HomeMy WebLinkAboutNC0024333_Authorization to Construct_20210923ROY COOPER
Governor
ELIZABETH S. BISER
Secretary
S. DANIEL SMITH
Director
NORTH CAROLINA
Environmental Quality
September 23, 2021
Mr. Russ Colbath
Director of Water Resources
City of Monroe, Depailment of Water Resources
2401 Walkup Avenue
Monroe, North Carolina 28110
SUBJECT: Authorization to Construct
A to C No. 024333A04
City of Monroe
Monroe WWTP
NPDES Permit No. NC0024333
Dear Mr. Colbath:
A letter of request for an Authorization to Construct was received June 14, 2021, by the
Division of Water Resources (Division). With additional information received on September 22,
2021, final plans and specifications for the subject project have been reviewed and found to be
satisfactory. Authorization is hereby granted for the construction of modifications to the existing
10.4 MGD Monroe WWTP, with discharge of treated wastewater into the Richardson Creek in the
Yadkin -Pee Dee River Basin.
This authorization results in no increase in design or permitted capacity and is awarded for
the construction of the following specific modifications:
Installation of one (1) 15 MG flow equalization earthen embankment dam equipped with a
geosynthetic clay liner, and all necessary piping and controls, in conformity with the
project plans, specifications, and other supporting documentation comprising the ATC
Permit Application package submitted to the Depailment of Environmental Quality.
This ATC is issued in accordance with Part III, Paragraph A of NPDES Permit No.
NC0024333 issued effective August 1, 2020, and shall be subject to revocation unless the
wastewater treatment facilities are constructed in accordance with the conditions and limitations
specified in Permit No. NC0024333.
It is the Owner's responsibility to ensure that the as -constructed project meets the
requirements of all applicable regulations and statutes, the ATC Permit Application package, and
all of the requirements contained herein. Failure to comply may result in penalties in accordance
with North Carolina General Statute §143-215.6A through §143-215.6C.
NO D_E _
RTH CAROLINA
Department el Environmental ouatily
North Carolina Department of Environmental Quality I Division of Water Resources
512 North Salisbury Street 11617 Mail Service Center f Raleigh, North Carolina 27699-1617
919.707.9000
Mr. Russ Colbath, Director of Water Resources
September 23, 2021
Page 2 of 3
The sludge generated from these treatment facilities must be disposed of in accordance
with G.S. 143-215.1 and in a manner approved by the Division.
In the event that the facilities fail to perform satisfactorily, including the creation of
nuisance conditions, the Permittee shall take immediate corrective action, including those as may
be required by the Division, such as the construction of additional or replacement wastewater
treatment or disposal facilities.
The Mooresville Regional Office, telephone number 704-633-1699, shall be notified at
least forty-eight (48) hours in advance of operation of the installed facilities so that an on -site
inspection can be made. Such notification to the regional supervisor shall be made during the
normal office hours from 8:00 a.m. until 5:00 p.m. on Monday through Friday, excluding State
Holidays.
Upon completion of construction and prior to operation of this permitted facility, a
certification must be received from a Professional Engineer certifying that the permitted facility
has been installed in accordance with the NPDES Permit and the ATC Permit Application package.
Mail the Certification to: Division of Water Resources, WQ Permitting — NPDES, 1617 Mail
Service Center, Raleigh, NC 27699-1617.
Upon classification of the facility by the Certification Commission, the Permittee shall
employ a certified wastewater treatment plant operator to be in responsible charge (ORC) of the
wastewater treatment facilities. The operator must hold a certificate of the type and grade at least
equivalent to or greater than the classification assigned to the wastewater treatment facilities by
the Certification Commission.
The Permittee must also employ a certified back-up operator of the appropriate type and
grade to comply with the conditions of T15A:8G.0202. The ORC of the facility must visit each
Class I facility at least weekly and each Class II, III and IV facility at least daily, excluding
weekends and holidays, must properly manage the facility, must document daily operation and
maintenance of the facility, and must comply with all other conditions of T15A:8G.0202.
A copy of the project plans and specifications shall be maintained on file by the
Permittee for the life of the facility.
During the construction of the proposed additions/modifications, the Permittee shall
continue to properly maintain and operate the existing wastewater treatment facilities at all times,
and in such a manner, as necessary to comply with the effluent limits specified in the NPDES
Permit.
You are reminded that it is mandatory for the project to be constructed in accordance with
the North Carolina Sedimentation Pollution Control Act, and when applicable, the North Carolina
Dam Safety Act. In addition, the specifications must clearly state what the contractor's
responsibilities shall be in complying with these Acts.
Mr. Russ Colbath, Director of Water Resources
September 23, 2021
Page 3 of 3
Prior to entering into any contract(s) for construction, the recipient must have obtained all
applicable permits from the State.
The issuance of this ATC does not preclude the Permittee from complying with any and
all statutes, rules, regulations, or ordinances which may be imposed by other government agencies
(local, state, and federal) which have jurisdiction.
If you have any questions or need additional information, please contact Min Xiao, PE at
telephone number (919) 707-3644 or by email at min.xiao@ncdenr.gov.
Sincerely,
DocuSigned by:
B0B410C9F6204F7...
for S. Daniel Smith
Director, Division of Water Resources
by Min Xiao, PE
NPDES Industrial Permitting Unit
With Engineer's Certificate attached:
cc: NPDES Files
ecopy: James Struve, PE
Hazen and Sawyer
Email: jstruve@hazenandsawyer.com
DWR Mooresville Regional Office, Water Quality Programs
Without Engineer's Certificate attached:
cc: Union County Health
City of Monroe
Monroe WWTP
Authorization to Construct No. 024333A04
Issued September 23, 2021
NPDES Permit No. NC0024333
Engineer's Certification
I, , as a duly registered Professional Engineer in
the State of North Carolina, having been authorized to observe (periodically/weekly/full time)
the construction of the modifications and improvements to the Monroe Wastewater Treatment
Plant, located in Union County, hereby state that, to the best of my abilities, due care and
diligence was used in the observation of the following construction:
Installation of one (1) 15 MG flow equalization earthen embankment dam
equipped with a geosynthetic clay liner, and all necessary piping and controls, in
conformity with the project plans, specifications, and other supporting
documentation comprising the ATC Permit Application package submitted to the
Depailment of Environmental Quality.
I certify that the construction of the above referenced project was observed to be built within
substantial compliance, intent and in conformity with all applicable regulations and statutes and
the project plans, specifications, and other supporting documentation comprising the
Authorization to Construct Permit Application package.
Signature Registration No.
Date
Mail this Certification to: Attn: Min Xiao, PE
NPDES Industrial Permitting Unit
DEQ/DWR/Water Quality Programs
1617 Mail Service Center
Raleigh, NC 27699-1617