January 30, 2009
C201371
R2502A & R-2502B
34438.3,3
MOORE & RICHMOND
US-1 from south of SR-1001
north of Moore County Line.
(Marston Rd) to existing 4-lanes
Pre-Construction Conference Minutes
In accordance with Article 108-3 of the Standard Specifications, a Preconstruction Conference
was held for the above referenced project on Tuesday, November 25, 2008 at 10:00 am at the
Division Engineer's Office in Aberdeen, North Carolina. The following persons attended:
Name
Representing
Phone
John Olinger
NCDOT-Division 8
910-944-2344
Marty C. Tillman
NCDOT-Division 8
919-776-9623
Ron T. Van Cleef
NCDOT-Division 8
919-776-9623
Jason L. Crissman
NCDOT-Division 8
919-777-3499
Jeremy B. Phillips
NCDOT-Division 8
919-776-9623
Jerrry Austin Jr.
Riley Paving Inc.
910-947-5376
Johnny Norris
Riley Paving Inc.
910-947-5376
Jimmy Riley
Riley Paving Inc.
910-947-5376
Phillip Bartholomew
Riley Paving Inc.
910-947-5376
Scott J. Riley
Riley Paving Inc.
910-947-5376
Tony Picerno
Riley Paving Inc.
910-947-5376
Barry Harrington
NCDOT/Roadside
919-776-2279
Brad Bass
NCDOT/Div RIW
910-944-2393
D. F. Rudd
Telics/AT&T
910-277-1009
Vickie Davis
NCDOT/Const. Unit
336-703-6576
Ron Shaw
Lee Construction
704-588-5272
James A. Goodson
R. E. Goodson
843-393-2253
Tom Goodson
R. E. Goodson
843-339-7108
Brett Calcutt
R. E. Goodson
843-307-0620
Ken Averitte
NCDENRIDWQ
910-433-3303
MAILING ADDRESS: TELEPHONE: 910-944-2344 LOCATION:
DIVOON ENGINEER'S OFFICE FAX: 910-944-5623 902 N. SANDHILLS BLVD.
P. 0. Box 1067 WESSITE. WWW.NCDOT.ORG ABERDEEN, NC 28315
ABERDEEN, NC 28315
Mr. Goodson
Preconstruction Minutes
January 30, 2009
Page 2
Name (Cont)
Representinq
Phone
J. R. Harrah
Willoughby
704 - 909 -9975
Billy Bledsoe
L &B Construction
843 - 537 -1766
Wayne Oldham
Windstream
910 -944 -3483
Andy Smith
Location Survey
336 - 625 -9254
Greg Myrick
Location Survey
336- 625 -9254
Ed Reams
NCDOT Utilities
919- 250 -4128
Richard Spencer
USACOE
910- 251 -4172
Art King
NCDOT - Division 8
910- 944 -2344
David Willett
NCDOT - Division 8
910 -947 -3930
Jim Dietrich
NCDOT - Division 8
910 - 944 -7554
Gary Phillips
NCDOT- Division 8
910 - 944 -7554
Introductions were made and the first topic of discussion was utilities.
Utility Items:
• R/W has been acquired for all utilities throughout the projects.
• Post office to be moved out by January 1, 2009.
• Bill boards may be taken down.
• Some concrete foundations /pads are with in the RIW. Contractor noted this will not be a
problem to remove. Contractor noted the Mr. J. J. Harren will be the Utility Coordinator
for R. E. Goodson.
• Ed Reams noted that at Station +1 -179 there is a fiber line that cannot be cut.
• Progress Energy has five clearing crews working at this time.
• Time Warner did not have anyone present. All facilities to be relocated by August 1,
2009.
• Windstream is waiting for Progress Energy to finish their work. All facilities to be
relocated by February 1, 2010.
• AT &T is also waiting on Progress Energy to complete their work. All facilities to be
relocated by October 1, 2009.
• No one was present for Verizon. There is a conflict with 30" drain pipe at station 179 rt.
--L -. Per contract Verizon requests a 3 week notice and 1 week construction time to
bore and jack installation.
• A meeting to be set up with all utility companies, the Department and the project utility
coordinator for Thursday December 4, 2008 at 10:00 am.
Permits/
Erosion Control:
• Contractor to have certified erosion and sediment control stormwater supervisor,
certified foremen, certified installers and certified designer.
• John Olinger stress that erosion control is a very serious issue and to keep plans on -site
and up to date.
• Department would like to make sure the survey party has a clear understanding of the
flagging at bridge sites. There is some hand clearing at this site.
• Mr. Spencer with the USACE stated the importance of not deviating from what the
permits show on the plans.
• Use Best Management Practices to minimize silt loss.
• If any erosion control issues arise bring them up and address them immediately.
• If we find out the permits differ from contract make Marty Tillman or Ron Van Cleef
aware so we can get it resolved in a timely manner.
Mr. Goodson
Preconstruction Minutes
January 30, 2009
Page 3
Permits/
Erosion Control: (Cont)
• Keep a rain gauge and log book on site.
• Orange fence to be installed at wet lands area.
• Keep weekly reports up to date.
• When measures are installed highlight in yellow and date.
• Make notes of any concern or blowouts so they can be addressed when roadside visits
project.
General Items:
• Contractor submitted a tentative progress schedule. This schedule will be updated after
the meeting with utility companies. Mr. Olinger advised Contractor no to exceed payout
schedule in contract. Mr. James Goodson stated they were working on the subcontract
agreements and are forthcoming.
• R. E. Goodson plans to start work sometime before Christmas.
• Project manager will be Mr. Torn Goodson.
• Traffic control coordinator will be Mr. Brett Calcutt.
• Liquidated Damages are $2,800.00 per calendar day.
• ICT 1 includes all major holidays and states that the contractor shall not narrow or close
a lane of traffic on US 1 and all —Y- lines, detain and / or alter the traffic flow on or
during holiday weekends, special events, or any other time when traffic is unusually
heavy.
• ICT 2 and 3 gives 30 days for each phase II steps 3A, 2A and has liquidated damages
of $500.00 per calendar day.
• ICT 4 gives 72 hours for phase III step 2 and has liquidated damages of $500.00 per
hour.
• Contractor to report all MBE's and WBE's. If a problem occurs with any minority
businesses please report it to Marty Tillman or Ron Van Cleef. Follow all guidelines
when replacing a minority business.
• John Olinger supplied the contractor a claim submittal form.
• This project has a twelve month guarantee.
• Prior to any work being done contractor to contact CSX representative Mr. J. D. Kirkland
at (919) 362 -9402. A 30" welded steel pipe under the tracks of CSX railway has a wall
thickness of 0.079 ". Department to look into this issue.
• Riley paving to cut cores for density.
• Mr. Olinger advised contractor to use a video camera to video tape project incase any
problems may arise in the future. Contractor to install temporary chain link fence prior
to removing existing fence at parcel 26.
• This contract does have a seeding incentive.
• Mr. Ron Shaw said they plan to use pipe piles for the temporary bridges and plan to use
a barge and mats to build the new structures.
• John Olinger stated we would be using CSL testing on some of the shafts.
• Mr. Shaw plans to send submittals straight to Raleigh. Copy of cover letter needs to be
send to Resident Engineer's Office.
• Mr. Tillman stated that class 11 safety vest shall be worn by all contractors personnel and
subcontractors.
• Back up alarms on trucks is a must. If a truck shows up with out a back up alarm they
will be asked to leave the project.
• When trenching and shoring a competent person must be onsite.
Mr. Goodson
Preconstruction Minutes
January 30, 2009
Page 4
• Keep all intersections clear of site for traveling public as well as guiding through the
project in a safe manner.
• Waterline specs will be the Departments specifications but we will also work with the
owners.
• When submitting supplemental agreements please provide the Department with a cost
breakdown of materials and labor.
• The Department to provide R. E. Goodson with electronic files to make model for
grading purposes.
These minutes are prepared as they are documented. Any discrepancies with the content of
these minutes should be submitted in writing to this office. Failure to do so will be an indication
of agreement.
Sincerely,
/�Jon R. G. linger, PE
Division Construction Engineer
c: R. A. Hancock, PE
M. C. Tillman
V. G. Davis, PE
D. R'. Scott, PE
Bradley D. Bass
Greg Myrick, PE
Ed Reams
Art King
David Willett
M. G. Phillips
Jerry Austin — Riley Paving
D. F. Rudd - Telics /A T &T
Ron Shaw - Lee Construction
Ken Averitte - NCDENRIDWQ
J. R. Harrah —Willoughby
Billy Bledsoe - L &B Construction
Wayne Oldham — Windstream
Richard Spencer -- USACOE
File