters and wetlands. These approvals must be submitted to the ARO-LQS office before the project begins. 4. Add construction notes so that any work within the riparian buffer meets the following requirements: stabilization matting must be 100% biodegradable, no fertilizer should be used in the riparian buffer, work to be stabilized at the end of each work day, only native riparian seeding is to be used in riparian buffer, and not to perform grading activities during wet weather or periods of predicted wet weather. {15A NCAC 04B .0106(a)(5)} 5. Provide construction sequence in plan set that instructs the contractor on which measures to install with respect to construction activities, to notify DEQ inspector prior to project starting and once project is ready to be closed out, and not to perform grading activities during wet weather or periods of predicted wet weather. {15A NCAC 04B .0106(a)(5)} Ref: G.S. 113A-54.1 through G.S. 113A-57 Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504 General Permit NCG 010000 NPDES for Construction Activities