Loading...
HomeMy WebLinkAboutNCC191956_NOT Closeout Documents_20211004North Carolina Department of Environmental Quality Land Resources: Systel Building, 225 Green Street, Suite 714, Fayetteville, NC 28301-5094 (910) 433-3300 County: Richmond Project: Rockingham Resource Center Pond Remediation River basin: Yadkin -Pee Dee Person financially responsible: Piedmont Natural Gas (Duke Energy Progress) - Ottis W Allen, Manager Project #: RICHM-2020-001 Land Services Regional Address: 550 South Tryon Street, Charlotte, NC 28202 1. Project Location: Enterprise Drive, Rockingham Pictures: No 2. Weather and soil conditions: sunny, workable 3. Is site currently under notice of violation? No 4. Is the site in compliance with S.P.C.A. and rules? Yes 5. Violations: 6. Is the site in compliance with the NPDES Permit? Yes Describe: Initial inspection: No If no, check violations below: 7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply) Degree of damage: 8. Contact made with (name): Joel Fox Inspection report: Sent Report 9. Corrective action needed: Title: Operations Manager Date given/sent: December 12, 2019 10. Comments: Rain gauge and completed self -monitoring records from September to December 2019 onsite. Project appears completed and adequately stabilized. Permanent ground cover sufficient to restrain erosion has been established and SPCA requirements have been met. No additional SPCA self -inspections are required, however NPDES self -monitoring must continue until termination of coverage under the NPDES General Stormwater Permit for Construction Activities has been submitted by the permittee via an electronic Notice of Termination (e-NOT). Please retain a copy of this inspection report to submit along with the Notice of Termination. Link to access the Notice of Termination (e-NOT): http s://deq.nc.gov/abouVdivisions/energy-mineral-land-re sources/energy-mineral-land-permits /stormwater-permits/construction-sw Reported by: Mike Lawyer Others present: Date of inspection: December 11, 2019 Time arriving on site: 10:20 AM Time leaving site: 10:35 AM cc: Joel Fox, Operations Manager — PNG; Mark Hamlett, PE - McAdams