HomeMy WebLinkAboutB-4929 Surf City Bridge Temporary Impact Site - Year 3 ReportANNUAL REPORT FOR 2021 Surf City Bridge Temporary Impact Site Pender County TIP No. B-4929 CAMA Permit No. 60-16 Prepared By: Roadside Environmental Unit and Environmental Analysis Unit North Carolina Department of Transportation September 2021 TABLE OF CONTENTS SUMMARY ........................................................................................................... 1 1.0 Introduction ............................................................................................... 2 .1 Project Description ......................................................................... 2 .2 Purpose .......................................................................................... 2 .3 Project History ................................................................................ 2 .4 Debit Ledger .................................................................................... 2 2.0 Vegetation: ................................................................................................ 3 .1 Success Criteria ............................................................................. 3 .2 Description of Species ..................................................................... 3 .3 Results of Vegetation Monitoring .................................................... 3 .4 Conclusions. ................................................................................... 4 3.0 Overall Conclusions and Recommendations ............................................. 4 FIGURES Figure 1 – Vicinity Map ........................................................................................ 5 APPENDICES Appendix A – Site Photos and Site Map 1 SUMMARY The Surf City Bridge Temporary Impact Site is located in Pender County. This is an annual report for temporary impacts associated with the bridge replacement of Bridge No. 16 on NC 50-210 over the Intracoastal Waterway. The project was accepted as complete on October 4, 2019. The temporary impacts encompass approximately 0.03 acres for roadway/bridge and 0.10 acres for utility temporary impacts from temporary fill and hand clearing in CAMA wetlands. The area that was impacted is being monitored to ensure that it re-attains jurisdictional wetland status. The areas to the North of the Intracoastal Waterway where the temporary work bridge pilings were removed and the temporary utility impact areas occurred adjacent to NC 50-210 were planted in June 2018. The temporary work bridge pilings to the South of the Intracoastal waterway and the temporary impact area from the NCDOT Geotechnical Unit’s boring machine adjacent to the Surf City Park were planted in April 2021. All other temporary impact areas were left to re-vegetate naturally. Hydrologic monitoring is not required for this site; however, vegetation monitoring is required for three years. After the third year of monitoring, the Surf City Bridge Temporary Impact Site shows by visual observation that the temporarily impacted areas are re-attaining jurisdictional wetland status. The area’s most recently planted which include Site 4 (temp. work bridge impact area) at Photo Point #2 and temporary impact area from the Geotechnical Unit’s boring machine adjacent to the Surf City Park at Photo Point #7 had marsh grass sprigs surviving at this time. NCDOT proposes to discontinue monitoring at the site except for Site 4 at Photo Point #2 and the temporary impact area adjacent to the Surf City Park at Photo Point #7. All other sites have re-vegetated properly at this time. NCDOT will continue vegetation monitoring at the Surf City Bridge Temporary Impact Site in 2022. 2 1.0 INTRODUCTION 1.1 Project Description The Surf City Bridge Temporary Impact Site is located in Pender County at Bridge No. 16 on NC 50-210 over the Intracoastal Waterway (Figure 1). The temporary impacts encompass approximately 0.03 acres for roadway/bridge and 0.10 acres for temporary utility impacts from temporary fill and hand clearing in CAMA wetlands. The area that was impacted is being monitored to ensure that it re-attains jurisdictional wetland status. Hydrologic monitoring is not required for this site; however, vegetation monitoring is required for three years. 1.2 Purpose In order for a temporary impact site to be considered successful, a site must meet vegetation success criteria. This report details the vegetation monitoring in 2021 at the Surf City Bridge Temporary Impact Site. Hydrologic monitoring was not required for the site. 1.3 Project History June 2018 Marsh Grass Planting September 2019 Vegetation Monitoring (Year 1) October 2019 Project Acceptance Date August 2020 Vegetation Monitoring (Year 2) April 2021 Marsh Grass Planting August 2021 Vegetation Monitoring (Year 3) 1.4 Debit Ledger The restoration of the Surf City Bridge temporary impact site was used entirely to compensate for temporary impacts on the B-4929 project. There were no wetland mitigation credits generated from the restoration of the impacted area. 3 2.0 VEGETATION: SURF CITY BRIDGE TEMPORARY IMPACT SITE (YEAR 3 MONITORING) 2.1 Success Criteria CAMA Condition #25 Due to the possibility that shading, compaction, hand clearing, mechanized clearing, excavation, and/or other site alterations might prevent the temporary Coastal Wetland impacts from re-attaining pre-project wetland functions, the permittee shall provide an annual update on the Coastal Wetland areas temporarily impacted by this project. This annual update shall consist of photographs and a brief written report on the progress of these temporarily impacted areas in re-attaining their pre-project functions. The permittee shall schedule a meeting with DCM to verify the extent and location of the temporary impacts upon project completion. Within three years after project completion, the permittee shall hold another agency field meeting with DCM to determine if the Coastal Wetland areas temporarily impacted by this project have re-attained pre-project wetland functions, DCM will determine whether compensatory mitigation shall be required for these impacts. 2.2 Description of Species The following wetland species were planted in the temporary impact areas to the North of the Intracoastal Waterway: Juncus roemerianus, Black Needle Rush Spartina alterniflora, Smooth Cordgrass 2.3 Results of Vegetation Monitoring The area where the temporary impacts occurred is re-attaining jurisdictional wetland status. The planted marsh grass is surviving and marsh grass is re-vegetating throughout the temporary impact areas. Site 4 (temporary work bridge area) at Photo Point #2 and the temporary impact area from the Geotechnical Unit’s boring machine adjacent to the Surf City Park at Photo Point #7 were recently planted in April 2021. Marsh grass sprigs were noted surviving within these recently planted areas. Other species noted within the temporary impacted areas included cattail, Spartina patens, glasswort, saltgrass, Juncus sp., big cordgrass, marsh-elder, and various marsh grass species. 4 2.4 Conclusions There were approximately 0.03 acres for roadway/bridge and 0.10 acres for temporary utility impacts from temporary fill and hand clearing in CAMA wetlands. There were no plots established on the site. By visual observation, the Surf City Bridge Temporary Impact Site shows that the planted species are surviving and the impacted areas are re- attaining jurisdictional wetland status. 4.0 OVERALL CONCLUSIONS AND RECOMMENDATIONS NCDOT proposes to discontinue monitoring at the site except for Site 4 at Photo Point #2 and the temporary impact area adjacent to the Surf City Park at Photo Point #7. All other sites have re-vegetated properly at this time. NCDOT will continue vegetation monitoring at the Surf City Bridge Temporary Impact Site in 2022. 5 Figure 1. Vicinity Map APPENDIX A SITE PHOTOS, PERMIT DRAWINGS, & PHOTO POINT LOCATIONS Surf City Bridge Temporary Impact Site PP# 1 Site 4 (temporary work bridge) PP#2 Site 4 (temporary work bridge) PP#3 Site 6 (pipe cleanout area) PP#4 Site 7 (pipe clean out area) PP#5 Site 3CAMA (utility temp. impact) PP#6 Site 3CAMA (utility temp. impact) August 2021 Surf City Bridge Temporary Impact Site PP# 7 (Geotech area adjacent to Surf City Park) August 2021