December 1, 2021
LETTER OF APPROVAL WITH MODIFICATIONS
NP Piedmont Commerce Center, LLC
Attention: Karen Rozar of CT Corporation System, NC Agent
160 Mine Lake Ct., Suite 200
Raleigh, NC 27615
RE: Project Name: Macy Grove
Acres Approved: 130
Project ID: GUILF-2022-004
County: Guilford
City: Kernersville
Address: Macy Grove Rd.
River Basin: Cape Fear
Stream Classification: WS-IV* - Randleman Lake Watershed
Submitted By: Kimley-Horn
Date Received by LQS: November 30, 2021
Plan Type: Revised
Dear Sir or Madam:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to
be acceptable with modifications and hereby issue this Letter of Approval with Modifications.
The Modifications Required for Approval are listed on the attached page. This plan approval shall
expire three (3) years following the date of approval, if no land -disturbing activity has been
undertaken, as is required by Title 15A NCAC 413.0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the
NCGO10000 Construction General Permit. After the form is reviewed and found to be complete,
you will receive a link with payment instructions for the $100 annual permit fee. After the fee
is processed, you will receive the COC via email. As the Financially Responsible Party shown on the
FRO form submitted for this project, you MUST obtain the COC prior to commencement of any land
disturbing activity. The eNOI form may be accessed at deq.nc.gov/NCG01. Please direct questions
about the eNOI form to the Stormwater Program staff in the Raleigh central office. If the
owner/operator of this project changes in the future, the new responsible party must obtain a
new COC.
North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
•��/}� Winston-Salem Regional Office 1 450 Hanes Mill Road, Suite 300 1 Winston-Salem, North Carolina 27[03
336.776.9800
Letter of Approval with Modifications
NP Piedmont Commerce Center, LLC
December 1, 2021
Page 2 of 3
Title 15A NCAC 4B .0118(a) and the NCG01 permit require that the following documentation be
kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection
to ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Program is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, it is determined that the erosion and sedimentation control plan
is inadequate to meet the requirements of the Sedimentation Pollution Control Act of 1973
(North Carolina General Statute 113A-51 through 66), this office may require revisions to the
plan and implementation of the revisions to ensure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State
water quality laws, regulations, and rules. In addition, local city or county ordinances or rules
may also apply to this land -disturbing activity. This approval does not supersede any other
permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. This permit allows for a land -disturbance,
as called for on the application plan, not to exceed the approved acres. Exceeding the acreage
will be a violation of this permit and would require a revised plan and additional application fee.
You are requested to file an amended form if there is any change in the information included on
the form. In addition, it would be helpful if you notify this office of the proposed starting date for
this project. Your cooperation is appreciated.
Sincerely,
Zachary Lentz, PE
Assistant Regional Engineer
Land Quality Section
Enclosures: Certificate of Approval
Modifications Required for Approval
NCG01 Fact Sheet
cc: Allison Bragg, PE of Kimley-Horn (via email)
WSRO file
Letter of Approval with Modifications
NP Piedmont Commerce Center, LLC
December 1, 2021
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Macy Grove
Project ID: GUILF-2022-004
County: Guilford
Modifications pursuant to applicable North Carolina General Statutes and/or Regulations:
1. This ESC plan was approved based on information submitted electronically to Zac Lentz, PE
on November 24, 2021. For inspection purposes, one hard copy of the revised plan set,
calculation packet, and disapproval letter response reflecting the E-mailed information must
be delivered to this office by December 8, 2021 or prior to the beginning of construction,
whichever date is earlier. Please reference Project ID in your cover memo.
[15A NCAC 4B .0107(c)]
Ref: G.S. 113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities