HomeMy WebLinkAboutWQ0035784_Extension Request_20220204From: Donald Feller
To: Plummer.Lauren; Caudle. Caitlin
Cc: Eric Youngs; Madelyn Mills; Sean DWYER; Christopher GARNIC; Paterson. Fern A.
Subject: [External] Extension Request for The Cottages of Boone NPDES Permit Renewal and Permit Modification
Applications
Date: Friday, February 4, 2022 4:13:58 PM
Attachments: imaae001.pna
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to Report Spam.
Good afternoon Lauren,
Please accept this email as an official request for a 60 day Extension for the submittal of The
Cottages of Boone Permit Renewal Application additional and supportive information, as well as the
requested Permit Modification Application originally scheduled for submittal by February 7, 2021.
We are requesting an extension due to scheduling delays with Brooks Engineering to complete and
submit signed and sealed engineering documents for the knife valve and Equalization Basin Overflow
modifications. All required information, applications, and engineering documentation will be
submitted on or before April 6, 2022, in one packet, as requested by DEQ staff. The most recent
correspondence from Brooks Engineering has suggested that they are 4-6 weeks from getting
started on the required engineering documents.
We appreciate your time and attention to this matter, and thank you for working with The Cottages
of Boone to get the Permit Renewal and Permit Modifications completed. Your response is greatly
appreciated. Thank you.
Sincerely,
Don Feller
Operations Manager - Envirolink of Ohio
Area Manager— Envirolink of NC Mountains Region
(919) 441-2091
dfeller(@envirolinkinc.com
www.envirolinkinc.com
E:NVIR01.1NK